Navajo Generating Station Owners Initial Proposal Timeline Discussion Glen D. Reeves February 4, 2011 2-04-11 NGS Owners I...
Key Challenges EPA Rulings Expected Co-Tenancy Expires LADWP Withdraws Lease Expires 323 Grants Expire Coal Contract Expir...
Timeline for Proposed Activities Surrounding NGS Efforts for Meeting the Goal of the Regional Haze Rule  2011 <ul><ul><ul>...
Timeline for Proposed Activities 2011 2064 “ Goal is to achieve natural background levels by 2064 (i.e., no manmade visibi...
Timeline for Proposed Activities 2011 2064 “ Goal is to achieve natural background levels by 2064 (i.e., no manmade visibi...
Timeline for Proposed Activities 2011 2064 2018 2028 2038 2048 2058 2 nd  SIP/FIP update for RHR is due in 2018  NGS Site ...
Key Durations <ul><li>Lease Negotiation and Navajo Nation Approval </li></ul><ul><ul><li>Assume End of 2011 </li></ul></ul...
Key Durations <ul><li>Legal Challenges - Assume 2 years  </li></ul><ul><li>Design, Procurement and Installation of SCR </l...
Key Owner Requirements <ul><li>No Major Capital Expenditures Until Lease is Approved, Grants are Issued, Ownership Resolve...
Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 2-04-11 NGS Owners Initial Proposal - GDReeves
Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) 2-04-11...
Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Pr...
Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Pr...
Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Pr...
Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Pr...
Proposed SCR Installation Period  2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Appr...
Installation Period Required if SCR is required in this BART 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 ...
IF Owners don’t take Risk of installing SCR without knowing NEPA outcome 2011 NGS Site Lease Termination (12/23/19) 3 3 3 ...
Proposed SCR Installation Period  2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Appr...
Upcoming SlideShare
Loading in …5
×

NGS Owners Initial Proposal Timeline Discussion

1,060 views

Published on

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
1,060
On SlideShare
0
From Embeds
0
Number of Embeds
186
Actions
Shares
0
Downloads
25
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide
  • EPA Clean Air Act Regional Haze Rules – program to improve visibility in Class 1 areas. Program requires a return to natural background by 2064. However, potential installation of SCR’s may be required much sooner.
  • NGS Owners Initial Proposal Timeline Discussion

    1. 1. Navajo Generating Station Owners Initial Proposal Timeline Discussion Glen D. Reeves February 4, 2011 2-04-11 NGS Owners Initial Proposal - GDReeves
    2. 2. Key Challenges EPA Rulings Expected Co-Tenancy Expires LADWP Withdraws Lease Expires 323 Grants Expire Coal Contract Expires Transmission Contracts Expire LADWP Seeks Withdrawal Environmental Critical Agreements Ownership Equipment Installation Requirement Expected Water Service Contract Expires 2-04-11 NGS Owners Initial Proposal - GDReeves 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
    3. 3. Timeline for Proposed Activities Surrounding NGS Efforts for Meeting the Goal of the Regional Haze Rule 2011 <ul><ul><ul><li>Regional Haze Rule </li></ul></ul></ul><ul><ul><ul><ul><li>Effective 2005 </li></ul></ul></ul></ul><ul><ul><ul><ul><li>Natural Background Visibility by 2064 </li></ul></ul></ul></ul><ul><ul><ul><ul><li>Class 1 Areas </li></ul></ul></ul></ul><ul><ul><ul><ul><li>(National Parks, Wilderness Areas) </li></ul></ul></ul></ul>2064 2-04-11 NGS Owners Initial Proposal - GDReeves 53 Years
    4. 4. Timeline for Proposed Activities 2011 2064 “ Goal is to achieve natural background levels by 2064 (i.e., no manmade visibility impairment)” 53 Years Every 10 years beginning in 2018 the previous SIP/FIP must be updated to account for current visibility and progress made toward the 2064 goal 2-04-11 NGS Owners Initial Proposal - GDReeves
    5. 5. Timeline for Proposed Activities 2011 2064 “ Goal is to achieve natural background levels by 2064 (i.e., no manmade visibility impairment)” 2018 2028 2038 2048 2058 Every 10 years beginning in 2018 the previous SIP/FIP must be updated to account for current visibility and progress made toward the 2064 goal 2 nd SIP/FIP update for RHR is due in 2018 2-04-11 NGS Owners Initial Proposal - GDReeves
    6. 6. Timeline for Proposed Activities 2011 2064 2018 2028 2038 2048 2058 2 nd SIP/FIP update for RHR is due in 2018 NGS Site Lease Termination (12/23/19) 2-04-11 NGS Owners Initial Proposal - GDReeves
    7. 7. Key Durations <ul><li>Lease Negotiation and Navajo Nation Approval </li></ul><ul><ul><li>Assume End of 2011 </li></ul></ul><ul><li>NEPA Process – (EIS required) </li></ul><ul><ul><li>Current average 5.9 years </li></ul></ul><ul><ul><li>Assume 6 years </li></ul></ul><ul><li>DOI Approval of all Grants and Leases </li></ul><ul><ul><li>Assume 6 months </li></ul></ul>2-04-11 NGS Owners Initial Proposal - GDReeves
    8. 8. Key Durations <ul><li>Legal Challenges - Assume 2 years </li></ul><ul><li>Design, Procurement and Installation of SCR </li></ul><ul><ul><li>43 months for 1 st unit </li></ul></ul><ul><ul><li>67 months for all 3 units </li></ul></ul><ul><li>Scheduled Unit Outages </li></ul><ul><ul><li>Major Outages </li></ul></ul><ul><ul><ul><li>2009, 2010, 2011 </li></ul></ul></ul><ul><ul><ul><li>2015, 2016, 2017 </li></ul></ul></ul><ul><ul><ul><li>2021, 2022, 2023 </li></ul></ul></ul><ul><ul><ul><li>2027, 2028, 2029 </li></ul></ul></ul>2-04-11 NGS Owners Initial Proposal - GDReeves
    9. 9. Key Owner Requirements <ul><li>No Major Capital Expenditures Until Lease is Approved, Grants are Issued, Ownership Resolved </li></ul><ul><li>Tie-In Outages Occur Simultaneous with Planned Major Outages. </li></ul><ul><ul><li>2 Months Required for Tie-in Outages </li></ul></ul><ul><ul><li>2 Months Required for Major Outages </li></ul></ul>2-04-11 NGS Owners Initial Proposal - GDReeves
    10. 10. Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 2-04-11 NGS Owners Initial Proposal - GDReeves
    11. 11. Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) 2-04-11 NGS Owners Initial Proposal - GDReeves
    12. 12. Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Process (Comp - 12/31/17) 2-04-11 NGS Owners Initial Proposal - GDReeves
    13. 13. Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Process (Comp - 12/31/17) 2-04-11 NGS Owners Initial Proposal - GDReeves
    14. 14. Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Process (Comp - 12/31/17) Legal Challenges (2 years ?) 2-04-11 NGS Owners Initial Proposal - GDReeves
    15. 15. Key Dates 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Process (Comp - 12/31/17) 2 nd SIP/FIP update for RHR is due in 2018 Legal Challenges (2 years ?) 2-04-11 NGS Owners Initial Proposal - GDReeves
    16. 16. Proposed SCR Installation Period 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Process (Comp - 12/31/17) 2 nd SIP/FIP update for RHR is due in 2018 SCR Design and installation Duration Legal Challenges (2 years ?) 2-04-11 NGS Owners Initial Proposal - GDReeves
    17. 17. Installation Period Required if SCR is required in this BART 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Process (Comp - 12/31/17) 2 nd SIP/FIP update for RHR is due in 2018 SCR Design and installation Duration Legal Challenges (2 years ?) 2-04-11 NGS Owners Initial Proposal - GDReeves
    18. 18. IF Owners don’t take Risk of installing SCR without knowing NEPA outcome 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Process (Comp - 12/31/17) 2 nd SIP/FIP update for RHR is due in 2018 SCR Design and installation Duration Legal Challenges (2 years ?) 2-04-11 NGS Owners Initial Proposal - GDReeves
    19. 19. Proposed SCR Installation Period 2011 NGS Site Lease Termination (12/23/19) 3 3 3 2 2 2 1 1 1 Lease Negotiations and Approvals (12/31/11) NEPA Process (Comp - 12/31/17) 2 nd SIP/FIP update for RHR is due in 2018 SCR Design and installation Duration Legal Challenges (2 years ?) 2-04-11 NGS Owners Initial Proposal - GDReeves

    ×