SlideShare a Scribd company logo
1 of 58
Download to read offline
Sanjivani Rural Education Society's
Sanjivani College of Engineering, Kopargaon 423603.
-Department of Strucutral Engineering-
By
Mr. Sumit S. Kolapkar (Assistant Professor)
Mail Id- kolapkarsumitst@sanjivani.org.in
Ø Introduction- Formwork as a Temporary
Strucutres
RC construction primarily consists of three components- formwork,
reinforcement and concrete.
1. Formwork accounts about 35 to 50 % of total construction cost.
2. Formwork operations consumes about 50 to 75 % of the total
time of construction.
3. Formwork components are highly loaded for a few hours during
concrete placement. Hence we can design these components by
allowing higher permissible stresses as compared to the stresses
taken for the design of permanent structures.
Ø Introduction- Temporary Strucutres
• Concrete Formwork (Shuttering)
• Scaffolding
• Falsework/Shoring
• Cofferdams
• Underpinning
• Diaphragm/Slurry Walls
• Earth retaining structures
• Construction dewatering
Ø Temporary Strucutres-
• Cofferdams- Watertight enclosure from which water is
pumped to expose the bed of a body of water in order
to permit the construction of a pier or other hydraulic
work below the waterline.
Ø Temporary Strucutres-
• Underpinning- Reinforcing of an existing building
foundation. It is required when the original foundation
is no longer strong enough to support the structure.
• Is provided underneath of an existing foundation to
maintain its stability. Used to repair, strengthen
foundation of existing structure.
Ø Temporary Strucutres-
• Diaphragm/Slurry Walls- An underground concrete
wall constructed panel-by-panel each interlocked to
ensure structural stability and water tightness.
• Uses: Earth retention (resisitng lateral load), load bearing
foundation, water proofing, groundwater barriers etc.
Ø Temporary Strucutres-
• Earth retaining structures-
• Construction dewatering-
Ø Temporary Strucutres-
• Concrete formwork-
• Purpose- To support its own weight and that of freshly
placed concrete as well as the construction live loads
including materials, equipment and workmen.
• It is a complete system of temporary structure built
to contain fresh concrete so as to form it into the
required shape and dimensions and to support it until
it hardens sufficiently to become self-supporting.
Ø Temporary Strucutres-
• Parts of Concrete formwork-
1. Sheeting (Sheathing)- That part of formwork, which is in contact with the
concrete.
2. Form (Shutter)- (a) That part of formwork, which consists of the sheeting and
its immediate supporting or stiffening members.
(b) A structure or mould in support of vertical strucutral member of concrete
while it is setting and gaining sufficient strength to be self-supporting.Ex:
Column, retaining wall, footings etc.
3. Falsework- (a) Falsework is the temporary structure erected to support the
work in the process of construction. It is composed of shores, formwork for
beams or slabs (or both) and lateral bracing. To hold the items in place.
(b) It supports the forms, usually for a long structure, such as a bridge.
4. Centering- It is a horizontal structural member supporting a structure.
Exd: soffit, slab etc. It is the formwork used in the construction of arches, shells
space structure where the entire falsework is struck or decentered as a unit, to
avoid introducing injurious stress in any part of the structure.
Ø Temporary Strucutres-
• Parts of Concrete formwork-
5. Mould- A frame for casting, precast concrete units.
6. Scaffold (Scaffolding)- A temporary structure for gaining access to higher
levels of the permanent structure during construction. For workers to stand on
while working on a building
Ø Temporary Strucutres-
• Concrete formwork-
• Requirements- Quality, safety and economy
• The formwork must be built and erected in such a way that the required shape, size, position,
quantity, and finish of the concrete are obtained.
• The formwork must be strong enough to take the pressure or weight of the fresh concrete, so
that the finish of the concrete is obtained. The material should not warp or get distorted.
• The formwork should be designed and constructed such that it can be easily and quickly
erected and struck with minimum skilled workforce leading to savings in both time and money. It
should be able to be set accurately to the desired line and levels.
• The formwork must be able to be struck without damage to the concrete or to the formwork itself.
• The formwork must be able to be handled using the available equipment or to be manually
handled, if necessary.
• The formwork arrangement must provide safe access for the handling of concrete and its
placing.
• The formwork must have all the necessary safety arrangement relating to working areas and
platforms.
• The formwork arrangement must be flexible enough to get the desired finish. That is, it should
be able to accommodate different types of sheathing material, e.g., plywood, steel etc.
• The formwork should also be able to accommodate any architectural features such as grooves,
surface grains etc. It should be possible to a ain tight joints so that there is no leakage of cement
grout.
Ø Temporary Strucutres-
• Concrete formwork-
• Requirements- Quality, safety and economy
Ø Temporary Strucutres-
• Concrete formwork-
• Selection-
1. the design of a building,
2. site constraints,
3. available resources,
4. the contractor’s experience with different systems, and their availability
5. The type of building element to be formed,
6. the type of sheathing material,
7. safety and serviceability of the structural frame,
8. economics
9. building design,
10. job specification,
11. local conditions, and
12. supporting organisation
Ø Temporary Strucutres-
• Concrete formwork-
• Types-
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Traditional classification
I) Conventional System of Formwork:
• In this system, timber and plywood are used predominantly.
• The various formwork components are connected with the help of nails.
• Disadvantages:
• limited reuse value,
• higher cost,
• can be fabricated, installed, and removed only by skilled workmen,
• since the skill of workmen and the quality of formwork material vary from site
to site, the quality of concrete structures obtained is not consistent,
• in large projects, it is difficult to ensure an efficient utilisation of the timber
available on site.
Note- All these factors adversely affect the cost of formwork.
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Traditional classification
I) Conventional System of Formwork:
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Traditional classification
II) Proprietary/Patented System of Formwork:
• Most of the disadvantages observed in conventional systems can be
overcome by adopting good proprietary systems, which make use of
standard factory made components
• Very less formwork are made at site, therefore saves labor cost
• with uniform quality standard products, it is possible to achieve uniformly
good workmanship, improved quality of concrete surface and high reuse
value
• Can be assembled and dismantled with unskilled/semi-skilled labor
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Traditional classification
II) Proprietary/Patented System of Formwork:
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Traditional classification
III) Modular System of Formwork:
• the formwork modules are manufactured in a factory set up, and delivered to
the site in a pre-fabricated form.
• can be assembled very quickly at the project locations.
• Advantages:
1. as it uses standardized modules, and their installation process is simple, it
requires less skilled workers.
2. considerable reduction in erection time at the site.
3. large number of repetitions (reuse) result in the cost of formwork being
considerably on a lower side.
4. The safety of workers and materials is ensured, as it has high strength of the
form.
5. The quality of the concrete surface obtained is extremely good which
reduces the need for further finishing work such as plastering, after removal of
the form.
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Traditional classification
III) Modular System of Formwork:
• Advantages:
6. it automate the formwork operation and improve the productivity as well as
the cost-effectiveness in a construction project.
7. for successful use of a modular formwork system, proper planning in the
architectural design stage as well as in the construction phase of a project is
necessary.
8. the factors such as the form reuse scheme, the allocation of modular form
sets, cranes, workers, etc., and the construction sequence need to be carefully
planned out to get the best out of the modular formwork.
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Traditional classification
III) Modular System of Formwork:
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Classification based on Hanna (1999)
I) Horizontal System of Formwork:
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Classification based on Hanna (1999)
I) Horizontal System of Formwork:
• In Hand set formwork, the commonly used formwork systems are: (a)
conventional wood system (also known as stick form) and (b) conventional
metal system (also known as improved stick form). The conventional wood
system is available for laying the foundation, beams and slabs, and columns
etc.
• In Crane set formwork systems, we have the flying formwork system, column
mounted shoring system, and tunnel forming system.
• In Special horizontal formwork systems, we have the joist slab forming
system, and dome forming system.
• Generally consist of a series of interconnected falsework bays, independent
props or system scaffolds and supporting a number of panels.
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Classification based on Hanna (1999)
I) Horizontal System of Formwork:
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Classification based on Hanna (1999)
II) Vertical System of Formwork:
Under vertical formwork system, we essentially have two subsystems: crane
dependent system and crane independent system.
• In crane dependent system, we have the conventional wall column framing
system, Ganged framing system, and Jump form.
• In crane independent system, the commonly used formwork systems are: (a)
slipform and (b) self raising formwork system.
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Classification based on Hanna (1999)
II) Vertical System of Formwork:
Ø Temporary Strucutres-
• Concrete formwork-
• Types- Classification based on DSR Formwork Items
In India, often the formwork items are presented in a specific form in the bill
of quantities. These items are mentioned in the Delhi Schedule of Rates
(DSR 2007). From that clue the third system of classification is referred to as
“classification based on Formwork items as used in DSR 2007”.
Ø Temporary Strucutres-
• Concrete formwork-
• Different Formwork Materials-
The selection of material to be used for formwork and shoring shall take into
account its strength, rigidity, durability, workability, finished quality of concreted surface,
effect on the fresh concrete placed, and the economy.
I) Timber: Requirements
i. locally available and cost effective
ii. reasonably seasoned to avoid warping
iii. should hold nails well
iv. use hard wood in cases of heavy structures imposing large loads on the
formwork
v. timber for formwork should be softwood of partially seasoned stock to avoid
swelling or warping as per IS: 883–1994.
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Characteristics
1. It should be easy to work with by hand or machine and should not split when nailed.
2. It should be hard enough to withstand damage on the contact surface under normal
conditions of erecting and stripping of the formwork, fixing steel reinforcement bars and
placing concrete.
3. It should be light enough for the workers to handle and carry to their respective work
areas.
4. It should be stiff so as to avoid undue deflection when loaded, and strong enough to
safely carry considerable loads and pressures that may be applied during concreting.
5. It should be reasonably stable and not unduly liable to cast or warp when exposed to
sun and rain or when unevenly we ed during rainy days or the monsoon seasons.
6. It should have the correct amount of moisture so that it will not warp and swell after
concrete is placed.
7. It should not have excessive formation of hemicelluloses (wood sugars) on the first
use after exposure to sunlight, as it will retard the curing of concrete.
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Commonly Used Timber Sections for Formwork and Their Properties
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Commonly Used Timber Sections for Formwork and Their Properties
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Specifications of Timber for Formwork Applications
The specification for timber to be used in a formwork application must
conform to IS: 3629–1986
Grades of Timber: Based on prohibited and permissible defects of cut timber-
Grade I-The estimated effect in reduction of the strength of timber is not more than 12.5 percent.
Grade II-The estimated effect in reduction of the strength of timber is not more than 25 percent.
Grade III-The estimated effect in reduction of the strength of timber is not more than 37.5 percent.
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Defects in Timber for Formwork Applications
Defects Prohibited - Loose grains, splits,heart wood rot, sap rot, warp,
worm holes made by powder post beetles and pitch pockets shall not be permitted.
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Permissible Stresses for Timber
IS: 883–1994 classifies timber for constructional purposes in three groups
based on their strength properties, namely, modulus of elasticity (E) and extreme fiber
stress in bending and tension (fb ).
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Permissible Stresses for Timber
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Modification Factors
The modification factors to allow for change in the slope of grain (represented by K1) are
provided in Table 2.8. The K1 values are provided for both beams and ties and posts or columns.
The modification factors for change in the duration of loading are provided in Table 2.9.
This modification factor is represented by K2. It may be noted that with the decrease in loading
duration, the K2 values increase. It is maximum for instantaneous or impact loading conditions.
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Grains
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Application of Timber in Formwork
Timber is used for formwork sheathing, joists, beam bottoms, batten
supporting floor boards, battens supporting vertical sheeting of vertical
formwork, and for timber posts (vertical shores).
Requirement for timber board as sheathing member:
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Application of Timber in Formwork
Requirement for timber board as sheathing member:
1) The material for the sheathing should not deteriorate extensively on the absorption of
moisture.
2) The repeated cycles of wetting and drying may cause some timber boards to crack,
spall, or become brittle. This may cause a considerable reduction in the strength. In
order to avoid the deterioration and consequently the reduction in strength, the
timber material should be selected and stored carefully.
3) The timber for formwork sheathing is usually made plain on the side in contact with
the concrete.
4) The timber should be rigid to avoid local bending and denting.
5) The block boards should not be used as sheathing member.
6) The recommended minimum thicknesses of timber board to act as a sheathing
member are given below for different applications-
i. For wall, vertical sides of beams : 25 mm
ii. For floors of normal loads : 30 mm
iii. For floors where heavier constructional loads are possible : 37 mm
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Application of Timber in Formwork
Requirement for timber joists, beam bottoms, batten supporting floor boards,
and battens supporting vertical sheeting of vertical formwork:
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Application of Timber in Formwork
Requirement for timber joists, beam bottoms, batten supporting floor boards,
and battens supporting vertical sheeting of vertical formwork:
The depth (or thickness) of battens or joists will be based on strength and deflection
requirements-
Note- Timber members used as joists, beam bottoms, battens supporting floor boards,
battens supporting vertical sheeting of walls act primarily in bending.
The maximum permissible unstiffened length is 50 times the width of the timber
batten (joist) for such applications.
For example, if the timber batten is 50 mm wide, the maximum spacing between
stiffeners (horizontal or vertical) or cross members shall be 50 x 50 = 2,500 mm = 2.5 m.
Ø Temporary Strucutres-
• Concrete formwork-
I) Timber: Application of Timber in Formwork
Requirement for timber posts (Vertical Shores):
The l/d ratio is one of the
where l = unsupported length of a member and
d = width of the face of the member under consideration, is one of the important design
parameters for timber shore design.
Note-
1. The floor to floor height in a normal building is of the order of 3 to 4 m.
2. The shores are provided with horizontal braces at a distance of about 1.80 m from
the floor level.
3. The 1.8 m distance is ensured, so that a crew member of average height can easily
work under the braces.
4. The effective length of the shores is about 2 times the height between the braces
(about 1.80 m as explained above).
5. The l/d ratio in case of long columns is recommended to be 50.
6. Thus, in order to avoid buckling and to avoid the shores against the collapse, the
minimum recommended cross section of timber shores/posts should be taken as 100
mm x 100 mm.
7. The free standing shores (without horizontal braces) of very large heights should be
avoided.
Ø Temporary Strucutres-
• Concrete formwork-
II) Plywood: Introduction
• Is the most commonly used material for formwork because of the ease with which it
can be cut and assembled on the site therefore reduces the cost of making.
• It is used as a sheathing material directly in contact with the concrete.
• With proper care and treatment of many reuses are possible with plywood.
• IS: 4990–1993 gives specification of the plywood used for the purpose of form lining
and sheathing.
• There are about 20 tests prescribed in IS: 1734–1983 for plywood testing.
• The concrete surface obtained by plywood can virtually eliminate the need of
plastering.
• Plywood can be used in a be er way both in the hot and the cold climatic conditions
as the external heat or cold does not penetrate through plywood unlike metal sheeting.
Ø Temporary Strucutres-
• Concrete formwork-
II) Plywood: Permissible Stresses in Plywood
• Based on the permissible deflection in plywood to be 1:270 (1/270th of the span
between the bearers), the permissible stresses have been worked out in Table
Note- 1. The above loads apply when the concrete is laid on concrete shuttering
plywood as in slabs and beams.
2. The same thickness of concrete in a wall can be held without excess deflection by
thinner boards.
3. According to IS: 4990–1993, the maximum load should be reduced to 75 % if wet
boards are used.
Ø Temporary Strucutres-
• Concrete formwork-
II) Plywood: Commonly Available Sizes of Plywood and Their Properties
Note- Thicknesses of plywood.
1. In India leading plywood manufacturer offers plywood in 4 mm, 6 mm, 9 mm, 12 mm,
16 mm, 19 mm, and 25 mm thicknesses.
2. The 12 mm and 19 mm plywood thicknesses are the most commonly used.
3. A minimum thickness of 12 mm with proper frame work is suggested.
4. The smaller thicknesses of plywood are used for applications such as casting curved
wall, dome etc. where it is desired to bend the plywood.
Ø Temporary Strucutres-
• Concrete formwork-
II) Plywood: Data on the weight in kg/m2 of plywood from a leading Indian
plywood manufacturer is given in Table
The code IS: 4990–1993 also suggests the minimum bending radii for the plywood of
different thicknesses. They are given in Table
Ø Temporary Strucutres-
• Concrete formwork-
II) Plywood: Requirement for Plywood for Formwork Application
As per IS: 4990–1993
1. The moisture absorption should be as low as possible, otherwise the plywood would
absorb the moisture from the concrete.
2. Moisture absorption leads to loss of binding ability of the resins used in the
manufacturing of plywood.
3. The moisture results in peeling off of the veneers of plywood. Hence it is
recommended to use hard wood veneers in conjunction with water insoluble resins.
4. As far as applicable, both the used and unused forms should be stored in shade.
5. The plywood must also be durable under alternate wetting and drying conditions.
6. The surface films in phenolic resin bonded plywood have the following advantages:
i. Makes the plywood invulnerable to moisture.
ii. Protection from deterioration caused by concrete and slurry.
iii. Smooth finish to the concrete.
iv. Large reuses are possible.
v. Very good for fair faced concrete application.
Ø Temporary Strucutres-
• Concrete formwork-
III) Steel: Introduction
• Compared to timber formwork, steel formwork provides smoother concrete surfaces
and is found to be economical if there are a large number of uses.
• It has adequate rigidity and strength.
• These forms can be erected, disassembled, moved and re-erected at a faster pace, if
suitable handling equipments are available.
• It facilitates in maintaining accurate alignment, levels and dimensions.
• The cost advantage would turn into disadvantage if there were less number of reuses
of the steel form.
• These forms offer little or no insulation protection to the concrete placed during cold
weather.
Ø Temporary Strucutres-
• Concrete formwork-
III) Steel: Commonly Used Steel Sections for Formwork and Their Properties
• Steel plates of 3.15 mm and 5.0 mm thicknesses are commonly used for fabricating
the sheathing.
• IS Angle sections 50 x 50 x 6 and 65 x 65 x 6 are commonly used for making steel
panels to be used in the wall, column, and slab and beam applications.
• Channel section ISMC 100 is the common fabrication material for fabricating walers
and soldiers.
• It is very common to use 40 NB circular steel pipes for shoring and scaffolding works.
• Note- Use IS: 2750–1964 for steel tubes of different diameters and their various
properties like cross sectional area (A), moment of inertia (I), section modulus (Z),
and radius of gyration (K) etc.
Ø Temporary Strucutres-
• Concrete formwork-
III) Steel: Permissible Stresses for Steel
Axial stress in compression— The permissible stress in compression can be
obtained from following figs.
Ø Temporary Strucutres-
• Concrete formwork-
III) Steel: Permissible Stresses for Steel
Axial stress in tension— The various stresses on the net cross-sectional area of
tubes shall not exceed the values specified in Table
Note: Some of the relevant IS codes providing specification on steel forms are
IS: 2062–2006, IS: 8500 –1991, IS: 1977–1996, IS: 800–2007, and IS:
1161–1998.
Ø Temporary Strucutres-
• Concrete formwork-
III) Steel: Application of Steel in Formwork
The various applications of steel in formwork and their brief features are given in Table
Ø Temporary Strucutres-
• Concrete formwork-
IV) Aluminium: Introduction and Features of Aluminum Formwork
1. The aluminum forms are similar to steel forms.
2. Because of lower density and being lighter than steel, it is necessary to use larger
sections when forms are made of aluminum as they have lower strength in tension and
compression compared to steel.
3. Very less labor required in erecting, handling, and disassembling. Handling is easy.
4. Pure aluminum is attacked chemically by wet concrete but certain aluminum alloys
are found resistant to wet concrete as well as atmospheric corrosion, and they are used
for making aluminum forms.
5. Lightweight props in aluminum alloy tubes are also used.
6. The aluminum forms are highly favored in countries where mechanical handling
equipment are used on a large scale, labor is in short supply, and the cost of engaging
labor is also prohibitive.
7. Some manufacturers claim upto 2,500 repetitions with aluminum form, provided
reasonable care, cleaning, and maintenance are carried out at reasonable intervals.
Ø Temporary Strucutres-
• Concrete formwork-
V) Plastic Forms:
1. It is a better alternative to wood.
2. Plastic formworks are eco-friendly.
3. It gives better finish, easy transportation, are light in weight, does not rust, easy
cleaning etc.
4. These moulds resist mechanical handling; they do not deform easily and can be
quickly assembled and stripped.
5. The jointing of plastic formworks is also easily achievable.
6. They can be re-used large number of times.
7. It allows greater freedom of design. We can mould even unusual textures and designs.
8. Best known plastic sheathings are those made of PVC, neoprene, and polyester
strengthened with glass fiber.
Ø Temporary Strucutres-
• Concrete formwork-
VI) Other Form Materials:
1. Plaster of Paris Forms- Used for architectural ornamental purposes
2. Hard Boards-Is a board manufactured from wood fiber under the controlled
combination of pressure, heat, and moisture. Tempered hard boards have improved
strength properties, lower rate of water absorption, better abrasion resistance and
therefore, these are used for formwork lining. Being thinner - about 6 mm — they are
flexible, and are used for lining of the curved surfaces.
3. Lost forms- Examples are precast concrete planks, pressed fiber planks, cardboard
tubes, precast reinforced concrete joists and clay filler blocks, ferrocement planks etc.
These forms are left along with the laid in-situ concrete and form an integral part of the
construction.
4. Fiber Forms- These are generally used as lost forms especially for concrete walls,
roofs and slabs. These are left in place on the exposed face of the concrete where it
gives an architectural look and also improves the acoustical and insulating properties.
Fiber boards are made from such substances as glass fibers or wood fibers.
Ø Temporary Strucutres-
• Concrete formwork-
VI) Other Form Materials:
5. Gypsum Boards- Gypsum moulds are generally used to provide artistic design or
ornamental pattern for the exposed concrete face. Gypsum mix is reinforced with
organic fiber or coir or sisal to get structure toughness. Concrete quality may improve
due to the absorption of superfluous water in the concrete. The fragility of gypsum
surfaces impedes its widespread use.
6. Asbestos Tiles- Corrugated asbestos tiles like corrugated sheets have been used as
the re-usable shuttering material where corrugated face is required.
7. Wire Mesh- The wire mesh is a kind of lost form. The wire mesh may act as a form
to take up plaster. Example is ferrocement structure
8. Inflated Membranes- Are used (1) occasionally to form structures of varied shapes
such as spherical, elliptical, cylindrical etc. (2) for providing block-outs or cavities in
areas where access is difficult and the application of other form materials is difficult.
9. Fabric Formwork- Fabric formwork uses a flexible textile membrane in place of the
rigid formwork panels.
Ø Introduction- Impact of Structural Design
on Formwork Cost
“The least amount of permanent materials in the structure will result in the least cost.”
For most economical design, the designer typically analyzes each individual member to
make certain that it is not heavier, wider, or deeper than its load requires. This is done
under the pre-tense that the minimum size and least weight result in the best design.
However, this approach to design neglects the impact of the cost of formwork, the
temporary support structure that must be fabricated and installed to support the
permanent materials. Focusing only on ways to economize on permanent materials, with
little or no consideration of the temporary formwork, can actually increase, rather than
decrease the total cost of a structure.
THANK YOU....

More Related Content

What's hot

REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1Natalie Ulza
 
Design of rcc structures note
Design of rcc structures noteDesign of rcc structures note
Design of rcc structures noteMahendra Poudel
 
Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920INTEZAAR ALAM
 
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Hossam Shafiq II
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge ConstructionRobin Nirwal
 
External Prestressing of Concrete Members
External Prestressing of Concrete MembersExternal Prestressing of Concrete Members
External Prestressing of Concrete MembersPraveen S.K
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of constructionSANJEEV Wazir
 
Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaKhyati Saggu
 
Construction practices
Construction practicesConstruction practices
Construction practicesArun Kurali
 
Structural analysis 1
Structural analysis   1Structural analysis   1
Structural analysis 1R VIJAYAKUMAR
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDFIDHAMUKI
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing MethodMd Tanvir Alam
 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsFawad Najam
 

What's hot (20)

REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1
 
Design of rcc structures note
Design of rcc structures noteDesign of rcc structures note
Design of rcc structures note
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
 
Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920
 
Deep beam
Deep beamDeep beam
Deep beam
 
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 
External Prestressing of Concrete Members
External Prestressing of Concrete MembersExternal Prestressing of Concrete Members
External Prestressing of Concrete Members
 
Bar bending schedule
Bar bending scheduleBar bending schedule
Bar bending schedule
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
 
Formwork
FormworkFormwork
Formwork
 
Design of beams
Design of beamsDesign of beams
Design of beams
 
Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In India
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Structural analysis 1
Structural analysis   1Structural analysis   1
Structural analysis 1
 
5 plastic analysis
5 plastic analysis5 plastic analysis
5 plastic analysis
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDF
 
Ppt
PptPpt
Ppt
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie Models
 

Similar to Formwork Types and Requirements

Similar to Formwork Types and Requirements (20)

Site report
Site reportSite report
Site report
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Formwork
FormworkFormwork
Formwork
 
national building code
national building codenational building code
national building code
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineering
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
Formwork
FormworkFormwork
Formwork
 
Special structure
Special structureSpecial structure
Special structure
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Table formwork
Table formwork Table formwork
Table formwork
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORK
 
building structures of architectural students.pptx
building structures of architectural students.pptxbuilding structures of architectural students.pptx
building structures of architectural students.pptx
 

More from sumitt6_25730773

Formwork Supports, Scaffolds and Failure.pdf
Formwork Supports, Scaffolds and Failure.pdfFormwork Supports, Scaffolds and Failure.pdf
Formwork Supports, Scaffolds and Failure.pdfsumitt6_25730773
 
Bending stresses and shear stresses
Bending stresses and shear stressesBending stresses and shear stresses
Bending stresses and shear stressessumitt6_25730773
 
Shear Force and Bending Moment Diagram
Shear Force and Bending Moment DiagramShear Force and Bending Moment Diagram
Shear Force and Bending Moment Diagramsumitt6_25730773
 

More from sumitt6_25730773 (6)

Formwork Supports, Scaffolds and Failure.pdf
Formwork Supports, Scaffolds and Failure.pdfFormwork Supports, Scaffolds and Failure.pdf
Formwork Supports, Scaffolds and Failure.pdf
 
Bending stresses and shear stresses
Bending stresses and shear stressesBending stresses and shear stresses
Bending stresses and shear stresses
 
Shear Force and Bending Moment Diagram
Shear Force and Bending Moment DiagramShear Force and Bending Moment Diagram
Shear Force and Bending Moment Diagram
 
Flow Through Pipe
Flow Through PipeFlow Through Pipe
Flow Through Pipe
 
Concept of Boundary Layer
Concept of Boundary LayerConcept of Boundary Layer
Concept of Boundary Layer
 
Flow through pipes
Flow through pipesFlow through pipes
Flow through pipes
 

Recently uploaded

Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Recently uploaded (20)

Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 

Formwork Types and Requirements

  • 1. Sanjivani Rural Education Society's Sanjivani College of Engineering, Kopargaon 423603. -Department of Strucutral Engineering- By Mr. Sumit S. Kolapkar (Assistant Professor) Mail Id- kolapkarsumitst@sanjivani.org.in
  • 2. Ø Introduction- Formwork as a Temporary Strucutres RC construction primarily consists of three components- formwork, reinforcement and concrete. 1. Formwork accounts about 35 to 50 % of total construction cost. 2. Formwork operations consumes about 50 to 75 % of the total time of construction. 3. Formwork components are highly loaded for a few hours during concrete placement. Hence we can design these components by allowing higher permissible stresses as compared to the stresses taken for the design of permanent structures.
  • 3. Ø Introduction- Temporary Strucutres • Concrete Formwork (Shuttering) • Scaffolding • Falsework/Shoring • Cofferdams • Underpinning • Diaphragm/Slurry Walls • Earth retaining structures • Construction dewatering
  • 4. Ø Temporary Strucutres- • Cofferdams- Watertight enclosure from which water is pumped to expose the bed of a body of water in order to permit the construction of a pier or other hydraulic work below the waterline.
  • 5. Ø Temporary Strucutres- • Underpinning- Reinforcing of an existing building foundation. It is required when the original foundation is no longer strong enough to support the structure. • Is provided underneath of an existing foundation to maintain its stability. Used to repair, strengthen foundation of existing structure.
  • 6. Ø Temporary Strucutres- • Diaphragm/Slurry Walls- An underground concrete wall constructed panel-by-panel each interlocked to ensure structural stability and water tightness. • Uses: Earth retention (resisitng lateral load), load bearing foundation, water proofing, groundwater barriers etc.
  • 7. Ø Temporary Strucutres- • Earth retaining structures- • Construction dewatering-
  • 8. Ø Temporary Strucutres- • Concrete formwork- • Purpose- To support its own weight and that of freshly placed concrete as well as the construction live loads including materials, equipment and workmen. • It is a complete system of temporary structure built to contain fresh concrete so as to form it into the required shape and dimensions and to support it until it hardens sufficiently to become self-supporting.
  • 9. Ø Temporary Strucutres- • Parts of Concrete formwork- 1. Sheeting (Sheathing)- That part of formwork, which is in contact with the concrete. 2. Form (Shutter)- (a) That part of formwork, which consists of the sheeting and its immediate supporting or stiffening members. (b) A structure or mould in support of vertical strucutral member of concrete while it is setting and gaining sufficient strength to be self-supporting.Ex: Column, retaining wall, footings etc. 3. Falsework- (a) Falsework is the temporary structure erected to support the work in the process of construction. It is composed of shores, formwork for beams or slabs (or both) and lateral bracing. To hold the items in place. (b) It supports the forms, usually for a long structure, such as a bridge. 4. Centering- It is a horizontal structural member supporting a structure. Exd: soffit, slab etc. It is the formwork used in the construction of arches, shells space structure where the entire falsework is struck or decentered as a unit, to avoid introducing injurious stress in any part of the structure.
  • 10. Ø Temporary Strucutres- • Parts of Concrete formwork- 5. Mould- A frame for casting, precast concrete units. 6. Scaffold (Scaffolding)- A temporary structure for gaining access to higher levels of the permanent structure during construction. For workers to stand on while working on a building
  • 11. Ø Temporary Strucutres- • Concrete formwork- • Requirements- Quality, safety and economy • The formwork must be built and erected in such a way that the required shape, size, position, quantity, and finish of the concrete are obtained. • The formwork must be strong enough to take the pressure or weight of the fresh concrete, so that the finish of the concrete is obtained. The material should not warp or get distorted. • The formwork should be designed and constructed such that it can be easily and quickly erected and struck with minimum skilled workforce leading to savings in both time and money. It should be able to be set accurately to the desired line and levels. • The formwork must be able to be struck without damage to the concrete or to the formwork itself. • The formwork must be able to be handled using the available equipment or to be manually handled, if necessary. • The formwork arrangement must provide safe access for the handling of concrete and its placing. • The formwork must have all the necessary safety arrangement relating to working areas and platforms. • The formwork arrangement must be flexible enough to get the desired finish. That is, it should be able to accommodate different types of sheathing material, e.g., plywood, steel etc. • The formwork should also be able to accommodate any architectural features such as grooves, surface grains etc. It should be possible to a ain tight joints so that there is no leakage of cement grout.
  • 12. Ø Temporary Strucutres- • Concrete formwork- • Requirements- Quality, safety and economy
  • 13. Ø Temporary Strucutres- • Concrete formwork- • Selection- 1. the design of a building, 2. site constraints, 3. available resources, 4. the contractor’s experience with different systems, and their availability 5. The type of building element to be formed, 6. the type of sheathing material, 7. safety and serviceability of the structural frame, 8. economics 9. building design, 10. job specification, 11. local conditions, and 12. supporting organisation
  • 14. Ø Temporary Strucutres- • Concrete formwork- • Types-
  • 15. Ø Temporary Strucutres- • Concrete formwork- • Types- Traditional classification I) Conventional System of Formwork: • In this system, timber and plywood are used predominantly. • The various formwork components are connected with the help of nails. • Disadvantages: • limited reuse value, • higher cost, • can be fabricated, installed, and removed only by skilled workmen, • since the skill of workmen and the quality of formwork material vary from site to site, the quality of concrete structures obtained is not consistent, • in large projects, it is difficult to ensure an efficient utilisation of the timber available on site. Note- All these factors adversely affect the cost of formwork.
  • 16. Ø Temporary Strucutres- • Concrete formwork- • Types- Traditional classification I) Conventional System of Formwork:
  • 17. Ø Temporary Strucutres- • Concrete formwork- • Types- Traditional classification II) Proprietary/Patented System of Formwork: • Most of the disadvantages observed in conventional systems can be overcome by adopting good proprietary systems, which make use of standard factory made components • Very less formwork are made at site, therefore saves labor cost • with uniform quality standard products, it is possible to achieve uniformly good workmanship, improved quality of concrete surface and high reuse value • Can be assembled and dismantled with unskilled/semi-skilled labor
  • 18. Ø Temporary Strucutres- • Concrete formwork- • Types- Traditional classification II) Proprietary/Patented System of Formwork:
  • 19. Ø Temporary Strucutres- • Concrete formwork- • Types- Traditional classification III) Modular System of Formwork: • the formwork modules are manufactured in a factory set up, and delivered to the site in a pre-fabricated form. • can be assembled very quickly at the project locations. • Advantages: 1. as it uses standardized modules, and their installation process is simple, it requires less skilled workers. 2. considerable reduction in erection time at the site. 3. large number of repetitions (reuse) result in the cost of formwork being considerably on a lower side. 4. The safety of workers and materials is ensured, as it has high strength of the form. 5. The quality of the concrete surface obtained is extremely good which reduces the need for further finishing work such as plastering, after removal of the form.
  • 20. Ø Temporary Strucutres- • Concrete formwork- • Types- Traditional classification III) Modular System of Formwork: • Advantages: 6. it automate the formwork operation and improve the productivity as well as the cost-effectiveness in a construction project. 7. for successful use of a modular formwork system, proper planning in the architectural design stage as well as in the construction phase of a project is necessary. 8. the factors such as the form reuse scheme, the allocation of modular form sets, cranes, workers, etc., and the construction sequence need to be carefully planned out to get the best out of the modular formwork.
  • 21. Ø Temporary Strucutres- • Concrete formwork- • Types- Traditional classification III) Modular System of Formwork:
  • 22. Ø Temporary Strucutres- • Concrete formwork- • Types- Classification based on Hanna (1999) I) Horizontal System of Formwork:
  • 23. Ø Temporary Strucutres- • Concrete formwork- • Types- Classification based on Hanna (1999) I) Horizontal System of Formwork: • In Hand set formwork, the commonly used formwork systems are: (a) conventional wood system (also known as stick form) and (b) conventional metal system (also known as improved stick form). The conventional wood system is available for laying the foundation, beams and slabs, and columns etc. • In Crane set formwork systems, we have the flying formwork system, column mounted shoring system, and tunnel forming system. • In Special horizontal formwork systems, we have the joist slab forming system, and dome forming system. • Generally consist of a series of interconnected falsework bays, independent props or system scaffolds and supporting a number of panels.
  • 24. Ø Temporary Strucutres- • Concrete formwork- • Types- Classification based on Hanna (1999) I) Horizontal System of Formwork:
  • 25. Ø Temporary Strucutres- • Concrete formwork- • Types- Classification based on Hanna (1999) II) Vertical System of Formwork: Under vertical formwork system, we essentially have two subsystems: crane dependent system and crane independent system. • In crane dependent system, we have the conventional wall column framing system, Ganged framing system, and Jump form. • In crane independent system, the commonly used formwork systems are: (a) slipform and (b) self raising formwork system.
  • 26. Ø Temporary Strucutres- • Concrete formwork- • Types- Classification based on Hanna (1999) II) Vertical System of Formwork:
  • 27. Ø Temporary Strucutres- • Concrete formwork- • Types- Classification based on DSR Formwork Items In India, often the formwork items are presented in a specific form in the bill of quantities. These items are mentioned in the Delhi Schedule of Rates (DSR 2007). From that clue the third system of classification is referred to as “classification based on Formwork items as used in DSR 2007”.
  • 28. Ø Temporary Strucutres- • Concrete formwork- • Different Formwork Materials- The selection of material to be used for formwork and shoring shall take into account its strength, rigidity, durability, workability, finished quality of concreted surface, effect on the fresh concrete placed, and the economy. I) Timber: Requirements i. locally available and cost effective ii. reasonably seasoned to avoid warping iii. should hold nails well iv. use hard wood in cases of heavy structures imposing large loads on the formwork v. timber for formwork should be softwood of partially seasoned stock to avoid swelling or warping as per IS: 883–1994.
  • 29. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Characteristics 1. It should be easy to work with by hand or machine and should not split when nailed. 2. It should be hard enough to withstand damage on the contact surface under normal conditions of erecting and stripping of the formwork, fixing steel reinforcement bars and placing concrete. 3. It should be light enough for the workers to handle and carry to their respective work areas. 4. It should be stiff so as to avoid undue deflection when loaded, and strong enough to safely carry considerable loads and pressures that may be applied during concreting. 5. It should be reasonably stable and not unduly liable to cast or warp when exposed to sun and rain or when unevenly we ed during rainy days or the monsoon seasons. 6. It should have the correct amount of moisture so that it will not warp and swell after concrete is placed. 7. It should not have excessive formation of hemicelluloses (wood sugars) on the first use after exposure to sunlight, as it will retard the curing of concrete.
  • 30. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Commonly Used Timber Sections for Formwork and Their Properties
  • 31. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Commonly Used Timber Sections for Formwork and Their Properties
  • 32. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Specifications of Timber for Formwork Applications The specification for timber to be used in a formwork application must conform to IS: 3629–1986 Grades of Timber: Based on prohibited and permissible defects of cut timber- Grade I-The estimated effect in reduction of the strength of timber is not more than 12.5 percent. Grade II-The estimated effect in reduction of the strength of timber is not more than 25 percent. Grade III-The estimated effect in reduction of the strength of timber is not more than 37.5 percent.
  • 33. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Defects in Timber for Formwork Applications Defects Prohibited - Loose grains, splits,heart wood rot, sap rot, warp, worm holes made by powder post beetles and pitch pockets shall not be permitted.
  • 34. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Permissible Stresses for Timber IS: 883–1994 classifies timber for constructional purposes in three groups based on their strength properties, namely, modulus of elasticity (E) and extreme fiber stress in bending and tension (fb ).
  • 35. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Permissible Stresses for Timber
  • 36. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Modification Factors The modification factors to allow for change in the slope of grain (represented by K1) are provided in Table 2.8. The K1 values are provided for both beams and ties and posts or columns. The modification factors for change in the duration of loading are provided in Table 2.9. This modification factor is represented by K2. It may be noted that with the decrease in loading duration, the K2 values increase. It is maximum for instantaneous or impact loading conditions.
  • 37. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Grains
  • 38. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Application of Timber in Formwork Timber is used for formwork sheathing, joists, beam bottoms, batten supporting floor boards, battens supporting vertical sheeting of vertical formwork, and for timber posts (vertical shores). Requirement for timber board as sheathing member:
  • 39. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Application of Timber in Formwork Requirement for timber board as sheathing member: 1) The material for the sheathing should not deteriorate extensively on the absorption of moisture. 2) The repeated cycles of wetting and drying may cause some timber boards to crack, spall, or become brittle. This may cause a considerable reduction in the strength. In order to avoid the deterioration and consequently the reduction in strength, the timber material should be selected and stored carefully. 3) The timber for formwork sheathing is usually made plain on the side in contact with the concrete. 4) The timber should be rigid to avoid local bending and denting. 5) The block boards should not be used as sheathing member. 6) The recommended minimum thicknesses of timber board to act as a sheathing member are given below for different applications- i. For wall, vertical sides of beams : 25 mm ii. For floors of normal loads : 30 mm iii. For floors where heavier constructional loads are possible : 37 mm
  • 40. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Application of Timber in Formwork Requirement for timber joists, beam bottoms, batten supporting floor boards, and battens supporting vertical sheeting of vertical formwork:
  • 41. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Application of Timber in Formwork Requirement for timber joists, beam bottoms, batten supporting floor boards, and battens supporting vertical sheeting of vertical formwork: The depth (or thickness) of battens or joists will be based on strength and deflection requirements- Note- Timber members used as joists, beam bottoms, battens supporting floor boards, battens supporting vertical sheeting of walls act primarily in bending. The maximum permissible unstiffened length is 50 times the width of the timber batten (joist) for such applications. For example, if the timber batten is 50 mm wide, the maximum spacing between stiffeners (horizontal or vertical) or cross members shall be 50 x 50 = 2,500 mm = 2.5 m.
  • 42. Ø Temporary Strucutres- • Concrete formwork- I) Timber: Application of Timber in Formwork Requirement for timber posts (Vertical Shores): The l/d ratio is one of the where l = unsupported length of a member and d = width of the face of the member under consideration, is one of the important design parameters for timber shore design. Note- 1. The floor to floor height in a normal building is of the order of 3 to 4 m. 2. The shores are provided with horizontal braces at a distance of about 1.80 m from the floor level. 3. The 1.8 m distance is ensured, so that a crew member of average height can easily work under the braces. 4. The effective length of the shores is about 2 times the height between the braces (about 1.80 m as explained above). 5. The l/d ratio in case of long columns is recommended to be 50. 6. Thus, in order to avoid buckling and to avoid the shores against the collapse, the minimum recommended cross section of timber shores/posts should be taken as 100 mm x 100 mm. 7. The free standing shores (without horizontal braces) of very large heights should be avoided.
  • 43. Ø Temporary Strucutres- • Concrete formwork- II) Plywood: Introduction • Is the most commonly used material for formwork because of the ease with which it can be cut and assembled on the site therefore reduces the cost of making. • It is used as a sheathing material directly in contact with the concrete. • With proper care and treatment of many reuses are possible with plywood. • IS: 4990–1993 gives specification of the plywood used for the purpose of form lining and sheathing. • There are about 20 tests prescribed in IS: 1734–1983 for plywood testing. • The concrete surface obtained by plywood can virtually eliminate the need of plastering. • Plywood can be used in a be er way both in the hot and the cold climatic conditions as the external heat or cold does not penetrate through plywood unlike metal sheeting.
  • 44. Ø Temporary Strucutres- • Concrete formwork- II) Plywood: Permissible Stresses in Plywood • Based on the permissible deflection in plywood to be 1:270 (1/270th of the span between the bearers), the permissible stresses have been worked out in Table Note- 1. The above loads apply when the concrete is laid on concrete shuttering plywood as in slabs and beams. 2. The same thickness of concrete in a wall can be held without excess deflection by thinner boards. 3. According to IS: 4990–1993, the maximum load should be reduced to 75 % if wet boards are used.
  • 45. Ø Temporary Strucutres- • Concrete formwork- II) Plywood: Commonly Available Sizes of Plywood and Their Properties Note- Thicknesses of plywood. 1. In India leading plywood manufacturer offers plywood in 4 mm, 6 mm, 9 mm, 12 mm, 16 mm, 19 mm, and 25 mm thicknesses. 2. The 12 mm and 19 mm plywood thicknesses are the most commonly used. 3. A minimum thickness of 12 mm with proper frame work is suggested. 4. The smaller thicknesses of plywood are used for applications such as casting curved wall, dome etc. where it is desired to bend the plywood.
  • 46. Ø Temporary Strucutres- • Concrete formwork- II) Plywood: Data on the weight in kg/m2 of plywood from a leading Indian plywood manufacturer is given in Table The code IS: 4990–1993 also suggests the minimum bending radii for the plywood of different thicknesses. They are given in Table
  • 47. Ø Temporary Strucutres- • Concrete formwork- II) Plywood: Requirement for Plywood for Formwork Application As per IS: 4990–1993 1. The moisture absorption should be as low as possible, otherwise the plywood would absorb the moisture from the concrete. 2. Moisture absorption leads to loss of binding ability of the resins used in the manufacturing of plywood. 3. The moisture results in peeling off of the veneers of plywood. Hence it is recommended to use hard wood veneers in conjunction with water insoluble resins. 4. As far as applicable, both the used and unused forms should be stored in shade. 5. The plywood must also be durable under alternate wetting and drying conditions. 6. The surface films in phenolic resin bonded plywood have the following advantages: i. Makes the plywood invulnerable to moisture. ii. Protection from deterioration caused by concrete and slurry. iii. Smooth finish to the concrete. iv. Large reuses are possible. v. Very good for fair faced concrete application.
  • 48. Ø Temporary Strucutres- • Concrete formwork- III) Steel: Introduction • Compared to timber formwork, steel formwork provides smoother concrete surfaces and is found to be economical if there are a large number of uses. • It has adequate rigidity and strength. • These forms can be erected, disassembled, moved and re-erected at a faster pace, if suitable handling equipments are available. • It facilitates in maintaining accurate alignment, levels and dimensions. • The cost advantage would turn into disadvantage if there were less number of reuses of the steel form. • These forms offer little or no insulation protection to the concrete placed during cold weather.
  • 49. Ø Temporary Strucutres- • Concrete formwork- III) Steel: Commonly Used Steel Sections for Formwork and Their Properties • Steel plates of 3.15 mm and 5.0 mm thicknesses are commonly used for fabricating the sheathing. • IS Angle sections 50 x 50 x 6 and 65 x 65 x 6 are commonly used for making steel panels to be used in the wall, column, and slab and beam applications. • Channel section ISMC 100 is the common fabrication material for fabricating walers and soldiers. • It is very common to use 40 NB circular steel pipes for shoring and scaffolding works. • Note- Use IS: 2750–1964 for steel tubes of different diameters and their various properties like cross sectional area (A), moment of inertia (I), section modulus (Z), and radius of gyration (K) etc.
  • 50. Ø Temporary Strucutres- • Concrete formwork- III) Steel: Permissible Stresses for Steel Axial stress in compression— The permissible stress in compression can be obtained from following figs.
  • 51. Ø Temporary Strucutres- • Concrete formwork- III) Steel: Permissible Stresses for Steel Axial stress in tension— The various stresses on the net cross-sectional area of tubes shall not exceed the values specified in Table Note: Some of the relevant IS codes providing specification on steel forms are IS: 2062–2006, IS: 8500 –1991, IS: 1977–1996, IS: 800–2007, and IS: 1161–1998.
  • 52. Ø Temporary Strucutres- • Concrete formwork- III) Steel: Application of Steel in Formwork The various applications of steel in formwork and their brief features are given in Table
  • 53. Ø Temporary Strucutres- • Concrete formwork- IV) Aluminium: Introduction and Features of Aluminum Formwork 1. The aluminum forms are similar to steel forms. 2. Because of lower density and being lighter than steel, it is necessary to use larger sections when forms are made of aluminum as they have lower strength in tension and compression compared to steel. 3. Very less labor required in erecting, handling, and disassembling. Handling is easy. 4. Pure aluminum is attacked chemically by wet concrete but certain aluminum alloys are found resistant to wet concrete as well as atmospheric corrosion, and they are used for making aluminum forms. 5. Lightweight props in aluminum alloy tubes are also used. 6. The aluminum forms are highly favored in countries where mechanical handling equipment are used on a large scale, labor is in short supply, and the cost of engaging labor is also prohibitive. 7. Some manufacturers claim upto 2,500 repetitions with aluminum form, provided reasonable care, cleaning, and maintenance are carried out at reasonable intervals.
  • 54. Ø Temporary Strucutres- • Concrete formwork- V) Plastic Forms: 1. It is a better alternative to wood. 2. Plastic formworks are eco-friendly. 3. It gives better finish, easy transportation, are light in weight, does not rust, easy cleaning etc. 4. These moulds resist mechanical handling; they do not deform easily and can be quickly assembled and stripped. 5. The jointing of plastic formworks is also easily achievable. 6. They can be re-used large number of times. 7. It allows greater freedom of design. We can mould even unusual textures and designs. 8. Best known plastic sheathings are those made of PVC, neoprene, and polyester strengthened with glass fiber.
  • 55. Ø Temporary Strucutres- • Concrete formwork- VI) Other Form Materials: 1. Plaster of Paris Forms- Used for architectural ornamental purposes 2. Hard Boards-Is a board manufactured from wood fiber under the controlled combination of pressure, heat, and moisture. Tempered hard boards have improved strength properties, lower rate of water absorption, better abrasion resistance and therefore, these are used for formwork lining. Being thinner - about 6 mm — they are flexible, and are used for lining of the curved surfaces. 3. Lost forms- Examples are precast concrete planks, pressed fiber planks, cardboard tubes, precast reinforced concrete joists and clay filler blocks, ferrocement planks etc. These forms are left along with the laid in-situ concrete and form an integral part of the construction. 4. Fiber Forms- These are generally used as lost forms especially for concrete walls, roofs and slabs. These are left in place on the exposed face of the concrete where it gives an architectural look and also improves the acoustical and insulating properties. Fiber boards are made from such substances as glass fibers or wood fibers.
  • 56. Ø Temporary Strucutres- • Concrete formwork- VI) Other Form Materials: 5. Gypsum Boards- Gypsum moulds are generally used to provide artistic design or ornamental pattern for the exposed concrete face. Gypsum mix is reinforced with organic fiber or coir or sisal to get structure toughness. Concrete quality may improve due to the absorption of superfluous water in the concrete. The fragility of gypsum surfaces impedes its widespread use. 6. Asbestos Tiles- Corrugated asbestos tiles like corrugated sheets have been used as the re-usable shuttering material where corrugated face is required. 7. Wire Mesh- The wire mesh is a kind of lost form. The wire mesh may act as a form to take up plaster. Example is ferrocement structure 8. Inflated Membranes- Are used (1) occasionally to form structures of varied shapes such as spherical, elliptical, cylindrical etc. (2) for providing block-outs or cavities in areas where access is difficult and the application of other form materials is difficult. 9. Fabric Formwork- Fabric formwork uses a flexible textile membrane in place of the rigid formwork panels.
  • 57. Ø Introduction- Impact of Structural Design on Formwork Cost “The least amount of permanent materials in the structure will result in the least cost.” For most economical design, the designer typically analyzes each individual member to make certain that it is not heavier, wider, or deeper than its load requires. This is done under the pre-tense that the minimum size and least weight result in the best design. However, this approach to design neglects the impact of the cost of formwork, the temporary support structure that must be fabricated and installed to support the permanent materials. Focusing only on ways to economize on permanent materials, with little or no consideration of the temporary formwork, can actually increase, rather than decrease the total cost of a structure.