BUILDING SCIENCE 2
PROJECT 2
INTEGRATION OF DAYLIGHTING & ARTIFICIAL LIGHTING STRATEGIES IN
MEDAN PASAR COMMUNITY LIBRARY DESIGN
TEO CHONG YIH
0314660
TUTOR: AR. EDWIN
1.0 Introduction
1.1 Objectives
1.2 ProjectIntroduction
2.0 Drawings
2.1 FloorPlans
2.2 Sections
3.0 LightAnalysis
3.1 DaylightAnalysisFormula
3.2 Shadowcasting
3.3 Artificial LightingAnalysisFormula
4.0 DaylightAnalysis
 Space A: Lobby
 Space B: Individual StudyArea
5.0 Artificial LightingAnalysis:
 Space A: Lobby
 Space B: Individual StudyArea
6.0 Reference
1.0 INTRODUCTION
1.1 Objectives
Thisprojectaimsto promote the understandingif the principlesof lightingbyintegrate withthe
communitylibrarydesign. Besides,thisprojectalsoaimstoimprove the designsolvingskillsinrelation
to sustainabilityissuesbasedonthe natural lightingandsite analysis.Thisprojectencompasses
advanceddaylightingsystemsandthe integrationsof electrical lighting,aswell asPSALImethodas
strategiesforlightingconditionsandproduce architectural qualityspaces.
1.2 Project introduction
The communitylibraryislocatedatJalan Hang Kasturi nearbyMedanPasar square.The conceptof the
libraryis“enhance the historyof the site bytying historical piecemeal of the site throughreminiscesof
the streetscape andrevitalize the area”.Derived fromthe site perception,“humanassignboard”comes
fromthe protrudingof the signboardaround the site whichisa clearand strong representationthe
character of the site itself aspeoplemeanderthroughthe site. The formof the buildingissplitintotwo
blocksto create an internal streettolinkthe spacesandencourage people towalkin. The splitcreated
a voidwhere the twistingof eachfloorcreate the differentinterestingview pointandalsoincrease the
passive contact.The voidallows penetrationof the light intothe libraryspacestoincrease the
sustainabilityof the library.
2.0 DRAIWNGS
GROUND FLOOR PLAN
SCALE 1: 150
FIRST FLOORPLAN
SCALE 1: 150
SECONDFLOOR PLAN
SCALE 1: 150
THIRD FLOOR PLA
SCALE 1: 150
SECTION
3.0 Lighting analysis
3.1 DaylightFactorAnalysis
Daylightfactoris definedasthe rationof interiorilluminance,Ei toavailable outdoorilluminance Eo
whichisunobstructedhorizontal exteriorilluminance:
DF = Ei (IndoorIlluminance) x 100%
Eo (OutdoorIlluminance)
ZONE DF (%) Distribution
Verybright >6 Large (includingthermal andglare problem)
Bright 3 – 6 Good
Average 1-3 Fair
Dark 0-1 Poor
Figure 3.1.1 Daylightfactorsand distribution(Departmentof standardMalaysia2007)
The daylightfactorconceptis applicable onlywhenthe skyilluminance distributionisknownorcan
reasonablybe estimated.Inthiscase study,the average outdoorilluminance inMalaysiaisassumed
accordingto the standardwhichis20000 lux.
Luminance level (lux) Example
120, 000 Brightestsunlight
110, 000 Brightsunlight
20, 000 Shade illuminatedbyentireclearblue sky,midday
1000 - 2000 Typical overcastday,midday
400 Sunrise/sunsetonclearday(ambientillumination)
<200 Extreme of darkeststormclouds,midday
40 Fullyovercast,sunrise/sunset
<1 Extreme oddarkeststormcloud,sunrise/sunset
Figure 3.1.2 Daylightintensityatdifferentcondition
Average Daylightfactor
Inside rooms,the maximumDFisnearthe windows,anditismainlydue tosky component.Inthe early
stagesof buildingdesign,the average daylightfactormaybe usedto assessthe adequacyof daylight:
Average 𝐷𝐹 =
𝑊
𝐴
×
𝑇0
(1−𝑅)
Where:W is the area of the window(m2
)
A is the total area of the internal surfaces(m2
)
T isthe glass transmittance correctedfordirt
0 isvisible skyangle indegreesfromthe centerof the window
R isthe average reflectance of areaA.
The valuesof these quantitiesare determinedformthe givendataandW,T and R are correctedby
usingfactorsgiveninthe BS DaylightCode andotherpublications.
3.2 Shadowcasting
Date: 21 June 2017
Time:9 a.m.
Weathercondition:Sunny
The morningsun fromthe East directionblockedbythe shophouses,mostof the spacesisaffectedby
the blockingof the sunlightfromEastdirection.
Date: 21 June 2017
Time:12 p.m.
Weathercondition:Sunny
Duringthishour,the directionof the sunlightiscomingfrom top.The excessive strongsunlightis
reducedasit isfilteredthroughthe louvers.
Date: 21 June 2017
Time:5 p.m.
Weathercondition:Sunny
The eveningsunaffectsthe westernsideof the buildingwhichisthe frontfaçade,butthe highrise hotel
infront of the libraryblockedmostof the sunlight Inorder to avoiduserdiscomfort,the frontfaçade is
installedwithmotorizedlouverstoreduce the directpenetrationof the eveningsun.Andthe greenery
area locatedat the secondflooract as a bufferzone andreduces the directsunlightfromenteringthe
spaces.
3.3Artificial Lighting Analysis
Lumen Method
Lumen method can be also calculated and used to determine the number of light should be installed on the
site. To know the number of lamps, calculation of total luminance of the space need to be done based on
the number of fixtures and examines the sufficiency of light fixtures on that particular space.
𝑁 =
𝐸 × 𝐴
𝐹 × 𝑈𝐹 × 𝑀𝐹
Where,
N = Number of lamps required
E = Illuminance level required (Lux)
A = Area at working plane height (m2
)
F = Average luminous flux from each lump (lm)
UF = Utilization factor, an allowance for light distribution of the luminaire and the room surfaces
MF = Maintenance factor, an allowance for reduced light output because of deterioration and dirt
RoomIndex
RoomIndex,RI,isthe ratioof roomplanarea to haft wall areabetweenthe workingandluminaire
planes,
Whichcan be calculate by: 𝑅𝐼 =
𝐿 𝑥 𝑊
𝐻 𝑚 𝑥 (𝐿+𝑊)
Where,
L = Lengthof room
W = Widthof room
Hm = Mountingheight,the vertical distance betweenthe workingplaneandthe luminaire
4.0 Space A (Lobby) DaylightAnalysis
Ground Floor Plan
FloorArea(m2
) 67m2
Areaof façade exposedtolight(m2)
Perimeter=(2.85 x 2.1) + (5.5 x 1) + (3.6 x1)
Area = 15.1 m2
Areaof skylight(m2
) 0
Exposedfaçade tolight& skylightareatoFloor
area ratio(Daylightfactor)
Average 𝐷𝐹 =
𝑊
𝐴
×
𝑇0
(1−𝑅)
=
15.1
148.9
×
0.6×40
(1−0.5)
= 4.8 %
Daylightfactor,DF
𝐷𝐹 =
𝐸𝑖
𝐸𝑜
× 100%
4.8 = (
𝐸𝑖
30000
) × 100%
Ei = 4.8 × 300
= 1440 lux
Daylightcontour
From the daylightanalysis,the lobbyof the libraryhasa daylightfactorof 4.8 % and the natural
illumination of 1440 lux.The openinghave ahigherlux value assunlightispenetratedintothe space.
The natural illuminance ismore thansufficientthanthe standardilluminationrequirementof 100lux,
thusblindsare installedtoreduce glare toa more comfortable setting.
Space B (Individual studyarea) DaylightAnalysis
Third floor plan
FloorArea(m2
) 74 m2
Areaof façade exposedtolight(m2)
Perimeter=(4 x 1) + (3.3 x 1 ) + (5.5 x 1) + (2.0 x 1)
Area = 14.8
Areaof skylight(m2
) 0
Exposedfaçade tolight& skylightareatoFloor
area ratio(Daylightfactor)
Average 𝐷𝐹 =
𝑊
𝐴
×
𝑇0
(1−𝑅)
=
14.8
165.3
×
0.6 ×90
(1−0.5)
= 9.72 %
Daylightfactor,DF
𝐷𝐹 =
𝐸𝑖
𝐸𝑜
× 100%
9.72 = (
𝐸𝑖
30000
) × 100%
Ei = 9.72 × 300
= 2916 lux
Daylightcontour
From the daylightanalysis,the individual studyareahasa daylightfactorof 9.72 % and the natural
illuminationof 2916 lux.The standardilluminationrequirementof the space is300 lux,thusthe natural
illuminance ismore thansufficienttoilluminatethe space.Blindsare installedtoreduce glare forthe
usersto studycomfortablywithinthe space.
5.0 Space A (Lobby) Artificial lightingAnalysis
Fixture Properties
Type of fixture RecessmountedCircularLEDDownlight
Image of fixture
Type of luminous Warm white
Luminousflux (lm) 900 lm
Power(W) 15
ColourTemperature (K) 6000
Colourrenderingindex 70
Room Indexcalculation
Dimensionof room(m) L = 13.8, W = 7
Total floorarea(m2
) 67
Heightof ceiling(m) 3.85
Type of lightfixture RecessmountedcircularLED Downlight
Luminousflux of lighting,F(lm) 900
Heightof luminaires(m) 0
Heightof workingplane (m) 0.8
Mountingheight(Hm) 3.85 – 0.8 = 3.05
StandardilluminationrequiredaccordingtoMS
1525 and JKR
100
Roomindex,RI(K) RI =
𝐿 ×𝑊
𝐻𝑚 ×(𝐿+𝑊)
RI =
96.6
3.05×(13.8+ 7)
= 1.52
LumenMethodCalculation
Reflectance factor
Plasterwall:0.45 Concrete ceiling:0.7 Woodenflooring:0.3V
Numberof lights(N)
Lux required,IESStandardillumination(E) 100
Areaat workingplane height(A,m2
) Dimensionsof Workshop = 67m2
LuminousFlux (F) 900 lm
Utilizationfactor(UF) 0.59
Maintenance factor(MF) 0.8 (standard)
LumenCalculation(N,numberof lights)
𝑁 =
𝐸 × 𝐴
𝐹 × 𝑀𝐹 × 𝑈𝐹
𝑁 =
100 × 67
900 × 0.59 × 0.8
𝑁 = 15.77
𝑁 = 16 𝑙𝑖𝑔ℎ𝑡𝑠
Spacingto heightratio,SHR
𝑆𝐻𝑅 = 1/Hm x √
𝐴
𝑁
= 1/3.05 x
√67
16
= 0.67
SHR = S/Hm
0.67 = S/3.05
S = 2.044m
Fittinglayout Fittingrequiredalong13.8mwall,
10/2.044 (m) = 4.89 ~ 5 rows
Numberof lampsineach row,
16/5 = 3.2 ~ 3 lamps
Spacingrequiredfor7m wall,
7/3 =2.33m
Spacingrequiredfor13.8m wall,
13.8/5 = 2.76m
Fristspacingfor the 13.8m wall will be half of the S,2.76/2 = 1.38m
Fristspacingfor the 7m wall will be 2.33 / 2 = 1.17m
Space A PSALI Method
LightFittingSpacingDiagram(ReflectedCeilingPlan)
Artificial LightContourDiagram
The previousdaylightcontourdiagramshownthatthe lobbyreceivesnatural lightenteredthroughthe
openingsalongthe walls.However asit islocatedonthe groundfloor, the sunlightpenetrationis
insufficienttoilluminate the space.The artificial lightingcontourabove showsthe lightingcondition
afterthe lightingfixture isinstalledandplannedalongthe space.The lightsource isdistributedevenly
throughoutthe space.RecessmountedcircularceilingLEDDownlightdistributes low luminouslevelsas
requiredby MS 1525 for a lobbyspace.
Space B (Individual study area) Artificial LightingAnalysis
Type of fixture LED PendentLight
Image of fixture
Type of luminous Warm white
Luminousflux (lm) 2800 lm
Power(W) 47
ColourTemperature (K) 5000
Colourrenderingindex 80
Room Indexcalculation
Dimensionof room(m) L = 15.8, W = 4.2
Total floorarea(m2
) 74m2
Heightof ceiling(m) 3.85
Type of lightfixture LED PendentLight
Luminousflux of lighting,F(lm) 618
Heightof luminaires(m) 3.85 – 0.45 – 0.8 = 2.6m
Heightof workingplane (m) 0.8
Mountingheight(Hm) 3.85 – 0.8 = 3.05
StandardilluminationrequiredaccordingtoMS
1525 and JKR
300
Roomindex,RI(K) RI =
𝐿 × 𝑊
𝐻𝑚 ×(𝐿+𝑊)
RI =
66.4
3.05×(15.8+ 4.2)
= 1.10
Lumen MethodCalculation
Reflectance factor
Plasterwall:0.45 Concrete ceiling:0.7 Woodenflooring:0.3
Numberof lights(N)
Lux required,IESStandardillumination(E) 300
Areaat workingplane height(A,m2
) Dimensionsof Workshop = 74m2
LuminousFlux (F) 800 lm
Utilizationfactor(UF) 0.59
Maintenance factor(MF) 0.8 (standard)
LumenCalculation(N,numberof lights)
𝑁 =
𝐸 × 𝐴
𝐹 × 𝑀𝐹 × 𝑈𝐹
𝑁 =
300 × 74
2800 × 0.59 × 0.8
𝑁 = 16.79
𝑁 = 16 𝑙𝑖𝑔ℎ𝑡𝑠
Spacingto heightratio,SHR
𝑆𝐻𝑅 = 1/Hm x √
𝐴
𝑁
= 1/3.05 x
√74
16
= 0.71
SHR = S/Hm
0.71 = S/3.05
S = 2.166m
Fittinglayout Fittingrequiredalong15.8mwall,
15.8/2.166 (m) = 7.295 ~ 7rows
Numberof lampsineach row,
16/7 = 2.285 ~ 2lamps
Spacingrequiredfor4.2m wall,
4.2/2 = 2.1m
Spacingrequiredfor15.8 wall,
15.8/13 = 2.26m
Fristspacingfor the 15.8m wall will be half of the S, 2.26/2 = 1.13m
Fristspacingfor the 4.2m wall will be 2.1/ 2 = 1.05m
Space B PSALI Method
LightFittingSpacingDiagram(ReflectedCeilingPlan)
Artificial LightContourDiagram
The previousdaylightcontourdiagramindicatesthatthe individual studyareareceivesnatural light
throughthe openingsandvoid.However,some of the sunlightisblockedbythe wallswhichcauses
unevensunlightdistribution.The artificial lightingcontourabove showsthe lightingconditionafterthe
lightingfixture isinstalledandplannedalongthe space.The lightsource isdistributedevenlythroughout
the space.The LED pendantlightdistributes 800lmof luminousflux toilluminatethe space sufficiently
for the usersto studyinthe evening.
6.0 Reference
MS 1525 2014 | BuildingInsulation|Ventilation(Architecture).(2017).Scribd.
Materials- LightReflectingFactors.(2017). Engineeringtoolbox.com.
LED Pendantlight-guidingpanel type |SmartArchi |lighting|Eco solutions|Business|Panasonic
Global.(2017). Panasonic.net.
LED DownLight| Consumer| Products| India| lighting|Eco solutions|Business|PanasonicGlobal.
(2017). Panasonic.net.

More Related Content

What's hot

Lighting Integration Project
Lighting Integration ProjectLighting Integration Project
Lighting Integration Project
jisunfoo
 
Building Science II Project 2: Report
Building Science II Project 2: ReportBuilding Science II Project 2: Report
Building Science II Project 2: Report
Ong Shi Hui
 

What's hot (20)

B science project 2
B science project 2B science project 2
B science project 2
 
Building Science II
Building Science IIBuilding Science II
Building Science II
 
Final report
Final reportFinal report
Final report
 
Building Science Project 2
Building Science Project 2Building Science Project 2
Building Science Project 2
 
Building Science 2
Building Science 2Building Science 2
Building Science 2
 
A4 report
A4 reportA4 report
A4 report
 
School of architecture
School of architectureSchool of architecture
School of architecture
 
Bscience ii
Bscience ii Bscience ii
Bscience ii
 
Final report
Final reportFinal report
Final report
 
community lib bsci
community lib bscicommunity lib bsci
community lib bsci
 
Lighting Integration Project
Lighting Integration ProjectLighting Integration Project
Lighting Integration Project
 
Building Science 2 Report
Building Science 2 ReportBuilding Science 2 Report
Building Science 2 Report
 
Building Science II Project 2: Report
Building Science II Project 2: ReportBuilding Science II Project 2: Report
Building Science II Project 2: Report
 
Building Science 2 (Project 2)
Building Science 2 (Project 2)Building Science 2 (Project 2)
Building Science 2 (Project 2)
 
Building science 2 project 2
Building science 2 project 2Building science 2 project 2
Building science 2 project 2
 
Building Science 2 Final Project Report
Building Science 2 Final Project ReportBuilding Science 2 Final Project Report
Building Science 2 Final Project Report
 
Building Science 2 Final Project
Building Science 2 Final ProjectBuilding Science 2 Final Project
Building Science 2 Final Project
 
Building Science 2
Building Science 2Building Science 2
Building Science 2
 
Building Science Project 2 Report
Building Science Project 2 ReportBuilding Science Project 2 Report
Building Science Project 2 Report
 
Lighting proposal
Lighting  proposalLighting  proposal
Lighting proposal
 

Similar to Building science project 2

Building science 2
Building science 2Building science 2
Building science 2
Eunice Chan
 

Similar to Building science project 2 (16)

Building Science_02_Report_Integration Project
Building Science_02_Report_Integration ProjectBuilding Science_02_Report_Integration Project
Building Science_02_Report_Integration Project
 
Building science 2
Building science 2Building science 2
Building science 2
 
Project 2 Building Science
Project 2 Building ScienceProject 2 Building Science
Project 2 Building Science
 
Final report project 2 GYN integration
Final report project 2 GYN integrationFinal report project 2 GYN integration
Final report project 2 GYN integration
 
Building Science II: Lighting Integration Report
Building Science II: Lighting Integration ReportBuilding Science II: Lighting Integration Report
Building Science II: Lighting Integration Report
 
Building science 2
Building science 2Building science 2
Building science 2
 
Bscience 2-project-2
Bscience 2-project-2Bscience 2-project-2
Bscience 2-project-2
 
Building Science P02
Building Science P02Building Science P02
Building Science P02
 
Bscience project 2
Bscience project 2Bscience project 2
Bscience project 2
 
Lighting Analysis: Integration project (Community library)
Lighting Analysis: Integration project (Community library)Lighting Analysis: Integration project (Community library)
Lighting Analysis: Integration project (Community library)
 
Bscience
BscienceBscience
Bscience
 
Bsc 2 project 2 report
Bsc 2 project 2 reportBsc 2 project 2 report
Bsc 2 project 2 report
 
Building science 2 final report
Building science 2 final reportBuilding science 2 final report
Building science 2 final report
 
REPORT AND CALCULATION
REPORT AND CALCULATIONREPORT AND CALCULATION
REPORT AND CALCULATION
 
Building Science Report
Building Science ReportBuilding Science Report
Building Science Report
 
Bb science project 2
Bb science project 2Bb science project 2
Bb science project 2
 

Recently uploaded

Seismic Method Estimate velocity from seismic data.pptx
Seismic Method Estimate velocity from seismic  data.pptxSeismic Method Estimate velocity from seismic  data.pptx
Seismic Method Estimate velocity from seismic data.pptx
AlMamun560346
 
GUIDELINES ON SIMILAR BIOLOGICS Regulatory Requirements for Marketing Authori...
GUIDELINES ON SIMILAR BIOLOGICS Regulatory Requirements for Marketing Authori...GUIDELINES ON SIMILAR BIOLOGICS Regulatory Requirements for Marketing Authori...
GUIDELINES ON SIMILAR BIOLOGICS Regulatory Requirements for Marketing Authori...
Lokesh Kothari
 
Conjugation, transduction and transformation
Conjugation, transduction and transformationConjugation, transduction and transformation
Conjugation, transduction and transformation
Areesha Ahmad
 
Biogenic Sulfur Gases as Biosignatures on Temperate Sub-Neptune Waterworlds
Biogenic Sulfur Gases as Biosignatures on Temperate Sub-Neptune WaterworldsBiogenic Sulfur Gases as Biosignatures on Temperate Sub-Neptune Waterworlds
Biogenic Sulfur Gases as Biosignatures on Temperate Sub-Neptune Waterworlds
Sérgio Sacani
 
Formation of low mass protostars and their circumstellar disks
Formation of low mass protostars and their circumstellar disksFormation of low mass protostars and their circumstellar disks
Formation of low mass protostars and their circumstellar disks
Sérgio Sacani
 
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 bAsymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Sérgio Sacani
 
Chemical Tests; flame test, positive and negative ions test Edexcel Internati...
Chemical Tests; flame test, positive and negative ions test Edexcel Internati...Chemical Tests; flame test, positive and negative ions test Edexcel Internati...
Chemical Tests; flame test, positive and negative ions test Edexcel Internati...
ssuser79fe74
 

Recently uploaded (20)

Site Acceptance Test .
Site Acceptance Test                    .Site Acceptance Test                    .
Site Acceptance Test .
 
Seismic Method Estimate velocity from seismic data.pptx
Seismic Method Estimate velocity from seismic  data.pptxSeismic Method Estimate velocity from seismic  data.pptx
Seismic Method Estimate velocity from seismic data.pptx
 
American Type Culture Collection (ATCC).pptx
American Type Culture Collection (ATCC).pptxAmerican Type Culture Collection (ATCC).pptx
American Type Culture Collection (ATCC).pptx
 
Nanoparticles synthesis and characterization​ ​
Nanoparticles synthesis and characterization​  ​Nanoparticles synthesis and characterization​  ​
Nanoparticles synthesis and characterization​ ​
 
GUIDELINES ON SIMILAR BIOLOGICS Regulatory Requirements for Marketing Authori...
GUIDELINES ON SIMILAR BIOLOGICS Regulatory Requirements for Marketing Authori...GUIDELINES ON SIMILAR BIOLOGICS Regulatory Requirements for Marketing Authori...
GUIDELINES ON SIMILAR BIOLOGICS Regulatory Requirements for Marketing Authori...
 
Conjugation, transduction and transformation
Conjugation, transduction and transformationConjugation, transduction and transformation
Conjugation, transduction and transformation
 
Clean In Place(CIP).pptx .
Clean In Place(CIP).pptx                 .Clean In Place(CIP).pptx                 .
Clean In Place(CIP).pptx .
 
Biogenic Sulfur Gases as Biosignatures on Temperate Sub-Neptune Waterworlds
Biogenic Sulfur Gases as Biosignatures on Temperate Sub-Neptune WaterworldsBiogenic Sulfur Gases as Biosignatures on Temperate Sub-Neptune Waterworlds
Biogenic Sulfur Gases as Biosignatures on Temperate Sub-Neptune Waterworlds
 
SAMASTIPUR CALL GIRL 7857803690 LOW PRICE ESCORT SERVICE
SAMASTIPUR CALL GIRL 7857803690  LOW PRICE  ESCORT SERVICESAMASTIPUR CALL GIRL 7857803690  LOW PRICE  ESCORT SERVICE
SAMASTIPUR CALL GIRL 7857803690 LOW PRICE ESCORT SERVICE
 
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...
 
Forensic Biology & Its biological significance.pdf
Forensic Biology & Its biological significance.pdfForensic Biology & Its biological significance.pdf
Forensic Biology & Its biological significance.pdf
 
9999266834 Call Girls In Noida Sector 22 (Delhi) Call Girl Service
9999266834 Call Girls In Noida Sector 22 (Delhi) Call Girl Service9999266834 Call Girls In Noida Sector 22 (Delhi) Call Girl Service
9999266834 Call Girls In Noida Sector 22 (Delhi) Call Girl Service
 
Proteomics: types, protein profiling steps etc.
Proteomics: types, protein profiling steps etc.Proteomics: types, protein profiling steps etc.
Proteomics: types, protein profiling steps etc.
 
GBSN - Microbiology (Unit 3)
GBSN - Microbiology (Unit 3)GBSN - Microbiology (Unit 3)
GBSN - Microbiology (Unit 3)
 
Formation of low mass protostars and their circumstellar disks
Formation of low mass protostars and their circumstellar disksFormation of low mass protostars and their circumstellar disks
Formation of low mass protostars and their circumstellar disks
 
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls AgencyHire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
 
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 bAsymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
 
Chemical Tests; flame test, positive and negative ions test Edexcel Internati...
Chemical Tests; flame test, positive and negative ions test Edexcel Internati...Chemical Tests; flame test, positive and negative ions test Edexcel Internati...
Chemical Tests; flame test, positive and negative ions test Edexcel Internati...
 
Botany 4th semester file By Sumit Kumar yadav.pdf
Botany 4th semester file By Sumit Kumar yadav.pdfBotany 4th semester file By Sumit Kumar yadav.pdf
Botany 4th semester file By Sumit Kumar yadav.pdf
 
CELL -Structural and Functional unit of life.pdf
CELL -Structural and Functional unit of life.pdfCELL -Structural and Functional unit of life.pdf
CELL -Structural and Functional unit of life.pdf
 

Building science project 2

  • 1. BUILDING SCIENCE 2 PROJECT 2 INTEGRATION OF DAYLIGHTING & ARTIFICIAL LIGHTING STRATEGIES IN MEDAN PASAR COMMUNITY LIBRARY DESIGN TEO CHONG YIH 0314660 TUTOR: AR. EDWIN
  • 2. 1.0 Introduction 1.1 Objectives 1.2 ProjectIntroduction 2.0 Drawings 2.1 FloorPlans 2.2 Sections 3.0 LightAnalysis 3.1 DaylightAnalysisFormula 3.2 Shadowcasting 3.3 Artificial LightingAnalysisFormula 4.0 DaylightAnalysis  Space A: Lobby  Space B: Individual StudyArea 5.0 Artificial LightingAnalysis:  Space A: Lobby  Space B: Individual StudyArea 6.0 Reference
  • 3. 1.0 INTRODUCTION 1.1 Objectives Thisprojectaimsto promote the understandingif the principlesof lightingbyintegrate withthe communitylibrarydesign. Besides,thisprojectalsoaimstoimprove the designsolvingskillsinrelation to sustainabilityissuesbasedonthe natural lightingandsite analysis.Thisprojectencompasses advanceddaylightingsystemsandthe integrationsof electrical lighting,aswell asPSALImethodas strategiesforlightingconditionsandproduce architectural qualityspaces. 1.2 Project introduction The communitylibraryislocatedatJalan Hang Kasturi nearbyMedanPasar square.The conceptof the libraryis“enhance the historyof the site bytying historical piecemeal of the site throughreminiscesof the streetscape andrevitalize the area”.Derived fromthe site perception,“humanassignboard”comes fromthe protrudingof the signboardaround the site whichisa clearand strong representationthe character of the site itself aspeoplemeanderthroughthe site. The formof the buildingissplitintotwo blocksto create an internal streettolinkthe spacesandencourage people towalkin. The splitcreated a voidwhere the twistingof eachfloorcreate the differentinterestingview pointandalsoincrease the passive contact.The voidallows penetrationof the light intothe libraryspacestoincrease the sustainabilityof the library.
  • 4. 2.0 DRAIWNGS GROUND FLOOR PLAN SCALE 1: 150
  • 9. 3.0 Lighting analysis 3.1 DaylightFactorAnalysis Daylightfactoris definedasthe rationof interiorilluminance,Ei toavailable outdoorilluminance Eo whichisunobstructedhorizontal exteriorilluminance: DF = Ei (IndoorIlluminance) x 100% Eo (OutdoorIlluminance) ZONE DF (%) Distribution Verybright >6 Large (includingthermal andglare problem) Bright 3 – 6 Good Average 1-3 Fair Dark 0-1 Poor Figure 3.1.1 Daylightfactorsand distribution(Departmentof standardMalaysia2007) The daylightfactorconceptis applicable onlywhenthe skyilluminance distributionisknownorcan reasonablybe estimated.Inthiscase study,the average outdoorilluminance inMalaysiaisassumed accordingto the standardwhichis20000 lux. Luminance level (lux) Example 120, 000 Brightestsunlight 110, 000 Brightsunlight 20, 000 Shade illuminatedbyentireclearblue sky,midday 1000 - 2000 Typical overcastday,midday 400 Sunrise/sunsetonclearday(ambientillumination) <200 Extreme of darkeststormclouds,midday 40 Fullyovercast,sunrise/sunset <1 Extreme oddarkeststormcloud,sunrise/sunset Figure 3.1.2 Daylightintensityatdifferentcondition Average Daylightfactor Inside rooms,the maximumDFisnearthe windows,anditismainlydue tosky component.Inthe early stagesof buildingdesign,the average daylightfactormaybe usedto assessthe adequacyof daylight: Average 𝐷𝐹 = 𝑊 𝐴 × 𝑇0 (1−𝑅) Where:W is the area of the window(m2 ) A is the total area of the internal surfaces(m2 ) T isthe glass transmittance correctedfordirt 0 isvisible skyangle indegreesfromthe centerof the window R isthe average reflectance of areaA. The valuesof these quantitiesare determinedformthe givendataandW,T and R are correctedby usingfactorsgiveninthe BS DaylightCode andotherpublications.
  • 10. 3.2 Shadowcasting Date: 21 June 2017 Time:9 a.m. Weathercondition:Sunny The morningsun fromthe East directionblockedbythe shophouses,mostof the spacesisaffectedby the blockingof the sunlightfromEastdirection. Date: 21 June 2017 Time:12 p.m. Weathercondition:Sunny Duringthishour,the directionof the sunlightiscomingfrom top.The excessive strongsunlightis reducedasit isfilteredthroughthe louvers.
  • 11. Date: 21 June 2017 Time:5 p.m. Weathercondition:Sunny The eveningsunaffectsthe westernsideof the buildingwhichisthe frontfaçade,butthe highrise hotel infront of the libraryblockedmostof the sunlight Inorder to avoiduserdiscomfort,the frontfaçade is installedwithmotorizedlouverstoreduce the directpenetrationof the eveningsun.Andthe greenery area locatedat the secondflooract as a bufferzone andreduces the directsunlightfromenteringthe spaces.
  • 12. 3.3Artificial Lighting Analysis Lumen Method Lumen method can be also calculated and used to determine the number of light should be installed on the site. To know the number of lamps, calculation of total luminance of the space need to be done based on the number of fixtures and examines the sufficiency of light fixtures on that particular space. 𝑁 = 𝐸 × 𝐴 𝐹 × 𝑈𝐹 × 𝑀𝐹 Where, N = Number of lamps required E = Illuminance level required (Lux) A = Area at working plane height (m2 ) F = Average luminous flux from each lump (lm) UF = Utilization factor, an allowance for light distribution of the luminaire and the room surfaces MF = Maintenance factor, an allowance for reduced light output because of deterioration and dirt RoomIndex RoomIndex,RI,isthe ratioof roomplanarea to haft wall areabetweenthe workingandluminaire planes, Whichcan be calculate by: 𝑅𝐼 = 𝐿 𝑥 𝑊 𝐻 𝑚 𝑥 (𝐿+𝑊) Where, L = Lengthof room W = Widthof room Hm = Mountingheight,the vertical distance betweenthe workingplaneandthe luminaire
  • 13. 4.0 Space A (Lobby) DaylightAnalysis Ground Floor Plan FloorArea(m2 ) 67m2 Areaof façade exposedtolight(m2) Perimeter=(2.85 x 2.1) + (5.5 x 1) + (3.6 x1) Area = 15.1 m2 Areaof skylight(m2 ) 0 Exposedfaçade tolight& skylightareatoFloor area ratio(Daylightfactor) Average 𝐷𝐹 = 𝑊 𝐴 × 𝑇0 (1−𝑅) = 15.1 148.9 × 0.6×40 (1−0.5) = 4.8 % Daylightfactor,DF 𝐷𝐹 = 𝐸𝑖 𝐸𝑜 × 100% 4.8 = ( 𝐸𝑖 30000 ) × 100% Ei = 4.8 × 300 = 1440 lux
  • 14. Daylightcontour From the daylightanalysis,the lobbyof the libraryhasa daylightfactorof 4.8 % and the natural illumination of 1440 lux.The openinghave ahigherlux value assunlightispenetratedintothe space. The natural illuminance ismore thansufficientthanthe standardilluminationrequirementof 100lux, thusblindsare installedtoreduce glare toa more comfortable setting.
  • 15. Space B (Individual studyarea) DaylightAnalysis Third floor plan FloorArea(m2 ) 74 m2 Areaof façade exposedtolight(m2) Perimeter=(4 x 1) + (3.3 x 1 ) + (5.5 x 1) + (2.0 x 1) Area = 14.8 Areaof skylight(m2 ) 0 Exposedfaçade tolight& skylightareatoFloor area ratio(Daylightfactor) Average 𝐷𝐹 = 𝑊 𝐴 × 𝑇0 (1−𝑅) = 14.8 165.3 × 0.6 ×90 (1−0.5) = 9.72 % Daylightfactor,DF 𝐷𝐹 = 𝐸𝑖 𝐸𝑜 × 100% 9.72 = ( 𝐸𝑖 30000 ) × 100% Ei = 9.72 × 300 = 2916 lux
  • 16. Daylightcontour From the daylightanalysis,the individual studyareahasa daylightfactorof 9.72 % and the natural illuminationof 2916 lux.The standardilluminationrequirementof the space is300 lux,thusthe natural illuminance ismore thansufficienttoilluminatethe space.Blindsare installedtoreduce glare forthe usersto studycomfortablywithinthe space.
  • 17. 5.0 Space A (Lobby) Artificial lightingAnalysis Fixture Properties Type of fixture RecessmountedCircularLEDDownlight Image of fixture Type of luminous Warm white Luminousflux (lm) 900 lm Power(W) 15 ColourTemperature (K) 6000 Colourrenderingindex 70
  • 18. Room Indexcalculation Dimensionof room(m) L = 13.8, W = 7 Total floorarea(m2 ) 67 Heightof ceiling(m) 3.85 Type of lightfixture RecessmountedcircularLED Downlight Luminousflux of lighting,F(lm) 900 Heightof luminaires(m) 0 Heightof workingplane (m) 0.8 Mountingheight(Hm) 3.85 – 0.8 = 3.05 StandardilluminationrequiredaccordingtoMS 1525 and JKR 100 Roomindex,RI(K) RI = 𝐿 ×𝑊 𝐻𝑚 ×(𝐿+𝑊) RI = 96.6 3.05×(13.8+ 7) = 1.52 LumenMethodCalculation Reflectance factor Plasterwall:0.45 Concrete ceiling:0.7 Woodenflooring:0.3V
  • 19. Numberof lights(N) Lux required,IESStandardillumination(E) 100 Areaat workingplane height(A,m2 ) Dimensionsof Workshop = 67m2 LuminousFlux (F) 900 lm Utilizationfactor(UF) 0.59 Maintenance factor(MF) 0.8 (standard) LumenCalculation(N,numberof lights) 𝑁 = 𝐸 × 𝐴 𝐹 × 𝑀𝐹 × 𝑈𝐹 𝑁 = 100 × 67 900 × 0.59 × 0.8 𝑁 = 15.77 𝑁 = 16 𝑙𝑖𝑔ℎ𝑡𝑠 Spacingto heightratio,SHR 𝑆𝐻𝑅 = 1/Hm x √ 𝐴 𝑁 = 1/3.05 x √67 16 = 0.67 SHR = S/Hm 0.67 = S/3.05 S = 2.044m Fittinglayout Fittingrequiredalong13.8mwall, 10/2.044 (m) = 4.89 ~ 5 rows Numberof lampsineach row, 16/5 = 3.2 ~ 3 lamps Spacingrequiredfor7m wall, 7/3 =2.33m Spacingrequiredfor13.8m wall, 13.8/5 = 2.76m Fristspacingfor the 13.8m wall will be half of the S,2.76/2 = 1.38m Fristspacingfor the 7m wall will be 2.33 / 2 = 1.17m
  • 20. Space A PSALI Method LightFittingSpacingDiagram(ReflectedCeilingPlan) Artificial LightContourDiagram The previousdaylightcontourdiagramshownthatthe lobbyreceivesnatural lightenteredthroughthe openingsalongthe walls.However asit islocatedonthe groundfloor, the sunlightpenetrationis insufficienttoilluminate the space.The artificial lightingcontourabove showsthe lightingcondition afterthe lightingfixture isinstalledandplannedalongthe space.The lightsource isdistributedevenly throughoutthe space.RecessmountedcircularceilingLEDDownlightdistributes low luminouslevelsas requiredby MS 1525 for a lobbyspace.
  • 21. Space B (Individual study area) Artificial LightingAnalysis Type of fixture LED PendentLight Image of fixture Type of luminous Warm white Luminousflux (lm) 2800 lm Power(W) 47 ColourTemperature (K) 5000 Colourrenderingindex 80
  • 22. Room Indexcalculation Dimensionof room(m) L = 15.8, W = 4.2 Total floorarea(m2 ) 74m2 Heightof ceiling(m) 3.85 Type of lightfixture LED PendentLight Luminousflux of lighting,F(lm) 618 Heightof luminaires(m) 3.85 – 0.45 – 0.8 = 2.6m Heightof workingplane (m) 0.8 Mountingheight(Hm) 3.85 – 0.8 = 3.05 StandardilluminationrequiredaccordingtoMS 1525 and JKR 300 Roomindex,RI(K) RI = 𝐿 × 𝑊 𝐻𝑚 ×(𝐿+𝑊) RI = 66.4 3.05×(15.8+ 4.2) = 1.10 Lumen MethodCalculation Reflectance factor Plasterwall:0.45 Concrete ceiling:0.7 Woodenflooring:0.3
  • 23. Numberof lights(N) Lux required,IESStandardillumination(E) 300 Areaat workingplane height(A,m2 ) Dimensionsof Workshop = 74m2 LuminousFlux (F) 800 lm Utilizationfactor(UF) 0.59 Maintenance factor(MF) 0.8 (standard) LumenCalculation(N,numberof lights) 𝑁 = 𝐸 × 𝐴 𝐹 × 𝑀𝐹 × 𝑈𝐹 𝑁 = 300 × 74 2800 × 0.59 × 0.8 𝑁 = 16.79 𝑁 = 16 𝑙𝑖𝑔ℎ𝑡𝑠 Spacingto heightratio,SHR 𝑆𝐻𝑅 = 1/Hm x √ 𝐴 𝑁 = 1/3.05 x √74 16 = 0.71 SHR = S/Hm 0.71 = S/3.05 S = 2.166m Fittinglayout Fittingrequiredalong15.8mwall, 15.8/2.166 (m) = 7.295 ~ 7rows Numberof lampsineach row, 16/7 = 2.285 ~ 2lamps Spacingrequiredfor4.2m wall, 4.2/2 = 2.1m Spacingrequiredfor15.8 wall, 15.8/13 = 2.26m Fristspacingfor the 15.8m wall will be half of the S, 2.26/2 = 1.13m Fristspacingfor the 4.2m wall will be 2.1/ 2 = 1.05m
  • 24. Space B PSALI Method LightFittingSpacingDiagram(ReflectedCeilingPlan) Artificial LightContourDiagram The previousdaylightcontourdiagramindicatesthatthe individual studyareareceivesnatural light throughthe openingsandvoid.However,some of the sunlightisblockedbythe wallswhichcauses unevensunlightdistribution.The artificial lightingcontourabove showsthe lightingconditionafterthe lightingfixture isinstalledandplannedalongthe space.The lightsource isdistributedevenlythroughout the space.The LED pendantlightdistributes 800lmof luminousflux toilluminatethe space sufficiently for the usersto studyinthe evening.
  • 25. 6.0 Reference MS 1525 2014 | BuildingInsulation|Ventilation(Architecture).(2017).Scribd. Materials- LightReflectingFactors.(2017). Engineeringtoolbox.com. LED Pendantlight-guidingpanel type |SmartArchi |lighting|Eco solutions|Business|Panasonic Global.(2017). Panasonic.net. LED DownLight| Consumer| Products| India| lighting|Eco solutions|Business|PanasonicGlobal. (2017). Panasonic.net.