SlideShare a Scribd company logo
1 of 53
ENVIRONMENTAL IMPACT
ASSESSMENTS (EIA)
Week 13
LEARNING OUTCOME
•Describe the purpose and role of EIA in the decision-making
process;
•understand the strengths of EIA in regard to environmental
management;
•understand the technical and social/political limitations of EIA;
•understand the scoping process and how it is applied;
•know the format of an EIA Report
LOOK AROUND
EIA :INTRODUCTION
•DOE was formed as a result of the section 34A:EQA
1974
•The emphasis was on control of pollution and
taking remedial action
•1970’s and 1980’s: agro based: palm oil and rubber
wastes
•1987:EIA was introduced for preventive control
WHAT IS EIA?
EIA is a study to identify, predict, evaluate and
communicate information about the impacts
on the environment of a proposed project and to
detail out the mitigating measures prior to project
approval and implementation.( DOE,Malaysia)
LEGAL REQUIREMENT IN MALAYSIA
•In Malaysia, EIA is required under section 34A, Environmental Quality Act, 1974 ,
which specifies the legal requirements in respect of EIA for Prescribed Activities.
•It empowers the Minister of Natural Resources and Environment after due
consultation, to prescribe any activity which may have significant environmental
impact as a Prescribed Activity.
•The section further requires the Project Proponent of a Prescribed Activity to
submit a report (the EIA) to the Director General of Environmental Quality before
approval for the proposed activity is granted by the relevant approving authority.
•The EIA report must be in accordance with the guidelines issued by the DOE
contain an assessment of the impact of the Prescribed Activity on the
environment; and detail the proposed measures that shall be instituted to prevent,
reduce or control adverse impacts on the environment
WHO CAN CONDUCT EIA STUDY?
•An EIA Study has to be conducted by
competent individuals who are registered with
the Department of Environment under the EIA
Consultant Registration Scheme.
How To Conduct EIA?
•In the preparation of EIA reports, project proponents
and EIA consultants may refer to A Handbook of
Environmental Impact Assessment Guidelines
(fourth edition) 2007 and EIA Guidelines for specific
activities published by the Department of Environment
and other relevant guidelines published by other
agencies
WHY DO WE NEED EIA?
•EIA is essentially a planning mechanism for preventing
environmental problems due to an action.
•It ensures that the potential problems are foreseen and addressed
at an early stage in the project planning and design.
•Thus this will avoid costly mistakes in project implementation, either
because of the environmental damages that are likely to arise
during project implementation, or because of modifications that may
be required subsequently in order to make the action
environmentally acceptable
•EIA when integrated into the existing planning and decision-making
structure, provides additional information towards a better decision-
making.
GENERIC LIMITATION OF EIA
•EIA occurs at the project level, not the policy program level
•EIA is typically done after feasibility studies and preliminary
decisions are made.
•The EIA is then and ‘add-on’ to meet legal requirements, and
serves largely to suggest mitigation measures for a project
already selected, rather than an opportunity to come up with
optimal project.
•Environmental values which have not or cannot be monetized
may fall through the cracks
•Consultation with public does not necessarily require a full
inclusion of all relevant stake-holders
•Social equity considerations are typically outside the scope of
EIA
•Although EIA occur before the project decision, they should also
be used AFTER the decision to help ensure robust
environmental monitoring and management throughout project
life but this id not done.
EIA:SCOPE
•Before initiating environmental studies, an agency determines
scopes of issues to be addressed in the EIS.
•If preliminary studies determines that significant environment
impacts are likely, the appropriate agency must prepare the EIS.
•Agency identifies individual citizens, interest groups, institutions
likely to be interested.
•Scoping also involves synchronizing environmental studies and
decision making time table.
EIA: COMPONENTS
•Statement of purpose
•Scoping
•Alternatives, including proposed action
•Environmental impact of each alternative
•Mitigation measures
•Consultation and coordination
•List of papers
EIA:AIM
•To assess the overall impact on the
environment of development projects proposed
by the public and private sectors.
EIA:OBJECTIVES
•To examine and select the best from the project options
available
•To identify and incorporate into the project plan appropriate
abatement and mitigating measures.
•To predict significant residual environmental impacts
•To determine the significant residual environmental impacts
predicted, and to identify the environmental costs and benefits of
the project to the community.
THE EIA DIRECTIVE
•The EIA should identify, describe and assess the
direct and indirect effects of a project on the following
factors:
o human beings, fauna and flora
o soil, water, air, climate and the landscape
o material assets and cultural heritage
o the interaction between the above factors
•EIA should therefore have a strong social dimension
Screening (does the project
require EIA?)
Scoping (what issues and
impacts should the EIA address?)
Baseline studies (establish the
environmental baseline)
Alternatives (consider the
different approaches)
Mitigation (what can be done to
alleviate negative impacts?)
EIS preparation/review
(document the EIA findings)
Public consultation (consult
general public and NGOs)
Monitoring (monitor impacts of
project)
Impact prediction (forecast
the environmental impacts)
Impact assessment
(interpreting the impacts)
SCREENING
•Is an EIA needed?
•A screening mechanism seeks to identify those
projects with potentially significant adverse
environmental effects
SCOPING
•The scope of an EIA is the issues and impacts it addresses
•Scoping is the process of deciding which of a project’s
possible alternatives and impacts should be addressed in
the EIA
•An EIA should focus only on the significant issues and
impacts
SCOPING
•Scoping is carried out in discussions between the
developer, the competent authority, relevant agencies
and, ideally, the public
•Effective scoping enables limited resources to be
allocated to best effect (i.e. through investigation of
only the most significant impacts)
•Scoping is not mandatory under the EIA Directive
BASELINE STUDIES
•Following the scoping phase, it is essential to
assemble all the relevant information on the current
status of the environment
•The baseline study should anticipate the future state of
the environment assuming the project is not
undertaken - the ‘no action alternative’
•This provides the ‘baseline’ against which future
impacts can be assessed
BASELINE STUDIES
•Baseline studies should be undertaken for each
alternative site so that the relative severity of the
impacts for each alternative can be assessed
•New field work may necessary (e.g. ecological survey)
if relevant data is not already available
ALTERNATIVES
•EIA is ideally undertaken for a project and its alternatives (e.g.
different locations, scales, designs)
•Alternatives are the ‘raw material’ of EIA
•The US Council on Environmental Quality (CEQ) has described
the discussion of alternatives as the ‘heart’ of the EIS
•Many EISs fail to consider alternatives
IMPACT ASSESSMENT
•Impact assessment involves evaluating the significance of the
impacts identified
•Significance can be determined through professional judgment,
reference to regulations etc.
•Potential for bias in determining what is significant
•The conclusions of the impact assessment can ultimately be
used by decision-makers when determining the fate of the
project application
MITIGATION
•Negative impacts on the environment identified during the EIA
can be alleviated through mitigation measures
•The mitigation hierarchy: Avoid - Reduce - Remedy -
Compensate - Enhance
•Impacts remaining after mitigation are known as residual
impacts
•The legislation obstructs the proper process of design
development
EIS PREPARATION / REVIEW
•The Environmental Impact Statement (EIS) is a formal
document which includes information on the development and
information relating to screening, scoping, baseline studies,
alternatives etc.
•Common requirement to include a non-technical summary
EIS PREPARATION / REVIEW
•Once complete, the EIS is submitted to the competent authority
(along with the planning application)
•The EIS is often reviewed (either formally or informally)
•The review enables the competent authority to decide whether
the EIA is adequate, accurate and unbiased
PUBLIC CONSULTATION
•The EIA Directive provides for public consultation on
the application for development and the EIS
POST-PROJECT MONITORING
•Monitoring should determine:
o the accuracy of the original predictions
o the degree of deviation from the predictions
o the possible reasons for any deviations
o the extent to which mitigation measures have achieved their
objectives
MALAYSIA EIA PROCEDURE
•The EIA procedure in Malaysia has been designed to follow the
integrated project planning concept so that EIA is carried out at
the pre-feasibility and feasibility stages.
•Comparable to the National Environmental Policy Act
1969(NEPA) model in US
EIA: PROCEDURES
EIA: PROCEDURES
•Preliminary assessments of all prescribed activities
•Detailed assessments of those prescribed activities for
which significant residual environmental impacts have
been predicted in the preliminary assessments
•Review of assessment reports
EIA: Steps- Preliminary Assessments
•Objectives
To examine and select the best from the project
options available
To identify and incorporate into the project plan
appropiate abatement and mitigating measures
To identify significant residual environmental
impacts
EIA: STEPS-DETAILED ASSESSMENTS
•Objectives
To describe the significant residual environmental
impacts predicted from the final project plan
To specify mitigating and abatement measures in
the final project plan
To identify the environmental costs and benefits of
the project to the community
AIR QUALITY
•Looking for
oOxides of nitrogen (NOx)
oOxides of sulphur (SOx)
oOzone O3
oParticulates PM10 and now
PM2.5
oDioxins and Furans for
Incinerators
oParticulates (dust)
oOdour
AIR QUALITY
•No legal standards
•Most projects have very limited impact
•Dioxins and Furans have become significant concerns
since the extremely low levels could be measured
FORESTRY AND AGRICULTURE
•Classification of land (Grade 1, 2, 3)
•Severance and viability
•Orphaning of land parcels
•Isolating buildings from fields etc
•Opportunities for landscaping on isolated pieces of land
WATER QUALITY
•Aquifer protection zones
•River designations
•Ecology impacts
•Hazard assessment from spills etc
LANDSCAPE AND VISUAL
AMENITY
•Visual assessment
•Site categorisation ( Conservation area)
•Inter visibility plots
•Landscape description
•Landscape value
•Opportunities for landscaping
HERITAGE AND ARCHAEOLOGY
•Site categorization (World Heritage
Site, Conservation Area)
•Locally important buildings without
designation
•English Heritage
•National Trust
•County Archaeologist
ECOLOGY
•Assessment of ecological value
•Site categorisation
•Inventory of flora and fauna
•Rare species
•Protected species
•Impact of severance, disruption etc
•English Nature, Wildlife Trusts etc
GEOLOGY AND SOILS
•Assessment of geological value
•Site protection
TRAFFIC IMPACT ASSESSMENT
•Traffic flows generally on roads
•Cars, taxis, trucks, buses, cycles
•Pedestrian journeys
•Public/private transport split
•Congestion/traffic management
•Proposed mitigation measures
SUSTAINABILITY ASSESSMENT
•Currently part of EIA
•Should be the over-arching process
•No current guidelines
CONSTRUCTION IMPACTS
•Traffic movements
•Dust
•Mud
•Social impacts itinerant workers
•Business generation
•Spoil heaps
•Contamination of rivers & streams
CONSTRUCTION IMPACTS
•Light pollution
•Noise
•Vibration of piling plant
•Materials stockpiles
•Construction sites
EIA: ISSUES AND PROBLEM
•Lack of awareness of the strength of EIA as a planning tool.
Many still perceive EIA as a stumbling block to development.
•Perception that carrying out EIA would delay project approval
and implementation
•EIA not carried out prior to final project design, so that issues
such as sitting and technology are not considered.
•Lack of baseline data on environmental quality
•Poor prediction of impacts
•Limitation public participation
EIA:CASE STUDY- BERIS DAM,KEDAH
•Title: Dam Project: Environmental Impacts and
mitigation Measures: A case of Beris Dam,
Kedah,Malaysia
•Purpose: To alleviate water shortage problems meting
the demands for the agricultural, domestic and
industrial needs
EIA:CASE STUDY-PRE-CONSTRUCTION
•There are various steps necessary to be taken during the
planning and site preparation.
•This include: providing sufficient buffer zones between a road
reserves and the project area and maintaining as far as possible
the natural topography of the project area.
•In an EIA report, it is required at this stage to prepare scheduled
earthworks in such a way that rainy seasons are avoided.
•Detailed earthworks plan shall be paved before the start of any
construction
•For site preparation prior to actual construction, any cleared
areas must be turned immediately. Cutting of trees should be
reduced to a minimum and only areas designated for
construction of building, roads or any other infrastructures shall
be cleared.
•Temporary sanitary facilities shall ne provided in the worker’s
camp.
•The ground conditions as described in the EIA is usually very
brief and further investigations are required to ascertain the sites
especially if the land use of the areas are known as former
industrial area or dumping sites.
•Studies on the state of the health of the site should be carried
out.
EIA:CASE STUDY-DURING CONSTRUCTION
•During construction, the disposal of construction wastes must be
removed within the project area and the open burning should not
be carried out.
•Noise level at the boundary of the construction site shall be
controlled as not exceed 55 dBA at night and 65 dBA during the
day.
•Silt trap shall be followed to minimized the impacts to river
quality.
•Vehicles and machineries used for transportation of construction
materials shall be cleaned before leaving the construction sites.
EIA:CASE STUDY- POST-CONSTRUCTION
•The period just before handing over and years beyond
require certain aspects of environmental management.
•The construction wastes and debris have to be
disposed at approved sites.
•Monitoring for river quality downstream of the site has
to be carried out if stated by the EIA report.
THANK YOU

More Related Content

What's hot

Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentBahadur Prasad
 
Assessing proposed project development under EIA
Assessing proposed project development under EIAAssessing proposed project development under EIA
Assessing proposed project development under EIAKisesa Hamis
 
EIA: The state of art.
EIA: The state of art.EIA: The state of art.
EIA: The state of art.Tulsi Makwana
 
ENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTgoswamikusum
 
Environmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit IIIEnvironmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit IIIGAURAV. H .TANDON
 
Current trends in EIA
Current trends in EIACurrent trends in EIA
Current trends in EIAtesdev
 
Environmental Impact Assessment (EIA) in Project Management
Environmental Impact Assessment (EIA) in Project ManagementEnvironmental Impact Assessment (EIA) in Project Management
Environmental Impact Assessment (EIA) in Project ManagementJoy Bhattacharjee
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentIntan Ayuna
 
Contemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessmentContemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessmentNasiru Ibrahim Barda
 
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...
National Environmental Policy Act (NEPA)  Writing Environmental Assessments (...National Environmental Policy Act (NEPA)  Writing Environmental Assessments (...
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...rshimoda2014
 
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1hirencd
 
Principles of environmental impact assessment
Principles of environmental impact assessmentPrinciples of environmental impact assessment
Principles of environmental impact assessmentAnirban Mandal
 
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...
National Environmental Policy Act (NEPA)  Writing Environmental Assessments (...National Environmental Policy Act (NEPA)  Writing Environmental Assessments (...
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...rshimoda2014
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIAbishal sapkota
 

What's hot (20)

EIA Process
EIA ProcessEIA Process
EIA Process
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Assessing proposed project development under EIA
Assessing proposed project development under EIAAssessing proposed project development under EIA
Assessing proposed project development under EIA
 
Eia (2)
Eia (2)Eia (2)
Eia (2)
 
EIA: The state of art.
EIA: The state of art.EIA: The state of art.
EIA: The state of art.
 
ENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENT
 
EIA-process
 EIA-process EIA-process
EIA-process
 
FUNCTIONS OF EPA
FUNCTIONS OF EPAFUNCTIONS OF EPA
FUNCTIONS OF EPA
 
Eia requirements
Eia requirementsEia requirements
Eia requirements
 
Environmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit IIIEnvironmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit III
 
Current trends in EIA
Current trends in EIACurrent trends in EIA
Current trends in EIA
 
Eia stages
Eia stagesEia stages
Eia stages
 
Environmental Impact Assessment (EIA) in Project Management
Environmental Impact Assessment (EIA) in Project ManagementEnvironmental Impact Assessment (EIA) in Project Management
Environmental Impact Assessment (EIA) in Project Management
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Contemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessmentContemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessment
 
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...
National Environmental Policy Act (NEPA)  Writing Environmental Assessments (...National Environmental Policy Act (NEPA)  Writing Environmental Assessments (...
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...
 
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
 
Principles of environmental impact assessment
Principles of environmental impact assessmentPrinciples of environmental impact assessment
Principles of environmental impact assessment
 
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...
National Environmental Policy Act (NEPA)  Writing Environmental Assessments (...National Environmental Policy Act (NEPA)  Writing Environmental Assessments (...
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIA
 

Similar to Ecw 579 week 13

Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptxthanga2
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptxthanga2
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentVinod Burdak
 
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)HNaliniNirala
 
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfBeige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfHajiraThabasum
 
Environment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in UgandaEnvironment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in Ugandakayondo alex
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfChandanLawrence
 
Environmental Impact Assignment
Environmental Impact Assignment Environmental Impact Assignment
Environmental Impact Assignment Hemant Thakur
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment Pramoda Raj
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)Angom Baleshwor
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrithvi Ghag
 
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...Mr.Allah Dad Khan
 
Phil-EIA-history_issues, REPORT AND ANALYSIS
Phil-EIA-history_issues, REPORT AND ANALYSISPhil-EIA-history_issues, REPORT AND ANALYSIS
Phil-EIA-history_issues, REPORT AND ANALYSISABEGAILBENCALO1
 

Similar to Ecw 579 week 13 (20)

Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
PEISS
PEISSPEISS
PEISS
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfBeige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
 
PEISS
PEISSPEISS
PEISS
 
eia.ppt
eia.ppteia.ppt
eia.ppt
 
eia.ppt
eia.ppteia.ppt
eia.ppt
 
Environment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in UgandaEnvironment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in Uganda
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdf
 
Environmental Impact Assignment
Environmental Impact Assignment Environmental Impact Assignment
Environmental Impact Assignment
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
 
Coastal Road Project
Coastal Road ProjectCoastal Road Project
Coastal Road Project
 
Phil-EIA-history_issues, REPORT AND ANALYSIS
Phil-EIA-history_issues, REPORT AND ANALYSISPhil-EIA-history_issues, REPORT AND ANALYSIS
Phil-EIA-history_issues, REPORT AND ANALYSIS
 

More from Adilah Anuar

Ecw 579 week 11. latest
Ecw 579 week 11. latestEcw 579 week 11. latest
Ecw 579 week 11. latestAdilah Anuar
 
Ecw 579 week 10. latest
Ecw 579 week 10. latestEcw 579 week 10. latest
Ecw 579 week 10. latestAdilah Anuar
 
Ecw 579 week 8. latest
Ecw 579 week 8. latestEcw 579 week 8. latest
Ecw 579 week 8. latestAdilah Anuar
 
Ecw 579 week 6. latest
Ecw 579 week 6. latestEcw 579 week 6. latest
Ecw 579 week 6. latestAdilah Anuar
 
Ecw 579 week 1. latest
Ecw 579 week 1. latestEcw 579 week 1. latest
Ecw 579 week 1. latestAdilah Anuar
 

More from Adilah Anuar (6)

Ecw 579 week 11. latest
Ecw 579 week 11. latestEcw 579 week 11. latest
Ecw 579 week 11. latest
 
Ecw 579 week 10. latest
Ecw 579 week 10. latestEcw 579 week 10. latest
Ecw 579 week 10. latest
 
Ecw 579 week 8. latest
Ecw 579 week 8. latestEcw 579 week 8. latest
Ecw 579 week 8. latest
 
Ecw 579 week 6. latest
Ecw 579 week 6. latestEcw 579 week 6. latest
Ecw 579 week 6. latest
 
Ecw 579 week 2
Ecw 579 week 2Ecw 579 week 2
Ecw 579 week 2
 
Ecw 579 week 1. latest
Ecw 579 week 1. latestEcw 579 week 1. latest
Ecw 579 week 1. latest
 

Recently uploaded

办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一z xss
 
Along the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"sAlong the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"syalehistoricalreview
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsprasan26
 
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full NightCall Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerLow Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerSuhani Kapoor
 
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesGwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Servicesnajka9823
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...Delhi Escorts
 
Sustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesSustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesDr. Salem Baidas
 
Soil pollution causes effects remedial measures
Soil pollution causes effects remedial measuresSoil pollution causes effects remedial measures
Soil pollution causes effects remedial measuresvasubhanot1234
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girlsssuser7cb4ff
 
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170simranguptaxx69
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BHbill846304
 
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCRCall In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCRjennyeacort
 

Recently uploaded (20)

办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 
Along the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"sAlong the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"s
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnids
 
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full NightCall Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
 
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerLow Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
 
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesGwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
 
Sustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesSustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and Challenges
 
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
 
Soil pollution causes effects remedial measures
Soil pollution causes effects remedial measuresSoil pollution causes effects remedial measures
Soil pollution causes effects remedial measures
 
FULL ENJOY Call Girls In kashmiri gate (Delhi) Call Us 9953056974
FULL ENJOY Call Girls In  kashmiri gate (Delhi) Call Us 9953056974FULL ENJOY Call Girls In  kashmiri gate (Delhi) Call Us 9953056974
FULL ENJOY Call Girls In kashmiri gate (Delhi) Call Us 9953056974
 
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
 
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BH
 
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCRCall In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
 
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Serviceyoung call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
 

Ecw 579 week 13

  • 2. LEARNING OUTCOME •Describe the purpose and role of EIA in the decision-making process; •understand the strengths of EIA in regard to environmental management; •understand the technical and social/political limitations of EIA; •understand the scoping process and how it is applied; •know the format of an EIA Report
  • 4. EIA :INTRODUCTION •DOE was formed as a result of the section 34A:EQA 1974 •The emphasis was on control of pollution and taking remedial action •1970’s and 1980’s: agro based: palm oil and rubber wastes •1987:EIA was introduced for preventive control
  • 5. WHAT IS EIA? EIA is a study to identify, predict, evaluate and communicate information about the impacts on the environment of a proposed project and to detail out the mitigating measures prior to project approval and implementation.( DOE,Malaysia)
  • 6. LEGAL REQUIREMENT IN MALAYSIA •In Malaysia, EIA is required under section 34A, Environmental Quality Act, 1974 , which specifies the legal requirements in respect of EIA for Prescribed Activities. •It empowers the Minister of Natural Resources and Environment after due consultation, to prescribe any activity which may have significant environmental impact as a Prescribed Activity. •The section further requires the Project Proponent of a Prescribed Activity to submit a report (the EIA) to the Director General of Environmental Quality before approval for the proposed activity is granted by the relevant approving authority. •The EIA report must be in accordance with the guidelines issued by the DOE contain an assessment of the impact of the Prescribed Activity on the environment; and detail the proposed measures that shall be instituted to prevent, reduce or control adverse impacts on the environment
  • 7. WHO CAN CONDUCT EIA STUDY? •An EIA Study has to be conducted by competent individuals who are registered with the Department of Environment under the EIA Consultant Registration Scheme.
  • 8. How To Conduct EIA? •In the preparation of EIA reports, project proponents and EIA consultants may refer to A Handbook of Environmental Impact Assessment Guidelines (fourth edition) 2007 and EIA Guidelines for specific activities published by the Department of Environment and other relevant guidelines published by other agencies
  • 9. WHY DO WE NEED EIA? •EIA is essentially a planning mechanism for preventing environmental problems due to an action. •It ensures that the potential problems are foreseen and addressed at an early stage in the project planning and design. •Thus this will avoid costly mistakes in project implementation, either because of the environmental damages that are likely to arise during project implementation, or because of modifications that may be required subsequently in order to make the action environmentally acceptable •EIA when integrated into the existing planning and decision-making structure, provides additional information towards a better decision- making.
  • 10. GENERIC LIMITATION OF EIA •EIA occurs at the project level, not the policy program level •EIA is typically done after feasibility studies and preliminary decisions are made. •The EIA is then and ‘add-on’ to meet legal requirements, and serves largely to suggest mitigation measures for a project already selected, rather than an opportunity to come up with optimal project.
  • 11. •Environmental values which have not or cannot be monetized may fall through the cracks •Consultation with public does not necessarily require a full inclusion of all relevant stake-holders •Social equity considerations are typically outside the scope of EIA •Although EIA occur before the project decision, they should also be used AFTER the decision to help ensure robust environmental monitoring and management throughout project life but this id not done.
  • 12. EIA:SCOPE •Before initiating environmental studies, an agency determines scopes of issues to be addressed in the EIS. •If preliminary studies determines that significant environment impacts are likely, the appropriate agency must prepare the EIS. •Agency identifies individual citizens, interest groups, institutions likely to be interested. •Scoping also involves synchronizing environmental studies and decision making time table.
  • 13. EIA: COMPONENTS •Statement of purpose •Scoping •Alternatives, including proposed action •Environmental impact of each alternative •Mitigation measures •Consultation and coordination •List of papers
  • 14. EIA:AIM •To assess the overall impact on the environment of development projects proposed by the public and private sectors.
  • 15. EIA:OBJECTIVES •To examine and select the best from the project options available •To identify and incorporate into the project plan appropriate abatement and mitigating measures. •To predict significant residual environmental impacts •To determine the significant residual environmental impacts predicted, and to identify the environmental costs and benefits of the project to the community.
  • 16. THE EIA DIRECTIVE •The EIA should identify, describe and assess the direct and indirect effects of a project on the following factors: o human beings, fauna and flora o soil, water, air, climate and the landscape o material assets and cultural heritage o the interaction between the above factors •EIA should therefore have a strong social dimension
  • 17. Screening (does the project require EIA?) Scoping (what issues and impacts should the EIA address?) Baseline studies (establish the environmental baseline) Alternatives (consider the different approaches) Mitigation (what can be done to alleviate negative impacts?) EIS preparation/review (document the EIA findings) Public consultation (consult general public and NGOs) Monitoring (monitor impacts of project) Impact prediction (forecast the environmental impacts) Impact assessment (interpreting the impacts)
  • 18. SCREENING •Is an EIA needed? •A screening mechanism seeks to identify those projects with potentially significant adverse environmental effects
  • 19. SCOPING •The scope of an EIA is the issues and impacts it addresses •Scoping is the process of deciding which of a project’s possible alternatives and impacts should be addressed in the EIA •An EIA should focus only on the significant issues and impacts
  • 20. SCOPING •Scoping is carried out in discussions between the developer, the competent authority, relevant agencies and, ideally, the public •Effective scoping enables limited resources to be allocated to best effect (i.e. through investigation of only the most significant impacts) •Scoping is not mandatory under the EIA Directive
  • 21. BASELINE STUDIES •Following the scoping phase, it is essential to assemble all the relevant information on the current status of the environment •The baseline study should anticipate the future state of the environment assuming the project is not undertaken - the ‘no action alternative’ •This provides the ‘baseline’ against which future impacts can be assessed
  • 22. BASELINE STUDIES •Baseline studies should be undertaken for each alternative site so that the relative severity of the impacts for each alternative can be assessed •New field work may necessary (e.g. ecological survey) if relevant data is not already available
  • 23. ALTERNATIVES •EIA is ideally undertaken for a project and its alternatives (e.g. different locations, scales, designs) •Alternatives are the ‘raw material’ of EIA •The US Council on Environmental Quality (CEQ) has described the discussion of alternatives as the ‘heart’ of the EIS •Many EISs fail to consider alternatives
  • 24. IMPACT ASSESSMENT •Impact assessment involves evaluating the significance of the impacts identified •Significance can be determined through professional judgment, reference to regulations etc. •Potential for bias in determining what is significant •The conclusions of the impact assessment can ultimately be used by decision-makers when determining the fate of the project application
  • 25. MITIGATION •Negative impacts on the environment identified during the EIA can be alleviated through mitigation measures •The mitigation hierarchy: Avoid - Reduce - Remedy - Compensate - Enhance •Impacts remaining after mitigation are known as residual impacts •The legislation obstructs the proper process of design development
  • 26. EIS PREPARATION / REVIEW •The Environmental Impact Statement (EIS) is a formal document which includes information on the development and information relating to screening, scoping, baseline studies, alternatives etc. •Common requirement to include a non-technical summary
  • 27. EIS PREPARATION / REVIEW •Once complete, the EIS is submitted to the competent authority (along with the planning application) •The EIS is often reviewed (either formally or informally) •The review enables the competent authority to decide whether the EIA is adequate, accurate and unbiased
  • 28. PUBLIC CONSULTATION •The EIA Directive provides for public consultation on the application for development and the EIS
  • 29. POST-PROJECT MONITORING •Monitoring should determine: o the accuracy of the original predictions o the degree of deviation from the predictions o the possible reasons for any deviations o the extent to which mitigation measures have achieved their objectives
  • 30. MALAYSIA EIA PROCEDURE •The EIA procedure in Malaysia has been designed to follow the integrated project planning concept so that EIA is carried out at the pre-feasibility and feasibility stages. •Comparable to the National Environmental Policy Act 1969(NEPA) model in US
  • 32. EIA: PROCEDURES •Preliminary assessments of all prescribed activities •Detailed assessments of those prescribed activities for which significant residual environmental impacts have been predicted in the preliminary assessments •Review of assessment reports
  • 33. EIA: Steps- Preliminary Assessments •Objectives To examine and select the best from the project options available To identify and incorporate into the project plan appropiate abatement and mitigating measures To identify significant residual environmental impacts
  • 34. EIA: STEPS-DETAILED ASSESSMENTS •Objectives To describe the significant residual environmental impacts predicted from the final project plan To specify mitigating and abatement measures in the final project plan To identify the environmental costs and benefits of the project to the community
  • 35. AIR QUALITY •Looking for oOxides of nitrogen (NOx) oOxides of sulphur (SOx) oOzone O3 oParticulates PM10 and now PM2.5 oDioxins and Furans for Incinerators oParticulates (dust) oOdour
  • 36. AIR QUALITY •No legal standards •Most projects have very limited impact •Dioxins and Furans have become significant concerns since the extremely low levels could be measured
  • 37. FORESTRY AND AGRICULTURE •Classification of land (Grade 1, 2, 3) •Severance and viability •Orphaning of land parcels •Isolating buildings from fields etc •Opportunities for landscaping on isolated pieces of land
  • 38. WATER QUALITY •Aquifer protection zones •River designations •Ecology impacts •Hazard assessment from spills etc
  • 39. LANDSCAPE AND VISUAL AMENITY •Visual assessment •Site categorisation ( Conservation area) •Inter visibility plots •Landscape description •Landscape value •Opportunities for landscaping
  • 40. HERITAGE AND ARCHAEOLOGY •Site categorization (World Heritage Site, Conservation Area) •Locally important buildings without designation •English Heritage •National Trust •County Archaeologist
  • 41. ECOLOGY •Assessment of ecological value •Site categorisation •Inventory of flora and fauna •Rare species •Protected species •Impact of severance, disruption etc •English Nature, Wildlife Trusts etc
  • 42. GEOLOGY AND SOILS •Assessment of geological value •Site protection
  • 43. TRAFFIC IMPACT ASSESSMENT •Traffic flows generally on roads •Cars, taxis, trucks, buses, cycles •Pedestrian journeys •Public/private transport split •Congestion/traffic management •Proposed mitigation measures
  • 44. SUSTAINABILITY ASSESSMENT •Currently part of EIA •Should be the over-arching process •No current guidelines
  • 45. CONSTRUCTION IMPACTS •Traffic movements •Dust •Mud •Social impacts itinerant workers •Business generation •Spoil heaps •Contamination of rivers & streams
  • 46. CONSTRUCTION IMPACTS •Light pollution •Noise •Vibration of piling plant •Materials stockpiles •Construction sites
  • 47. EIA: ISSUES AND PROBLEM •Lack of awareness of the strength of EIA as a planning tool. Many still perceive EIA as a stumbling block to development. •Perception that carrying out EIA would delay project approval and implementation •EIA not carried out prior to final project design, so that issues such as sitting and technology are not considered. •Lack of baseline data on environmental quality •Poor prediction of impacts •Limitation public participation
  • 48. EIA:CASE STUDY- BERIS DAM,KEDAH •Title: Dam Project: Environmental Impacts and mitigation Measures: A case of Beris Dam, Kedah,Malaysia •Purpose: To alleviate water shortage problems meting the demands for the agricultural, domestic and industrial needs
  • 49. EIA:CASE STUDY-PRE-CONSTRUCTION •There are various steps necessary to be taken during the planning and site preparation. •This include: providing sufficient buffer zones between a road reserves and the project area and maintaining as far as possible the natural topography of the project area. •In an EIA report, it is required at this stage to prepare scheduled earthworks in such a way that rainy seasons are avoided. •Detailed earthworks plan shall be paved before the start of any construction
  • 50. •For site preparation prior to actual construction, any cleared areas must be turned immediately. Cutting of trees should be reduced to a minimum and only areas designated for construction of building, roads or any other infrastructures shall be cleared. •Temporary sanitary facilities shall ne provided in the worker’s camp. •The ground conditions as described in the EIA is usually very brief and further investigations are required to ascertain the sites especially if the land use of the areas are known as former industrial area or dumping sites. •Studies on the state of the health of the site should be carried out.
  • 51. EIA:CASE STUDY-DURING CONSTRUCTION •During construction, the disposal of construction wastes must be removed within the project area and the open burning should not be carried out. •Noise level at the boundary of the construction site shall be controlled as not exceed 55 dBA at night and 65 dBA during the day. •Silt trap shall be followed to minimized the impacts to river quality. •Vehicles and machineries used for transportation of construction materials shall be cleaned before leaving the construction sites.
  • 52. EIA:CASE STUDY- POST-CONSTRUCTION •The period just before handing over and years beyond require certain aspects of environmental management. •The construction wastes and debris have to be disposed at approved sites. •Monitoring for river quality downstream of the site has to be carried out if stated by the EIA report.