The document summarizes carbon capture and storage (CCS) projects in North Dakota that have received regulatory permits. It describes the adaptive management approach used to balance technical and financial risks during project development. It provides timelines and details of CCS projects like Red Trail Energy's ethanol plant capturing 3 million tons of CO2 and injecting it into the Broom Creek formation. It also outlines North Dakota's regulatory framework and incentives to support CCS deployment like the 45Q tax credit and how projects integrate different incentive programs and regulatory requirements.
6. CHALLENGES TO CCUS DEPLOYMENT
REGULATIONS AND PERMITTING
LONG-TERM LIABILITY
ECONOMICS
TECHNOLOGY PROOF OF CONCEPT
INFRASTRUCTURE DEVELOPMENT
7. ADAPTIVE MANAGEMENT APPROACH TO PROJECT
IMPLEMENTATION
• Staged approach to manage uncertainty
and inform investment strategy
• Implementation can be accelerated
– Higher investment needed at lower
levels of confidence
– Concurrent vs. sequential
development
– Balance financial and technical risk
♦ Site qualification
♦ Permitting
♦ Incentive programs and revenue
♦ Investment
♦ 45Q start of construction
8. Generalized Timeline to Implement Geologic CO2 Storage
Operations
Drill and construct injection and monitoring
wells; install infrastructure; update permits
Investment & Construction
Regulatory Review
of Permit
Project Design &
Permit Application
Feasibility
Baseline Monitoring
AOR (legacy wells)
Financial Assurance
Unitization & Project Exhibits
Qualify Site/Project
Design Specifications
FEED
45Q Start
Construction by
01/01/2033
File
Permits
Receive
Permit
Approvals
Storage Facility
Defined
No. Injection Wells
No. Monitoring Wells
Go/
No-Go
Acquire pore space and
negotiate access agreements
Screening
Go/
No-Go
FID
Go/
No-Go
(3-6 months) (9-18 months) (6-18 months) (7-12 months +)
Legacy Data
Acquire
Site-Specific Data
Compliance with IRS 45Q Tax Credit Program:
EPA-Approved GHGR Subpart RR MRV Plan
Projects that Qualify for CARB LCFS Markets::
CARB LCFS Permanence Protocol
Welll Logs
Core Analysis
Sampling/Testing
Seismic
9. CO2 Point Sources
• Ethanol production
• Coal-fired power generation
• Gasification
• Fertilizer production
• Natural gas processing
• Natural gas power generation
• Industrial processes
Capture/Storage Models
• Source/sink-matched
• Source aggregation and storage hub
• Capture hub with distributed storage
• Hybrid storage with enhanced oil recovery,
minerals recovery, and/or other utilization
10. CCS PROJECTS IN NORTH DAKOTA
Broom Creek Formation: >10
billion tons CO2 storage
potential
RTE CCS: ~18 million tons
CO2 (if injecting up to 100
years)
Broom Creek Formation:
>10 billion tonnes CO2 Storage Potential
• Red Trail Energy CCS:
~3 million tonnes of CO2 total
~100,000 tonnes per year
• Project Tundra:
~77 million tonnes of CO2 total
~4 million tonnes per year
• Dakota Gasification Company:
~26 million tonnes of CO2 total
~3 million tonnes per year
Project
Tundra
Dakota
Gasification
Company
11. GEOLOGIC STORAGE PERMITS IN NORTH DAKOTA
Image credit – EERC
Red Trail Richardton Ethanol Broom Creek Storage Facility No. 1
– Approved October 19, 2021
CarbonSAFE North Dakota Storage Facility
– Approved January 21, 2022
12. RED TRAIL ENERGY, LLC
Richardton, ND
12
23 millionbushels
of Corn
46 Employees 233,000 tons of
Coproducts
64 milliongallonsof
Ethanol
Approximately $350 million
of EconomicImpact
Over $149 million
in Gross Sales
Coproducts
Support 220,000
head of Cattle
928 Investors
Corn Oil Sold
for Biodiesel
Corn-Based Biorefinery
13. CCS Components
& Major Activities
2021 2022
Q1 Q2 Q3 Q4 Q1 Q2 Q3
Characterization &
Monitoring*
Capture System
Permits & Wells
CCS Components
& Major Activities
2019 2020
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Characterization &
Monitoring*
Capture System
Permits & Wells
Capture
Bids
Seismic Data
Acquisition
Near-Surface
Monitoring (start)
Drill RTE-10
Injection Well**
Well Design/Permit
Application (start)
*Includes
modeling/simulation
updates with major
data acquisition
events
**Stratigraphic test
(coring, testing,
logging)
Capture
Start
Injection
Start
Operational
Monitoring
Capture
Construction (start)
Core, Testing, & Downhole/
Baseline Monitoring
13
Contract
Capture System
Drill RTE-10.2
Monitoring Well**
Baseline
Monitoring
RTE CCS ACTIVITES TIMELINE
1st ND Class VI
APPROVED
Class VI
Application
16. CCS Components
& Major Activities
2022 2022
Q1 Q2 Q3 Q4 Q1 Q2 Q3
Characterization &
Monitoring*
Capture System
Permits & Wells
CCS Components
& Major Activities
2020 2021
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Characterization &
Monitoring*
Capture System
Permits & Wells
Environmental Information
Volume (EIV) Drafted
Seismic Data
Acquisition
Near-Surface
Monitoring (start)
Drill J-LOC1
Well Design/Permit
Application
(J-ROC and J-LOC1)
*Includes
modeling/simulation
updates with major
data acquisition
events
**Stratigraphic test
(coring, testing,
logging)
EIV Submitted to
the DOE
Core, Testing, & Downhole/
Baseline Monitoring
16
Baseline
Monitoring
PROJECT TUNDRAACTIVITIES TIMELINE
Drill J-ROC1
Class VI Permits
Submitted
Class VI Permits
Approved
Permit to Drill
(Injection wells)
17. Milton R. Young
Station
CarbonSAFE
Phase III
Strat Test
(J-ROC1)
1 mile
CarbonSAFE
Phase II
Strat Test
(BNI-1)
J-LOC1 Well
(Potential
Monitor)
Facility
Coal fired power plant which can supply 250
MW (Unit 1) and 455 MW (Unit 2)
Tonnage ~4 million tonnes per annum
Injector Design
Three CO2 injectors into two storage
reservoirs: the Broom Creek and the Dead
Regulatory
Status (NDIC) Class VI Permit approved
PROJECT TUNDRA SITE
18. DAKOTAGASIFICATION
COMPANY GREAT
PLAINS CO2
SEQUESTRATION
PROJECT
• CO2 Capture Began in 2000
• 40 MMt Captured
• 26 MMt over an ~12-year injection
period
• First project to implement a pattern
injection approach to optimize
storage and project footprint
• Pending state approval
19. STORAGE FACILITY PERMIT
North Dakota CO2 Storage Facility
Permit (Class VI) Checklist
Pore Space Access
Geologic Exhibits
Geologic Model and Simulations
Area of Review (AOR)
Supporting Plans
Testing and Monitoring Plan
Postinjection Site and Facility Closure Plan
Emergency and Remedial Response Plan
Worker Safety Plan
Well Casing and Cementing Program
Plugging Plan
Financial Assurance Demonstration Plan
Injection Well and Storage Reservoir Information
19
20. GEOLOGIC EXHIBITS
North Dakota CO2 Storage Facility
Permit (Class VI) Checklist
Storage Reservoir
Minerology
Mechanisms of Geologic Confinement
Geochemical Information of the Injection
Zone
Confining Zones
Upper Confining Zone
Additional Overlying Confining Zones
Lower Confining Zone
Geomechanical Information of Confining
Zone
Faults, Fractures, and Seismic Activity
Potential Mineral Zones
20
21. STORAGE FACILITY PERMIT TIMELINE
App
Submitted
Draft Permit
Reg. Review
(60 days)
Landowner
Mineral
Notice
(45 Days)
Public Comment
Period
(30 days)
Public
Hearing
Public
Comment
Response
Final
Permit
Three Parts
1. Geologic Storage
2. Amalgamation
3. Financial Assurance
Response to significant comments
Written comments on draft permit
22. INTEGRATING PERMITTINGAND INCENTIVE PROGRAMS
22
LCFS Pathway
Certified CI Values
CO2 Credits
North Dakota CO2
SFP (Class VI)
California CCS
Protocol: CCS
Permanence
Certification
MRV Plan
CCS Project
Certification
Sequestration
Site
Certification
EPA Greenhouse Gas
Reporting Program
(GHGRP) Subpart
Resource Recovery (RR)
IRS Section 45Q
CCS Tax Credits
[+ 3rd party reviews]
[+ 3rd party verification]
Enhancement of Carbon Dioxide
Sequestration Credit (a.k.a. Section
45Q): Approved EPA Monitoring,
Reporting, and Verification (MRV) Plan
Low Carbon Fuel Standard (LCFS)
with CCS: Certified Carbon Intensity (CI)
Value + CCS Protocol Certification
23. CCS
INCENTIVES
• No sales tax on capture-
related infrastructure
• No sales tax on CO2 sold
for EOR
• Coal conversion tax: tax
reduction with CO2
capture (up to 50%)
• No sales tax on
construction of pipeline
• Property tax-exempt for 10
years (equipment)
• No sales tax on CO2 EOR infrastructure
• 0% extraction tax for 20 years for tertiary
incremental recovery
• Production tax still applies
• Projects beginning construction before January 1, 2033, can
claim credits for 12 years after operations begin.
• Tax credits claimed by the taxpayer capturing the emissions or
transferred to operators of CO2 EOR projects.
• Tax credit for CO2 stored in a qualified EOR project (10-year
ramp-up to a maximum of $60/tonne in 2033).
• Tax credit for CO2 stored in a saline formation (10-year ramp-up
to a maximum of $85/tonne in 2033).
45Q Tax Credits
• Credits trading price range
$218 - $64 per ton (October
2022)
West Coast LCFS
Markets
North Dakota CCUS Incentives
Image Credit – EERC
EPA GHGRP
Subpart RR MRV Plan
(IRS 45Q)
Monitoring Area
Delineation
Leakage Pathways
Evaluation
Mass Balance and
Sequestration
Volumes
24. The adaptive management approach
developed at the EERC has helped guide
projects towards successful CCS projects.
CCS projects are incentivized to operate
based on a variety of voluntary markets
each with their own regulatory
requirements.
The risk of a project is contingent on
financial scope and expected timelines.
BALANCING INCENTIVES AND TECHNICAL RISKS
25. Lessons Learned:
Outreach
Open houses
Results of geologic characterization and
monitoring provided to landowners
Webpage with FAQ
Visibility in the community
Frequent engagement and briefings to
regulators and county/city
commissioners
Alternative approaches to in-person
outreach activities
– Informational videos, virtual question-
and-answer forums, and a series of
media/materials releases, etc.
25
Images Credit: Energy &
Environmental Research Center
26. Energy & Environmental
Research Center
University of North Dakota
15 North 23rd Street, Stop 9018
Grand Forks, ND 58202-9018
www.undeerc.org
701.777.5000 (phone)
701.777.5181 (fax)
Josh Regorrah
Permitting and Regulatory Specialist
jregorrah@undeerc.org
701.777.5346 (phone)
THANK YOU Critical Challenges. Practical Solutions.