SlideShare a Scribd company logo
1 of 26
CAPITAL PROGRAMS – O’HARE 21
PRESENTATION TO CMAA CHICAGO CHAPTER
NOVEMBER 17, 2016
OVERALL PLAN & STATUS
ORD PROJECTS
MDW MODERNIZATION
Mayor’s Goals
Customer Service Facilities, Technology, Preclearance, Amenities and Service Culture
Connectivity Air Service, Express Rail, Western access
Benefit to Chicago Direct development on airport; Indirect, business & job growth
CDA Programs to Achieve
O’Hare 21
1. Airfield package
2. New lease negotiations & capital plan
Domestic Terminals Gates, technology, concessions – ability to expand for future needs
OHare Express Rail (OER) Optimize customer access / cost to maximize private viability
Latin America/ International
Air service development, increase international gates, increase proximity to
domestic gates
Hotels 2 new hotels; refurbish and expand existing Hilton
2015-2019 Plan
3
CONNECTING THE WORLD TO
CHICAGO
STATUS – O’HARE KEY PROJECTS
4CONFIDENTIAL – DRAFT – PREDECISIONAL
Approved/
Underway
Under
Negotiation/Review
Airfield u
Domestic Gates
L “Stinger” 5-RJ Gate Expansion u
New Concourses u
International Gates
T5 M-Concourse 9 WB gate expansion u
New T2 International/domestic terminal u
RFP for Hotel Operator u
O’Hare Express Rail
Conceptual Engineering u
RFP for Hotel Developer u
STATUS – O’HARE PROJECTS
• Innovation Lanes, T1 and T3 November 2016
• Northeast Cargo Phase II December 2016
• L Stinger completion February 2018
• Multi Modal Facility December 2018
• Concessions
– Goose Island B concourse – food service in hold rooms started last week
– Food cart delivers food to hold room area
– ARN Award
• New Flights in November
– EVA to Taipei and on to Bangkok
– ANA to Tokyo Haneda and on to Asia
– Interjet to Mexico City
– Frontier to Cancun, Cabo and PV
5CONFIDENTIAL – DRAFT – PREDECISIONAL
STATUS – MIDWAY MODERNIZATION
• Concessions Proposal Completed
– City Council December
• Ground breaking dates for Midway Modernization
– Security Checkpoint (new bridge) March 2017
– Parking Expansion/ CTA connection upgrade June 2017
• Completion dates for Midway Modernization
– Security Bridges & Parking Structure June 2019
6CONFIDENTIAL – DRAFT – PREDECISIONAL
OVERVIEW – O’HARE
TERMINAL AREA
PROGRAM (TAP)
8
POTENTIAL CONFIGURATIONS FOR NEW CONCOURSES
8
O’HARE 21 – TERMINAL AREA PROGRAM
• The Modernization of O’Hare has completed approximately $5.8B of improvements, including:
– Two New Airport Traffic Control Towers
– Extension of Runway 10L/28R
– New Runway 9L/27R
– New Runway 10C/28C
– New Runway 10R/28L
– Multiple Taxiway Improvements (K&L, LL, others)
– On-going Runway 9C/27C
– On-going Centralized Deicing Facility and Cross Field Taxiway
– On-going Consolidated Rental Car/Parking Multimodal Facility
– On-going ATS Modernization and Extension
• Next goal – Terminal Expansion and remaining airfield improvements
CONFIDENTIAL – DRAFT – PREDECISIONAL 9
O’HARE 21 – TERMINAL AREA PROGRAM (CONTINUED)
• Consistent with the approved Airport Layout Plan, the next step in the process is to build terminals
and concourses to increase gate capacity
– Additional domestic and international gates
– Increased concession space
– Enhanced Passenger Experience
– Increase efficiency
– Reduce Operating Costs
– State-of-the-art building systems
– Enhanced transit connections (intra-terminal/downtown)
– Replacement of aged facilities
CONFIDENTIAL – DRAFT – PREDECISIONAL 10
PROGRAM MANAGER FOR O’HARE 21
• Owner’s Representative Services for Terminal Area Plan and ultimately ORD’s Capital Improvement
Program
• Manage multiple construction managers
• Design and engineering management
• Project control services
– Master Program Plan
– Schedule Development
• Anticipated term: 8 years
• Anticipated Advertisement Date: 4th Quarter 2016
CONFIDENTIAL – DRAFT – PREDECISIONAL 11
LEAD DESIGN SERVICES FOR TERMINAL DEVELOPMENT
• One lead A/E firm will be chosen for the design of new terminal development at O’Hare
• Primary focus will be on the anticipated O’Hare Central Facility
• The O’Hare Central Facility is the centerpiece of the terminal area plan for O’Hare 21 and the design
should reflect the significance of this component of the project
• Design team will be expected to include industry leading experts on security technology, as well as
new technology for passenger amenities
• Anticipated project delivery method is Construction Manager at Risk (CM@R). Accordingly, design
team will work closely with CM@R firm during preconstruction services and throughout the life of the
project
• Anticipated Advertisement Date: 1st Quarter 2017
CONFIDENTIAL – DRAFT – PREDECISIONAL 12
13
TARGET MARKET DESIGN CONTRACTS
• Non-federal engineering task order contracts will be bid target market
• Contracts designated for competition limited to MBEs or WBEs
• The Target Market Program reserves a percentage of the City’s non-
construction contracts and limits participation to M/WBEs
• Contracts are not eligible for the program unless there are at least three
qualified MBEs or WBEs interested in participating in that type of contract
• The prime contractor on a Target Market Contract must perform at least 50
percent of the dollar value
14
• Multiple target market Construction Manager contracts will be awarded to
oversee various segments of O’Hare 21 Terminal Area Plan and the upcoming
Capital Improvement program
• Projects will include airside work, landside projects, terminal projects, site
preparation and security packages
TARGET MARKET CONSTRUCTION MANAGEMENT SERVICES
Anticipated
Term:
5 Years
Anticipated Advertisement Date:
4th Quarter 2016
Anticipated Award Date:
3rd Quarter 2017
The procurement method has aspects of professional services procurement. For the construction planning
phase, the City can require the successful proposers to implement subcontractor mentoring, use of hiring and
training for citizens in socioeconomic disadvantaged neighborhoods, and targeted outreach.
15
CM@RISK HIGHLIGHTS
Contractor
DBE
Goal
DBE
Actual
DFW International Terminal “D” 26% 33%
Nashville Airport (CONRAC) 10% 22%
Atlanta Airport (CONRAC) 34% 36%
Phoenix Airport (CONRAC) 10% 24%
Miami Airport 20% 28%
Sacramento Airport Terminal B 0% 10%
LAX World Airport West Gates 14% 21%
LAX World Airport TBIT Core 14% 14%
DART Transit Expansion 42% 54%
Texas Instruments RFAB 35% 50%
Toyota World Headquarters 20% 30%
A project delivery method in which the Construction Manager
acts as a consultant to the Owner in the development and
design phases, but assumes the risk for construction
performance as the equivalent of a general contractor holding
all the trade subcontracts during the construction phase
• CMAR delivers the project within Guaranteed
Maximum Price (GMP)
• Used for projects where the Owner gains the benefit of
having the Contractors input during planning and
design
• Provides the ability to start construction on portions of
the work even if the overall design is not finalized
The procurement method has aspects of professional services procurement. For the construction planning
phase, the City can require the successful proposers to implement subcontractor mentoring, use of hiring and
training for citizens in socioeconomic disadvantaged neighborhoods, and targeted outreach.
16
• CM-at-Risk contracts to construct the Terminal 5 M Extension projects as well
as additional O’Hare 21 Projects
• Projects will include airside work, landside projects, terminal projects, site
preparation and security packages
CM@RISK FOR T5 EXTENSION AND ADDITIONAL O’HARE 21
PROJECTS (ANTICIPATED TO BE TWO CONTRACTS)
Anticipated
Term:
TBD
Anticipated Advertisement
Date:
4th Quarter 2016
Anticipated Award
Date:
2nd Quarter 2017
EXPANSION OF TERMINAL 5 SUPPORTING INCREASED DEMAND
17
 Terminal expansion includes 9 new wide-body gates
 Provides for a second A380 capable gate at O’Hare
 Addresses near-term demand and capacity of International Terminal gates and facilities
 Provides additional capacity for domestic flights
 Includes expanded security screening and Federal Inspection Services (FIS) facilities
STATUS – TERMINAL 5 EXTENSION
 Design NTP (Sitework) 4th Quarter 2016
 Design NTP (Facility) 4th Quarter 2016
 Advertise Sitework Construction 2nd Quarter 2017
 NTP Sitework Construction 3rd Quarter 2017
 Advertise Facility Construction 1st Quarter 2018
 NTP Facility Construction 1st Quarter 2018
 Operational Facility 4th Quarter 2019
18CONFIDENTIAL – DRAFT – PREDECISIONAL
CAPITAL IMPROVEMENT
PROGRAM (CIP)
PROJECTS
UPCOMING CONSTRUCTION – CIP UNDER $30M
Project Description Anticipated
Ad Date
Estimated
Contract Value
DBE/MBE/WBE/
SBE Goals:
United Airlines Employee Parking
Lot Reconstruction
Remove existing asphalt pavement and reconstruct the parking lot with
latex concrete.
Bids Due: 11/15/16 $1 – 1.5 Million SBE 51%
MDW Taxiway A Extension Construction of a new Taxiway A extension, including pavement,
associated drainage, and lighting installation.
1st Quarter 2017 $3 – 5 Million DBE 30%
Building 521 Renovation 16,500sf of conditioned space for police use and 2,770sf of garage
space.
1st Quarter 2017 $3 – 4 Million MBE 26% / WBE 6%
Trunk Radio System Replacement Replace trunking systems, backup systems, core controllers, repeaters,
dispatch consoles, recorders, and fiber infrastructure.
1st Quarter 2017 $5 – 7 Million MBE 26% / WBE 6%
Restroom Modernization – Phase 5 Renovation of nine restrooms throughout Terminals 1 & 3. 1st Quarter 2017 $10 – 15 Million MBE 26% / WBE 6%
Bessie Coleman Water Main Replace 5,000LF of water main along Bessie Coleman Drive. 1st Quarter 2017 $2 – 3 Million MBE 26% / WBE 6%
MDW Airfield Lighting Infrastructure
Improvements
Installation of a new duct bank system for Airfield lighting. 1st Quarter 2017 $10 – 15 Million DBE 30%
MDW Airport Maintenance Complex
Improvements
Replacement of HVAC, roof, overhead doors, and emergency egress
doors for the MDW AMC facility.
1st Quarter 2017 $10 – 15 Million MBE 26% / WBE 6%
UPCOMING CONSTRUCTION – CIP PROJECTS OVER $30M
Project Description Anticipated
Ad Date
Estimated
Contract Value
DBE/MBE/WBE/
SBE Goals:
Replace High Temperature
Water Generators
Replace all eight (8) 75,000 MBH High Temperature Water
(HTW) Generators along with their associated equipment.
4th Quarter 2016 $55 – 60 Million MBE 26% / WBE 6%
MDW Security Checkpoint
Expansion
Widening of the existing passenger bridge as a means to
accommodate current and future pedestrian traffic flow.
4th Quarter 2016 $80 – 85 Million DBE 30%
MDW Terminal Parking Garage
Extension
Expansion of existing Terminal Parking Garage, adding
approximately 1,500 parking spaces.
1st Quarter 2017 $115 – 125 Million MBE 26% / WBE 6%
RUNWAY 9C/27C AND
ADDITIONAL AIRFIELD
IMPROVEMENT PROJECTS
RUNWAY 9C/27C AND OTHER AIRFIELD PROJECTS
• Overall Program is
estimated at roughly
$1.3B
• Graphic depicts the
projects CDA is
leading
• Other associated
projects, such as
relocation of Airline
Support Facilities
relocation and fuel
line relocations are
not reflected herein
CONFIDENTIAL – DRAFT – PREDECISIONAL 23
RWY 9C PROJECTS AND TIMELINES
Project Description Anticipated
Ad Date
Estimated
Contract Value
DBE/MBE/WBE/
SBE Goals:
Centralized Deicing Facility – Mass
Grading Project
Mass grading (earthwork) including sorting, transport, cut and
embankment, and other incidental work to prepare the site for the
paving of these improvements. Project extends and prepared a portion
of the Elgin-O’Hare Bypass. Project site is located in the Aircraft
Operations Area (AOA)
4th Quarter 2016 $55-75 Million MBE 26% / WBE 6%
Rwy 9C/27C Package 1 Construction of temporary and permanent airfield pavements (PCC &
AC Shoulders), airfield lighting, signage, grading drainage, site
restoration, utility infrastructure (power & communications) and other
incidental work. Project site is located in the Aircraft Operations Area
(AOA). Work will be phased to accommodate aircraft operations and
may require off peak construction. Key work items include approximately
201,000 SY of PCC pavement and 85,000 SY of AC pavement.
4th Quarter 2016 $80 – 120 Million DBE 30%
Twy ZJ and TFR – Package A Construction of an on-airport two lane road and two taxiways. The
project includes earthwork, utility construction, lighting, signage, PCC
and AC pavements, site restoration, drainage and other incidental work.
Project site is located in the Aircraft Operations Area (AOA).
4th Quarter 2016 $48 – 57 Million DBE 30%
10R Safety and Security Package 2 Miscellaneous improvements including grading, roadway signage,
fencing and utility work.
1st Quarter 2017 $5 – 7 Million DBE 30%
Centralized Deicing Facility –
Paving/Electrical Project
Construction of a new pavement area dedicated to deice aircraft during
winter operations and to stage aircraft during the balance of the year.
This project also includes the construction of two parallel taxiways.
Scope includes PCC Pavement, airfield lighting and signage, flood
lighting, deicing fluid collection systems, drainage, and other incidental
work. Project site is located in the Aircraft Operations Area (AOA).
2nd Quarter 2017 $75 – 85 Million MBE 26% / WBE 6%
RWY 9C PROJECTS AND TIMELINES (CONTINUED)
Project Description Anticipated
Ad Date
Estimated
Contract Value
DBE/MBE/WBE/
SBE Goals:
Relocation of ARFF#2 Construction of a replacement on-airport aircraft rescue and fire fighting
station (ARFF) on the north east side of the airfield. Construction will be
located airside. Structure will be single story with a mechanical
mezzanine, with 6-high bay apparatus bays. Project site is located in the
Aircraft Operations Area (AOA).
2nd Quarter 2017 $15 – 25 Million DBE 30%
East Lighting Control Vault Construction of a new airfield lighting vault (similar to the south vault)
housing the switchgear, ALSC and regulators needed to power the
airfield lighting and signage for Runway 9C/27C, Runway 9R/27L and
associated taxiways. Site for this facility will be adjacent to the ARFF #2
on the north east of the airfield. Project site is located in the Aircraft
Operations Area (AOA).
2nd Quarter 2017 $15 – 25 Million DBE 30%
Rwy 9C/27C Package 2 Construction of airfield pavements, PCC and AC, airfield lighting and
signage, demolitions of existing structures and underground utilities and
other improvements, site preparation, grading and drainage, site
restoration, utilities and other appurtenances and incidental work.
Project site is located in the Aircraft Operations Area (AOA). Key work
items include approximately 510,000 SY of PCC pavement and 270,000
SY of asphalt pavement.
1st Quarter 2018 $120 – 160 Million DBE 30%
Rwy 9C/27C Package 3 Phased construction of airfield pavements, PCC and AC, airfield lighting
and signage, site preparation, grading and drainage, site restoration,
utilities and other appurtenances and incidental work. Project site is
located in the Aircraft Operations Area (AOA). Key work items include
approximately 150,000 SY of PCC pavement and 82,000 SY of asphalt
pavement.
3rd Quarter 2018 $40 – 60 Million DBE 30%
RWY 9C PROJECTS AND TIMELINES (CONTINUED)
Project Description Anticipated
Ad Date
Estimated
Contract Value
DBE/MBE/WBE/
SBE Goals:
Relocation of Taxiways A and B Phased construction of airfield pavements, PCC and AC, airfield lighting
and signage, pavement removal, PCCP crushing, and underground
utilities and other improvements, site preparation, grading and drainage,
site restoration, utilities and other appurtenances and incidental work.
Project site is located in the Aircraft Operations Area (AOA).
2nd Quarter 2018 $100 – 140 Million MBE 26% / WBE 6%
ATS Lot E Station Demolition Demolition of the structure and platform of this station, modification of
wayside systems, power systems and track work as required and site
restoration. Construction will require coordination with and limited
interruption of services of the Airport’s Transit System Project site is in
the current Public Parking Lot E.
4th Quarter 2019 $10 – 20 Million DBE 30%

More Related Content

What's hot

Warren Tann Resume 2016
Warren Tann Resume 2016Warren Tann Resume 2016
Warren Tann Resume 2016
Warren Tann
 
Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.
Joseph Raftery
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
jamsheer p
 
Troy Weiss Resume
Troy Weiss ResumeTroy Weiss Resume
Troy Weiss Resume
Troy Weiss
 
NIZAM ENTERPRISE profile (1)
NIZAM ENTERPRISE profile (1)NIZAM ENTERPRISE profile (1)
NIZAM ENTERPRISE profile (1)
hassand bindin
 
150804-DTAE-Brochure-Master Plan-Cargo
150804-DTAE-Brochure-Master Plan-Cargo150804-DTAE-Brochure-Master Plan-Cargo
150804-DTAE-Brochure-Master Plan-Cargo
Douglas Tobin
 

What's hot (19)

David's CV, 2017
David's CV, 2017David's CV, 2017
David's CV, 2017
 
CV Bernard Graves
CV Bernard GravesCV Bernard Graves
CV Bernard Graves
 
Warren Tann Resume 2016
Warren Tann Resume 2016Warren Tann Resume 2016
Warren Tann Resume 2016
 
Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.
 
control tower
control towercontrol tower
control tower
 
ASHRAFUL AZIZ Resume
ASHRAFUL AZIZ ResumeASHRAFUL AZIZ Resume
ASHRAFUL AZIZ Resume
 
SIEMENS HQ
SIEMENS HQSIEMENS HQ
SIEMENS HQ
 
CV-Padmanabh
CV-PadmanabhCV-Padmanabh
CV-Padmanabh
 
Kcn 2016 March Resume
Kcn 2016 March ResumeKcn 2016 March Resume
Kcn 2016 March Resume
 
Krishna kumar cv
Krishna kumar cvKrishna kumar cv
Krishna kumar cv
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
 
Troy Weiss Resume
Troy Weiss ResumeTroy Weiss Resume
Troy Weiss Resume
 
CV Amr Zaki - PMP®
CV Amr Zaki - PMP®CV Amr Zaki - PMP®
CV Amr Zaki - PMP®
 
Dhanasekaran_Resume
Dhanasekaran_ResumeDhanasekaran_Resume
Dhanasekaran_Resume
 
NIZAM ENTERPRISE profile (1)
NIZAM ENTERPRISE profile (1)NIZAM ENTERPRISE profile (1)
NIZAM ENTERPRISE profile (1)
 
150804-DTAE-Brochure-Master Plan-Cargo
150804-DTAE-Brochure-Master Plan-Cargo150804-DTAE-Brochure-Master Plan-Cargo
150804-DTAE-Brochure-Master Plan-Cargo
 
CV - Fakruddin R01
CV - Fakruddin  R01CV - Fakruddin  R01
CV - Fakruddin R01
 
walid abou lhaf CV
walid abou lhaf  CVwalid abou lhaf  CV
walid abou lhaf CV
 
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014
 

Viewers also liked

Clean Rivers, Clean Lake 8 -- River Walk Investment -- Alyssa Remington
Clean Rivers, Clean Lake 8 -- River Walk Investment -- Alyssa RemingtonClean Rivers, Clean Lake 8 -- River Walk Investment -- Alyssa Remington
Clean Rivers, Clean Lake 8 -- River Walk Investment -- Alyssa Remington
Sweet Water
 
Catalogo Lechuza Premium Collection 2011
Catalogo Lechuza Premium Collection 2011Catalogo Lechuza Premium Collection 2011
Catalogo Lechuza Premium Collection 2011
DeDi
 

Viewers also liked (20)

Clark Construction/PD3 Presentation - McCormick HQ
Clark Construction/PD3 Presentation - McCormick HQClark Construction/PD3 Presentation - McCormick HQ
Clark Construction/PD3 Presentation - McCormick HQ
 
UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...
 
CMAA January Luncheon - Illinois Tollway
CMAA January Luncheon - Illinois TollwayCMAA January Luncheon - Illinois Tollway
CMAA January Luncheon - Illinois Tollway
 
CMAA Riverwalk Presentation
CMAA Riverwalk PresentationCMAA Riverwalk Presentation
CMAA Riverwalk Presentation
 
Ppt
PptPpt
Ppt
 
Clean Rivers, Clean Lake 8 -- River Walk Investment -- Alyssa Remington
Clean Rivers, Clean Lake 8 -- River Walk Investment -- Alyssa RemingtonClean Rivers, Clean Lake 8 -- River Walk Investment -- Alyssa Remington
Clean Rivers, Clean Lake 8 -- River Walk Investment -- Alyssa Remington
 
Summertime nutrition hydration and d
Summertime nutrition hydration and dSummertime nutrition hydration and d
Summertime nutrition hydration and d
 
Butch O'Hare: The Rest of the Story.
Butch O'Hare: The Rest of the Story.Butch O'Hare: The Rest of the Story.
Butch O'Hare: The Rest of the Story.
 
Fita de Led - Starlux
 Fita de Led - Starlux Fita de Led - Starlux
Fita de Led - Starlux
 
EasyBib Presentation with Objectives
EasyBib Presentation with ObjectivesEasyBib Presentation with Objectives
EasyBib Presentation with Objectives
 
Билатеральная последовательная ретроперитонеоскопическая уретеролитотомиябила...
Билатеральная последовательная ретроперитонеоскопическая уретеролитотомиябила...Билатеральная последовательная ретроперитонеоскопическая уретеролитотомиябила...
Билатеральная последовательная ретроперитонеоскопическая уретеролитотомиябила...
 
лапароскопическая урология на региональном уровне. доклад.
лапароскопическая урология на региональном уровне. доклад.лапароскопическая урология на региональном уровне. доклад.
лапароскопическая урология на региональном уровне. доклад.
 
опыт применения ультразвуковой энергии в лапароскопии
опыт применения ультразвуковой энергии в лапароскопииопыт применения ультразвуковой энергии в лапароскопии
опыт применения ультразвуковой энергии в лапароскопии
 
Торакоскопический доступ к дистопированной кисте правой почки
Торакоскопический доступ к дистопированной кисте правой почкиТоракоскопический доступ к дистопированной кисте правой почки
Торакоскопический доступ к дистопированной кисте правой почки
 
Séminaire BASTIA 2017
Séminaire BASTIA 2017Séminaire BASTIA 2017
Séminaire BASTIA 2017
 
Catalogo Lechuza Premium Collection 2011
Catalogo Lechuza Premium Collection 2011Catalogo Lechuza Premium Collection 2011
Catalogo Lechuza Premium Collection 2011
 
Two true stories!!
Two true  stories!!Two true  stories!!
Two true stories!!
 
Rolt group 2015 pro
Rolt group 2015 proRolt group 2015 pro
Rolt group 2015 pro
 
Marca como Compromiso _ Pacto Verde Vitoria-Gasteiz (Noviembre 2016)
Marca como Compromiso _ Pacto Verde Vitoria-Gasteiz (Noviembre 2016)Marca como Compromiso _ Pacto Verde Vitoria-Gasteiz (Noviembre 2016)
Marca como Compromiso _ Pacto Verde Vitoria-Gasteiz (Noviembre 2016)
 
Riverfront development
Riverfront developmentRiverfront development
Riverfront development
 

Similar to Capital Programs - O'Hare 21

MODE_Sector-Brochure-Transport&Infrastructure_V1_LQ
MODE_Sector-Brochure-Transport&Infrastructure_V1_LQMODE_Sector-Brochure-Transport&Infrastructure_V1_LQ
MODE_Sector-Brochure-Transport&Infrastructure_V1_LQ
Rhonan OBrien
 
Update-May2007-e
Update-May2007-eUpdate-May2007-e
Update-May2007-e
WJ
 
Tawfig Khidir - CV
Tawfig Khidir - CVTawfig Khidir - CV
Tawfig Khidir - CV
Tawfig Adham
 
The Construction Manager-General Contractor method for consctruction of trans...
The Construction Manager-General Contractor method for consctruction of trans...The Construction Manager-General Contractor method for consctruction of trans...
The Construction Manager-General Contractor method for consctruction of trans...
Angel Damian Rivera-Saez
 
Capita Symonds Aviation capability
Capita Symonds Aviation capability Capita Symonds Aviation capability
Capita Symonds Aviation capability
Capita Symonds
 
Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docx
cravennichole326
 

Similar to Capital Programs - O'Hare 21 (20)

Toronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project PresentationToronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project Presentation
 
ASCE T&DI Abstract 40 - Final Paper
ASCE T&DI Abstract 40 - Final PaperASCE T&DI Abstract 40 - Final Paper
ASCE T&DI Abstract 40 - Final Paper
 
Toronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyToronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy Study
 
Philippine real estate investment project terms for ADMC
Philippine real estate investment project terms for ADMCPhilippine real estate investment project terms for ADMC
Philippine real estate investment project terms for ADMC
 
923 2 wheeler_public privat partnerships
923 2 wheeler_public privat partnerships923 2 wheeler_public privat partnerships
923 2 wheeler_public privat partnerships
 
CV- Project Control Manager PMP
CV- Project Control Manager PMPCV- Project Control Manager PMP
CV- Project Control Manager PMP
 
AirportCreators PTE Amsterdam 2017 - introduction
AirportCreators PTE Amsterdam 2017 - introductionAirportCreators PTE Amsterdam 2017 - introduction
AirportCreators PTE Amsterdam 2017 - introduction
 
MODE_Sector-Brochure-Transport&Infrastructure_V1_LQ
MODE_Sector-Brochure-Transport&Infrastructure_V1_LQMODE_Sector-Brochure-Transport&Infrastructure_V1_LQ
MODE_Sector-Brochure-Transport&Infrastructure_V1_LQ
 
Update-May2007-e
Update-May2007-eUpdate-May2007-e
Update-May2007-e
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
4
44
4
 
Tawfig Khidir - CV
Tawfig Khidir - CVTawfig Khidir - CV
Tawfig Khidir - CV
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
Corgan
CorganCorgan
Corgan
 
The Construction Manager-General Contractor method for consctruction of trans...
The Construction Manager-General Contractor method for consctruction of trans...The Construction Manager-General Contractor method for consctruction of trans...
The Construction Manager-General Contractor method for consctruction of trans...
 
JohnsonBruce 2015
JohnsonBruce 2015JohnsonBruce 2015
JohnsonBruce 2015
 
Capita Symonds Aviation capability
Capita Symonds Aviation capability Capita Symonds Aviation capability
Capita Symonds Aviation capability
 
KHURRAM ASHFAQ KHAN CV updated
KHURRAM ASHFAQ KHAN  CV updatedKHURRAM ASHFAQ KHAN  CV updated
KHURRAM ASHFAQ KHAN CV updated
 
Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docx
 

More from Ausrine Rakauskaite

State Farm Center: Renovation and Addition Project
State Farm Center: Renovation and Addition ProjectState Farm Center: Renovation and Addition Project
State Farm Center: Renovation and Addition Project
Ausrine Rakauskaite
 

More from Ausrine Rakauskaite (8)

Kaplan Institute Constuction - Illinois Tech
Kaplan Institute Constuction - Illinois TechKaplan Institute Constuction - Illinois Tech
Kaplan Institute Constuction - Illinois Tech
 
Project Delivery and Best Practices
Project Delivery and Best PracticesProject Delivery and Best Practices
Project Delivery and Best Practices
 
ACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD PresentationACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD Presentation
 
State Farm Center: Renovation and Addition Project
State Farm Center: Renovation and Addition ProjectState Farm Center: Renovation and Addition Project
State Farm Center: Renovation and Addition Project
 
CMAA April Luncheon - Focal Point
CMAA April Luncheon - Focal PointCMAA April Luncheon - Focal Point
CMAA April Luncheon - Focal Point
 
CMAA Presentation Final Cook County
CMAA Presentation Final Cook CountyCMAA Presentation Final Cook County
CMAA Presentation Final Cook County
 
November 2014 CCM Newsletter
November 2014 CCM NewsletterNovember 2014 CCM Newsletter
November 2014 CCM Newsletter
 
The State of Rail in Illinois
The State of Rail in IllinoisThe State of Rail in Illinois
The State of Rail in Illinois
 

Recently uploaded

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 

Recently uploaded (20)

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 

Capital Programs - O'Hare 21

  • 1. CAPITAL PROGRAMS – O’HARE 21 PRESENTATION TO CMAA CHICAGO CHAPTER NOVEMBER 17, 2016
  • 2. OVERALL PLAN & STATUS ORD PROJECTS MDW MODERNIZATION
  • 3. Mayor’s Goals Customer Service Facilities, Technology, Preclearance, Amenities and Service Culture Connectivity Air Service, Express Rail, Western access Benefit to Chicago Direct development on airport; Indirect, business & job growth CDA Programs to Achieve O’Hare 21 1. Airfield package 2. New lease negotiations & capital plan Domestic Terminals Gates, technology, concessions – ability to expand for future needs OHare Express Rail (OER) Optimize customer access / cost to maximize private viability Latin America/ International Air service development, increase international gates, increase proximity to domestic gates Hotels 2 new hotels; refurbish and expand existing Hilton 2015-2019 Plan 3 CONNECTING THE WORLD TO CHICAGO
  • 4. STATUS – O’HARE KEY PROJECTS 4CONFIDENTIAL – DRAFT – PREDECISIONAL Approved/ Underway Under Negotiation/Review Airfield u Domestic Gates L “Stinger” 5-RJ Gate Expansion u New Concourses u International Gates T5 M-Concourse 9 WB gate expansion u New T2 International/domestic terminal u RFP for Hotel Operator u O’Hare Express Rail Conceptual Engineering u RFP for Hotel Developer u
  • 5. STATUS – O’HARE PROJECTS • Innovation Lanes, T1 and T3 November 2016 • Northeast Cargo Phase II December 2016 • L Stinger completion February 2018 • Multi Modal Facility December 2018 • Concessions – Goose Island B concourse – food service in hold rooms started last week – Food cart delivers food to hold room area – ARN Award • New Flights in November – EVA to Taipei and on to Bangkok – ANA to Tokyo Haneda and on to Asia – Interjet to Mexico City – Frontier to Cancun, Cabo and PV 5CONFIDENTIAL – DRAFT – PREDECISIONAL
  • 6. STATUS – MIDWAY MODERNIZATION • Concessions Proposal Completed – City Council December • Ground breaking dates for Midway Modernization – Security Checkpoint (new bridge) March 2017 – Parking Expansion/ CTA connection upgrade June 2017 • Completion dates for Midway Modernization – Security Bridges & Parking Structure June 2019 6CONFIDENTIAL – DRAFT – PREDECISIONAL
  • 7. OVERVIEW – O’HARE TERMINAL AREA PROGRAM (TAP)
  • 9. O’HARE 21 – TERMINAL AREA PROGRAM • The Modernization of O’Hare has completed approximately $5.8B of improvements, including: – Two New Airport Traffic Control Towers – Extension of Runway 10L/28R – New Runway 9L/27R – New Runway 10C/28C – New Runway 10R/28L – Multiple Taxiway Improvements (K&L, LL, others) – On-going Runway 9C/27C – On-going Centralized Deicing Facility and Cross Field Taxiway – On-going Consolidated Rental Car/Parking Multimodal Facility – On-going ATS Modernization and Extension • Next goal – Terminal Expansion and remaining airfield improvements CONFIDENTIAL – DRAFT – PREDECISIONAL 9
  • 10. O’HARE 21 – TERMINAL AREA PROGRAM (CONTINUED) • Consistent with the approved Airport Layout Plan, the next step in the process is to build terminals and concourses to increase gate capacity – Additional domestic and international gates – Increased concession space – Enhanced Passenger Experience – Increase efficiency – Reduce Operating Costs – State-of-the-art building systems – Enhanced transit connections (intra-terminal/downtown) – Replacement of aged facilities CONFIDENTIAL – DRAFT – PREDECISIONAL 10
  • 11. PROGRAM MANAGER FOR O’HARE 21 • Owner’s Representative Services for Terminal Area Plan and ultimately ORD’s Capital Improvement Program • Manage multiple construction managers • Design and engineering management • Project control services – Master Program Plan – Schedule Development • Anticipated term: 8 years • Anticipated Advertisement Date: 4th Quarter 2016 CONFIDENTIAL – DRAFT – PREDECISIONAL 11
  • 12. LEAD DESIGN SERVICES FOR TERMINAL DEVELOPMENT • One lead A/E firm will be chosen for the design of new terminal development at O’Hare • Primary focus will be on the anticipated O’Hare Central Facility • The O’Hare Central Facility is the centerpiece of the terminal area plan for O’Hare 21 and the design should reflect the significance of this component of the project • Design team will be expected to include industry leading experts on security technology, as well as new technology for passenger amenities • Anticipated project delivery method is Construction Manager at Risk (CM@R). Accordingly, design team will work closely with CM@R firm during preconstruction services and throughout the life of the project • Anticipated Advertisement Date: 1st Quarter 2017 CONFIDENTIAL – DRAFT – PREDECISIONAL 12
  • 13. 13 TARGET MARKET DESIGN CONTRACTS • Non-federal engineering task order contracts will be bid target market • Contracts designated for competition limited to MBEs or WBEs • The Target Market Program reserves a percentage of the City’s non- construction contracts and limits participation to M/WBEs • Contracts are not eligible for the program unless there are at least three qualified MBEs or WBEs interested in participating in that type of contract • The prime contractor on a Target Market Contract must perform at least 50 percent of the dollar value
  • 14. 14 • Multiple target market Construction Manager contracts will be awarded to oversee various segments of O’Hare 21 Terminal Area Plan and the upcoming Capital Improvement program • Projects will include airside work, landside projects, terminal projects, site preparation and security packages TARGET MARKET CONSTRUCTION MANAGEMENT SERVICES Anticipated Term: 5 Years Anticipated Advertisement Date: 4th Quarter 2016 Anticipated Award Date: 3rd Quarter 2017 The procurement method has aspects of professional services procurement. For the construction planning phase, the City can require the successful proposers to implement subcontractor mentoring, use of hiring and training for citizens in socioeconomic disadvantaged neighborhoods, and targeted outreach.
  • 15. 15 CM@RISK HIGHLIGHTS Contractor DBE Goal DBE Actual DFW International Terminal “D” 26% 33% Nashville Airport (CONRAC) 10% 22% Atlanta Airport (CONRAC) 34% 36% Phoenix Airport (CONRAC) 10% 24% Miami Airport 20% 28% Sacramento Airport Terminal B 0% 10% LAX World Airport West Gates 14% 21% LAX World Airport TBIT Core 14% 14% DART Transit Expansion 42% 54% Texas Instruments RFAB 35% 50% Toyota World Headquarters 20% 30% A project delivery method in which the Construction Manager acts as a consultant to the Owner in the development and design phases, but assumes the risk for construction performance as the equivalent of a general contractor holding all the trade subcontracts during the construction phase • CMAR delivers the project within Guaranteed Maximum Price (GMP) • Used for projects where the Owner gains the benefit of having the Contractors input during planning and design • Provides the ability to start construction on portions of the work even if the overall design is not finalized The procurement method has aspects of professional services procurement. For the construction planning phase, the City can require the successful proposers to implement subcontractor mentoring, use of hiring and training for citizens in socioeconomic disadvantaged neighborhoods, and targeted outreach.
  • 16. 16 • CM-at-Risk contracts to construct the Terminal 5 M Extension projects as well as additional O’Hare 21 Projects • Projects will include airside work, landside projects, terminal projects, site preparation and security packages CM@RISK FOR T5 EXTENSION AND ADDITIONAL O’HARE 21 PROJECTS (ANTICIPATED TO BE TWO CONTRACTS) Anticipated Term: TBD Anticipated Advertisement Date: 4th Quarter 2016 Anticipated Award Date: 2nd Quarter 2017
  • 17. EXPANSION OF TERMINAL 5 SUPPORTING INCREASED DEMAND 17  Terminal expansion includes 9 new wide-body gates  Provides for a second A380 capable gate at O’Hare  Addresses near-term demand and capacity of International Terminal gates and facilities  Provides additional capacity for domestic flights  Includes expanded security screening and Federal Inspection Services (FIS) facilities
  • 18. STATUS – TERMINAL 5 EXTENSION  Design NTP (Sitework) 4th Quarter 2016  Design NTP (Facility) 4th Quarter 2016  Advertise Sitework Construction 2nd Quarter 2017  NTP Sitework Construction 3rd Quarter 2017  Advertise Facility Construction 1st Quarter 2018  NTP Facility Construction 1st Quarter 2018  Operational Facility 4th Quarter 2019 18CONFIDENTIAL – DRAFT – PREDECISIONAL
  • 20. UPCOMING CONSTRUCTION – CIP UNDER $30M Project Description Anticipated Ad Date Estimated Contract Value DBE/MBE/WBE/ SBE Goals: United Airlines Employee Parking Lot Reconstruction Remove existing asphalt pavement and reconstruct the parking lot with latex concrete. Bids Due: 11/15/16 $1 – 1.5 Million SBE 51% MDW Taxiway A Extension Construction of a new Taxiway A extension, including pavement, associated drainage, and lighting installation. 1st Quarter 2017 $3 – 5 Million DBE 30% Building 521 Renovation 16,500sf of conditioned space for police use and 2,770sf of garage space. 1st Quarter 2017 $3 – 4 Million MBE 26% / WBE 6% Trunk Radio System Replacement Replace trunking systems, backup systems, core controllers, repeaters, dispatch consoles, recorders, and fiber infrastructure. 1st Quarter 2017 $5 – 7 Million MBE 26% / WBE 6% Restroom Modernization – Phase 5 Renovation of nine restrooms throughout Terminals 1 & 3. 1st Quarter 2017 $10 – 15 Million MBE 26% / WBE 6% Bessie Coleman Water Main Replace 5,000LF of water main along Bessie Coleman Drive. 1st Quarter 2017 $2 – 3 Million MBE 26% / WBE 6% MDW Airfield Lighting Infrastructure Improvements Installation of a new duct bank system for Airfield lighting. 1st Quarter 2017 $10 – 15 Million DBE 30% MDW Airport Maintenance Complex Improvements Replacement of HVAC, roof, overhead doors, and emergency egress doors for the MDW AMC facility. 1st Quarter 2017 $10 – 15 Million MBE 26% / WBE 6%
  • 21. UPCOMING CONSTRUCTION – CIP PROJECTS OVER $30M Project Description Anticipated Ad Date Estimated Contract Value DBE/MBE/WBE/ SBE Goals: Replace High Temperature Water Generators Replace all eight (8) 75,000 MBH High Temperature Water (HTW) Generators along with their associated equipment. 4th Quarter 2016 $55 – 60 Million MBE 26% / WBE 6% MDW Security Checkpoint Expansion Widening of the existing passenger bridge as a means to accommodate current and future pedestrian traffic flow. 4th Quarter 2016 $80 – 85 Million DBE 30% MDW Terminal Parking Garage Extension Expansion of existing Terminal Parking Garage, adding approximately 1,500 parking spaces. 1st Quarter 2017 $115 – 125 Million MBE 26% / WBE 6%
  • 22. RUNWAY 9C/27C AND ADDITIONAL AIRFIELD IMPROVEMENT PROJECTS
  • 23. RUNWAY 9C/27C AND OTHER AIRFIELD PROJECTS • Overall Program is estimated at roughly $1.3B • Graphic depicts the projects CDA is leading • Other associated projects, such as relocation of Airline Support Facilities relocation and fuel line relocations are not reflected herein CONFIDENTIAL – DRAFT – PREDECISIONAL 23
  • 24. RWY 9C PROJECTS AND TIMELINES Project Description Anticipated Ad Date Estimated Contract Value DBE/MBE/WBE/ SBE Goals: Centralized Deicing Facility – Mass Grading Project Mass grading (earthwork) including sorting, transport, cut and embankment, and other incidental work to prepare the site for the paving of these improvements. Project extends and prepared a portion of the Elgin-O’Hare Bypass. Project site is located in the Aircraft Operations Area (AOA) 4th Quarter 2016 $55-75 Million MBE 26% / WBE 6% Rwy 9C/27C Package 1 Construction of temporary and permanent airfield pavements (PCC & AC Shoulders), airfield lighting, signage, grading drainage, site restoration, utility infrastructure (power & communications) and other incidental work. Project site is located in the Aircraft Operations Area (AOA). Work will be phased to accommodate aircraft operations and may require off peak construction. Key work items include approximately 201,000 SY of PCC pavement and 85,000 SY of AC pavement. 4th Quarter 2016 $80 – 120 Million DBE 30% Twy ZJ and TFR – Package A Construction of an on-airport two lane road and two taxiways. The project includes earthwork, utility construction, lighting, signage, PCC and AC pavements, site restoration, drainage and other incidental work. Project site is located in the Aircraft Operations Area (AOA). 4th Quarter 2016 $48 – 57 Million DBE 30% 10R Safety and Security Package 2 Miscellaneous improvements including grading, roadway signage, fencing and utility work. 1st Quarter 2017 $5 – 7 Million DBE 30% Centralized Deicing Facility – Paving/Electrical Project Construction of a new pavement area dedicated to deice aircraft during winter operations and to stage aircraft during the balance of the year. This project also includes the construction of two parallel taxiways. Scope includes PCC Pavement, airfield lighting and signage, flood lighting, deicing fluid collection systems, drainage, and other incidental work. Project site is located in the Aircraft Operations Area (AOA). 2nd Quarter 2017 $75 – 85 Million MBE 26% / WBE 6%
  • 25. RWY 9C PROJECTS AND TIMELINES (CONTINUED) Project Description Anticipated Ad Date Estimated Contract Value DBE/MBE/WBE/ SBE Goals: Relocation of ARFF#2 Construction of a replacement on-airport aircraft rescue and fire fighting station (ARFF) on the north east side of the airfield. Construction will be located airside. Structure will be single story with a mechanical mezzanine, with 6-high bay apparatus bays. Project site is located in the Aircraft Operations Area (AOA). 2nd Quarter 2017 $15 – 25 Million DBE 30% East Lighting Control Vault Construction of a new airfield lighting vault (similar to the south vault) housing the switchgear, ALSC and regulators needed to power the airfield lighting and signage for Runway 9C/27C, Runway 9R/27L and associated taxiways. Site for this facility will be adjacent to the ARFF #2 on the north east of the airfield. Project site is located in the Aircraft Operations Area (AOA). 2nd Quarter 2017 $15 – 25 Million DBE 30% Rwy 9C/27C Package 2 Construction of airfield pavements, PCC and AC, airfield lighting and signage, demolitions of existing structures and underground utilities and other improvements, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Aircraft Operations Area (AOA). Key work items include approximately 510,000 SY of PCC pavement and 270,000 SY of asphalt pavement. 1st Quarter 2018 $120 – 160 Million DBE 30% Rwy 9C/27C Package 3 Phased construction of airfield pavements, PCC and AC, airfield lighting and signage, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Aircraft Operations Area (AOA). Key work items include approximately 150,000 SY of PCC pavement and 82,000 SY of asphalt pavement. 3rd Quarter 2018 $40 – 60 Million DBE 30%
  • 26. RWY 9C PROJECTS AND TIMELINES (CONTINUED) Project Description Anticipated Ad Date Estimated Contract Value DBE/MBE/WBE/ SBE Goals: Relocation of Taxiways A and B Phased construction of airfield pavements, PCC and AC, airfield lighting and signage, pavement removal, PCCP crushing, and underground utilities and other improvements, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Aircraft Operations Area (AOA). 2nd Quarter 2018 $100 – 140 Million MBE 26% / WBE 6% ATS Lot E Station Demolition Demolition of the structure and platform of this station, modification of wayside systems, power systems and track work as required and site restoration. Construction will require coordination with and limited interruption of services of the Airport’s Transit System Project site is in the current Public Parking Lot E. 4th Quarter 2019 $10 – 20 Million DBE 30%

Editor's Notes

  1. ANTICIPATED BID DATE - January 2017
  2. ANTICIPATED BID DATE - January 2017
  3. ANTICIPATED BID DATE - January 2017
  4. ANTICIPATED BID DATE - January 2017
  5. ANTICIPATED BID DATE - January 2017