SlideShare a Scribd company logo
1 of 41
Download to read offline
ESTABLISHING THE PERFORMANCE 
MEASUREMENT BASELINE (PMB) 
Glen B. Alleman 
Niwotridge Consulting 
1/40 
The Performance Measurement Baseline is a time–phased schedule of all the 
work to be performed, the budgeted cost for this work, and the organizational 
elements that produce the deliverables from this work.
The Performance Measurement Baseline is really 
3 baselines – Technical , Schedule, and Cost. 
2/40 5 
Perform 
Functional 
Analysis 
Technical Baseline 
Schedule Baseline 
Cost Baseline 
Determine 
Scope and 
Approach 
Develop 
Technical 
Logic 
Develop 
Technical 
Baseline 
Develop 
WBS 
Define 
Activities 
Estimate 
Time 
Durations 
Sequence 
Activities 
Finalize 
Schedule 
Identify 
Apportioned 
Milestones 
Determine 
Resource 
Requirements 
Prepare 
Cost 
Estimate 
Resource 
Load 
Schedule 
Approve 
PMB 
Finalize 
Apportioned 
Milestones 
Determine 
Funding 
Constraints 
Copyright © 2012, Niwot Ridge, LLC
The core element of the Performance 
Measurement Baseline (PMB) … 
3/40 6 
…Is a collection of Work Packages, that define: 
! The deliverables that fulfill the needed business 
capabilities, 
! The estimated duration and work effort for each Work 
Package, 
! The resources needed to produce these deliverables 
within the needed time period, and 
! Any dependencies – internal or external – needed to 
start a Work Package. 
It’s the deliverables that the customer bought. These deliverables contain the Business Value of the 
project. Connecting the Deliverables with the needed capabilities is the basis of a credible project 
execution process – then we can answer Why we are doing something. 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
6 STEPS TO ESTABLISHING 
THE PERFORMANCE 
MEASUREMENT BASELINE 
4/40 
Building the Performance Measurement Baseline requires six straightforward 
steps. Each must be performed. Each is critical. Each cannot be skipped.
5/40 
Never tell people how to do 
things. Tell them what 
needs to be done and they 
will surprise you with their 
ingenuity. – Gen. George 
Patton 
I need the capability to disengage 
from offense activities and move 
a brigade of 3,000 to 5,000 
troops 100 miles in ten hours, 
and arrive at Bastogne Holland 
before General Rommel does to 
rescue the 101st Airborne 
Division 
Capabilities-based planning 
specifies the outcome but does 
not specify how to do that cause 
that outcome to appear. 
Action Outcome 
Implement Strategy 
Ensure Capabilities 
Prioritize Problems And Solutions 
Identify Redundancies 
Deliver Solutions 
Copyright © 2012, Niwot Ridge, LLC
Decompose the Project Scope into a product based Work Breakdown Structure (WBS), then 
further into Work Packages describing the production of all deliverables traceable to the 
requirements 
Decompose 
Scope into Work 
Packages 
Assign Responsibility to Work Packages (the groupings of deliverables) for the named 
owner accountable for the management of resource allocation and cost baseline and 
technical delivery 
Assign 
Responsibility 
for Deliverables 
Arrange the Work Packages in a well formed network with defined deliverables, 
milestones, internal and external dependencies, appropriate schedule and cost 
margin. 
Arrange 
Work Packages 
in Logical Order 
Develop a Time–Phased Budgeted Cost for Work Scheduled (BCWS) from labor and 
material costs in each Work Package and the Project as a whole. Assure proper resource 
allocations can be met and budget profiles match expectations of the project sponsor 
Develop 
BCWS for Work 
Packages 
Assign object Measure of Performance (MOP) and Measures of Effectiveness (MOE) for 
each Work Package and summarize these for the Project as a whole 
Assign WP 
Measures of 
Performance 
Build a time–phased network of schedule activities describing the work to be performed, the 
budgeted cost for this work, the organizational elements that produce the deliverables, and 
the performance measures showing this work is proceeding according to plan. 
Establish 
the Performance 
Measurement 
Baseline A Baselined Schedule that Creates the Services or Products to Meet The Requirements 
3.0 
3.1 
3.2 
3.3 
3.4 
3.5 
Establish a Performance Measurement Baseline (PMB) used to forecast Work Package 
and Project ongoing and completion cost and schedule metrics 
Set 
3.6 
Performance 
Measurement 
Baseline 
7 
6/437 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
3.1 DECOMPOSE THE 
7/40 
PROJECT SCOPE INTO 
WORK PACKAGES EACH 
WITH A SINGLE 
DELIVERABLE 
Starting with the Business Requirements, the Work Breakdown 
Structure (WBS) guides the development of the Work Packages.
Business Capabilities, WBS, and Work Packages 
are connected to define what “Done” look like. 
8/40 8 
There is likely no 
factor that 
would contribute 
more to the 
success of any 
project than 
having a good 
and complete 
definition of the 
project's scope 
of work 
‒ Quentin 
Fleming and 
Joel 
Koppelman, 
Earned Value 
Project 
Management 
Business Capability 
Process Invoices for 
Top Tier Suppliers 
1st Level 
Electronic Invoice 
Submittal 
1st Level 
Routing to Payables 
Department 
2nd Level 
Payables Account 
Verification 
2nd Level 
Payment Scheduling 
2nd Level 
Material receipt 
verification 
2nd Level 
“On hand” balance 
Updates 
Copyright © 2012, Niwot Ridge, LLC
What does a good WBS NOT look like? 
9/40 10 
The whole notion 
of spending time 
building the WBS 
may seen odd. 
How hard can this 
be? 
It turns out of 
course that any 
definition of 
“done” can be 
traced back to the 
definitions of 
“what are we 
providing to the 
customer in terms 
of deliverables?” 
That’s the contents 
of the WBS. 
! It’s not a laundry list of work to be 
done. 
! It’s not a functional decomposition. 
! It’s not a direct map of the 
requirements. 
! It’s not a reflection of the underlying 
software partitioning. 
! It’s not the first structure we might think 
of, it takes several iterations to get it 
right. 
Copyright © 2012, Niwot Ridge, LLC
Connect the WBS to Work Packages, then define 
the Tasks for the Deliverables to produce Value. 
10/40 12 
The WBS is derived 
from the breakdown 
of the business 
capabilities and their 
stated requirements. 
From this WBS Work 
Packages are 
defined with their 
deliverables. 
The tasks that 
produce these 
deliverables are not 
explicitly stated in the 
Performance 
Measurement 
Baseline, but rather 
are held by the Work 
Package Manager. 
Physical percent 
complete 
performance is 
measured through 
apportioned 
milestones or a 0%/ 
100% outcome for 
the Work Package 
Business Need 
Process Invoices for Top 
Tier Suppliers 
1st Level 
Electronic Invoice 
Submittal 
1st Level 
Routing to Payables 
Department 
2nd Level 
Payables Account 
Verification 
2nd Level 
Payment Scheduling 
2nd Level 
Material receipt 
verification 
2nd Level 
“On hand” balance 
Updates 
Deliverables defined in WP 
Copyright © 2012, Niwot Ridge, LLC
Steps in Building the Work Packages. 
11/40 13 
! Step 1 – define what is going to be delivered to 
produce business value 
! One Deliverable produced within a Work Package 
! Try not to have more than one deliverable per Work 
Package 
! Step 2 – define the effort and duration along with 
the confidence levels 
! Only effort and total duration 
! Level of confidence for effort and duration 
Copyright © 2012, Niwot Ridge, LLC
Naming Work Packages may seem simple, but it’s not 
What’s in a Name? Juliet (Romeo and Juliet II, ii 1-2) 
12/40 18 
! Turns out there is a lot in a name 
! The name should convey not only the work activities but 
also the delivered result of these activities 
! There is a powerful result from this effort 
! The project plan and the list of Work Packages is the 
concise statement of the work for the project – all held in 
a single place – the Project Plan 
Adjective Verb Noun Verb 
Demonstrates 
Maturity 
A step in the 
process End Item Final Status 
Preliminary Design Processes Complete 
Preliminary design of transaction processes complete 
The Bambino 
and Iron Horse 
Famous names 
that carried 
meaning to the 
reader 
Copyright © 2012, Niwot Ridge, LLC
The Basis of Estimate (BOE) must be recorded, 
reviewed and approved. 
13/40 20 
! A short description of how we got to the estimate of 
effort and the duration of the work 
! I’ve done this before 
! I asked someone who has done this before 
! I ran an experiment to determine how long it would take 
! I took a guess and multiplied it by 2 
Remember we’re filling out worksheets for the Work Packages. No project 
management tools. Resist skipping to the end, until we have some notion of the 
total effort and duration. 
Committing too soon is just as bad as committing too late 
Copyright © 2012, Niwot Ridge, LLC
Completion Criteria for each Work Packages is 
used to measure physical progress to Plan. 
14/40 21 
! The completion criteria for the Work Package are 
the Exit Criteria describing the Work Package’s 
100% complete measures. 
! There is no “partial” completion of the Work 
Package, no “almost done.” 
! The deliverable may be partially complete, but the 
Work Package is 0%/100% complete. 
! Either we are done or we are not done – no partial 
done allowed. 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
3.2 ASSIGN 
RESPONSIBILITIES 
15/40 
Identify the single person accountable for the Work Package. This person is 
accountable for the duration, effort, and resource requirements for the Work 
Package.
Responsibilities – Actually Accountability for the 
Work Package is written and visible to everyone. 
16/40 22 
! Each Work Package has one and only one person 
Accountable for the successful delivery of the Work 
Package 
! Put that person’s name on the Work Package 
! Build a Responsibility Assignment Matrix (RAM) from 
the HR files for the project team 
! Naming the person is a start 
! It’s better to start what this person does and how they 
contribute to the project 
Copyright © 2012, Niwot Ridge, LLC
Assign accountability for each component of the 
Work Package. 
17/40 23 
! Each Work Package has a single owner who is 
accountable for: 
! Defining the deliverables 
! Assigning resources 
! Balancing the resource usage 
! Defining the Earned Value measurement criteria 
! Identifying any apportioned milestones 
! Reporting physical percent complete 
! Name this person in the Work Package and the 
Master Schedule 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
3.3 ARRANGE WORK 
18/40 
PACKAGES WITHIN EACH 
WORKSTREAM 
Arranging the Work Packages in a logical network within each work stream starts with 
grouping the Work Packages into “bundles” of business value that are recognizable 
by the customer.
Identify the Predecessors and Successors between 
Work Packages to sequence the work effort. 
19/40 24 
! Give some thought about the sequence of the 
Work Packages 
! What deliverables come first? 
! What deliverables come next? 
! The reason for this should be obvious 
! Use a Work Authorization (WA) processes to 
keep the sequence of work intact 
Lay out the Work Packages on the wall. Move then around to see how they 
flow. Stand back is see if the arrangement actually makes any sense in terms 
of the flow of work and the production of deliverables 
Copyright © 2012, Niwot Ridge, LLC
Arrange the Work Packages in the sequence that 
ensures value is being produced along the way. 
20/40 25 
Copyright © 2012, Niwot Ridge, LLC
“Arranging” the Work Packages Is An Iterative 
And Incremental Process 
In this example, the 
Work Package 
Managers collectively 
come to an 
agreement on how 
the sequence of how 
the work will be 
performed. 
The result is a 
collective ownership 
of the outcome. This 
ownership comes from 
the collective 
development of the 
project plan. 
This process is a 
Product Development 
Kaizen (PDK) 
21/40 
"Any intelligent fool can make things bigger, more complex, and more 
violent. It takes a touch of genius—and a lot of courage—to move in the 
opposite direction." ~Albert Einstein 
Copyright © 2012, Niwot Ridge, LLC
Start with a “notional” arrangement of the 
“Bundles” of work within a Workstream 
22/40 27 
! WPs should have No intermediate connections 
7w 
7w 
5w 
5w 
1w 3w 3w 
3w 
2w 
7w 
5w 
! The first approach is to 
have long running WPs 
with negative or 
positive lags to 
maintain sequencing 
! A better approach is 
to break the WP into 
separate deliverables 
and sequence Finish to 
Start 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
3.4 DEVELOP THE BUDGET 
FOR THE WORK 
SCHEDULED IN EACH 
WORKSTREAM 
23/40 
Using the individual Work Package cost spreads, the project or project 
budget spreads are developed to match the available resources.
Develop a time–phased budget from the network 
of Work Packages based on resource loads 
24/40 28 
Duration of the Work Package 
Budget 
Duration of the Work Package 
Budget 
Duration of the Work Package 
Budget 
Duration of the Work Package 
Budget 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
25/40 
3.5 ASSIGN PERFORMANCE 
MEASURES 
The only programmatic performance measure of a Work Package is Physical Percent 
Complete (PPC). This can be defined in a variety of ways. But expended effort is 
NEVER the way to define progress.
Identify objective measures of performance for 
each Work Package 
26/40 31 
! Define the Planned Value for each Work Package 
completion or apportioned milestone within a Work 
Package 
! Only Physical Percent Complete should be used to 
measure progress – no “opinions” of progress 
! Answer the question 
! How are we going to recognize that progress is being made 
! The passage of time and consumption of resources is NEVER 
a measure of progress 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
3.6 SET PERFORMANCE 
BASELINE 
27/40 
With the Work Packages sequenced, labor spreads assigned and balanced, 
deliverables defined, and performance measures established, it's time to 
baseline the plan.
Baseline the schedule to establish the planned 
budget spreads for each Work Package 
28/40 32 
! Baselining the Performance Measurement Baseline is 
the first step in successfully of Executing the project 
plan 
! Without the baseline and the rigorous change 
control over this baseline, the needed credible 
performance predictions will be not possible 
There are two phases of any complex project: 
Too early to tell and too late to stop 
‒ Mr. Blaise Durante, Senior Executive Service, Deputy Assistant 
Secretary for Acquisition Integration, Office of the Assistant 
Secretary of the Air Force for Acquisition, Washington, D.C. 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
29/40 
BUILDING THE PROJECT 
SCHEDULE FROM THE 
BASELINE WORK PACKAGES 
With the baselined sequence of Work Packages, the detailed execution schedule can 
be started. This is an iterative and incremental process that balances the resources 
against needed business capabilities.
Assembling the Work Packages into credible 
project schedule, starting with 
30/40 
! Total Work Package duration 
! Total Work Package work effort 
! Start dates aligned with the project start date 
defined in the Project menu 
! The result is a Gantt–style picture of the flow of 
Work Package value 
Henry Laurence Gantt, A.B., M.E, 1861–1919 
33 
Copyright © 2012, Niwot Ridge, LLC
Sequencing the Work Packages starts with finding 
the best value flow for the work effort 
31/40 34 
! Confirm the Total Effort and Total Duration of each 
Work Package represents the agreed on information 
captured from the team 
! One of two approaches comes next: 
! Sequence the individual WP’s into a logical network – 
then assign resources 
! Assign resources – then sequence the WP’s into a logical 
network 
Copyright © 2012, Niwot Ridge, LLC
Project maturity flow for work streams defines in 
the increasing maturity of the deliverables 
32/40 35 
Demo conversion process, member reconciliation 
Shared group matrix reports and interfaces 
Shared member crosswalk and members to Facets 
Accumulators of converted members 
Status Mock and trigger conversions 
Data in TibMarts 
for EVIR 
Member & 
Employer Portal 
include 
converted 
members 
Members 
termed to 
legacy 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
33/40 
MAKING THE SCHEDULE 
CREDIBLE 
A credible schedule cannot be just a list of activities. It must be an accurate 
model of the project strategy and execution that can be analyzed, assessed, 
and used to answer risk based questions.
Analyzing and assessing the network of Work 
Packages to assess credibility 
! Critical Path 
! Accuracy 
! Integration 
! Realism 
! Performance 
! Variances 
! Forecasting 
! What–if’s 
! Risk 
! Resources 
34/40 
I Que Es La Veritat? = What is Truth? 
Over the portal of the "Sagrada Familia" church in Barcelona, Spain 
36 
Copyright © 2012, Niwot Ridge, LLC
Risk Management Process is a starting point for a 
credible Performance Measurement Baseline 
35/40 37 
“Risk Analysis Techniques, Schedule, Cost and Other Aspects, INCOSE Heartland 
Chapter October 24, 2001, Futon Corporation 
Copyright © 2012, Niwot Ridge, LLC
Cost, Schedule and Technical Risk Model are 
inseparable – anything else is a Ponzi Scheme 
36/40 39 
Cost, Schedule, Technical Model† 
WBS 
Task 100 
Task 101 
Task 102 
Task 103 
Task 104 
Task 105 
Task 106 
Probability 
Density 
Function 
† This is a Key concept. This is the part of the technique that integrates the cost 
and schedule risk impacts to provide the basis of a credible schedule. 
" Research the Project 
" Find Analogies 
" Ask Endless Questions 
" Analyze the Results 
" What can go wrong? 
" How likely is it to go wrong? 
" What is the cause? 
" What is the consequence? 
Monte Carlo Simulation 
Tool is Mandatory 
Cumulative Distribution Function 
1.0 
.8 
.6 
.4 
.2 
0 
Days, Facilities, Parts, People 
Copyright © 2012, Niwot Ridge, LLC
Assessment of the probabilistic duration is the 
basis of any credible schedule 
37/40 41 
! Any path could be critical depending on the arrangement of the underlying 
task completion time probability distribution functions 
! The independence or dependency 
of each task with others in the 
network, greatly influences the 
outcome of the total project 
duration 
! Understanding this dependence is 
critical to assessing the credibility 
of the plan as well as the total 
completion time of that plan 
Prepare for the unknown by studying how others in the past have coped with the unforeseen 
and the unpredictable – General, George S. Patton 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwotridge Consulting 
38/40 
WRAPPING UP FOR TODAY 
THIS OF COURSE IS JUST THE 
TIP OF THE ICEBERG 
There is a tremendous amount of information in this Work Shop. No one single session 
can move it from here into practice. In the end programmatic control of a project is a 
practice not a procedure.
In the end, its all about the schedule. We can find 
more money, but we can never find more time. 
! A slipping the schedule is simply unacceptable in 
any project with business value 
! “Attack” the schedule as soon as possible and never 
stop attacking 
! Update schedules frequently, look at it daily 
! Keep all the data “clean” and use it to make 
management decisions 
39/40 
How long are we willing to wait before we find out we’re late? 
Measure progress and update our forecast at ½ that time. More 
frequently for critical items. 
42 
Copyright © 2012, Niwot Ridge, LLC
Glen B. Alleman 
Niwot Ridge Consulting 
4347 Pebble Beach Drive 
Niwot, Colorado 80503 
303.241.9633 
glen.alleman@niwotridge.com 
Performance-Based Project Management® 
Integrated Master Plan 
Integrated Master Schedule 
Earned Value Management Systems 
Risk Management 
Proposal Support Services 
Copyright © 2012, Niwot Ridge, LLC 41/34

More Related Content

What's hot

Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short CourseGlen Alleman
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPKevin West
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceGlen Alleman
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?Glen Alleman
 
PGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPMPGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPMGlen Alleman
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as OpportunityGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Keynote 2 - SE and PPM a Match Made in Heaven
Keynote 2 - SE and PPM a Match Made in HeavenKeynote 2 - SE and PPM a Match Made in Heaven
Keynote 2 - SE and PPM a Match Made in HeavenGlen Alleman
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountGlen Alleman
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management ProceduresGlen Alleman
 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGlen Alleman
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
Scrum lifecycle for Enterprise IT
Scrum lifecycle for Enterprise ITScrum lifecycle for Enterprise IT
Scrum lifecycle for Enterprise ITGlen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 

What's hot (20)

Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short Course
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?
 
PGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPMPGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPM
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Keynote 2 - SE and PPM a Match Made in Heaven
Keynote 2 - SE and PPM a Match Made in HeavenKeynote 2 - SE and PPM a Match Made in Heaven
Keynote 2 - SE and PPM a Match Made in Heaven
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class Workshop
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Scrum lifecycle for Enterprise IT
Scrum lifecycle for Enterprise ITScrum lifecycle for Enterprise IT
Scrum lifecycle for Enterprise IT
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 

Similar to Establishing the performance measurement baseline (pmi northern utah)(v1)

Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Glen Alleman
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineGlen Alleman
 
Defining The Project
Defining The ProjectDefining The Project
Defining The ProjectEarl Tongol
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
Observe, Orient, Design, Act - OODA and Project Management
Observe, Orient, Design, Act - OODA and Project ManagementObserve, Orient, Design, Act - OODA and Project Management
Observe, Orient, Design, Act - OODA and Project Managementstatelibaz
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based PlanningGlen Alleman
 
Project Charter V 2.0Project CharterProjec.docx
Project Charter V 2.0Project CharterProjec.docxProject Charter V 2.0Project CharterProjec.docx
Project Charter V 2.0Project CharterProjec.docxstilliegeorgiana
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning Glen Alleman
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentationGlen Alleman
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure CycleGlen Alleman
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 secondsGlen Alleman
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based PlanningGlen Alleman
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter
 

Similar to Establishing the performance measurement baseline (pmi northern utah)(v1) (20)

Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
Defining The Project
Defining The ProjectDefining The Project
Defining The Project
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
Observe, Orient, Design, Act - OODA and Project Management
Observe, Orient, Design, Act - OODA and Project ManagementObserve, Orient, Design, Act - OODA and Project Management
Observe, Orient, Design, Act - OODA and Project Management
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based Planning
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
Project Charter V 2.0Project CharterProjec.docx
Project Charter V 2.0Project CharterProjec.docxProject Charter V 2.0Project CharterProjec.docx
Project Charter V 2.0Project CharterProjec.docx
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentation
 
EAC-ETCETERA
EAC-ETCETERAEAC-ETCETERA
EAC-ETCETERA
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based Planning
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)Glen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 

Recently uploaded

Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 

Recently uploaded (20)

Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 

Establishing the performance measurement baseline (pmi northern utah)(v1)

  • 1. ESTABLISHING THE PERFORMANCE MEASUREMENT BASELINE (PMB) Glen B. Alleman Niwotridge Consulting 1/40 The Performance Measurement Baseline is a time–phased schedule of all the work to be performed, the budgeted cost for this work, and the organizational elements that produce the deliverables from this work.
  • 2. The Performance Measurement Baseline is really 3 baselines – Technical , Schedule, and Cost. 2/40 5 Perform Functional Analysis Technical Baseline Schedule Baseline Cost Baseline Determine Scope and Approach Develop Technical Logic Develop Technical Baseline Develop WBS Define Activities Estimate Time Durations Sequence Activities Finalize Schedule Identify Apportioned Milestones Determine Resource Requirements Prepare Cost Estimate Resource Load Schedule Approve PMB Finalize Apportioned Milestones Determine Funding Constraints Copyright © 2012, Niwot Ridge, LLC
  • 3. The core element of the Performance Measurement Baseline (PMB) … 3/40 6 …Is a collection of Work Packages, that define: ! The deliverables that fulfill the needed business capabilities, ! The estimated duration and work effort for each Work Package, ! The resources needed to produce these deliverables within the needed time period, and ! Any dependencies – internal or external – needed to start a Work Package. It’s the deliverables that the customer bought. These deliverables contain the Business Value of the project. Connecting the Deliverables with the needed capabilities is the basis of a credible project execution process – then we can answer Why we are doing something. Copyright © 2012, Niwot Ridge, LLC
  • 4. Glen B. Alleman Niwotridge Consulting 6 STEPS TO ESTABLISHING THE PERFORMANCE MEASUREMENT BASELINE 4/40 Building the Performance Measurement Baseline requires six straightforward steps. Each must be performed. Each is critical. Each cannot be skipped.
  • 5. 5/40 Never tell people how to do things. Tell them what needs to be done and they will surprise you with their ingenuity. – Gen. George Patton I need the capability to disengage from offense activities and move a brigade of 3,000 to 5,000 troops 100 miles in ten hours, and arrive at Bastogne Holland before General Rommel does to rescue the 101st Airborne Division Capabilities-based planning specifies the outcome but does not specify how to do that cause that outcome to appear. Action Outcome Implement Strategy Ensure Capabilities Prioritize Problems And Solutions Identify Redundancies Deliver Solutions Copyright © 2012, Niwot Ridge, LLC
  • 6. Decompose the Project Scope into a product based Work Breakdown Structure (WBS), then further into Work Packages describing the production of all deliverables traceable to the requirements Decompose Scope into Work Packages Assign Responsibility to Work Packages (the groupings of deliverables) for the named owner accountable for the management of resource allocation and cost baseline and technical delivery Assign Responsibility for Deliverables Arrange the Work Packages in a well formed network with defined deliverables, milestones, internal and external dependencies, appropriate schedule and cost margin. Arrange Work Packages in Logical Order Develop a Time–Phased Budgeted Cost for Work Scheduled (BCWS) from labor and material costs in each Work Package and the Project as a whole. Assure proper resource allocations can be met and budget profiles match expectations of the project sponsor Develop BCWS for Work Packages Assign object Measure of Performance (MOP) and Measures of Effectiveness (MOE) for each Work Package and summarize these for the Project as a whole Assign WP Measures of Performance Build a time–phased network of schedule activities describing the work to be performed, the budgeted cost for this work, the organizational elements that produce the deliverables, and the performance measures showing this work is proceeding according to plan. Establish the Performance Measurement Baseline A Baselined Schedule that Creates the Services or Products to Meet The Requirements 3.0 3.1 3.2 3.3 3.4 3.5 Establish a Performance Measurement Baseline (PMB) used to forecast Work Package and Project ongoing and completion cost and schedule metrics Set 3.6 Performance Measurement Baseline 7 6/437 Copyright © 2012, Niwot Ridge, LLC
  • 7. Glen B. Alleman Niwotridge Consulting 3.1 DECOMPOSE THE 7/40 PROJECT SCOPE INTO WORK PACKAGES EACH WITH A SINGLE DELIVERABLE Starting with the Business Requirements, the Work Breakdown Structure (WBS) guides the development of the Work Packages.
  • 8. Business Capabilities, WBS, and Work Packages are connected to define what “Done” look like. 8/40 8 There is likely no factor that would contribute more to the success of any project than having a good and complete definition of the project's scope of work ‒ Quentin Fleming and Joel Koppelman, Earned Value Project Management Business Capability Process Invoices for Top Tier Suppliers 1st Level Electronic Invoice Submittal 1st Level Routing to Payables Department 2nd Level Payables Account Verification 2nd Level Payment Scheduling 2nd Level Material receipt verification 2nd Level “On hand” balance Updates Copyright © 2012, Niwot Ridge, LLC
  • 9. What does a good WBS NOT look like? 9/40 10 The whole notion of spending time building the WBS may seen odd. How hard can this be? It turns out of course that any definition of “done” can be traced back to the definitions of “what are we providing to the customer in terms of deliverables?” That’s the contents of the WBS. ! It’s not a laundry list of work to be done. ! It’s not a functional decomposition. ! It’s not a direct map of the requirements. ! It’s not a reflection of the underlying software partitioning. ! It’s not the first structure we might think of, it takes several iterations to get it right. Copyright © 2012, Niwot Ridge, LLC
  • 10. Connect the WBS to Work Packages, then define the Tasks for the Deliverables to produce Value. 10/40 12 The WBS is derived from the breakdown of the business capabilities and their stated requirements. From this WBS Work Packages are defined with their deliverables. The tasks that produce these deliverables are not explicitly stated in the Performance Measurement Baseline, but rather are held by the Work Package Manager. Physical percent complete performance is measured through apportioned milestones or a 0%/ 100% outcome for the Work Package Business Need Process Invoices for Top Tier Suppliers 1st Level Electronic Invoice Submittal 1st Level Routing to Payables Department 2nd Level Payables Account Verification 2nd Level Payment Scheduling 2nd Level Material receipt verification 2nd Level “On hand” balance Updates Deliverables defined in WP Copyright © 2012, Niwot Ridge, LLC
  • 11. Steps in Building the Work Packages. 11/40 13 ! Step 1 – define what is going to be delivered to produce business value ! One Deliverable produced within a Work Package ! Try not to have more than one deliverable per Work Package ! Step 2 – define the effort and duration along with the confidence levels ! Only effort and total duration ! Level of confidence for effort and duration Copyright © 2012, Niwot Ridge, LLC
  • 12. Naming Work Packages may seem simple, but it’s not What’s in a Name? Juliet (Romeo and Juliet II, ii 1-2) 12/40 18 ! Turns out there is a lot in a name ! The name should convey not only the work activities but also the delivered result of these activities ! There is a powerful result from this effort ! The project plan and the list of Work Packages is the concise statement of the work for the project – all held in a single place – the Project Plan Adjective Verb Noun Verb Demonstrates Maturity A step in the process End Item Final Status Preliminary Design Processes Complete Preliminary design of transaction processes complete The Bambino and Iron Horse Famous names that carried meaning to the reader Copyright © 2012, Niwot Ridge, LLC
  • 13. The Basis of Estimate (BOE) must be recorded, reviewed and approved. 13/40 20 ! A short description of how we got to the estimate of effort and the duration of the work ! I’ve done this before ! I asked someone who has done this before ! I ran an experiment to determine how long it would take ! I took a guess and multiplied it by 2 Remember we’re filling out worksheets for the Work Packages. No project management tools. Resist skipping to the end, until we have some notion of the total effort and duration. Committing too soon is just as bad as committing too late Copyright © 2012, Niwot Ridge, LLC
  • 14. Completion Criteria for each Work Packages is used to measure physical progress to Plan. 14/40 21 ! The completion criteria for the Work Package are the Exit Criteria describing the Work Package’s 100% complete measures. ! There is no “partial” completion of the Work Package, no “almost done.” ! The deliverable may be partially complete, but the Work Package is 0%/100% complete. ! Either we are done or we are not done – no partial done allowed. Copyright © 2012, Niwot Ridge, LLC
  • 15. Glen B. Alleman Niwotridge Consulting 3.2 ASSIGN RESPONSIBILITIES 15/40 Identify the single person accountable for the Work Package. This person is accountable for the duration, effort, and resource requirements for the Work Package.
  • 16. Responsibilities – Actually Accountability for the Work Package is written and visible to everyone. 16/40 22 ! Each Work Package has one and only one person Accountable for the successful delivery of the Work Package ! Put that person’s name on the Work Package ! Build a Responsibility Assignment Matrix (RAM) from the HR files for the project team ! Naming the person is a start ! It’s better to start what this person does and how they contribute to the project Copyright © 2012, Niwot Ridge, LLC
  • 17. Assign accountability for each component of the Work Package. 17/40 23 ! Each Work Package has a single owner who is accountable for: ! Defining the deliverables ! Assigning resources ! Balancing the resource usage ! Defining the Earned Value measurement criteria ! Identifying any apportioned milestones ! Reporting physical percent complete ! Name this person in the Work Package and the Master Schedule Copyright © 2012, Niwot Ridge, LLC
  • 18. Glen B. Alleman Niwotridge Consulting 3.3 ARRANGE WORK 18/40 PACKAGES WITHIN EACH WORKSTREAM Arranging the Work Packages in a logical network within each work stream starts with grouping the Work Packages into “bundles” of business value that are recognizable by the customer.
  • 19. Identify the Predecessors and Successors between Work Packages to sequence the work effort. 19/40 24 ! Give some thought about the sequence of the Work Packages ! What deliverables come first? ! What deliverables come next? ! The reason for this should be obvious ! Use a Work Authorization (WA) processes to keep the sequence of work intact Lay out the Work Packages on the wall. Move then around to see how they flow. Stand back is see if the arrangement actually makes any sense in terms of the flow of work and the production of deliverables Copyright © 2012, Niwot Ridge, LLC
  • 20. Arrange the Work Packages in the sequence that ensures value is being produced along the way. 20/40 25 Copyright © 2012, Niwot Ridge, LLC
  • 21. “Arranging” the Work Packages Is An Iterative And Incremental Process In this example, the Work Package Managers collectively come to an agreement on how the sequence of how the work will be performed. The result is a collective ownership of the outcome. This ownership comes from the collective development of the project plan. This process is a Product Development Kaizen (PDK) 21/40 "Any intelligent fool can make things bigger, more complex, and more violent. It takes a touch of genius—and a lot of courage—to move in the opposite direction." ~Albert Einstein Copyright © 2012, Niwot Ridge, LLC
  • 22. Start with a “notional” arrangement of the “Bundles” of work within a Workstream 22/40 27 ! WPs should have No intermediate connections 7w 7w 5w 5w 1w 3w 3w 3w 2w 7w 5w ! The first approach is to have long running WPs with negative or positive lags to maintain sequencing ! A better approach is to break the WP into separate deliverables and sequence Finish to Start Copyright © 2012, Niwot Ridge, LLC
  • 23. Glen B. Alleman Niwotridge Consulting 3.4 DEVELOP THE BUDGET FOR THE WORK SCHEDULED IN EACH WORKSTREAM 23/40 Using the individual Work Package cost spreads, the project or project budget spreads are developed to match the available resources.
  • 24. Develop a time–phased budget from the network of Work Packages based on resource loads 24/40 28 Duration of the Work Package Budget Duration of the Work Package Budget Duration of the Work Package Budget Duration of the Work Package Budget Copyright © 2012, Niwot Ridge, LLC
  • 25. Glen B. Alleman Niwotridge Consulting 25/40 3.5 ASSIGN PERFORMANCE MEASURES The only programmatic performance measure of a Work Package is Physical Percent Complete (PPC). This can be defined in a variety of ways. But expended effort is NEVER the way to define progress.
  • 26. Identify objective measures of performance for each Work Package 26/40 31 ! Define the Planned Value for each Work Package completion or apportioned milestone within a Work Package ! Only Physical Percent Complete should be used to measure progress – no “opinions” of progress ! Answer the question ! How are we going to recognize that progress is being made ! The passage of time and consumption of resources is NEVER a measure of progress Copyright © 2012, Niwot Ridge, LLC
  • 27. Glen B. Alleman Niwotridge Consulting 3.6 SET PERFORMANCE BASELINE 27/40 With the Work Packages sequenced, labor spreads assigned and balanced, deliverables defined, and performance measures established, it's time to baseline the plan.
  • 28. Baseline the schedule to establish the planned budget spreads for each Work Package 28/40 32 ! Baselining the Performance Measurement Baseline is the first step in successfully of Executing the project plan ! Without the baseline and the rigorous change control over this baseline, the needed credible performance predictions will be not possible There are two phases of any complex project: Too early to tell and too late to stop ‒ Mr. Blaise Durante, Senior Executive Service, Deputy Assistant Secretary for Acquisition Integration, Office of the Assistant Secretary of the Air Force for Acquisition, Washington, D.C. Copyright © 2012, Niwot Ridge, LLC
  • 29. Glen B. Alleman Niwotridge Consulting 29/40 BUILDING THE PROJECT SCHEDULE FROM THE BASELINE WORK PACKAGES With the baselined sequence of Work Packages, the detailed execution schedule can be started. This is an iterative and incremental process that balances the resources against needed business capabilities.
  • 30. Assembling the Work Packages into credible project schedule, starting with 30/40 ! Total Work Package duration ! Total Work Package work effort ! Start dates aligned with the project start date defined in the Project menu ! The result is a Gantt–style picture of the flow of Work Package value Henry Laurence Gantt, A.B., M.E, 1861–1919 33 Copyright © 2012, Niwot Ridge, LLC
  • 31. Sequencing the Work Packages starts with finding the best value flow for the work effort 31/40 34 ! Confirm the Total Effort and Total Duration of each Work Package represents the agreed on information captured from the team ! One of two approaches comes next: ! Sequence the individual WP’s into a logical network – then assign resources ! Assign resources – then sequence the WP’s into a logical network Copyright © 2012, Niwot Ridge, LLC
  • 32. Project maturity flow for work streams defines in the increasing maturity of the deliverables 32/40 35 Demo conversion process, member reconciliation Shared group matrix reports and interfaces Shared member crosswalk and members to Facets Accumulators of converted members Status Mock and trigger conversions Data in TibMarts for EVIR Member & Employer Portal include converted members Members termed to legacy Copyright © 2012, Niwot Ridge, LLC
  • 33. Glen B. Alleman Niwotridge Consulting 33/40 MAKING THE SCHEDULE CREDIBLE A credible schedule cannot be just a list of activities. It must be an accurate model of the project strategy and execution that can be analyzed, assessed, and used to answer risk based questions.
  • 34. Analyzing and assessing the network of Work Packages to assess credibility ! Critical Path ! Accuracy ! Integration ! Realism ! Performance ! Variances ! Forecasting ! What–if’s ! Risk ! Resources 34/40 I Que Es La Veritat? = What is Truth? Over the portal of the "Sagrada Familia" church in Barcelona, Spain 36 Copyright © 2012, Niwot Ridge, LLC
  • 35. Risk Management Process is a starting point for a credible Performance Measurement Baseline 35/40 37 “Risk Analysis Techniques, Schedule, Cost and Other Aspects, INCOSE Heartland Chapter October 24, 2001, Futon Corporation Copyright © 2012, Niwot Ridge, LLC
  • 36. Cost, Schedule and Technical Risk Model are inseparable – anything else is a Ponzi Scheme 36/40 39 Cost, Schedule, Technical Model† WBS Task 100 Task 101 Task 102 Task 103 Task 104 Task 105 Task 106 Probability Density Function † This is a Key concept. This is the part of the technique that integrates the cost and schedule risk impacts to provide the basis of a credible schedule. " Research the Project " Find Analogies " Ask Endless Questions " Analyze the Results " What can go wrong? " How likely is it to go wrong? " What is the cause? " What is the consequence? Monte Carlo Simulation Tool is Mandatory Cumulative Distribution Function 1.0 .8 .6 .4 .2 0 Days, Facilities, Parts, People Copyright © 2012, Niwot Ridge, LLC
  • 37. Assessment of the probabilistic duration is the basis of any credible schedule 37/40 41 ! Any path could be critical depending on the arrangement of the underlying task completion time probability distribution functions ! The independence or dependency of each task with others in the network, greatly influences the outcome of the total project duration ! Understanding this dependence is critical to assessing the credibility of the plan as well as the total completion time of that plan Prepare for the unknown by studying how others in the past have coped with the unforeseen and the unpredictable – General, George S. Patton Copyright © 2012, Niwot Ridge, LLC
  • 38. Glen B. Alleman Niwotridge Consulting 38/40 WRAPPING UP FOR TODAY THIS OF COURSE IS JUST THE TIP OF THE ICEBERG There is a tremendous amount of information in this Work Shop. No one single session can move it from here into practice. In the end programmatic control of a project is a practice not a procedure.
  • 39. In the end, its all about the schedule. We can find more money, but we can never find more time. ! A slipping the schedule is simply unacceptable in any project with business value ! “Attack” the schedule as soon as possible and never stop attacking ! Update schedules frequently, look at it daily ! Keep all the data “clean” and use it to make management decisions 39/40 How long are we willing to wait before we find out we’re late? Measure progress and update our forecast at ½ that time. More frequently for critical items. 42 Copyright © 2012, Niwot Ridge, LLC
  • 40.
  • 41. Glen B. Alleman Niwot Ridge Consulting 4347 Pebble Beach Drive Niwot, Colorado 80503 303.241.9633 glen.alleman@niwotridge.com Performance-Based Project Management® Integrated Master Plan Integrated Master Schedule Earned Value Management Systems Risk Management Proposal Support Services Copyright © 2012, Niwot Ridge, LLC 41/34