SlideShare a Scribd company logo
1 of 22
Download to read offline
LogiKal Projects – Performance Management Specialist
Managing Change on a Capital Programme
Back to Basics
LogiKal Projects – Performance Management SpecialistContext of Change
NEEDS why do we need to manage change?
ORGANISATION what are the organisation requirements?
STRATEGY what is the strategy for managing change?
CONTROL how do we control change?
OPPORTUNITIES how do we manage opportunities (+/-)?
RISKS what could possibly go wrong?
LogiKal Projects – Performance Management SpecialistMeet your CLIENT
This is Andrew. He is CEO of a business that NEEDS
capital investment to deliver for its customers.
Andrew’s performance is measured on the benefits he brings to customers.
Andrew knows roughly what benefits he has to deliver.
His regulator, or his customers and marketing team tell him.
He has established some initial requirements to deliver those benefits.
He now needs to know some options:
• What benefits (including discounted cash flow and the cost of borrowing money) will each bring?
• When can each be delivered?
• What investment is needed for each option before benefits accrue?
Andrew and his board approve funding to engage a PROGRAMME TEAM to
work up options.
LogiKal Projects – Performance Management SpecialistMeet your FINANCIAL DIRECTOR
Meet Janet.
Janet has to make sure the organisation does not
commit to spending what it does not have. And to
make sure any investment is worthwhile.
Janet knows she cannot approve funding for everything Andrew wants.
She has to justify to Andrew what investment the organisation can make.
Andrew’s bonus is affected if he does not make performance targets.
But if his organisation goes bust then he is out of a job. So he listens to Janet.
He needs to consider changes to requirements that affect the baseline.
Janet needs to see the year-on-year effect of each change to requirements.
This is because her customers can only supply so much funding per year.
LogiKal Projects – Performance Management SpecialistMeet your PROGRAMME DIRECTOR
Here’s Beth.
Beth’s job is to turn Andrew’s requirements into
scope, time and cost. And if funding is approved,
manage delivery.
At the moment her programme has pretty much finalised an option.
She even has a Performance Measurement Baseline for the preferred option.
Requirements, Scope, Schedule and Cost are linked by common WBS.
But her programme has not yet got funding.
Beth’s organisation’s is planning investment for the next 10 years.
Janet has told Andrew the programme may not be affordable.
Beth needs her delivery team to sign on to changes to the baseline.
Beth needs a controls ORGANISATION to help.
LogiKal Projects – Performance Management SpecialistMeet your CONTROLS TEAM
Charles’s job is to manage change on the programme. He knows each change
has to have scope, cost and schedule evaluation. He has to tell Beth the
effect of each change so that FD can be assured the programme is
affordable. He is the CHANGE MANAGER.
Davinder’s role is to work with the delivery teams to establish the schedule
effect of any change to requirements. We normally call him the PLANNER. He
knows how important it is to use the WBS and code the schedule carefully to
place each activity in the right planning package.
Faisal knows a lot about data. He makes sure all the reporting sources are
complete and accurate. He is ace at interpreting the data and helping
delivery teams and Beth understand where the project is. He integrates the
cost of each change with the schedule. He is REPORTING MANAGER.
Emma has to co-ordinate tracking RISKS and OPPORTUNITIES to the planned
spend profile. She works with the delivery teams to surface those. If risks are
properly understood, the programme will get FUNDING for them. She is the
RISK MANAGER.
LogiKal Projects – Performance Management SpecialistYour Programe Controls Manager
Grant has been around a long time. He can evaluate the direct cost of each
change. But he doesn’t really work for the CONTROLS team – he reports to
the commercial director. He often has to produce an estimate before there is
a WBS. But without the schedule he can’t estimate the effect of INFLATION.
Helen values people, process and technology. She has struck a deal with the
commercial director, where Davinder and Ed will work closely together.
Davinder doesn’t want to cost load the schedule, because it’s a lot of work,
and cost isn’t his bag. But Helen knows Faisal can help.
Ingrid is one of the delivery managers. She has a PLANNER and COST
ENGINEER to help manage schedule and cost on her sub-programme. But
she relies on Helen, Davinder and Faisal to pull everything together and tell
her where she is.
And some other players…
LogiKal Projects – Performance Management SpecialistThe ORGANISATION
Charles has quite a job to
get all these people on
the same page. He needs
a STRATEGY for
considering change.
Fortunately, his Programme
Management Office have established
guidelines for each programme to work
within.
LogiKal Projects – Performance Management SpecialistThe STRATEGY for Change
Programme Management
Direct Costs, including Design and Delivery
Risk
Estimating Uncertainty
Indexation
Change Control on a Capital Programme is there to manage budgets and value for money.
Before expenditure is approved, most Clients require a programme to seek ‘Sanction’ from
the executive board.
The following funds are usually separately treated within an expenditure Sanction for a set of
defined benefits (and therefore scope – at least outline scope)
INCLUDED IN PERFORMANCE MEASUREMENT BASELINE (PMB) AND
PROGRAMME HAS AUTHORITY TO MANAGE WITHIN THIS LIMIT
SUBJECT TO PROGRAMME BOARD AVAILABLE TO DRAW DOWN
ONLY AVAILABLE FOR PROGRAMME TO DRAW DOWN BASED ON
AUTHORITY OF THE EXECUTIVE BOARD
This gives rise to the so called ‘Delegation of Authority’
Executive Board Programme Project Managers
LogiKal Projects – Performance Management SpecialistThe STRATEGY for Change
LogiKal Projects – Performance Management SpecialistCONTROLS – the Change Process
Step Change Board Chg
Manager
Estimator
Cost Mgr
Controls
Manager
Planner Reporting
Mgr
Identify the change and
log the request
Evaluate the scope, cost
and schedule effect
Identify level of approval
needed
Approve/reject/recycle
the change
Implement the change
to the baseline
Change within 1 project not affecting programme EFC – PM
Chg>1 project OR affecting EFC but within Sanction minus Uncertainty/Indexation OR RISK Drawdown – Programme Manager
Change affecting EFC outside Sanction OR converting Uncertainty/Indexation to Risk or PMB – Executive Board
LogiKal Projects – Performance Management SpecialistA Scenario - 1
Reduce expenditure over next 3 years, but maintain benefit delivery date at now+6 years.
Three opportunities have been identified by VALUE ENGINEERING to deliver similar benefits for different scope.
Some activities can be deferred out of the next 3 years, but this will increase indexation and estimated final cost (EFC), and
delay the start of implementation.
A different implementation strategy has been identified to save time in years 4-6 but it will be more expensive and more
risky.
Charles logs these as 5 separate changes, because Janet, the
FD, does not know yet how much this programme has to save.
She needs all programmes to do this exercise, and may not
need to take all 5 changes.
If she could – she would keep current delivery strategy – any
change to the EFC and spend profile may need a revisit to the
business case for each programme.
LogiKal Projects – Performance Management SpecialistA Scenario - 2
Schedule Impact Analysis
The Value Engineering opportunities do not change activity timings – only cost, in this case.
Davinder produces a ‘what-if’ schedule (or reflection in P6, if appropriate) for:
a) – the deferral of some activities to start after year 3
b) – the revised implementation strategy
After much ‘to-ing and fro-ing’ with the delivery teams he has a solution that delivers benefits on time.
Some activities are no longer required – Davinder ‘retires’
these so that activity ID duplicates are not required.
Each activity is ‘weighted’ for input into the cost control
solution. There are new activities which must be weighted, and
weights from old activities should be redistributed.
Davinder passes the schedule output to Faisal, the reporting
manager for integration with cost.
LogiKal Projects – Performance Management SpecialistA Scenario - 3
Cost Impact Analysis
Grant produces a revision of the estimate.
Each change for value engineering is cross-referenced to:
• An ‘Omit’ or negative quantity for the scope item that is removed
• An ‘Add’ or positive quantity for the new scope item
The change for revised implementation strategy contains:
• A ‘cross the board’ increase (‘Add’) in implementation resources
• An increase (‘Add’) in temporary material costs
Grant can identify each item in the estimate to a change –
both add and omit.
But he cannot evaluate indexation because he does not know
the timing of each of the activities that relate to the adds and
omits.
And the breakdown of his estimate items does not match
activities in the schedule.
LogiKal Projects – Performance Management SpecialistA Scenario - 4
Integration and Effect of Indexation
Cost of Omits per WBS
element
Item 1 £ 5000
Item 2 £ 65000
Item 3 £ 30000
TOTAL £100000
Original Activities in WBS Element
Activity a 20d – weight 20000
Activity b 15d – weight 15000
Activity c 30d – weight 30000
Activity d 35d – weight 35000
Total 100d
• The WBS element must have a reasonably uniform
rate of production or cost per day
• Do not mix design and delivery WBS elements into
one ‘group’
• OK if you do not need to track the time-phased
effect of each change, just the aggregate
Original Activities in WBS Element
Activity a 20d – Mar 22
Activity b 15d – Apr 22
Activity c 30d – Jun-Jul 22
Activity d 35d – Aug-Sep 23
• Index for each period gives indexation cost for WBS
element, over time
• Need to divide activities into periods – normally
years
• Ideally needs a query or a database
Periods
Period 1 £ 5000
Period 2 £ 7500
Period 3 £ 15000
Etc
Faisal can evaluate weighting for each activity, and indexation for
WBS element.
This can be integrated into the cost management solution.
Time-phased effect of each change really requires a database or
specialist solution
LogiKal Projects – Performance Management SpecialistOPPORTUNITIES and RISKS
LogiKal Projects – Performance Management SpecialistGOTCHA - 1
Managing the stakeholders
• Make sure all the providers of data – planner, estimator, cost manager etc – know the
timetable for each change.
• Do not bring anything to change board which has incomplete data.
• Keep an up to date change log and action list and bring that to change board.
• Make sure all the approvers have verbally confirmed ‘no objection’ or ‘discussion
required’ before change board.
• Remember that after approval the change still needs to be implemented – some
stakeholders will look to get ‘implementation’ actions as ‘approval’ actions to ensure
‘proper’ implementation, so…
• Be prompt and efficient with implementation actions and make sure changes approved
at one board are implemented by the next.
LogiKal Projects – Performance Management SpecialistGOTCHA - 2
‘Change’ which is not really change
• A change is an identifiable difference between a set of configured items:
• Benefit dates
• Estimate versions
• Requirements versions
• A change affects BASELINE documents – it probably also affects FINAL COST and
PHASING, but…
• A change which asks for an increase in cost without corresponding scope change is NOT
a change – it is a cost variance and the baseline should not be changed.
• A change which alters schedule dates due to productivity variations is not change – it is
a schedule variance and the baseline should not be changed.
LogiKal Projects – Performance Management SpecialistGOTCHA - 3
Territory and structure disputes between finance, commercial and controls
• Often the estimator will report to the commercial function – not controls.
• Mostly the estimate is in a different (sometimes very different) structure to the
schedule.
• Keep the Work Breakdown Structure as the governing structure for estimate and
schedule.
• Map estimate costs for each WBS element to the group of schedule activities for each
WBS element to give a weighting.
• Remember that finance colleagues will have data requirements.
• Ensure that there is only one source of truth for costs forecast and change – preferably
the cost management solution – not the schedule, or finance system or ‘skunk works’
spreadsheets. The forecast from the cost management solution should feed the
financial system. Make sure all data, including change data, satisfies all stakeholders.
LogiKal Projects – Performance Management SpecialistGOTCHA - 4
Change on change without approvals
• Change 100 affects scope items A, B, C: C = 100m3 of concrete, with change C adding
10m3 @£100/m3
• Change 101 affects scope items C, D, E: C is changed from grade C30 to grade C40
concrete (adding £5/m3)
• Change 102 affects scope items C, F, G: C has different finish adding £2/m3
• How to evaluate the effect on both changes on C for approval purposes, whilst
attributing a cost to each change, bearing in mind change may not be approved?
• Answer 1
• Evaluate from a fixed ‘control budget’ – change 100= £1000, change 101= £500,
change 102= £200
• Answer 2
• Evaluate in the order they are raised – change 100 = £1000, change 101 = £550,
change 102 = £220
LogiKal Projects – Performance Management SpecialistGOTCHA - 5
Finance want to see the time phased effect of each potential change, including indexation
• This can be a lot of work, even for a medium sized change.
• Effect of each change has to be translated from estimate items to activities to time-
periods (normally months or 4 weekly intervals).
• Without prompt change approvals, or a solution that integrates estimating, schedule,
cost control and change, tracking change on change (especially over time) becomes
very difficult and time-consuming.
• Approval order may well make a difference to the final amounts depending on how
change is evaluated for approval.
• If this is required, use a specialist solution or….
• Be prepared for a lot of data manipulation using expert excel users – more than one!
LogiKal Projects – Performance Management SpecialistRECAP
NEEDS
ORGANISATION
STRATEGY
CONTROL
OPPORTUNITIES
RISKS
Customers/shareholders and/or regulatory requirements drive
the CEOs investment decisions – and priorities and needs
change often
Programmes have to be delivered by people – in a structure or
operating model
Managing investment needs a strategy for dealing with change
– normally within a delegation of authority
Before change is approved it must be evaluated for its impact
but try to use a simple evaluation process
Use the change control process to manage opportunities or
risks into the performance measurement baseline
Watch out for: managing the stakeholders, change which is not change, territory disputes between
finance, commercial and controls, change on change, tracking the time-phased effect of each change

More Related Content

What's hot

Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...Project Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Project Controls Expo
 
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo
 
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo
 
Enterprise Projects Performance: Going Beyond Project Controls by "Mark White...
Enterprise Projects Performance: Going Beyond Project Controls by "Mark White...Enterprise Projects Performance: Going Beyond Project Controls by "Mark White...
Enterprise Projects Performance: Going Beyond Project Controls by "Mark White...Project Controls Expo
 
Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...
Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...
Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...Project Controls Expo
 
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleSession W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleProject Controls Expo
 
Detailed project reports
Detailed project reportsDetailed project reports
Detailed project reportsAKANSHA GURELE
 
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Project Controls Expo
 
Detailed project report
Detailed project reportDetailed project report
Detailed project reportSelva Prakash
 
Avoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAvoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAconex
 
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesaAconex
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedEnergy Construction Forum
 

What's hot (20)

Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
 
M3 - An overview of High Speed 2
M3 - An overview of High Speed 2M3 - An overview of High Speed 2
M3 - An overview of High Speed 2
 
Where did it go wrong?
Where did it go wrong?Where did it go wrong?
Where did it go wrong?
 
PAC Webinar - CAPEX - Dec 7 2010
PAC Webinar - CAPEX - Dec 7 2010PAC Webinar - CAPEX - Dec 7 2010
PAC Webinar - CAPEX - Dec 7 2010
 
Enterprise Projects Performance: Going Beyond Project Controls by "Mark White...
Enterprise Projects Performance: Going Beyond Project Controls by "Mark White...Enterprise Projects Performance: Going Beyond Project Controls by "Mark White...
Enterprise Projects Performance: Going Beyond Project Controls by "Mark White...
 
Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...
Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...
Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...
 
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleSession W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
 
Detailed project reports
Detailed project reportsDetailed project reports
Detailed project reports
 
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
 
Detailed project report
Detailed project reportDetailed project report
Detailed project report
 
LI, GUANGYA
LI,  GUANGYALI,  GUANGYA
LI, GUANGYA
 
Avoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAvoid the risk and streamline your project controls
Avoid the risk and streamline your project controls
 
Project appraisal
Project appraisalProject appraisal
Project appraisal
 
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
 

Similar to Managing Changes on a Capital Programme by "Iain Cameron - Technical Director for LogiKal Projects, UK" at Project Controls Expo 2017, Arsenal Stadium, London

Value destruction: why most projects fail to realise the benefits used to mak...
Value destruction: why most projects fail to realise the benefits used to mak...Value destruction: why most projects fail to realise the benefits used to mak...
Value destruction: why most projects fail to realise the benefits used to mak...Association for Project Management
 
The power of TOP Value Equation™
The power of TOP Value Equation™The power of TOP Value Equation™
The power of TOP Value Equation™John D'Arcy
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Benefit Realisation - a whitepaper
Benefit Realisation - a whitepaperBenefit Realisation - a whitepaper
Benefit Realisation - a whitepaperNewport Consulting
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure CycleGlen Alleman
 
Program management scope management
Program management   scope managementProgram management   scope management
Program management scope managementJulen Mohanty
 
1010 cd overview light
1010 cd overview light1010 cd overview light
1010 cd overview lightAndrew Hudson
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 
New projectplandefinition1
New projectplandefinition1New projectplandefinition1
New projectplandefinition1Jonathan Joyce
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management ProjectMary Stevenson
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineGlen Alleman
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baselineguest9da059
 

Similar to Managing Changes on a Capital Programme by "Iain Cameron - Technical Director for LogiKal Projects, UK" at Project Controls Expo 2017, Arsenal Stadium, London (20)

Value destruction: why most projects fail to realise the benefits used to mak...
Value destruction: why most projects fail to realise the benefits used to mak...Value destruction: why most projects fail to realise the benefits used to mak...
Value destruction: why most projects fail to realise the benefits used to mak...
 
The power of TOP Value Equation™
The power of TOP Value Equation™The power of TOP Value Equation™
The power of TOP Value Equation™
 
Project Management Process
Project Management ProcessProject Management Process
Project Management Process
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Benefit Realisation - a whitepaper
Benefit Realisation - a whitepaperBenefit Realisation - a whitepaper
Benefit Realisation - a whitepaper
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Program management scope management
Program management   scope managementProgram management   scope management
Program management scope management
 
1010 cd overview light
1010 cd overview light1010 cd overview light
1010 cd overview light
 
Enabling success business_change
Enabling success business_changeEnabling success business_change
Enabling success business_change
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
New projectplandefinition1
New projectplandefinition1New projectplandefinition1
New projectplandefinition1
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 

More from Project Controls Expo

Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
 
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...Project Controls Expo
 
The Future of Project Controls: Improve project performance using Big Data by...
The Future of Project Controls: Improve project performance using Big Data by...The Future of Project Controls: Improve project performance using Big Data by...
The Future of Project Controls: Improve project performance using Big Data by...Project Controls Expo
 
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...The impact of Risk on the Five Immutable Principles of Project Success by "Ri...
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...Project Controls Expo
 
Integration is key to successful Project Controls by "David Hurren" at at Pro...
Integration is key to successful Project Controls by "David Hurren" at at Pro...Integration is key to successful Project Controls by "David Hurren" at at Pro...
Integration is key to successful Project Controls by "David Hurren" at at Pro...Project Controls Expo
 
Optimising Portfolios and Programmes in an ever changing world by "Matthew Wa...
Optimising Portfolios and Programmes in an ever changing world by "Matthew Wa...Optimising Portfolios and Programmes in an ever changing world by "Matthew Wa...
Optimising Portfolios and Programmes in an ever changing world by "Matthew Wa...Project Controls Expo
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Project Controls Expo
 

More from Project Controls Expo (20)

Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
 
The Future of Project Controls: Improve project performance using Big Data by...
The Future of Project Controls: Improve project performance using Big Data by...The Future of Project Controls: Improve project performance using Big Data by...
The Future of Project Controls: Improve project performance using Big Data by...
 
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...The impact of Risk on the Five Immutable Principles of Project Success by "Ri...
The impact of Risk on the Five Immutable Principles of Project Success by "Ri...
 
Integration is key to successful Project Controls by "David Hurren" at at Pro...
Integration is key to successful Project Controls by "David Hurren" at at Pro...Integration is key to successful Project Controls by "David Hurren" at at Pro...
Integration is key to successful Project Controls by "David Hurren" at at Pro...
 
Optimising Portfolios and Programmes in an ever changing world by "Matthew Wa...
Optimising Portfolios and Programmes in an ever changing world by "Matthew Wa...Optimising Portfolios and Programmes in an ever changing world by "Matthew Wa...
Optimising Portfolios and Programmes in an ever changing world by "Matthew Wa...
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
 

Recently uploaded

Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptssuser319dad
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptxBasil Achie
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringSebastiano Panichella
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )Pooja Nehwal
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfhenrik385807
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxFamilyWorshipCenterD
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)Basil Achie
 

Recently uploaded (20)

Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.ppt
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software Engineering
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
 

Managing Changes on a Capital Programme by "Iain Cameron - Technical Director for LogiKal Projects, UK" at Project Controls Expo 2017, Arsenal Stadium, London

  • 1. LogiKal Projects – Performance Management Specialist Managing Change on a Capital Programme Back to Basics
  • 2. LogiKal Projects – Performance Management SpecialistContext of Change NEEDS why do we need to manage change? ORGANISATION what are the organisation requirements? STRATEGY what is the strategy for managing change? CONTROL how do we control change? OPPORTUNITIES how do we manage opportunities (+/-)? RISKS what could possibly go wrong?
  • 3. LogiKal Projects – Performance Management SpecialistMeet your CLIENT This is Andrew. He is CEO of a business that NEEDS capital investment to deliver for its customers. Andrew’s performance is measured on the benefits he brings to customers. Andrew knows roughly what benefits he has to deliver. His regulator, or his customers and marketing team tell him. He has established some initial requirements to deliver those benefits. He now needs to know some options: • What benefits (including discounted cash flow and the cost of borrowing money) will each bring? • When can each be delivered? • What investment is needed for each option before benefits accrue? Andrew and his board approve funding to engage a PROGRAMME TEAM to work up options.
  • 4. LogiKal Projects – Performance Management SpecialistMeet your FINANCIAL DIRECTOR Meet Janet. Janet has to make sure the organisation does not commit to spending what it does not have. And to make sure any investment is worthwhile. Janet knows she cannot approve funding for everything Andrew wants. She has to justify to Andrew what investment the organisation can make. Andrew’s bonus is affected if he does not make performance targets. But if his organisation goes bust then he is out of a job. So he listens to Janet. He needs to consider changes to requirements that affect the baseline. Janet needs to see the year-on-year effect of each change to requirements. This is because her customers can only supply so much funding per year.
  • 5. LogiKal Projects – Performance Management SpecialistMeet your PROGRAMME DIRECTOR Here’s Beth. Beth’s job is to turn Andrew’s requirements into scope, time and cost. And if funding is approved, manage delivery. At the moment her programme has pretty much finalised an option. She even has a Performance Measurement Baseline for the preferred option. Requirements, Scope, Schedule and Cost are linked by common WBS. But her programme has not yet got funding. Beth’s organisation’s is planning investment for the next 10 years. Janet has told Andrew the programme may not be affordable. Beth needs her delivery team to sign on to changes to the baseline. Beth needs a controls ORGANISATION to help.
  • 6. LogiKal Projects – Performance Management SpecialistMeet your CONTROLS TEAM Charles’s job is to manage change on the programme. He knows each change has to have scope, cost and schedule evaluation. He has to tell Beth the effect of each change so that FD can be assured the programme is affordable. He is the CHANGE MANAGER. Davinder’s role is to work with the delivery teams to establish the schedule effect of any change to requirements. We normally call him the PLANNER. He knows how important it is to use the WBS and code the schedule carefully to place each activity in the right planning package. Faisal knows a lot about data. He makes sure all the reporting sources are complete and accurate. He is ace at interpreting the data and helping delivery teams and Beth understand where the project is. He integrates the cost of each change with the schedule. He is REPORTING MANAGER. Emma has to co-ordinate tracking RISKS and OPPORTUNITIES to the planned spend profile. She works with the delivery teams to surface those. If risks are properly understood, the programme will get FUNDING for them. She is the RISK MANAGER.
  • 7. LogiKal Projects – Performance Management SpecialistYour Programe Controls Manager Grant has been around a long time. He can evaluate the direct cost of each change. But he doesn’t really work for the CONTROLS team – he reports to the commercial director. He often has to produce an estimate before there is a WBS. But without the schedule he can’t estimate the effect of INFLATION. Helen values people, process and technology. She has struck a deal with the commercial director, where Davinder and Ed will work closely together. Davinder doesn’t want to cost load the schedule, because it’s a lot of work, and cost isn’t his bag. But Helen knows Faisal can help. Ingrid is one of the delivery managers. She has a PLANNER and COST ENGINEER to help manage schedule and cost on her sub-programme. But she relies on Helen, Davinder and Faisal to pull everything together and tell her where she is. And some other players…
  • 8. LogiKal Projects – Performance Management SpecialistThe ORGANISATION Charles has quite a job to get all these people on the same page. He needs a STRATEGY for considering change. Fortunately, his Programme Management Office have established guidelines for each programme to work within.
  • 9. LogiKal Projects – Performance Management SpecialistThe STRATEGY for Change Programme Management Direct Costs, including Design and Delivery Risk Estimating Uncertainty Indexation Change Control on a Capital Programme is there to manage budgets and value for money. Before expenditure is approved, most Clients require a programme to seek ‘Sanction’ from the executive board. The following funds are usually separately treated within an expenditure Sanction for a set of defined benefits (and therefore scope – at least outline scope) INCLUDED IN PERFORMANCE MEASUREMENT BASELINE (PMB) AND PROGRAMME HAS AUTHORITY TO MANAGE WITHIN THIS LIMIT SUBJECT TO PROGRAMME BOARD AVAILABLE TO DRAW DOWN ONLY AVAILABLE FOR PROGRAMME TO DRAW DOWN BASED ON AUTHORITY OF THE EXECUTIVE BOARD This gives rise to the so called ‘Delegation of Authority’ Executive Board Programme Project Managers
  • 10. LogiKal Projects – Performance Management SpecialistThe STRATEGY for Change
  • 11. LogiKal Projects – Performance Management SpecialistCONTROLS – the Change Process Step Change Board Chg Manager Estimator Cost Mgr Controls Manager Planner Reporting Mgr Identify the change and log the request Evaluate the scope, cost and schedule effect Identify level of approval needed Approve/reject/recycle the change Implement the change to the baseline Change within 1 project not affecting programme EFC – PM Chg>1 project OR affecting EFC but within Sanction minus Uncertainty/Indexation OR RISK Drawdown – Programme Manager Change affecting EFC outside Sanction OR converting Uncertainty/Indexation to Risk or PMB – Executive Board
  • 12. LogiKal Projects – Performance Management SpecialistA Scenario - 1 Reduce expenditure over next 3 years, but maintain benefit delivery date at now+6 years. Three opportunities have been identified by VALUE ENGINEERING to deliver similar benefits for different scope. Some activities can be deferred out of the next 3 years, but this will increase indexation and estimated final cost (EFC), and delay the start of implementation. A different implementation strategy has been identified to save time in years 4-6 but it will be more expensive and more risky. Charles logs these as 5 separate changes, because Janet, the FD, does not know yet how much this programme has to save. She needs all programmes to do this exercise, and may not need to take all 5 changes. If she could – she would keep current delivery strategy – any change to the EFC and spend profile may need a revisit to the business case for each programme.
  • 13. LogiKal Projects – Performance Management SpecialistA Scenario - 2 Schedule Impact Analysis The Value Engineering opportunities do not change activity timings – only cost, in this case. Davinder produces a ‘what-if’ schedule (or reflection in P6, if appropriate) for: a) – the deferral of some activities to start after year 3 b) – the revised implementation strategy After much ‘to-ing and fro-ing’ with the delivery teams he has a solution that delivers benefits on time. Some activities are no longer required – Davinder ‘retires’ these so that activity ID duplicates are not required. Each activity is ‘weighted’ for input into the cost control solution. There are new activities which must be weighted, and weights from old activities should be redistributed. Davinder passes the schedule output to Faisal, the reporting manager for integration with cost.
  • 14. LogiKal Projects – Performance Management SpecialistA Scenario - 3 Cost Impact Analysis Grant produces a revision of the estimate. Each change for value engineering is cross-referenced to: • An ‘Omit’ or negative quantity for the scope item that is removed • An ‘Add’ or positive quantity for the new scope item The change for revised implementation strategy contains: • A ‘cross the board’ increase (‘Add’) in implementation resources • An increase (‘Add’) in temporary material costs Grant can identify each item in the estimate to a change – both add and omit. But he cannot evaluate indexation because he does not know the timing of each of the activities that relate to the adds and omits. And the breakdown of his estimate items does not match activities in the schedule.
  • 15. LogiKal Projects – Performance Management SpecialistA Scenario - 4 Integration and Effect of Indexation Cost of Omits per WBS element Item 1 £ 5000 Item 2 £ 65000 Item 3 £ 30000 TOTAL £100000 Original Activities in WBS Element Activity a 20d – weight 20000 Activity b 15d – weight 15000 Activity c 30d – weight 30000 Activity d 35d – weight 35000 Total 100d • The WBS element must have a reasonably uniform rate of production or cost per day • Do not mix design and delivery WBS elements into one ‘group’ • OK if you do not need to track the time-phased effect of each change, just the aggregate Original Activities in WBS Element Activity a 20d – Mar 22 Activity b 15d – Apr 22 Activity c 30d – Jun-Jul 22 Activity d 35d – Aug-Sep 23 • Index for each period gives indexation cost for WBS element, over time • Need to divide activities into periods – normally years • Ideally needs a query or a database Periods Period 1 £ 5000 Period 2 £ 7500 Period 3 £ 15000 Etc Faisal can evaluate weighting for each activity, and indexation for WBS element. This can be integrated into the cost management solution. Time-phased effect of each change really requires a database or specialist solution
  • 16. LogiKal Projects – Performance Management SpecialistOPPORTUNITIES and RISKS
  • 17. LogiKal Projects – Performance Management SpecialistGOTCHA - 1 Managing the stakeholders • Make sure all the providers of data – planner, estimator, cost manager etc – know the timetable for each change. • Do not bring anything to change board which has incomplete data. • Keep an up to date change log and action list and bring that to change board. • Make sure all the approvers have verbally confirmed ‘no objection’ or ‘discussion required’ before change board. • Remember that after approval the change still needs to be implemented – some stakeholders will look to get ‘implementation’ actions as ‘approval’ actions to ensure ‘proper’ implementation, so… • Be prompt and efficient with implementation actions and make sure changes approved at one board are implemented by the next.
  • 18. LogiKal Projects – Performance Management SpecialistGOTCHA - 2 ‘Change’ which is not really change • A change is an identifiable difference between a set of configured items: • Benefit dates • Estimate versions • Requirements versions • A change affects BASELINE documents – it probably also affects FINAL COST and PHASING, but… • A change which asks for an increase in cost without corresponding scope change is NOT a change – it is a cost variance and the baseline should not be changed. • A change which alters schedule dates due to productivity variations is not change – it is a schedule variance and the baseline should not be changed.
  • 19. LogiKal Projects – Performance Management SpecialistGOTCHA - 3 Territory and structure disputes between finance, commercial and controls • Often the estimator will report to the commercial function – not controls. • Mostly the estimate is in a different (sometimes very different) structure to the schedule. • Keep the Work Breakdown Structure as the governing structure for estimate and schedule. • Map estimate costs for each WBS element to the group of schedule activities for each WBS element to give a weighting. • Remember that finance colleagues will have data requirements. • Ensure that there is only one source of truth for costs forecast and change – preferably the cost management solution – not the schedule, or finance system or ‘skunk works’ spreadsheets. The forecast from the cost management solution should feed the financial system. Make sure all data, including change data, satisfies all stakeholders.
  • 20. LogiKal Projects – Performance Management SpecialistGOTCHA - 4 Change on change without approvals • Change 100 affects scope items A, B, C: C = 100m3 of concrete, with change C adding 10m3 @£100/m3 • Change 101 affects scope items C, D, E: C is changed from grade C30 to grade C40 concrete (adding £5/m3) • Change 102 affects scope items C, F, G: C has different finish adding £2/m3 • How to evaluate the effect on both changes on C for approval purposes, whilst attributing a cost to each change, bearing in mind change may not be approved? • Answer 1 • Evaluate from a fixed ‘control budget’ – change 100= £1000, change 101= £500, change 102= £200 • Answer 2 • Evaluate in the order they are raised – change 100 = £1000, change 101 = £550, change 102 = £220
  • 21. LogiKal Projects – Performance Management SpecialistGOTCHA - 5 Finance want to see the time phased effect of each potential change, including indexation • This can be a lot of work, even for a medium sized change. • Effect of each change has to be translated from estimate items to activities to time- periods (normally months or 4 weekly intervals). • Without prompt change approvals, or a solution that integrates estimating, schedule, cost control and change, tracking change on change (especially over time) becomes very difficult and time-consuming. • Approval order may well make a difference to the final amounts depending on how change is evaluated for approval. • If this is required, use a specialist solution or…. • Be prepared for a lot of data manipulation using expert excel users – more than one!
  • 22. LogiKal Projects – Performance Management SpecialistRECAP NEEDS ORGANISATION STRATEGY CONTROL OPPORTUNITIES RISKS Customers/shareholders and/or regulatory requirements drive the CEOs investment decisions – and priorities and needs change often Programmes have to be delivered by people – in a structure or operating model Managing investment needs a strategy for dealing with change – normally within a delegation of authority Before change is approved it must be evaluated for its impact but try to use a simple evaluation process Use the change control process to manage opportunities or risks into the performance measurement baseline Watch out for: managing the stakeholders, change which is not change, territory disputes between finance, commercial and controls, change on change, tracking the time-phased effect of each change