SlideShare a Scribd company logo
1 of 50
Download to read offline
Vibrated  and  Driven  
Piles	
K.  R.  Massarsch	
Geo  Risk  &  Vibration  AB,  Stockholm,  Sweden  
Overview	
•  Pile  classification  systems	
•  Driven  pre-­‐‑formed  piles	
•  Advantages  and  disadvantages	
•  Aspects  of  pile  installation	
•  Aspects  of  driven  pile  installation	
•  Vibratory  driving
Pile  Classification  System	
1.  Method  of  installation:  bored/augered,  
continuous  augered,  driven,  screw-­‐‑in	
2.  Degree  of  displacement:  large,  small,  non  	
3.  Pile  material:  concrete,  steel,  timber,  
composite	
4.  Manufacture:  in-­‐‑situ,  preformed,  combined	
5.  Support  during  pile  installation:  no  
support,  temporary  casing,  permanent  
casing,  drilling  mud,  soil  concrete/grout	
6.	
Enlarged  base
Driven  Pre-­‐‑formed  Piles	
Probably  the  oldes  pile  installation  method
Driving  of  Concrete  Piles
Advantages  of  Driven  Pile  
Installation	
•  Material  of  pile  can  be  inspected  before  it  
goes  into  the  ground	
•  Stable  in  "ʺsqueezing"ʺ  ground	
•  Low  risk  of  damage  by  ground  heave  
when  driving  adjacent  piles	
•  Construction  procedure  unaffected  by  
ground  water	
•  Can  be  readily  carried  above  ground  level,  
especially  in  marine  structures	
•  Can  be  driven  in  very  long  lengths  
•  Hard  driving  may  damage  or  break  pile	
•  Uneconomical  if  pile  design  governed  by  
handling/driving  stresses  rather  than  
permanent  loading	
•  Noise  and  vibration  during  driving	
•  Displacement  of  soil  during  pile  driving  
Cannot  be  driven  in  very  large  diameters	
•  End  enlargements  not  always  advantages	
•  Cannot  be  driven  in  low  headroom  
conditions  	
Disadvantages  of  Driven  
Piles
Aspects  of  Pile  Installation	
Driving  methods:  impact  methods  	
or  
	
vibratory  driving   	
     	
  	
Driving  components:  pile  shoes,  
	
jointing,  splicing,  pile  helmets  &  
	
packing 	
    	
Driving  aids:  pre-­‐‑blasting,  pre-­‐‑drilling,  
	
pre-­‐‑driving,  jeQing  	
 	
  	
Post  treatment:  re-­‐‑driving,  grouting
Pile  Driving  Hammers	
Vibratory  hammers	
Electric  vibrators	
Hydraulic  vibrators	
Impact  hammers	
Air  and  steam  hammers:  single-­‐‑acting  
hammers,  double-­‐‑acting  hammers	
Diesel  hammer	
Drop  hammer	
Hydraulic  hammer
Diesel  Hammer                	
Hydraulic  Hammer
Pile  Materials	
Timber	
Concrete:  reinforced  and  prestressed	
Steel:  tubular,  steel  profiles,  sheet  piles	
Composite:  steel  –  concrete  -­‐‑  timber  
Timber  	
 	
Concrete
Steel  Piles
Manufacture  of  Pile	
Cast  in-­‐‑situ:  concrete	
Preformed:  timber,  steel,  concrete	
Combined:  concrete,  steel  etc.  	
	
Jointed  piles
Cast  in-­‐‑situ  Driven  Pile
Pre-­‐‑formed  Spun  Piles
Swedish  Concrete  Pile  Joint
Driving  Aids	
Pre-­‐‑drilling:  auger	
Pre-­‐‑driving:  vibrator  or  hammer	
JeTing:  water  and/or  air	
Grouting:  cement  and/or  bentonite	
Pre-­‐‑blasting
Pre-­‐‑boring  with  Auger
Grouted  Driven  Pile
JeQing  of  Driven  Piles
Vibratory  Driving  Systems
Significance  of  Vibration  
Frequency  for  Driving  of  
Piles  and  Sheet  Piles  
Why  is  Vibration  Frequency  of  Importance  
for  Pile  Driving?	
•  Driving efficiency: pile
penetration is affected.
•  Intensity of ground
vibrations: emitted to
surroundings.
•  Pile capacity: change of
stress conditions in soil.
FV = Me ω2
Centrifugal  Force,  Fv	
s =
Me
mt
Displacement  Amplitude,  s	
Me = ms e
Eccentric  Moment,  Me	
ω  =  2π  f	
Circular  frequency,  ω
Important  Vibrator  Parameters
Electronic  Monitoring  and  Control	
Geophone
0
10
20
30
40
14:22:26 14:23:18 14:24:10 14:25:02
DEPTH, m
TIME, h:min:s
Depth m
Depth m
Pile  Penetration  Depth
0
10
20
30
40
14:22:26 14:23:18 14:24:10 14:25:02
PRESSURE, MPa
TIME, h:min:s
Frequency Hz Depth m
DEPTH, m
Variation  of  Frequency
0
10
20
30
40
0
10
20
30
40
14:22:26 14:23:18 14:24:10 14:25:02
FREQUENCY, Hz
PRESSURE, MPa
TIME, h:min:s
Pressure MPa Frequency Hz
Depth m
DEPTH, m
Variation  of  Hydraulic  Pressure
0
10
20
30
40
0
10
20
30
40
14:22:26 14:23:18 14:24:10 14:25:02
FREQUENCY, Hz
VELOCITY, mm/sPRESSURE, MPa
TIME, h:min:s
Pressure MPa Frequency Hz
Depth m Geo z mm/s
DEPTH, m
Ground  Response  due  to  Frequency  Variation
0	
5	
10	
15	
20	
25	
0	
 5	
 10	
 15	
 20	
 25	
 30	
 35	
 40	
VERTICAL  VIBRATION  VELOCITY  ,  mm/s	
VIBRATION  FREQUENCY,  Hz	
Vertical	
Penetration	
Ground  Vibrations  during  Vibratory  Driving
0	
5	
10	
15	
20	
25	
0	
 5	
 10	
 15	
 20	
 25	
 30	
 35	
 40	
VERTICAL  VIBRATION  VELOCITY  ,  mm/s	
VIBRATION  FREQUENCY,  Hz	
Vertical	
RESONANCE	
Ground  Vibrations  during  Vibratory  Driving
0	
5	
10	
15	
20	
25	
0	
 5	
 10	
 15	
 20	
 25	
 30	
 35	
 40	
HORIZONTAL  VIBRATION  VELOCITY,  mm/s	
VIBRATION  FREQUENCY,  Hz	
Radial	
Ground  Vibrations  during  Vibratory  Driving
0	
5	
10	
15	
20	
25	
0	
 5	
 10	
 15	
 20	
 25	
 30	
 35	
 40	
HORIZONTAL  VIBRATION  VELOCITY,  mm/s	
VIBRATION  FREQUENCY,  Hz	
Tangential	
Ground  Vibrations  during  Vibratory  Driving
F	
GEOPHONE	
Toe
resistance	
Shaft
resistance
mS	
kS	
 dS	
Calculation  of  Resonance  Frequency  of  Pile  
Vibrated  into  a  Soil  Deposit
Calculation  of  Resonance  Frequency  of  Pile  
Vibrated  into  a  Soil  Deposit	
mP	
mS	
kS	
kT	
 dT	
dS	
dM	
kM
mS	
kS	
kT	
 dT	
dS	
dM	
kM	
Calculation  of  Resonance  Frequency  of  Pile  
Vibrated  into  a  Soil  Deposit	
mP	
F(t)	
uP  
(t)
F(t)	
uP  
(t)	
Calculation  of  Resonance  Frequency  of  Pile  
Vibrated  into  a  Soil  Deposit	
mP	
mS	
kS	
kT	
 dT	
dS	
dM	
kM	
uS  
(t)
FREQUENCY,  Hz	
DISPLACEMENT,  
mm	
Eccentric  moment:  me=10  kgm  -­‐‑  Shear  wave  speed:  cS=225  m/s:  	
Resonance  
frequency	
Absolute	
Imaginar
y	
Real	
Resonance  Frequency  of  Vibrating  Pile
Start-­‐‑up  of  vibrator  without  
vibrations  to  required  speed  
without  vibrations	
Resonance-­‐‑free  Vibratory  Driving
Gradual  increase  of  vibration  
amplitude  rotating  lower  row  of  
masses  against  upper  row.	
Resonance-­‐‑free  Vibratory  Driving
Maximum  vibration  amplitude  
of  vibrator  at  largest  eccentricity	
Resonance-­‐‑free  Vibratory  Driving
Vibration-­‐‑free  Start-­‐‑up  of  Vibrator	
Sheet  Pile  Driving  in  Vibration-­‐‑sensitive  Area
Sheet  Pile  Driving  in  Vibration-­‐‑sensitive  Area	
Monitoring  of  ground  vibrations  by  geophone	
Sheet  pile  driving  with  resonance-­‐‑free,  high  frequency  vibrator	
Vibration-­‐‑
sensitive  
embankmen
t
Sheet  Pile  Driving  in  Vibration-­‐‑sensitive  Area	
Monitoring  of  ground  vibrations  by  geophone	
Sheet  pile  driving  with  resonance-­‐‑free,  high  frequency  vibrator
Summary  and  Conclusions	
•  Driven piles are in many cases a cost-
effective foundation solution.
•  Driving piles requires competent personnel
and suitable equipment.
•  Vibratory driving can be efficient in suitable
ground conditions.
•  By adjusting the operating parameters of
modern vibrators, pile driving and ground
compaction can be optimized.
•  The performance of vibrators can be
monitored and opitmized using different
types of sensors.
Thank  You!	
SWEDISH  PILE  DRIVING  
TECHNOLOGY

More Related Content

What's hot

What's hot (20)

VIBROFLOTATION - Ground Improvement - Welcome to a New Era...
VIBROFLOTATION - Ground Improvement - Welcome to a New Era...VIBROFLOTATION - Ground Improvement - Welcome to a New Era...
VIBROFLOTATION - Ground Improvement - Welcome to a New Era...
 
Advance Construction & Equipment
Advance Construction & EquipmentAdvance Construction & Equipment
Advance Construction & Equipment
 
Temeltas Bored Piling 25.06
Temeltas Bored Piling 25.06Temeltas Bored Piling 25.06
Temeltas Bored Piling 25.06
 
PILE FOUNDATION (basics)
PILE FOUNDATION (basics)PILE FOUNDATION (basics)
PILE FOUNDATION (basics)
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Drilling Rig Components ( Illustrated Glossary )
Drilling Rig Components ( Illustrated Glossary )Drilling Rig Components ( Illustrated Glossary )
Drilling Rig Components ( Illustrated Glossary )
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Pile
PilePile
Pile
 
HMA joint construction
HMA joint constructionHMA joint construction
HMA joint construction
 
Mudline Suspension (MLS)
Mudline Suspension (MLS)Mudline Suspension (MLS)
Mudline Suspension (MLS)
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4
 
Rubber Products Presentation on Bridges
Rubber Products Presentation on BridgesRubber Products Presentation on Bridges
Rubber Products Presentation on Bridges
 
Semi submersible
Semi submersibleSemi submersible
Semi submersible
 
Presentation 1 drilling rigs
Presentation 1 drilling rigsPresentation 1 drilling rigs
Presentation 1 drilling rigs
 
Rig types and components
Rig types and componentsRig types and components
Rig types and components
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
 
DISCOVERY DRILLING EQUIPMENT
DISCOVERY DRILLING EQUIPMENTDISCOVERY DRILLING EQUIPMENT
DISCOVERY DRILLING EQUIPMENT
 
support system in metal mine
support system in metal minesupport system in metal mine
support system in metal mine
 
Intro to offshore drilling
Intro to offshore drilling Intro to offshore drilling
Intro to offshore drilling
 
Rotary drilling rig (onshore)
Rotary drilling rig (onshore)Rotary drilling rig (onshore)
Rotary drilling rig (onshore)
 

Viewers also liked

French standard for deep foundations roger frank
French standard for deep foundations   roger frankFrench standard for deep foundations   roger frank
French standard for deep foundations roger frankcfpbolivia
 
Integrity frank rausche
Integrity  frank rauscheIntegrity  frank rausche
Integrity frank rauschecfpbolivia
 
The flat dilatomer test silvano marchetti
The flat dilatomer test   silvano marchettiThe flat dilatomer test   silvano marchetti
The flat dilatomer test silvano marchetticfpbolivia
 
Ingeniería sostenible de fundaciones profundas alessandro mandolini
Ingeniería sostenible de fundaciones profundas   alessandro mandoliniIngeniería sostenible de fundaciones profundas   alessandro mandolini
Ingeniería sostenible de fundaciones profundas alessandro mandolinicfpbolivia
 
4.4 integrity gray
4.4   integrity gray4.4   integrity gray
4.4 integrity graycfpbolivia
 
Massarsch krm swedish geo
Massarsch    krm swedish geoMassarsch    krm swedish geo
Massarsch krm swedish geocfpbolivia
 
Design and dynamic testing of precast piles oscar varde
Design and dynamic testing of precast piles   oscar vardeDesign and dynamic testing of precast piles   oscar varde
Design and dynamic testing of precast piles oscar vardecfpbolivia
 
Congreso cfpb2015 huesker
Congreso cfpb2015   hueskerCongreso cfpb2015   huesker
Congreso cfpb2015 hueskercfpbolivia
 
Spt energy calibration frank rausche
Spt energy calibration  frank rauscheSpt energy calibration  frank rausche
Spt energy calibration frank rauschecfpbolivia
 
3.6 spt energy calibration -gray
3.6   spt energy calibration -gray3.6   spt energy calibration -gray
3.6 spt energy calibration -graycfpbolivia
 
Pda capwap - frank rausche
Pda capwap - frank rauschePda capwap - frank rausche
Pda capwap - frank rauschecfpbolivia
 
Spt spt t procedures and practical applications -luciano decourt
Spt  spt t procedures and practical applications -luciano decourtSpt  spt t procedures and practical applications -luciano decourt
Spt spt t procedures and practical applications -luciano decourtcfpbolivia
 
El ensayo dilatométrico de marchetti silvano marchetti
El ensayo dilatométrico de marchetti   silvano marchettiEl ensayo dilatométrico de marchetti   silvano marchetti
El ensayo dilatométrico de marchetti silvano marchetticfpbolivia
 
Fellenius bases de diseño de pilotes de fundación
Fellenius   bases de diseño de pilotes de fundaciónFellenius   bases de diseño de pilotes de fundación
Fellenius bases de diseño de pilotes de fundacióncfpbolivia
 
Keynote silvano marchetti
Keynote   silvano marchettiKeynote   silvano marchetti
Keynote silvano marchetticfpbolivia
 
Unisoft software bengt h. fellenius, pierre goudrault
Unisoft software   bengt h. fellenius, pierre goudraultUnisoft software   bengt h. fellenius, pierre goudrault
Unisoft software bengt h. fellenius, pierre goudraultcfpbolivia
 
Ringtracs andre estevao silva
Ringtracs   andre estevao silvaRingtracs   andre estevao silva
Ringtracs andre estevao silvacfpbolivia
 
Influence of deep foundation installation methods morgan nesmith
Influence of deep foundation installation methods   morgan nesmithInfluence of deep foundation installation methods   morgan nesmith
Influence of deep foundation installation methods morgan nesmithcfpbolivia
 
Las fundaciones profundas en bolivia en los últimos 50 años mario terceros h.
Las fundaciones profundas en bolivia en los últimos 50 años   mario terceros h.Las fundaciones profundas en bolivia en los últimos 50 años   mario terceros h.
Las fundaciones profundas en bolivia en los últimos 50 años mario terceros h.cfpbolivia
 
Decourt provas de carga podem
Decourt    provas de carga podemDecourt    provas de carga podem
Decourt provas de carga podemcfpbolivia
 

Viewers also liked (20)

French standard for deep foundations roger frank
French standard for deep foundations   roger frankFrench standard for deep foundations   roger frank
French standard for deep foundations roger frank
 
Integrity frank rausche
Integrity  frank rauscheIntegrity  frank rausche
Integrity frank rausche
 
The flat dilatomer test silvano marchetti
The flat dilatomer test   silvano marchettiThe flat dilatomer test   silvano marchetti
The flat dilatomer test silvano marchetti
 
Ingeniería sostenible de fundaciones profundas alessandro mandolini
Ingeniería sostenible de fundaciones profundas   alessandro mandoliniIngeniería sostenible de fundaciones profundas   alessandro mandolini
Ingeniería sostenible de fundaciones profundas alessandro mandolini
 
4.4 integrity gray
4.4   integrity gray4.4   integrity gray
4.4 integrity gray
 
Massarsch krm swedish geo
Massarsch    krm swedish geoMassarsch    krm swedish geo
Massarsch krm swedish geo
 
Design and dynamic testing of precast piles oscar varde
Design and dynamic testing of precast piles   oscar vardeDesign and dynamic testing of precast piles   oscar varde
Design and dynamic testing of precast piles oscar varde
 
Congreso cfpb2015 huesker
Congreso cfpb2015   hueskerCongreso cfpb2015   huesker
Congreso cfpb2015 huesker
 
Spt energy calibration frank rausche
Spt energy calibration  frank rauscheSpt energy calibration  frank rausche
Spt energy calibration frank rausche
 
3.6 spt energy calibration -gray
3.6   spt energy calibration -gray3.6   spt energy calibration -gray
3.6 spt energy calibration -gray
 
Pda capwap - frank rausche
Pda capwap - frank rauschePda capwap - frank rausche
Pda capwap - frank rausche
 
Spt spt t procedures and practical applications -luciano decourt
Spt  spt t procedures and practical applications -luciano decourtSpt  spt t procedures and practical applications -luciano decourt
Spt spt t procedures and practical applications -luciano decourt
 
El ensayo dilatométrico de marchetti silvano marchetti
El ensayo dilatométrico de marchetti   silvano marchettiEl ensayo dilatométrico de marchetti   silvano marchetti
El ensayo dilatométrico de marchetti silvano marchetti
 
Fellenius bases de diseño de pilotes de fundación
Fellenius   bases de diseño de pilotes de fundaciónFellenius   bases de diseño de pilotes de fundación
Fellenius bases de diseño de pilotes de fundación
 
Keynote silvano marchetti
Keynote   silvano marchettiKeynote   silvano marchetti
Keynote silvano marchetti
 
Unisoft software bengt h. fellenius, pierre goudrault
Unisoft software   bengt h. fellenius, pierre goudraultUnisoft software   bengt h. fellenius, pierre goudrault
Unisoft software bengt h. fellenius, pierre goudrault
 
Ringtracs andre estevao silva
Ringtracs   andre estevao silvaRingtracs   andre estevao silva
Ringtracs andre estevao silva
 
Influence of deep foundation installation methods morgan nesmith
Influence of deep foundation installation methods   morgan nesmithInfluence of deep foundation installation methods   morgan nesmith
Influence of deep foundation installation methods morgan nesmith
 
Las fundaciones profundas en bolivia en los últimos 50 años mario terceros h.
Las fundaciones profundas en bolivia en los últimos 50 años   mario terceros h.Las fundaciones profundas en bolivia en los últimos 50 años   mario terceros h.
Las fundaciones profundas en bolivia en los últimos 50 años mario terceros h.
 
Decourt provas de carga podem
Decourt    provas de carga podemDecourt    provas de carga podem
Decourt provas de carga podem
 

Similar to Bolivia driven vibrated piles 04 30.compressed

Micropiling & Heaving of Piles
Micropiling & Heaving of PilesMicropiling & Heaving of Piles
Micropiling & Heaving of PilesSagar Kaptan
 
Excav & Deep Foundations Fall 09
Excav & Deep Foundations Fall 09Excav & Deep Foundations Fall 09
Excav & Deep Foundations Fall 09Richard Luxenburg
 
Massarsch uevos desarrollos en pilotes de fundación
Massarsch    uevos desarrollos en pilotes de fundaciónMassarsch    uevos desarrollos en pilotes de fundación
Massarsch uevos desarrollos en pilotes de fundacióncfpbolivia
 
shaftab-170524171214.pdf
shaftab-170524171214.pdfshaftab-170524171214.pdf
shaftab-170524171214.pdfSaimHaq
 
Shaft sinking
Shaft sinking Shaft sinking
Shaft sinking OmKaitade
 
Vs30 measurements for Seismic Site Classification
Vs30 measurements for Seismic Site ClassificationVs30 measurements for Seismic Site Classification
Vs30 measurements for Seismic Site ClassificationAli Osman Öncel
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifaSUNILPRASAD68
 
Adsc products presentation_3.17.10[1]
Adsc products presentation_3.17.10[1]Adsc products presentation_3.17.10[1]
Adsc products presentation_3.17.10[1]DennisConTech
 
Process for non process1
Process for non process1Process for non process1
Process for non process1pradeepdeepi
 
Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operationSafdar Ali
 
oil & gas drilling preliminaries
oil & gas drilling preliminariesoil & gas drilling preliminaries
oil & gas drilling preliminariesKartikeya Pandey
 
Pile foundation
Pile foundationPile foundation
Pile foundationFatihoktr
 
presentation-of-cofferdam-design.pptx
presentation-of-cofferdam-design.pptxpresentation-of-cofferdam-design.pptx
presentation-of-cofferdam-design.pptxglencristianrivera
 
Offshore Petroleum Production Systems
Offshore Petroleum Production SystemsOffshore Petroleum Production Systems
Offshore Petroleum Production SystemsSahyog Shishodia
 
TYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSTYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSMaharshi Dave
 

Similar to Bolivia driven vibrated piles 04 30.compressed (20)

Micropiling & Heaving of Piles
Micropiling & Heaving of PilesMicropiling & Heaving of Piles
Micropiling & Heaving of Piles
 
Excav & Deep Foundations Fall 09
Excav & Deep Foundations Fall 09Excav & Deep Foundations Fall 09
Excav & Deep Foundations Fall 09
 
Massarsch uevos desarrollos en pilotes de fundación
Massarsch    uevos desarrollos en pilotes de fundaciónMassarsch    uevos desarrollos en pilotes de fundación
Massarsch uevos desarrollos en pilotes de fundación
 
Advanced Drilling & Blasting
Advanced Drilling & Blasting Advanced Drilling & Blasting
Advanced Drilling & Blasting
 
Shaft
Shaft Shaft
Shaft
 
shaftab-170524171214.pdf
shaftab-170524171214.pdfshaftab-170524171214.pdf
shaftab-170524171214.pdf
 
Shaft sinking
Shaft sinking Shaft sinking
Shaft sinking
 
Vs30 measurements for Seismic Site Classification
Vs30 measurements for Seismic Site ClassificationVs30 measurements for Seismic Site Classification
Vs30 measurements for Seismic Site Classification
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifa
 
Adsc products presentation_3.17.10[1]
Adsc products presentation_3.17.10[1]Adsc products presentation_3.17.10[1]
Adsc products presentation_3.17.10[1]
 
Process for non process1
Process for non process1Process for non process1
Process for non process1
 
Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operation
 
4_5960597283161505958.ppt
4_5960597283161505958.ppt4_5960597283161505958.ppt
4_5960597283161505958.ppt
 
Concrete
ConcreteConcrete
Concrete
 
oil & gas drilling preliminaries
oil & gas drilling preliminariesoil & gas drilling preliminaries
oil & gas drilling preliminaries
 
Pile
PilePile
Pile
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
presentation-of-cofferdam-design.pptx
presentation-of-cofferdam-design.pptxpresentation-of-cofferdam-design.pptx
presentation-of-cofferdam-design.pptx
 
Offshore Petroleum Production Systems
Offshore Petroleum Production SystemsOffshore Petroleum Production Systems
Offshore Petroleum Production Systems
 
TYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSTYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONS
 

More from cfpbolivia

The static loading test bengt h. fellenius
The  static loading test   bengt h. felleniusThe  static loading test   bengt h. fellenius
The static loading test bengt h. felleniuscfpbolivia
 
Static load testing and prediction bengt h. fellenius
Static load testing  and prediction   bengt h. felleniusStatic load testing  and prediction   bengt h. fellenius
Static load testing and prediction bengt h. felleniuscfpbolivia
 
Risk evaluation according to standards cristina de hc tsuha
Risk evaluation according to standards  cristina de hc tsuhaRisk evaluation according to standards  cristina de hc tsuha
Risk evaluation according to standards cristina de hc tsuhacfpbolivia
 
Grlweap frank rausche
Grlweap  frank rauscheGrlweap  frank rausche
Grlweap frank rauschecfpbolivia
 
2.5 pda-capwap - gray
2.5   pda-capwap - gray2.5   pda-capwap - gray
2.5 pda-capwap - graycfpbolivia
 
1.1 grlweap - gray
1.1   grlweap - gray1.1   grlweap - gray
1.1 grlweap - graycfpbolivia
 
Bolivia seismic properties k. rainer massarsch
Bolivia seismic properties   k. rainer massarschBolivia seismic properties   k. rainer massarsch
Bolivia seismic properties k. rainer massarschcfpbolivia
 
Seismic cpt (scpt) peter robertson
Seismic cpt (scpt)   peter robertsonSeismic cpt (scpt)   peter robertson
Seismic cpt (scpt) peter robertsoncfpbolivia
 
Prospección geofísica aplicada en las investigaciones geotécnicas noel perez
Prospección geofísica aplicada en las investigaciones geotécnicas  noel perezProspección geofísica aplicada en las investigaciones geotécnicas  noel perez
Prospección geofísica aplicada en las investigaciones geotécnicas noel perezcfpbolivia
 
Patologia das fundaçõe desafios para melhoria - jarbas milititsky
Patologia das fundaçõe  desafios para melhoria - jarbas milititskyPatologia das fundaçõe  desafios para melhoria - jarbas milititsky
Patologia das fundaçõe desafios para melhoria - jarbas milititskycfpbolivia
 
Fellenius bases de diseño de pilotes de fundación
Fellenius   bases de diseño de pilotes de fundaciónFellenius   bases de diseño de pilotes de fundación
Fellenius bases de diseño de pilotes de fundacióncfpbolivia
 

More from cfpbolivia (11)

The static loading test bengt h. fellenius
The  static loading test   bengt h. felleniusThe  static loading test   bengt h. fellenius
The static loading test bengt h. fellenius
 
Static load testing and prediction bengt h. fellenius
Static load testing  and prediction   bengt h. felleniusStatic load testing  and prediction   bengt h. fellenius
Static load testing and prediction bengt h. fellenius
 
Risk evaluation according to standards cristina de hc tsuha
Risk evaluation according to standards  cristina de hc tsuhaRisk evaluation according to standards  cristina de hc tsuha
Risk evaluation according to standards cristina de hc tsuha
 
Grlweap frank rausche
Grlweap  frank rauscheGrlweap  frank rausche
Grlweap frank rausche
 
2.5 pda-capwap - gray
2.5   pda-capwap - gray2.5   pda-capwap - gray
2.5 pda-capwap - gray
 
1.1 grlweap - gray
1.1   grlweap - gray1.1   grlweap - gray
1.1 grlweap - gray
 
Bolivia seismic properties k. rainer massarsch
Bolivia seismic properties   k. rainer massarschBolivia seismic properties   k. rainer massarsch
Bolivia seismic properties k. rainer massarsch
 
Seismic cpt (scpt) peter robertson
Seismic cpt (scpt)   peter robertsonSeismic cpt (scpt)   peter robertson
Seismic cpt (scpt) peter robertson
 
Prospección geofísica aplicada en las investigaciones geotécnicas noel perez
Prospección geofísica aplicada en las investigaciones geotécnicas  noel perezProspección geofísica aplicada en las investigaciones geotécnicas  noel perez
Prospección geofísica aplicada en las investigaciones geotécnicas noel perez
 
Patologia das fundaçõe desafios para melhoria - jarbas milititsky
Patologia das fundaçõe  desafios para melhoria - jarbas milititskyPatologia das fundaçõe  desafios para melhoria - jarbas milititsky
Patologia das fundaçõe desafios para melhoria - jarbas milititsky
 
Fellenius bases de diseño de pilotes de fundación
Fellenius   bases de diseño de pilotes de fundaciónFellenius   bases de diseño de pilotes de fundación
Fellenius bases de diseño de pilotes de fundación
 

Recently uploaded

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 

Recently uploaded (20)

POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 

Bolivia driven vibrated piles 04 30.compressed

  • 1. Vibrated  and  Driven   Piles K.  R.  Massarsch Geo  Risk  &  Vibration  AB,  Stockholm,  Sweden  
  • 2. Overview •  Pile  classification  systems •  Driven  pre-­‐‑formed  piles •  Advantages  and  disadvantages •  Aspects  of  pile  installation •  Aspects  of  driven  pile  installation •  Vibratory  driving
  • 3. Pile  Classification  System 1.  Method  of  installation:  bored/augered,   continuous  augered,  driven,  screw-­‐‑in 2.  Degree  of  displacement:  large,  small,  non   3.  Pile  material:  concrete,  steel,  timber,   composite 4.  Manufacture:  in-­‐‑situ,  preformed,  combined 5.  Support  during  pile  installation:  no   support,  temporary  casing,  permanent   casing,  drilling  mud,  soil  concrete/grout 6. Enlarged  base
  • 4. Driven  Pre-­‐‑formed  Piles Probably  the  oldes  pile  installation  method
  • 6. Advantages  of  Driven  Pile   Installation •  Material  of  pile  can  be  inspected  before  it   goes  into  the  ground •  Stable  in  "ʺsqueezing"ʺ  ground •  Low  risk  of  damage  by  ground  heave   when  driving  adjacent  piles •  Construction  procedure  unaffected  by   ground  water •  Can  be  readily  carried  above  ground  level,   especially  in  marine  structures •  Can  be  driven  in  very  long  lengths  
  • 7. •  Hard  driving  may  damage  or  break  pile •  Uneconomical  if  pile  design  governed  by   handling/driving  stresses  rather  than   permanent  loading •  Noise  and  vibration  during  driving •  Displacement  of  soil  during  pile  driving   Cannot  be  driven  in  very  large  diameters •  End  enlargements  not  always  advantages •  Cannot  be  driven  in  low  headroom   conditions   Disadvantages  of  Driven   Piles
  • 8. Aspects  of  Pile  Installation Driving  methods:  impact  methods   or   vibratory  driving         Driving  components:  pile  shoes,   jointing,  splicing,  pile  helmets  &   packing     Driving  aids:  pre-­‐‑blasting,  pre-­‐‑drilling,   pre-­‐‑driving,  jeQing     Post  treatment:  re-­‐‑driving,  grouting
  • 9. Pile  Driving  Hammers Vibratory  hammers Electric  vibrators Hydraulic  vibrators Impact  hammers Air  and  steam  hammers:  single-­‐‑acting   hammers,  double-­‐‑acting  hammers Diesel  hammer Drop  hammer Hydraulic  hammer
  • 10. Diesel  Hammer                 Hydraulic  Hammer
  • 11. Pile  Materials Timber Concrete:  reinforced  and  prestressed Steel:  tubular,  steel  profiles,  sheet  piles Composite:  steel  –  concrete  -­‐‑  timber  
  • 14. Manufacture  of  Pile Cast  in-­‐‑situ:  concrete Preformed:  timber,  steel,  concrete Combined:  concrete,  steel  etc.   Jointed  piles
  • 18. Driving  Aids Pre-­‐‑drilling:  auger Pre-­‐‑driving:  vibrator  or  hammer JeTing:  water  and/or  air Grouting:  cement  and/or  bentonite Pre-­‐‑blasting
  • 23. Significance  of  Vibration   Frequency  for  Driving  of   Piles  and  Sheet  Piles  
  • 24. Why  is  Vibration  Frequency  of  Importance   for  Pile  Driving? •  Driving efficiency: pile penetration is affected. •  Intensity of ground vibrations: emitted to surroundings. •  Pile capacity: change of stress conditions in soil.
  • 25. FV = Me ω2 Centrifugal  Force,  Fv s = Me mt Displacement  Amplitude,  s Me = ms e Eccentric  Moment,  Me ω  =  2π  f Circular  frequency,  ω Important  Vibrator  Parameters
  • 26. Electronic  Monitoring  and  Control Geophone
  • 27.
  • 28. 0 10 20 30 40 14:22:26 14:23:18 14:24:10 14:25:02 DEPTH, m TIME, h:min:s Depth m Depth m Pile  Penetration  Depth
  • 29. 0 10 20 30 40 14:22:26 14:23:18 14:24:10 14:25:02 PRESSURE, MPa TIME, h:min:s Frequency Hz Depth m DEPTH, m Variation  of  Frequency
  • 30. 0 10 20 30 40 0 10 20 30 40 14:22:26 14:23:18 14:24:10 14:25:02 FREQUENCY, Hz PRESSURE, MPa TIME, h:min:s Pressure MPa Frequency Hz Depth m DEPTH, m Variation  of  Hydraulic  Pressure
  • 31. 0 10 20 30 40 0 10 20 30 40 14:22:26 14:23:18 14:24:10 14:25:02 FREQUENCY, Hz VELOCITY, mm/sPRESSURE, MPa TIME, h:min:s Pressure MPa Frequency Hz Depth m Geo z mm/s DEPTH, m Ground  Response  due  to  Frequency  Variation
  • 32. 0 5 10 15 20 25 0 5 10 15 20 25 30 35 40 VERTICAL  VIBRATION  VELOCITY  ,  mm/s VIBRATION  FREQUENCY,  Hz Vertical Penetration Ground  Vibrations  during  Vibratory  Driving
  • 33. 0 5 10 15 20 25 0 5 10 15 20 25 30 35 40 VERTICAL  VIBRATION  VELOCITY  ,  mm/s VIBRATION  FREQUENCY,  Hz Vertical RESONANCE Ground  Vibrations  during  Vibratory  Driving
  • 34. 0 5 10 15 20 25 0 5 10 15 20 25 30 35 40 HORIZONTAL  VIBRATION  VELOCITY,  mm/s VIBRATION  FREQUENCY,  Hz Radial Ground  Vibrations  during  Vibratory  Driving
  • 35. 0 5 10 15 20 25 0 5 10 15 20 25 30 35 40 HORIZONTAL  VIBRATION  VELOCITY,  mm/s VIBRATION  FREQUENCY,  Hz Tangential Ground  Vibrations  during  Vibratory  Driving
  • 37. mS kS dS Calculation  of  Resonance  Frequency  of  Pile   Vibrated  into  a  Soil  Deposit
  • 38. Calculation  of  Resonance  Frequency  of  Pile   Vibrated  into  a  Soil  Deposit mP mS kS kT dT dS dM kM
  • 39. mS kS kT dT dS dM kM Calculation  of  Resonance  Frequency  of  Pile   Vibrated  into  a  Soil  Deposit mP F(t) uP   (t)
  • 40. F(t) uP   (t) Calculation  of  Resonance  Frequency  of  Pile   Vibrated  into  a  Soil  Deposit mP mS kS kT dT dS dM kM uS   (t)
  • 41. FREQUENCY,  Hz DISPLACEMENT,   mm Eccentric  moment:  me=10  kgm  -­‐‑  Shear  wave  speed:  cS=225  m/s:   Resonance   frequency Absolute Imaginar y Real Resonance  Frequency  of  Vibrating  Pile
  • 42.
  • 43. Start-­‐‑up  of  vibrator  without   vibrations  to  required  speed   without  vibrations Resonance-­‐‑free  Vibratory  Driving
  • 44. Gradual  increase  of  vibration   amplitude  rotating  lower  row  of   masses  against  upper  row. Resonance-­‐‑free  Vibratory  Driving
  • 45. Maximum  vibration  amplitude   of  vibrator  at  largest  eccentricity Resonance-­‐‑free  Vibratory  Driving
  • 46. Vibration-­‐‑free  Start-­‐‑up  of  Vibrator Sheet  Pile  Driving  in  Vibration-­‐‑sensitive  Area
  • 47. Sheet  Pile  Driving  in  Vibration-­‐‑sensitive  Area Monitoring  of  ground  vibrations  by  geophone Sheet  pile  driving  with  resonance-­‐‑free,  high  frequency  vibrator Vibration-­‐‑ sensitive   embankmen t
  • 48. Sheet  Pile  Driving  in  Vibration-­‐‑sensitive  Area Monitoring  of  ground  vibrations  by  geophone Sheet  pile  driving  with  resonance-­‐‑free,  high  frequency  vibrator
  • 49. Summary  and  Conclusions •  Driven piles are in many cases a cost- effective foundation solution. •  Driving piles requires competent personnel and suitable equipment. •  Vibratory driving can be efficient in suitable ground conditions. •  By adjusting the operating parameters of modern vibrators, pile driving and ground compaction can be optimized. •  The performance of vibrators can be monitored and opitmized using different types of sensors.
  • 50. Thank  You! SWEDISH  PILE  DRIVING   TECHNOLOGY