L&T Construction| 1
Sensitivity: LNT Construction Internal Use
Design & Build-
Free Trade Warehousing Zone
at JNPT, Mumbai
L&T Construction| 2
Sensitivity: LNT Construction Internal Use
Design & Build- Free Trade Warehousing Zone at JNPT,
Mumbai
Weekly Progress Report
26-Dec-2022 to 01-Jan-2023 (Week No-114)
L&T Construction| 3
Sensitivity: LNT Construction Internal Use
Contents
1 General Details
2 EHS Report
3 Overall Progress
4 Schedule Progress Update
5 Agency approvals
6 Finishing Schedule
7 Statutory approvals
8 Progress Report Pictorial View
9 Methodology/Risk assessment approval summary
10 Material / Agency Approval Summary
11 Resource Report
12 Quality report
13 Document submission status/Input required- Client
14 List of Action points among DP World and JNPT SEZ Team
15 Photographic report
16 Insurance Details
L&T Construction| 4
Sensitivity: LNT Construction Internal Use
General Details
Name of Employer M/s Nhava Sheva Business Park Pvt. Ltd.
Name of Design Consultant M/s C R Narayan Rao Pvt. Ltd.
Name of the Contractor M/s Larsen & Toubro Ltd.
Name of Project Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai
Project Start Date 20th Oct 20
Scheduled End Date
Phase 1- 19th Dec 2021
Phase 2- 19th Apr 2022
No. of Days of Contract 546 Days
Scope of Work Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai
L&T Construction| 5
Sensitivity: LNT Construction Internal Use
EHS Report- Photographs
PEP talk given to workmen about Repairing Work PEP talk about Safe Work during Material handling
L&T Construction| 6
Sensitivity: LNT Construction Internal Use
EHS Report
Sl. No. Description This week Total
1 No. of Manhours Worked 20048 4595400
2 No. of accidents reported - 1
3 No. of near misses - 6
4 Lost time injury (LTI) - 1
5 Safety Observation 2 298
6 Safety Induction 12 7639
7 Training / Awareness Session. 2 201
8 Mass Toolbox Talks conducted 2 370
9 No. of safety site walks conducted 1 106
L&T Construction| 7
Sensitivity: LNT Construction Internal Use
Admin Interior Work
Task Name Remarks
•Admin (GF)
Painting – Final Coat- Pending
Carpet laying & aluminum skirting- Completed
Granite on ledge wall fixing- Completed
Flooring in Reception area – Lift lobby floor tile pending
Toilet Cubical installation- Completed
MEP accessories in Toilet- Completed
•Admin (FF)
Painting – Final Coat- Pending
Carpet laying & aluminum skirting- Completed
Granite on ledge wall fixing –Completed
Toilet Cubical installation- Completed
MEP accessories in Toilet- Completed
L&T Construction| 8
Sensitivity: LNT Construction Internal Use
Admin Interior Work
Task Name Remarks
•Admin (SF)
Painting –Pending
Carpet laying & aluminum skirting- Ongoing
Granite on ledge wall fixing – Completed
Toilet Cubical installation- Completed
MEP accessories in Toilet- Almost Completed
Terrace
Granite Counter- Almost Completed
Painting
L&T Construction| 9
Sensitivity: LNT Construction Internal Use
Progress Report Pictorial View
Subgrade
GSB
DLC
Flooring
W-3
W-2
W-1
WMM
W-3
SUB.
W-6
Paver Block
DBM
Parking
UG
BC
W-6
Grass Crete
PQC
W-4
W-5
W-4
L&T Construction| 10
Sensitivity: LNT Construction Internal Use
Resource Report
Manpower
Staff Description Nos. Remark
Project Management &
Planning
03 -
Account & Admin 01 -
EHS 01 -
QA/QC 01 -
P&M 01 -
Execution-Civil & PEB 07 -
Execution-MEP 05 -
Total- 19 Nos.
Workmen Description Nos. Remark
Driver/Operator 9 -
Workmen & Helper 222 -
Workmen (Temp. Works) 5 -
Supervisor & Others 23 -
Total- 273 Nos.
Machinery
Type Nos.
Backhoe loader 01
Roller 01
Tractor 01
Boom lift 05
Trailer 01
F-15 01
L&T Construction| 11
Sensitivity: LNT Construction Internal Use
IGBC Critical Client Points
S No Description Remarks
1 Landscape Drawing AutoCAD format with the mentioned area marked – Tree Area, Shrub Area, Total Landscape
Area, Lawn (Turf) Area, and Number of Trees. Plant & Trees Species to be specified.
Pending
2 Tkm calculation Sheet to satisfy Case A & Case B mentioned in via Email Need to modify
3 MHE vehicles Invoice (Fork lift + Pallet Truck + Reach Truck) till date. Received
4 MHE vehicles and charging point photos (With signage) Photo Shared, Signages Required
5 Golf cart Invoice Received
6 Golf Cart calculation ensuring 5% of occupants (excluding visitors) are catered Received
7
Declaration mentioning
Organise atleast two outreach/ educational programmes in a year on eco-friendly practices/ green initiatives.
The outreach/ educational programmes can include, but not limited to, clean & green, water conservation, energy
conservation, waste segregation & recycling, use bio-degradable plastic/ avoid single use plastic, air pollution, world
green building week and earth hour
-
8
Declaration mentioning
Atleast 75 % of the fleet (road fleet) complies with BS IV or latest emissions norms.
(And)
Entire fleet (road fleet) of the service provider will be periodically serviced to ensure efficient vehicle performance.
(And)
Awareness programmes will be organised periodically, by the service provider, to train the drivers on vehicle maintenance
and driving etiquette.
-
L&T Construction| 12
Sensitivity: LNT Construction Internal Use
IGBC Critical Client Points
S No Description Remarks
9 Provide Posters with education material for drivers shall be placed in drivers’ dormitories or resting areas (vehicle
maintenance and driving etiquette)
Pending
10 No smoking area photos with signage
Pending
11 Floor plans with waste bins Proposal Received, Yet to send to CEFD Team
12 Organic Waste Composter with capacity of 160Kg/day to be installed (occupant number considered – 1650)
Pending
12
Install permanent educational signage in common areas of the park/ warehouse with green concepts such as Go Green,
Save Earth; Water is Precious, Save it; Turn off Lights, when not in use; Say no to Mixed Waste; Plant a Tree, Save the
Environment, etc
-
14
Undertaking for shuttle service connecting local public transit stops in the operating stage – Kindly reshare as the document
file got corrupted
-
15
Project Activity to be identified for Green activity beyond fence. Below are the IGBC recommended projects –
• RainWater Harvesting
• Sewage Treatment Plant
• Water Body
• Public Parks/Avenues
• Mass Plantation
• Renewable Energy
• Basic Facilities like – Provide at least four of the following : Bus Shelters, Street Lighting, Public toilets, Play area &
Sports kit, Tot-lot, Drinking water ATM or equipment, Organic waste management, other basic facilities
-
L&T Construction| 13
Sensitivity: LNT Construction Internal Use
Document submission status/Input required- Client
 Handover for Wh-1 & 2 – Taking Over Certificate issuance
 Disbursement of RAB-22 Main works
 Tax Invoice raise confirmation against of RAB-3 Interior works
 Tax Invoice raise confirmation against of RAB-24 Interior works
 EOT approval
 Road Marking details approval
 Column guard proposal confirmation
 Admin Building High resolution graphics details
 Cold Storage Cage ladder finalization
 View confirmation of cladding fixed over WH-1 & 2 wall along Grid 22
 Change order confirmation (Reefer & ELV)
L&T Construction| 14
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building
L&T Construction| 15
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building
L&T Construction| 16
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building GF Lift Lobby Admin Building GF Custom Reception
L&T Construction| 17
Sensitivity: LNT Construction Internal Use
Site Photographs
Staircase Admin Building SF Conference table Completed
L&T Construction| 18
Sensitivity: LNT Construction Internal Use
Site Photographs
Warehouse-02 Bollard Installed Warehouse-01 Bollard Installed
L&T Construction| 19
Sensitivity: LNT Construction Internal Use
Site Photographs
Warehouse-03 Bollard Installation ongoing Warehouse-04 Bollard Installation ongoing
L&T Construction| 21
Sensitivity: LNT Construction Internal Use
Thank you!

More Related Content

Similar to WPR_02.01.2023 W-114 - Copy (1).pptx

Gemmen- Industrial Site Certification & Site Readiness
Gemmen- Industrial Site Certification & Site ReadinessGemmen- Industrial Site Certification & Site Readiness
Gemmen- Industrial Site Certification & Site ReadinessEMRoundtable
 
Cincinnati's Permits and Inspections Streamlining Initiative
Cincinnati's Permits and Inspections Streamlining InitiativeCincinnati's Permits and Inspections Streamlining Initiative
Cincinnati's Permits and Inspections Streamlining InitiativeHarry Black
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Cost effective construction and green building
Cost effective construction and green buildingCost effective construction and green building
Cost effective construction and green buildingManjunath N V
 
Green Hydrogen Financial Model Toolkit
Green Hydrogen Financial Model ToolkitGreen Hydrogen Financial Model Toolkit
Green Hydrogen Financial Model ToolkitFadi Maalouf, PMP
 
Environmental clearance of airports
Environmental clearance of airportsEnvironmental clearance of airports
Environmental clearance of airportsAbhishek Kumar Sinha
 
Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2Wallace Roberts & Todd
 
Project Induction Program 11.02.2016
Project Induction Program 11.02.2016Project Induction Program 11.02.2016
Project Induction Program 11.02.2016Lasantha Perera
 
District One Public Works Integrating Committee Applicant Workshop
District One Public Works Integrating Committee Applicant WorkshopDistrict One Public Works Integrating Committee Applicant Workshop
District One Public Works Integrating Committee Applicant WorkshopCuyahoga County Planning Commission
 
CV-ABDELKHALIG 2016 - CONSTRUCTION &MAINTENA NCE
CV-ABDELKHALIG 2016 - CONSTRUCTION &MAINTENA NCECV-ABDELKHALIG 2016 - CONSTRUCTION &MAINTENA NCE
CV-ABDELKHALIG 2016 - CONSTRUCTION &MAINTENA NCEAbdoo Sowar
 
Land Development Process - Orange County, Florida
Land Development Process - Orange County, FloridaLand Development Process - Orange County, Florida
Land Development Process - Orange County, FloridaScott Skraban, MPA, CH-ERIM
 
2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishmentsmckay
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management PlanAnuragBhat7
 
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14Competition Advisory Services (India) LLP
 
Cavalline presentation 4 13-10
Cavalline presentation 4 13-10Cavalline presentation 4 13-10
Cavalline presentation 4 13-10zaqqy
 

Similar to WPR_02.01.2023 W-114 - Copy (1).pptx (20)

Gemmen- Industrial Site Certification & Site Readiness
Gemmen- Industrial Site Certification & Site ReadinessGemmen- Industrial Site Certification & Site Readiness
Gemmen- Industrial Site Certification & Site Readiness
 
Cincinnati's Permits and Inspections Streamlining Initiative
Cincinnati's Permits and Inspections Streamlining InitiativeCincinnati's Permits and Inspections Streamlining Initiative
Cincinnati's Permits and Inspections Streamlining Initiative
 
CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016
 
Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Cost effective construction and green building
Cost effective construction and green buildingCost effective construction and green building
Cost effective construction and green building
 
Green Hydrogen Financial Model Toolkit
Green Hydrogen Financial Model ToolkitGreen Hydrogen Financial Model Toolkit
Green Hydrogen Financial Model Toolkit
 
Environmental clearance of airports
Environmental clearance of airportsEnvironmental clearance of airports
Environmental clearance of airports
 
Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2
 
Project Induction Program 11.02.2016
Project Induction Program 11.02.2016Project Induction Program 11.02.2016
Project Induction Program 11.02.2016
 
District One Public Works Integrating Committee Applicant Workshop
District One Public Works Integrating Committee Applicant WorkshopDistrict One Public Works Integrating Committee Applicant Workshop
District One Public Works Integrating Committee Applicant Workshop
 
Breeam
BreeamBreeam
Breeam
 
CV-ABDELKHALIG 2016 - CONSTRUCTION &MAINTENA NCE
CV-ABDELKHALIG 2016 - CONSTRUCTION &MAINTENA NCECV-ABDELKHALIG 2016 - CONSTRUCTION &MAINTENA NCE
CV-ABDELKHALIG 2016 - CONSTRUCTION &MAINTENA NCE
 
Land Development Process - Orange County, Florida
Land Development Process - Orange County, FloridaLand Development Process - Orange County, Florida
Land Development Process - Orange County, Florida
 
chinthaka silva
chinthaka silvachinthaka silva
chinthaka silva
 
2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management Plan
 
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
 
Cavalline presentation 4 13-10
Cavalline presentation 4 13-10Cavalline presentation 4 13-10
Cavalline presentation 4 13-10
 
Plexux holding
Plexux holdingPlexux holding
Plexux holding
 

Recently uploaded

8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessorAshwiniTodkar4
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257subhasishdas79
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information SystemsAnge Felix NSANZIYERA
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesRashidFaridChishti
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelDrAjayKumarYadav4
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdfKamal Acharya
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 

Recently uploaded (20)

8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 

WPR_02.01.2023 W-114 - Copy (1).pptx

  • 1. L&T Construction| 1 Sensitivity: LNT Construction Internal Use Design & Build- Free Trade Warehousing Zone at JNPT, Mumbai
  • 2. L&T Construction| 2 Sensitivity: LNT Construction Internal Use Design & Build- Free Trade Warehousing Zone at JNPT, Mumbai Weekly Progress Report 26-Dec-2022 to 01-Jan-2023 (Week No-114)
  • 3. L&T Construction| 3 Sensitivity: LNT Construction Internal Use Contents 1 General Details 2 EHS Report 3 Overall Progress 4 Schedule Progress Update 5 Agency approvals 6 Finishing Schedule 7 Statutory approvals 8 Progress Report Pictorial View 9 Methodology/Risk assessment approval summary 10 Material / Agency Approval Summary 11 Resource Report 12 Quality report 13 Document submission status/Input required- Client 14 List of Action points among DP World and JNPT SEZ Team 15 Photographic report 16 Insurance Details
  • 4. L&T Construction| 4 Sensitivity: LNT Construction Internal Use General Details Name of Employer M/s Nhava Sheva Business Park Pvt. Ltd. Name of Design Consultant M/s C R Narayan Rao Pvt. Ltd. Name of the Contractor M/s Larsen & Toubro Ltd. Name of Project Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai Project Start Date 20th Oct 20 Scheduled End Date Phase 1- 19th Dec 2021 Phase 2- 19th Apr 2022 No. of Days of Contract 546 Days Scope of Work Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai
  • 5. L&T Construction| 5 Sensitivity: LNT Construction Internal Use EHS Report- Photographs PEP talk given to workmen about Repairing Work PEP talk about Safe Work during Material handling
  • 6. L&T Construction| 6 Sensitivity: LNT Construction Internal Use EHS Report Sl. No. Description This week Total 1 No. of Manhours Worked 20048 4595400 2 No. of accidents reported - 1 3 No. of near misses - 6 4 Lost time injury (LTI) - 1 5 Safety Observation 2 298 6 Safety Induction 12 7639 7 Training / Awareness Session. 2 201 8 Mass Toolbox Talks conducted 2 370 9 No. of safety site walks conducted 1 106
  • 7. L&T Construction| 7 Sensitivity: LNT Construction Internal Use Admin Interior Work Task Name Remarks •Admin (GF) Painting – Final Coat- Pending Carpet laying & aluminum skirting- Completed Granite on ledge wall fixing- Completed Flooring in Reception area – Lift lobby floor tile pending Toilet Cubical installation- Completed MEP accessories in Toilet- Completed •Admin (FF) Painting – Final Coat- Pending Carpet laying & aluminum skirting- Completed Granite on ledge wall fixing –Completed Toilet Cubical installation- Completed MEP accessories in Toilet- Completed
  • 8. L&T Construction| 8 Sensitivity: LNT Construction Internal Use Admin Interior Work Task Name Remarks •Admin (SF) Painting –Pending Carpet laying & aluminum skirting- Ongoing Granite on ledge wall fixing – Completed Toilet Cubical installation- Completed MEP accessories in Toilet- Almost Completed Terrace Granite Counter- Almost Completed Painting
  • 9. L&T Construction| 9 Sensitivity: LNT Construction Internal Use Progress Report Pictorial View Subgrade GSB DLC Flooring W-3 W-2 W-1 WMM W-3 SUB. W-6 Paver Block DBM Parking UG BC W-6 Grass Crete PQC W-4 W-5 W-4
  • 10. L&T Construction| 10 Sensitivity: LNT Construction Internal Use Resource Report Manpower Staff Description Nos. Remark Project Management & Planning 03 - Account & Admin 01 - EHS 01 - QA/QC 01 - P&M 01 - Execution-Civil & PEB 07 - Execution-MEP 05 - Total- 19 Nos. Workmen Description Nos. Remark Driver/Operator 9 - Workmen & Helper 222 - Workmen (Temp. Works) 5 - Supervisor & Others 23 - Total- 273 Nos. Machinery Type Nos. Backhoe loader 01 Roller 01 Tractor 01 Boom lift 05 Trailer 01 F-15 01
  • 11. L&T Construction| 11 Sensitivity: LNT Construction Internal Use IGBC Critical Client Points S No Description Remarks 1 Landscape Drawing AutoCAD format with the mentioned area marked – Tree Area, Shrub Area, Total Landscape Area, Lawn (Turf) Area, and Number of Trees. Plant & Trees Species to be specified. Pending 2 Tkm calculation Sheet to satisfy Case A & Case B mentioned in via Email Need to modify 3 MHE vehicles Invoice (Fork lift + Pallet Truck + Reach Truck) till date. Received 4 MHE vehicles and charging point photos (With signage) Photo Shared, Signages Required 5 Golf cart Invoice Received 6 Golf Cart calculation ensuring 5% of occupants (excluding visitors) are catered Received 7 Declaration mentioning Organise atleast two outreach/ educational programmes in a year on eco-friendly practices/ green initiatives. The outreach/ educational programmes can include, but not limited to, clean & green, water conservation, energy conservation, waste segregation & recycling, use bio-degradable plastic/ avoid single use plastic, air pollution, world green building week and earth hour - 8 Declaration mentioning Atleast 75 % of the fleet (road fleet) complies with BS IV or latest emissions norms. (And) Entire fleet (road fleet) of the service provider will be periodically serviced to ensure efficient vehicle performance. (And) Awareness programmes will be organised periodically, by the service provider, to train the drivers on vehicle maintenance and driving etiquette. -
  • 12. L&T Construction| 12 Sensitivity: LNT Construction Internal Use IGBC Critical Client Points S No Description Remarks 9 Provide Posters with education material for drivers shall be placed in drivers’ dormitories or resting areas (vehicle maintenance and driving etiquette) Pending 10 No smoking area photos with signage Pending 11 Floor plans with waste bins Proposal Received, Yet to send to CEFD Team 12 Organic Waste Composter with capacity of 160Kg/day to be installed (occupant number considered – 1650) Pending 12 Install permanent educational signage in common areas of the park/ warehouse with green concepts such as Go Green, Save Earth; Water is Precious, Save it; Turn off Lights, when not in use; Say no to Mixed Waste; Plant a Tree, Save the Environment, etc - 14 Undertaking for shuttle service connecting local public transit stops in the operating stage – Kindly reshare as the document file got corrupted - 15 Project Activity to be identified for Green activity beyond fence. Below are the IGBC recommended projects – • RainWater Harvesting • Sewage Treatment Plant • Water Body • Public Parks/Avenues • Mass Plantation • Renewable Energy • Basic Facilities like – Provide at least four of the following : Bus Shelters, Street Lighting, Public toilets, Play area & Sports kit, Tot-lot, Drinking water ATM or equipment, Organic waste management, other basic facilities -
  • 13. L&T Construction| 13 Sensitivity: LNT Construction Internal Use Document submission status/Input required- Client  Handover for Wh-1 & 2 – Taking Over Certificate issuance  Disbursement of RAB-22 Main works  Tax Invoice raise confirmation against of RAB-3 Interior works  Tax Invoice raise confirmation against of RAB-24 Interior works  EOT approval  Road Marking details approval  Column guard proposal confirmation  Admin Building High resolution graphics details  Cold Storage Cage ladder finalization  View confirmation of cladding fixed over WH-1 & 2 wall along Grid 22  Change order confirmation (Reefer & ELV)
  • 14. L&T Construction| 14 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building
  • 15. L&T Construction| 15 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building
  • 16. L&T Construction| 16 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building GF Lift Lobby Admin Building GF Custom Reception
  • 17. L&T Construction| 17 Sensitivity: LNT Construction Internal Use Site Photographs Staircase Admin Building SF Conference table Completed
  • 18. L&T Construction| 18 Sensitivity: LNT Construction Internal Use Site Photographs Warehouse-02 Bollard Installed Warehouse-01 Bollard Installed
  • 19. L&T Construction| 19 Sensitivity: LNT Construction Internal Use Site Photographs Warehouse-03 Bollard Installation ongoing Warehouse-04 Bollard Installation ongoing
  • 20. L&T Construction| 21 Sensitivity: LNT Construction Internal Use Thank you!