SlideShare a Scribd company logo
1 of 2
Status
• Overall Phase 1
• April 7 – Department Of General Services (VA)
issued TCOs for all rail facilities good for a period of
60 days
• April 24 – MWAA concurrence with DTP’s
Declaration of Substantial Completions for Phase 1
on April 9 (after 15 day review)
• April 27 - WMATA and MWAA reach agreement on
work that must be completed in order for WMATA
to declare a Operational Readiness Date (ORD) -33
items
• ORD - when the project is turned over to
WMATA custody and control
• Late May projected date to achieve ORD
• April 28 – MWAA issues letter to Macerich for work
to proceed with pavilion connection
• May 1 – DPZ concurs that MWAA has complied with
the SE conditions for the station landscaping plans
• Wiehle garage – Complete
• Connector staff in the facility
• Record of Decision roadway improvements –minor
work remains
• West Falls Church rail yard:
• Sound Box Completed – Feb 2014
• Noise Study Completed – Final Report to be issued
• Phase 1 project budget - $ 2.906B
Follow On Activities
• Following ORD WMATA has up to 90 days for testing,
employee training, and emergency drills prior to
passenger service
• Tri-State Oversight Committee will review project for
safety certification
• Estimated to be a 60 day process concurrent with
WMATA’s up to 90 day period
• WMATA will provide weekly press updates on progress of
outstanding work
• Regional coordination for bus service and marketing
outreach ongoing
• www. silverlinemetro.com
• Punch List and Testing
1
6 May 2014
Status
• Phase 2 fully in design stage
• 60% and some 90% design packages received
• Issued for Construction packets – Starting Spring
2014
• Coordination ongoing
• Town of Herndon
• Adjacent Land Owners
• Project Partners
• Herndon and Innovation Center Station garages
• Fairfax County has committed to fund and
construct parking garages - Design ongoing
• Innovation Center Station Garage - Land use case
ongoing (June 2014)
• Herndon Garage - staff has developed a number of
concept designs (2232)
• Scheduled tracks completion of the garages to the
completion of Phase 2
• Status of Phase 2 Bid Packages:
• Packet A - rail Line, station, and systems (includes
Innovation Center Station) - Awarded
• Packet B - Maintenance Facility at Dulles Airport –
Technical Proposals received and under review
• Award – Summer 2014
• NTP – Summer 2014
• Completion Summer 2018
Budget/Schedule
• Cost Estimate: $3.093B
• Cost Estimate with value engineering , Packet A savings,
and garages funding outside the project: $2.6B
• Substantial Completion: Summer 2018
• Revenue Operations: Late 2018
Current Milestones – Past 30 Days
• TIFIA Application Approved
• MWAA intention to hold tolls on the Dulles Toll
Road at current rates through 2018 (as a result of
TIFIA financing)
• Design coordination ongoing
2
6 May 2014

More Related Content

What's hot

Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Fairfax County
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the BeltwayFairfax County
 
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement StudyFairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement StudyFairfax County
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes ExtensionFairfax County
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Fairfax County
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingFairfax County
 
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Fairfax County
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationFairfax County
 
Reston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsReston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsFairfax County
 
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County
 
Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Fairfax County
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Fairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Fairfax County
 
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016Fairfax County
 
Fairfax County Bicycle Master Plan
Fairfax County Bicycle Master PlanFairfax County Bicycle Master Plan
Fairfax County Bicycle Master PlanFairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateFairfax County
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Fairfax County
 
Citizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road WalkwayCitizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road WalkwayFairfax County
 

What's hot (19)

Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the Beltway
 
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement StudyFairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes Extension
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and Funding
 
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II Implementation
 
Reston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsReston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation Results
 
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
 
Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
 
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
 
Fairfax County Bicycle Master Plan
Fairfax County Bicycle Master PlanFairfax County Bicycle Master Plan
Fairfax County Bicycle Master Plan
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
 
Citizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road WalkwayCitizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road Walkway
 

Viewers also liked

Student Free Fare Program Update: April 19, 2016
Student Free Fare Program Update: April 19, 2016Student Free Fare Program Update: April 19, 2016
Student Free Fare Program Update: April 19, 2016Fairfax County
 
Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016   Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016 Fairfax County
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyFairfax County
 
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Fairfax County
 
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....Fairfax County
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare ProgramFairfax County
 
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016Fairfax County
 
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495Fairfax County
 
Reston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsReston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsFairfax County
 
North Kings Highway (VA 241) Intersection Improvements Study
North Kings Highway (VA 241) Intersection Improvements StudyNorth Kings Highway (VA 241) Intersection Improvements Study
North Kings Highway (VA 241) Intersection Improvements StudyFairfax County
 
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016Fairfax County
 
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Fairfax County
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilityFairfax County
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Fairfax County
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County
 
I-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the BeltwayI-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the BeltwayFairfax County
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesFairfax County
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Fairfax County
 

Viewers also liked (20)

Student Free Fare Program Update: April 19, 2016
Student Free Fare Program Update: April 19, 2016Student Free Fare Program Update: April 19, 2016
Student Free Fare Program Update: April 19, 2016
 
Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016   Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning Study
 
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
 
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare Program
 
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
 
Reston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsReston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost Allocations
 
North Kings Highway (VA 241) Intersection Improvements Study
North Kings Highway (VA 241) Intersection Improvements StudyNorth Kings Highway (VA 241) Intersection Improvements Study
North Kings Highway (VA 241) Intersection Improvements Study
 
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
 
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
 
I-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the BeltwayI-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the Beltway
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016
 

Similar to Silver Line Phase 1-Status Report: May 6, 2014

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Fairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Fairfax County
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Fairfax County
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Fairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationFairfax County
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Fairfax County
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Fairfax County
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Fairfax County
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
Watlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptxWatlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptxParabakaranBalasubra1
 
Pakistan Grand Prix (Project Management)
Pakistan Grand Prix (Project Management)Pakistan Grand Prix (Project Management)
Pakistan Grand Prix (Project Management)Sikander Sardar
 
Formula F1 Project Management
Formula F1 Project ManagementFormula F1 Project Management
Formula F1 Project ManagementMuhammad Awais
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
Community presentation 20150326 3.26.201
Community presentation 20150326 3.26.201Community presentation 20150326 3.26.201
Community presentation 20150326 3.26.201TAYLOR_Arch
 

Similar to Silver Line Phase 1-Status Report: May 6, 2014 (20)

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Watlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptxWatlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptx
 
Pakistan Grand Prix (Project Management)
Pakistan Grand Prix (Project Management)Pakistan Grand Prix (Project Management)
Pakistan Grand Prix (Project Management)
 
Formula F1 Project Management
Formula F1 Project ManagementFormula F1 Project Management
Formula F1 Project Management
 
Fitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement ProjectFitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement Project
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Community presentation 20150326 3.26.201
Community presentation 20150326 3.26.201Community presentation 20150326 3.26.201
Community presentation 20150326 3.26.201
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

May 2024 - Crypto Market Report_FINAL.pdf
May 2024 - Crypto Market Report_FINAL.pdfMay 2024 - Crypto Market Report_FINAL.pdf
May 2024 - Crypto Market Report_FINAL.pdfmanisha194592
 
2024 - Love and Madness - a book about love, madness, heartbreak and politics
2024 - Love and Madness - a book about love, madness, heartbreak and politics2024 - Love and Madness - a book about love, madness, heartbreak and politics
2024 - Love and Madness - a book about love, madness, heartbreak and politicsConradSmit5
 
CaseThe legal victory in the turmeric patent case safeguarded traditional kno...
CaseThe legal victory in the turmeric patent case safeguarded traditional kno...CaseThe legal victory in the turmeric patent case safeguarded traditional kno...
CaseThe legal victory in the turmeric patent case safeguarded traditional kno...alpha012343210
 
21052024_First India Newspaper Jaipur.pdf
21052024_First India Newspaper Jaipur.pdf21052024_First India Newspaper Jaipur.pdf
21052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Meta_AI_ads_investigation.pdfldoljjwejolejolol
Meta_AI_ads_investigation.pdfldoljjwejolejololMeta_AI_ads_investigation.pdfldoljjwejolejolol
Meta_AI_ads_investigation.pdfldoljjwejolejololbhavenpr
 
Have A Complimentary Cheat Sheet, On Us!!!
Have A Complimentary Cheat Sheet, On Us!!!Have A Complimentary Cheat Sheet, On Us!!!
Have A Complimentary Cheat Sheet, On Us!!!Abdul-Hakim Shabazz
 
Embed-3-1-1.pdf The ECI direction on April 2, 2024 can be read here:
Embed-3-1-1.pdf  The ECI direction on April 2, 2024 can be read here:Embed-3-1-1.pdf  The ECI direction on April 2, 2024 can be read here:
Embed-3-1-1.pdf The ECI direction on April 2, 2024 can be read here:bhavenpr
 
israeil_bnetaniahou_panel_report_eng.pdf
israeil_bnetaniahou_panel_report_eng.pdfisraeil_bnetaniahou_panel_report_eng.pdf
israeil_bnetaniahou_panel_report_eng.pdfssuser5750e1
 
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatóriosR$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatóriosMaurílio Júnior
 
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[bhavenpr
 
Minnesota Timberwolves Bring Ya Ass T Shirt
Minnesota Timberwolves Bring Ya Ass T ShirtMinnesota Timberwolves Bring Ya Ass T Shirt
Minnesota Timberwolves Bring Ya Ass T Shirtniherranjansingha
 
23052024_First India Newspaper Jaipur.pdf
23052024_First India Newspaper Jaipur.pdf23052024_First India Newspaper Jaipur.pdf
23052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
24052024_First India Newspaper Jaipur.pdf
24052024_First India Newspaper Jaipur.pdf24052024_First India Newspaper Jaipur.pdf
24052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
19052024_First India Newspaper Jaipur.pdf
19052024_First India Newspaper Jaipur.pdf19052024_First India Newspaper Jaipur.pdf
19052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
25052024_First India Newspaper Jaipur.pdf
25052024_First India Newspaper Jaipur.pdf25052024_First India Newspaper Jaipur.pdf
25052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Dominican American Coalition PAC Executive Summary
Dominican American Coalition PAC Executive SummaryDominican American Coalition PAC Executive Summary
Dominican American Coalition PAC Executive SummaryRDE GROUP CORP
 
Encore portal Project PPt on live portal
Encore portal Project PPt on live portalEncore portal Project PPt on live portal
Encore portal Project PPt on live portalEshantRawat2
 
Positive Effects Of Social Media On Mental Health
Positive Effects Of Social Media On Mental HealthPositive Effects Of Social Media On Mental Health
Positive Effects Of Social Media On Mental HealthTheUnitedIndian
 
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...Faga1939
 
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;jEmbed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;jbhavenpr
 

Recently uploaded (20)

May 2024 - Crypto Market Report_FINAL.pdf
May 2024 - Crypto Market Report_FINAL.pdfMay 2024 - Crypto Market Report_FINAL.pdf
May 2024 - Crypto Market Report_FINAL.pdf
 
2024 - Love and Madness - a book about love, madness, heartbreak and politics
2024 - Love and Madness - a book about love, madness, heartbreak and politics2024 - Love and Madness - a book about love, madness, heartbreak and politics
2024 - Love and Madness - a book about love, madness, heartbreak and politics
 
CaseThe legal victory in the turmeric patent case safeguarded traditional kno...
CaseThe legal victory in the turmeric patent case safeguarded traditional kno...CaseThe legal victory in the turmeric patent case safeguarded traditional kno...
CaseThe legal victory in the turmeric patent case safeguarded traditional kno...
 
21052024_First India Newspaper Jaipur.pdf
21052024_First India Newspaper Jaipur.pdf21052024_First India Newspaper Jaipur.pdf
21052024_First India Newspaper Jaipur.pdf
 
Meta_AI_ads_investigation.pdfldoljjwejolejolol
Meta_AI_ads_investigation.pdfldoljjwejolejololMeta_AI_ads_investigation.pdfldoljjwejolejolol
Meta_AI_ads_investigation.pdfldoljjwejolejolol
 
Have A Complimentary Cheat Sheet, On Us!!!
Have A Complimentary Cheat Sheet, On Us!!!Have A Complimentary Cheat Sheet, On Us!!!
Have A Complimentary Cheat Sheet, On Us!!!
 
Embed-3-1-1.pdf The ECI direction on April 2, 2024 can be read here:
Embed-3-1-1.pdf  The ECI direction on April 2, 2024 can be read here:Embed-3-1-1.pdf  The ECI direction on April 2, 2024 can be read here:
Embed-3-1-1.pdf The ECI direction on April 2, 2024 can be read here:
 
israeil_bnetaniahou_panel_report_eng.pdf
israeil_bnetaniahou_panel_report_eng.pdfisraeil_bnetaniahou_panel_report_eng.pdf
israeil_bnetaniahou_panel_report_eng.pdf
 
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatóriosR$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
 
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
 
Minnesota Timberwolves Bring Ya Ass T Shirt
Minnesota Timberwolves Bring Ya Ass T ShirtMinnesota Timberwolves Bring Ya Ass T Shirt
Minnesota Timberwolves Bring Ya Ass T Shirt
 
23052024_First India Newspaper Jaipur.pdf
23052024_First India Newspaper Jaipur.pdf23052024_First India Newspaper Jaipur.pdf
23052024_First India Newspaper Jaipur.pdf
 
24052024_First India Newspaper Jaipur.pdf
24052024_First India Newspaper Jaipur.pdf24052024_First India Newspaper Jaipur.pdf
24052024_First India Newspaper Jaipur.pdf
 
19052024_First India Newspaper Jaipur.pdf
19052024_First India Newspaper Jaipur.pdf19052024_First India Newspaper Jaipur.pdf
19052024_First India Newspaper Jaipur.pdf
 
25052024_First India Newspaper Jaipur.pdf
25052024_First India Newspaper Jaipur.pdf25052024_First India Newspaper Jaipur.pdf
25052024_First India Newspaper Jaipur.pdf
 
Dominican American Coalition PAC Executive Summary
Dominican American Coalition PAC Executive SummaryDominican American Coalition PAC Executive Summary
Dominican American Coalition PAC Executive Summary
 
Encore portal Project PPt on live portal
Encore portal Project PPt on live portalEncore portal Project PPt on live portal
Encore portal Project PPt on live portal
 
Positive Effects Of Social Media On Mental Health
Positive Effects Of Social Media On Mental HealthPositive Effects Of Social Media On Mental Health
Positive Effects Of Social Media On Mental Health
 
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
 
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;jEmbed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
 

Silver Line Phase 1-Status Report: May 6, 2014

  • 1. Status • Overall Phase 1 • April 7 – Department Of General Services (VA) issued TCOs for all rail facilities good for a period of 60 days • April 24 – MWAA concurrence with DTP’s Declaration of Substantial Completions for Phase 1 on April 9 (after 15 day review) • April 27 - WMATA and MWAA reach agreement on work that must be completed in order for WMATA to declare a Operational Readiness Date (ORD) -33 items • ORD - when the project is turned over to WMATA custody and control • Late May projected date to achieve ORD • April 28 – MWAA issues letter to Macerich for work to proceed with pavilion connection • May 1 – DPZ concurs that MWAA has complied with the SE conditions for the station landscaping plans • Wiehle garage – Complete • Connector staff in the facility • Record of Decision roadway improvements –minor work remains • West Falls Church rail yard: • Sound Box Completed – Feb 2014 • Noise Study Completed – Final Report to be issued • Phase 1 project budget - $ 2.906B Follow On Activities • Following ORD WMATA has up to 90 days for testing, employee training, and emergency drills prior to passenger service • Tri-State Oversight Committee will review project for safety certification • Estimated to be a 60 day process concurrent with WMATA’s up to 90 day period • WMATA will provide weekly press updates on progress of outstanding work • Regional coordination for bus service and marketing outreach ongoing • www. silverlinemetro.com • Punch List and Testing 1 6 May 2014
  • 2. Status • Phase 2 fully in design stage • 60% and some 90% design packages received • Issued for Construction packets – Starting Spring 2014 • Coordination ongoing • Town of Herndon • Adjacent Land Owners • Project Partners • Herndon and Innovation Center Station garages • Fairfax County has committed to fund and construct parking garages - Design ongoing • Innovation Center Station Garage - Land use case ongoing (June 2014) • Herndon Garage - staff has developed a number of concept designs (2232) • Scheduled tracks completion of the garages to the completion of Phase 2 • Status of Phase 2 Bid Packages: • Packet A - rail Line, station, and systems (includes Innovation Center Station) - Awarded • Packet B - Maintenance Facility at Dulles Airport – Technical Proposals received and under review • Award – Summer 2014 • NTP – Summer 2014 • Completion Summer 2018 Budget/Schedule • Cost Estimate: $3.093B • Cost Estimate with value engineering , Packet A savings, and garages funding outside the project: $2.6B • Substantial Completion: Summer 2018 • Revenue Operations: Late 2018 Current Milestones – Past 30 Days • TIFIA Application Approved • MWAA intention to hold tolls on the Dulles Toll Road at current rates through 2018 (as a result of TIFIA financing) • Design coordination ongoing 2 6 May 2014