MCRB, together with the Ministry of Environment and Natural Resources Conservation (MONREC) and Vermont Law School, with support from Heinrich Boll Foundation, held a workshop for local Environmental Impact Assessment Consultants with a focus on assessing social impacts – i.e. impacts on people - and the value of public participation and consultation in identifying these.
Read more: http://www.myanmar-responsiblebusiness.org/news/consultants-biggest-challenge.html
2. Outline
1. Organization
2. Law and Regulation
3. Submission Process
4. International Cooperation and EIA Guidelines
5. Situation of Environmental Assessment Report
6. Requirements
2
3. 3
Organization Structure of MONREC
MONREC
Mining Environment
Mini
ng
Dep;
DGS
ME
ME
1
ME
2
MGE MPE FD MTE
DZ
GD
ECD SD
4. 4
Organization Structure of ECD
ECD
Administration
Policy, Int.
Relation, Research
and Training
Division
Pollution Control
Natural Resources
& EIA Division
Policy
Planni
ng
Climate
Change
Int.
Relation
& Res
& Ext.
Admin Budget
Human
Resourc
es
Urban
&
Industr
ies
Env.
Quality
Natural
Res.
Cons.
EIA
6. 6
Environmental Conservation Law, 2012
Section 7 (m)
to lay down and carry out a system of EIA
and SIA as to whether or not a project or activity
to be undertaken by any Government department,
organization or person may cause a significant
impact on the environment;
7. 7
EIA process
SCREENING
Initial Environmental
Examination
Environmental Impact
Assessment
Environmental
Management Plan
Investigations &
Reporting
Review & Approval
Process
Investigations &
Reporting
Review & Approval
Process (RT)
Appeal Process
Scoping
Environmental Compliance
Certificate (ECC)
RejectOTHER
PERMITTING
PROCESSES
Investigations &
Reporting
Review & Approval
Process
8. Project Proposal
Article - 23
a) The Project Proponent shall submit the Project Proposal to the Ministry for
Screening.
Project Proposal shall include (www.ecd.gov.mm)
• an executive summary
• over view of the project,
• contact details of the proponent,
• basic specification of the project,
• the environmental / social aspects in the project site and its
surrounding area, (Art – 25,28)
• the major likely impacts caused by the project,
• current status of the project (e.g. new project, existing project, project
expansion)
12. Selected Consultant
Selected Consultant submission shall include (EIA)
• Informed Letter
• Submission Form
• Consultant List
• Registration Certificate
Selected Consultant submission shell include (IEE)
• Informed Letter
• Submission Form
• Consultant List
• Registration Certificate (or) Profile and Expertise of Consultant
20. Transitional Consultant Registration
Article 17 to 22
a) If specific terms, conditions and/or registration procedures have not been
separately issued by the Ministry, any Third Person or Organization, whether
foreign or domestic, who wishes to prepare an IEE and EIA shall first apply
to the Department.
21. Situation of Transitional Consultant Registration
Issue Date Organization Individual
20-7-2017 37 142
Screening 6 28
TOTAL 43 170
22. 2222
ADB (Environmental Safeguard Institutional Strengthening)
JICA (Capacity Development in Basic Water Environmental
Management and EIA System Development in Myanmar)
Vermont Law School (Public Participation Guideline & EIA Capacity
building)
IFC (Improving Environmental and Social Standards of the
Hydropower Sector in Myanmar)
NEA (Oil for Development program & Management of Hazardous
waste in Myanmar)
23. 2323
Guideline Support Org; Situation
EIA General Guideline and ECC ADB Final Draft
EIA Oil and Gas Guideline NEA Final Draft
EIA Hydropower Guideline IFC Final Draft
Publication Participation Guideline VLS Final Draft
EIA Mining Guideline WWF & ADB First Draft
HIA Guideline ADB Initial