SlideShare a Scribd company logo
1 of 38
Download to read offline
1
Lecture - 5
2
The Critical Path Method (CPM)
3
Who develops the WBS?
A WBS is developed by the A/E at the end of the design phase.
and/or by the bidders during the proposal (procurement phase).
4
TYPES OF ACTIVITIES
1. Production Activities
Those that can be taken directly from plans and specifications
2. Procurement Activities
Procurement of material and equipment
3. Management Decision Activities
Activities that can be created by management to avoid certain situations
Delay Concrete
Company Vacation
5
Example
Draw the logic network and perform the CPM calculations for the schedule shown next.
Duration
IPA
Activity
5
-
A
8
A
B
6
A
C
9
B
D
6
B,C
E
3
C
F
1
D,E,F
G
6
In mathematical terms, the ES for activity j is as follows :
ESj =max( EFi )
where (EFi) represents the EF for all preceding activities.
Likewise, the EF time for activity j is as follows :
EF j= ESj + Dur j
where Dur j is the duration of activity j
Forward pass: The process of navigating through a network from start to end and calculating the
completion date for the project and the early dates for each activity
Forward pass calculations
7
A
5
G
1
C
6
D
9
B
8
E
6
F
3
22,23
5,11
5,13 13,22
13,19
11,14
0,5
Solution :
Duration
IPA
Activity
5
-
A
8
A
B
6
A
C
9
B
D
6
B,C
E
3
C
F
1
D,E,F
G
8
In mathematical terms, the late finish LF for activity j is as follows :
(
LFj =min(LSk
where (LSk) represents the late start date for all succeeding activities.
Likewise, the LS time for activity j (LS j) is as follows :
LS j= LFj - Dur j
where Dur j is the duration of activity
Backward pass: The process of navigating through a network from end to start and calculating the late dates for
each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the
amount of float each activity has.
Backward pass calculations
9
Solution :
A
5
G
1
C
6
D
9
B
8
E
6
F
3
22,23
5,11
5,13 13,22
13,19
11,14
0,5
22,23
13,22
19,22
16,22
5,13
10,16
0,5
CPM ( ES = LS , EF = LF , TF = FF = 0)
10
Types Of Floats
There are several types of float. The simplest and most important type of float is
Total Float (TF)
 Total float (TF): The maximum amount of time an activity can be delayed from its
early start without delaying the entire project.
TF = LS – ES
or
TF = LF - EF
or
TF = LF - Dur - ES
11
 Free Float: may be defined as the maximum amount of time an activity can be delayed
without delaying the early start of the succeeding activities
FFi = min(ESi+1) - EFi
where min (ESi+1) means the least (i.e., earliest) of the early start dates of succeeding activities
12
In the previous example we can find the free float and total float for each activity as the following :
Activity C’s free float, FF = 11 - 11 = 0 days
And
Activity C’s total float, TF =16 - 11= 5 days …… and so on.
FF
TF
LF
LS
EF
ES
Duration
Activity
0
0
5
0
5
0
5
A
0
0
13
5
13
5
8
B
0
5
16
10
11
5
6
C
0
0
22
13
22
13
9
D
3
3
22
16
19
13
6
E
8
8
22
19
14
11
3
F
0
0
23
22
23
22
1
G
 Critical activity
 Note : We must always realize that FF ≤ TF
13
Node Format
Activity Name
Activity ID
Duration
ES EF
LS LF
TF FF
14
Example
Activity Duration IPA
A 5 -
B 6 A
C 5 A
D 3 A
E 3 B
F 4 B, C
G 4 D
H 7 B,C,G
I 8 E, F
J 2 F
K 3 H, J
L 2 I, J
15
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
16
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
0, 5
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
25
23, 25
22, 25
15, 23
20, 22
15, 22
12, 15
11, 15
11, 15
5, 11
6, 11
8, 11
1
3
1
3
5
3 3
Graphic Solution
17
Activity ES EF LS LF TF FF
A 0 5 0 5 0 0
B 5 11 5 11 0 0
C 5 10 6 11 1 1
D 5 8 8 11 3 0
E 11 14 12 15 1 1
F 11 15 11 15 0 0
G 8 12 11 15 3 0
H 12 19 15 22 3 0
I 15 23 15 23 0 0
J 15 17 20 22 5 2
K 19 22 22 25 3 3
L 23 25 23 25 0 0
Tabular Solution
18
Comments on the Solution
 Near-critical activities may be as important as critical activities
 It is a good practice for the project manager not to give subordinates two sets of
dates
 PM has to choose one set of dates within the range of Early – Late
 Management may reserve a number of days as “management float” or “time contingency”
19
Float Discussion
 Total float –in general- belongs to a path rather than the activity itself
 If an activity uses “its” float, successors may lose some or all of “their” float
 Total float versus free float
20
 The question is: “who owns the float”?
 Float distribution attempts
 Review the contract – what if it is not mentioned?
 Float with resource leveling
 Shifting activities within their float may affect:
 Start / finish dates of succeeding activities
 Resource usage: Labor and equipment (crews)
 Materials: delivery, storage
 Cash flow
21
Lags in Node Networks
 A lag is a minimum compulsory waiting period between the start/finish of an
activity and the start/finish of the successor
 A lead is a negative lag
 The lag is added in the CPM’s forward pass calculations and subtracted in the
backward pass
22
Examples:
 Concrete curing (before formwork stripping or reshoring)
 Asphalt curing (before striping)
 Waiting for a permit to be issued
 Waiting for the delivery of a custom material or equipment
23
Example
Activity Duration IPA Lag
A 5 -
B 3 -
C 6 -
D 7 A
E 7 A
B 4
F 4 A,B,C
G 5 E
F 3
H 6 D
G 2
I 3 D,G
24
C
6
B
3
A
5
G
5
F
4
E
7
D
7
H
6
I
3
4
3
2
PS PF
27
0
0 27
0, 5 5, 12
0, 3
0, 6
7, 14
6, 10
14, 19
21, 27
19, 22
21, 27
24, 27
14, 19
14, 21
7, 14
7, 11
2, 7
0, 3
1, 7
Graphic Solution
25
Activity ES EF LS LF TF FF
A 0 5 2 7 2 0
B 0 3 0 3 0 0
C 0 6 1 7 1 0
D 5 12 14 21 9 7
E 7 14 7 14 0 0
F 6 10 7 11 1 1
G 14 19 14 19 0 0
H 21 27 21 27 0 0
I 19 22 24 27 5 5
Tabular Solution
26
Effect of Imposed Finish Date
 Imposed Finish Date is the project’s completion date, as specified in the contract or
stipulated by the owner
 When compared to the calculated finish date:
 Calculated finish date < imposed finish date
• You are in good shape
• What happens if you enter the imposed date?
 Calculated finish date > imposed finish date
• Negative float appears when you enter the imposed date
• You need to accelerate / crash the schedule
27
Examples with Imposed Finish Dates
Repeat Example 3 with imposed finish date of 28 days
Repeat Example 3 with imposed finish date of 22 days
28
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
0, 5
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
25
23, 25
22, 25
15, 23
20, 22
15, 22
12, 15
11, 15
11, 15
5, 11
6, 11
8, 11
1
3
1
3
5
3 3
With out Imposed finished date
29
Imposed Finish Date > Calculated Finish Date
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
3, 8
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
28
26, 28
25, 28
18, 26
23, 25
18, 25
15, 18
14, 18
14, 18
8, 14
9, 14
11, 14
3 4
6 6 6 6
8
4
3 3
3
3
30
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
-3, 2
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
22
20, 22
19, 22
12, 20
17, 19
12, 19
9, 12
8, 12
8, 12
2, 8
3, 8
5, 8
-3
-3
-3
-2 -3
-3
-2 2
0 0 0 0
Imposed Finish Date < Calculated Finish Date
31
 Negative float is a situation that occurs when performing an activity even
on its early dates, fails to meet the project’s imposed finish date or other
constraint
 It may occur in one of two cases:
Before construction starts
During construction (after normal start)
Negative Float
32
Event Times in Arrow Networks
 The early event time, TE, is the largest (latest) date obtained to reach an event (going from
start to finish).
 The late event time, TL, is the smallest (earliest) date obtained to reach an event (going from
finish to start).
Example
Perform the CPM calculations, including the event times, for the arrow network shown below.
33
10 30
40
20 60
C
E
B
50
D
F
70
A
G
H
10
5
7
8
9
4
5
8
d1
d2
Arrow network for example
34
The preceding logic is similar to that of the forward and backward passes: When you are going forward, pick
the largest number. When you are going backward, pick the smallest number.
i j
Act. Name
Dur.
TEi
TLi
TEj
TLj
CPM
35
10 30
40
20 60
C
E
B
50
D
F
70
A
G
H
10
5
7
8
9
4
5
8
d1
d2
10
10
7
0
0
15
10
10
19
19
24
27
27
27
(0,10)
(0,10)
(5,10)
(0,5)
(0,7)
(8,15)
(10,18)
(11,19)
(10,19)
(10,19)
(7,11)
(15,19)
(19,24)
(22,27)
(19,27)
(19,27)
36
Definitions
Activity, or task: A basic unit of work as part of the total project that is easily measured and
controlled. It is time- and resource consuming.
Backward pass: The process of navigating through a network from end to start and calculating the
late dates for each activity. The late dates (along with the early dates) determine the critical
activities, the critical path, and the amount of float each activity has.
Critical activity: An activity on the critical path. Any delay in the start or finish of a critical activity will
result in a delay in the entire project.
Critical path: The longest path in a network, from start to finish, including lags and constraints.
.
37
Early dates: The early start date and early finish date of an activity.
Early finish (EF): The earliest date on which an activity can finish within project constraints.
Early start (ES): The earliest date on which an activity can start within project constraints.
Event: A point in time marking a start or an end of an activity. In contrast to an activity, an event does not consume time or
resources.
Forward pass: The process of navigating through a network from start to end and calculating the completion date for the
project and the early dates for each activity.
Late dates: The late start date and late finish date of an activity.
Late finish (LF): The latest date on which an activity can finish without extending the project duration.
Late start (LS): The latest date on which an activity can start without extending the project duration.
38
A
B
C
Improper Proper
A
B
C
PF
(a) Do not end a network with more than one node

More Related Content

Similar to Lecture 5.pdf

Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques Mohammad Younus
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chaintanishkagupta907
 
Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03jncgw5t6xq
 
MP assignment for printing
MP assignment for printingMP assignment for printing
MP assignment for printingHieu Pham
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptxLJay7
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.pptDejeneDay
 
Management Science : Project SchedulingPert_cpm.ppt
Management Science : Project SchedulingPert_cpm.pptManagement Science : Project SchedulingPert_cpm.ppt
Management Science : Project SchedulingPert_cpm.pptShahAbeshRahman743A
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptBetshaTizazu2
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completionAniruddha Kulkarni
 
Project management
Project managementProject management
Project managementTrade Expert
 
Project Management Fundamental
Project Management FundamentalProject Management Fundamental
Project Management FundamentalAndy Pham, PMP
 

Similar to Lecture 5.pdf (20)

Cpm pert
Cpm pertCpm pert
Cpm pert
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Networktechniques
NetworktechniquesNetworktechniques
Networktechniques
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
 
Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03
 
MP assignment for printing
MP assignment for printingMP assignment for printing
MP assignment for printing
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Project Scheduling.ppt
Project Scheduling.pptProject Scheduling.ppt
Project Scheduling.ppt
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Management Science : Project SchedulingPert_cpm.ppt
Management Science : Project SchedulingPert_cpm.pptManagement Science : Project SchedulingPert_cpm.ppt
Management Science : Project SchedulingPert_cpm.ppt
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completion
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
 
Project management
Project managementProject management
Project management
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project Management Fundamental
Project Management FundamentalProject Management Fundamental
Project Management Fundamental
 

Recently uploaded

mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 

Recently uploaded (20)

mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 

Lecture 5.pdf

  • 2. 2 The Critical Path Method (CPM)
  • 3. 3 Who develops the WBS? A WBS is developed by the A/E at the end of the design phase. and/or by the bidders during the proposal (procurement phase).
  • 4. 4 TYPES OF ACTIVITIES 1. Production Activities Those that can be taken directly from plans and specifications 2. Procurement Activities Procurement of material and equipment 3. Management Decision Activities Activities that can be created by management to avoid certain situations Delay Concrete Company Vacation
  • 5. 5 Example Draw the logic network and perform the CPM calculations for the schedule shown next. Duration IPA Activity 5 - A 8 A B 6 A C 9 B D 6 B,C E 3 C F 1 D,E,F G
  • 6. 6 In mathematical terms, the ES for activity j is as follows : ESj =max( EFi ) where (EFi) represents the EF for all preceding activities. Likewise, the EF time for activity j is as follows : EF j= ESj + Dur j where Dur j is the duration of activity j Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity Forward pass calculations
  • 8. 8 In mathematical terms, the late finish LF for activity j is as follows : ( LFj =min(LSk where (LSk) represents the late start date for all succeeding activities. Likewise, the LS time for activity j (LS j) is as follows : LS j= LFj - Dur j where Dur j is the duration of activity Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has. Backward pass calculations
  • 10. 10 Types Of Floats There are several types of float. The simplest and most important type of float is Total Float (TF)  Total float (TF): The maximum amount of time an activity can be delayed from its early start without delaying the entire project. TF = LS – ES or TF = LF - EF or TF = LF - Dur - ES
  • 11. 11  Free Float: may be defined as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities FFi = min(ESi+1) - EFi where min (ESi+1) means the least (i.e., earliest) of the early start dates of succeeding activities
  • 12. 12 In the previous example we can find the free float and total float for each activity as the following : Activity C’s free float, FF = 11 - 11 = 0 days And Activity C’s total float, TF =16 - 11= 5 days …… and so on. FF TF LF LS EF ES Duration Activity 0 0 5 0 5 0 5 A 0 0 13 5 13 5 8 B 0 5 16 10 11 5 6 C 0 0 22 13 22 13 9 D 3 3 22 16 19 13 6 E 8 8 22 19 14 11 3 F 0 0 23 22 23 22 1 G  Critical activity  Note : We must always realize that FF ≤ TF
  • 13. 13 Node Format Activity Name Activity ID Duration ES EF LS LF TF FF
  • 14. 14 Example Activity Duration IPA A 5 - B 6 A C 5 A D 3 A E 3 B F 4 B, C G 4 D H 7 B,C,G I 8 E, F J 2 F K 3 H, J L 2 I, J
  • 16. 16 A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 0, 5 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 25 23, 25 22, 25 15, 23 20, 22 15, 22 12, 15 11, 15 11, 15 5, 11 6, 11 8, 11 1 3 1 3 5 3 3 Graphic Solution
  • 17. 17 Activity ES EF LS LF TF FF A 0 5 0 5 0 0 B 5 11 5 11 0 0 C 5 10 6 11 1 1 D 5 8 8 11 3 0 E 11 14 12 15 1 1 F 11 15 11 15 0 0 G 8 12 11 15 3 0 H 12 19 15 22 3 0 I 15 23 15 23 0 0 J 15 17 20 22 5 2 K 19 22 22 25 3 3 L 23 25 23 25 0 0 Tabular Solution
  • 18. 18 Comments on the Solution  Near-critical activities may be as important as critical activities  It is a good practice for the project manager not to give subordinates two sets of dates  PM has to choose one set of dates within the range of Early – Late  Management may reserve a number of days as “management float” or “time contingency”
  • 19. 19 Float Discussion  Total float –in general- belongs to a path rather than the activity itself  If an activity uses “its” float, successors may lose some or all of “their” float  Total float versus free float
  • 20. 20  The question is: “who owns the float”?  Float distribution attempts  Review the contract – what if it is not mentioned?  Float with resource leveling  Shifting activities within their float may affect:  Start / finish dates of succeeding activities  Resource usage: Labor and equipment (crews)  Materials: delivery, storage  Cash flow
  • 21. 21 Lags in Node Networks  A lag is a minimum compulsory waiting period between the start/finish of an activity and the start/finish of the successor  A lead is a negative lag  The lag is added in the CPM’s forward pass calculations and subtracted in the backward pass
  • 22. 22 Examples:  Concrete curing (before formwork stripping or reshoring)  Asphalt curing (before striping)  Waiting for a permit to be issued  Waiting for the delivery of a custom material or equipment
  • 23. 23 Example Activity Duration IPA Lag A 5 - B 3 - C 6 - D 7 A E 7 A B 4 F 4 A,B,C G 5 E F 3 H 6 D G 2 I 3 D,G
  • 24. 24 C 6 B 3 A 5 G 5 F 4 E 7 D 7 H 6 I 3 4 3 2 PS PF 27 0 0 27 0, 5 5, 12 0, 3 0, 6 7, 14 6, 10 14, 19 21, 27 19, 22 21, 27 24, 27 14, 19 14, 21 7, 14 7, 11 2, 7 0, 3 1, 7 Graphic Solution
  • 25. 25 Activity ES EF LS LF TF FF A 0 5 2 7 2 0 B 0 3 0 3 0 0 C 0 6 1 7 1 0 D 5 12 14 21 9 7 E 7 14 7 14 0 0 F 6 10 7 11 1 1 G 14 19 14 19 0 0 H 21 27 21 27 0 0 I 19 22 24 27 5 5 Tabular Solution
  • 26. 26 Effect of Imposed Finish Date  Imposed Finish Date is the project’s completion date, as specified in the contract or stipulated by the owner  When compared to the calculated finish date:  Calculated finish date < imposed finish date • You are in good shape • What happens if you enter the imposed date?  Calculated finish date > imposed finish date • Negative float appears when you enter the imposed date • You need to accelerate / crash the schedule
  • 27. 27 Examples with Imposed Finish Dates Repeat Example 3 with imposed finish date of 28 days Repeat Example 3 with imposed finish date of 22 days
  • 28. 28 A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 0, 5 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 25 23, 25 22, 25 15, 23 20, 22 15, 22 12, 15 11, 15 11, 15 5, 11 6, 11 8, 11 1 3 1 3 5 3 3 With out Imposed finished date
  • 29. 29 Imposed Finish Date > Calculated Finish Date A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 3, 8 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 28 26, 28 25, 28 18, 26 23, 25 18, 25 15, 18 14, 18 14, 18 8, 14 9, 14 11, 14 3 4 6 6 6 6 8 4 3 3 3 3
  • 30. 30 A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 -3, 2 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 22 20, 22 19, 22 12, 20 17, 19 12, 19 9, 12 8, 12 8, 12 2, 8 3, 8 5, 8 -3 -3 -3 -2 -3 -3 -2 2 0 0 0 0 Imposed Finish Date < Calculated Finish Date
  • 31. 31  Negative float is a situation that occurs when performing an activity even on its early dates, fails to meet the project’s imposed finish date or other constraint  It may occur in one of two cases: Before construction starts During construction (after normal start) Negative Float
  • 32. 32 Event Times in Arrow Networks  The early event time, TE, is the largest (latest) date obtained to reach an event (going from start to finish).  The late event time, TL, is the smallest (earliest) date obtained to reach an event (going from finish to start). Example Perform the CPM calculations, including the event times, for the arrow network shown below.
  • 34. 34 The preceding logic is similar to that of the forward and backward passes: When you are going forward, pick the largest number. When you are going backward, pick the smallest number. i j Act. Name Dur. TEi TLi TEj TLj CPM
  • 36. 36 Definitions Activity, or task: A basic unit of work as part of the total project that is easily measured and controlled. It is time- and resource consuming. Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has. Critical activity: An activity on the critical path. Any delay in the start or finish of a critical activity will result in a delay in the entire project. Critical path: The longest path in a network, from start to finish, including lags and constraints. .
  • 37. 37 Early dates: The early start date and early finish date of an activity. Early finish (EF): The earliest date on which an activity can finish within project constraints. Early start (ES): The earliest date on which an activity can start within project constraints. Event: A point in time marking a start or an end of an activity. In contrast to an activity, an event does not consume time or resources. Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity. Late dates: The late start date and late finish date of an activity. Late finish (LF): The latest date on which an activity can finish without extending the project duration. Late start (LS): The latest date on which an activity can start without extending the project duration.
  • 38. 38 A B C Improper Proper A B C PF (a) Do not end a network with more than one node