SlideShare a Scribd company logo
1 of 46
State Farm Center
Renovation and Addition Project
Project Leadership
 Owner
 University of Illinois F&S
 DIA
 Construction Manager
 Design Team
 AECOM – Architectural
 Thorton Tomasetti – Structural
 Henderson Engineers – Mechanical, Electrical
 ESD – Plumbing
Project Specifics
 160 Million Renovations and Addition
 New Mechanical Spaces and Systems
 Reconfiguration of the arena
 New Luxury Seating
 New Ramps and Walks
 6 phases
 1,3,5 – Basketball Phases
 2,4,6 – “Construction” Phases
 Peak manpower for Phase 2 – 160
 Peak manpower for Phase 4 – 250
Google Earth
State Farm Center12/02/2013 – 02/28/2014
Phase 1 –
Site Work
Key
Construction
No Service
Ongoing
In Use
Other
State Farm Center12/02/2013 – 02/28/2014
PRV Room
Demo HV-10
T/C Offices
Phase 1 –
Mechanical Level
Key
Construction
No Service
Ongoing
In Use
Other
State Farm CenterState Farm Center
Phase 1 Construction Logistics
December 2013 To February 2014
St. Mary’s Road
FourthStreetFourthStreet
St. Mary’s Road
Kirby Avenue Kirby Avenue
Orange Lot
No Construction
Parking
Brown Lot
No Construction
Parking
Blue Lot
No Construction
Parking
N
Relocate
Fence As
Work
Progresses
Relocate
Fence As
Work
Progresses
B
C
C
C
C
C
C
C
C
C
C
B
B
B
B
B B
P
P
-6’ High chain link fence (with posts in
ground)
-6’ High chain link fence, moveable fence
supported by bases and sandbags and/or
pins
-Primary construction truck ingress and
egress
-”B” level entrance into building via stairs
(must be maintained for ingress and egress)
-”C” level entrance into building via existing
ramps
-Maintain pedestrian access/egress into SFC
at “B” level
-Maintain pedestrian access/egress via
ramps to “C” level entrance
-Public drop off
-30’ Wide Sliding Gate
-25’ Wide Swing Gate
-25’ Wide Sliding Gate
-Masonry Silo
-800 AMP 120/208V Service for Trailers
G1
G7
G5
G4
G2
G6
G3
C
B
B
C
P
Relocate
Fence As
Work
Progresses
Relocate
Fence As
Work
Progresses
G5
G5
G5
M
TE
Dumpster
Dumpster
Dumpster
Dumpster
Dumpster
Tool Trailers – 34 Spaces
340’ x 60’
Storage/Staging
Area
Notes: Typical Work of Phase 1
1) U.G. Utility Contractor shall provide, install,
maintain, and reposition moveable chain link fence
around all excavations, equipment, and disturbed
areas during installations.
2) Any existing roads, sidewalks or pavements shall
be restored via 3000 PSI concrete, 4 inches thick
after underground installation to allow pedestrian
or vehicle traffic.
3) U.G. Utility Contractor to provide and maintain
steel road plates over areas where pavement can
not be replaced to allow access to SFC.
4) U.G. Utility Contractor to schedule and
coordinate work to always provide ingress and
egress to the SFC “B” Level entrances and ramps to
the “C” Level entrances.
B
West Construction Staging Area Construction Road
G8
G9 Plywood
Canopy
Protection
*Trades Men
Parking For Phase 1
Only
G1
1
G1
1
Service Level
Dock Below
Construction Field
Office and Staging
RED PARKING LOT
Temporary
Fence Panels
Site Utilities Conflicts
Site Utilities Conflicts
Equipment Selection
Equipment Selection
State Farm CenterState Farm Center
St. Mary’s Road
FourthStreet
Kirby Avenue Kirby Avenue
Orange Lot
No Construction
Parking
Brown Lot
Construction Parking
(Phase 2 Only)
Blue Lot
No Construction
Parking
-6’ High chain link fence (with posts in
ground)
-6’ High chain link fence, moveable
fence supported by bases and sandbags
and/or pins
-Primary construction truck ingress and
egress
-Public drop off
-Earth Retention
-30’ Wide Sliding Gate
-25’ Wide Swing Gate
-25’ Wide Sliding Gate
-Masonry Silo
-800 AMP 120/208V Service for Trailers
-30’ Wide Swing Gate
P
Crane
Pad
Plywood
Canopy
Protection
Crane Pad
50’ x 100’
STAGING AREA
FOR WEST
STAGING AREA
FOR NORTH
STAGING AREA FOR SOUTH
STAGING AREA FOR EAST
FourthStreet
St. Mary’s Road
G1
G7
G2
G3
Dumpster
Dumpster
Dumpster
Dumpster
Dumpster
Tool Trailers – 34 Spaces
340’ x 60’
Storage/Staging
Area
G5
G5
G5
M
TE
G5
30’ Wide Road< Ramp <
There will be no
ramp to service
level
Contractor must
provide their own
cranes for hoisting
Construction
hoisting access to
service level after
concrete floor at
Level B is poured
West Construction Staging Area
New
Road
Phase 2 Construction Logistics
March 2014 To November 2014
Crane Pads to be constructed
of CA-A plus 6” of CA-6 with
top elevation@ 749’
G13
G5
G6
G1
2
G1
0
G1
1
G1
0
G9
G4
G8
G9
*No Construction
Parking
East Staging Area
50’ x 200’
Crane Pad
50’ x 100’
Crane
Pad
New U.G. electrical
ductbank, water
main, and steam
installations in this
area.
G1
1
G1
1
G8
G9
Access to loading dock
at event level
Service Level
Dock Below
N
03/01/2014 – 10/31/2014
BTN Work Room
Loading Dock Walk
Shops
Security
Phase 2 –
Service Level
Key
Construction
No Service
Ongoing
In Use
Other
East Mechanical
West Mechanical
Micro Piles from Above
Earth Retention - Arena
03/01/2014 – 10/31/2014
Operations Offices
Substation A & B
Tunnel Abatement
Phase 2 –
Mechanical Level
Key
Construction
No Service
Ongoing
In Use
Abatement
Chilled Water Main to AHU 18
Demo Chiller
Generator Base
PRV Room
East Mechanical Tunnel
West Mechanical Tunnel
Micro Piles from Above
Earth Retention – Additions
Earth Retention/ Excavation -
Additions
Earth Retention – Soil Nail Wall
Earth Retention – Soil Nail Wall
Earth Retention – Soil Nail Wall
Earth Retention – Soil Nail Wall
Earth Retention – Soil Nail Wall
Remove Insulrock
East Addition
03/01/2014 – 10/31/2014
Phase 2 –
B Level Concourse
Key
Construction
No Service
Ongoing
In Use
Other
Abate Office Areas
Demo Office Areas
Demo Toilet Lids
Domestic Water Loop
West Addition
Fit Out (No Service)
South Ramps and Plaza
Demo Stair Over
Substation A & B
Excavation – Link Tunnels
Excavation – Link Tunnels
Crane Usage
Single Sided Forms
03/01/2014 – 10/31/2014
Bowl Retention Piles
New Tunnel Piles
Raker Duct Lining
Phase 2 –
Event Bowl
Key
Construction
No Service
Ongoing
In Use
Preparation
Booth Exterior
Vom. Infills
C-Level Seating
Provide Raker Access
Prepare Catwalk for Phase 6
Raker Openings
Seating Infills
Seating Installation
03/01/2014 – 10/31/2014
Temporary Stairs
Demolition of Stairs at Substation
5 Portables
2 ADA Ramps
East Addition
Phase 2 –
C Level Concourse
Key
Construction
No Service
Ongoing
In Use
Temporary
South Ramps
& Plaza
West Addition
Dust Protection Tent
Phase 3 Egress Plan
Phase 3 – Basketball Season
• Work continues on the East and West Addition
Service Level Fitout
• Closeout of the Bid Package 1 Contractors
• EXTENSIVE scheduling and pre-planning session for
Phase 4
Phase 4 Arena Bowl Demolition
Day 1
Phase 4 Arena Bowl Demolition
Day 6
NE Tunnel Excavation
Tie Backs for the NE Tunnel
Load Transfer Beam Placement
“”Other” Work
Project Challenges
 Aggressive design schedule and even more
aggressive construction schedule
 Public client with state procurement limitations
 Renovation of a 50 year old building
 Finding qualified local manpower to be able to support
a project of this magnitude
 Despite all the challenges so far the project remains
on schedule and within budget.
Questions ?

More Related Content

What's hot

Institut du Monde Arabe By Jean Nouvel
Institut du Monde Arabe By Jean NouvelInstitut du Monde Arabe By Jean Nouvel
Institut du Monde Arabe By Jean NouvelHanady14
 
ICSA 2016 - Pedestrian Bridge as Public Art: Detailing in Exposed Steel
ICSA 2016 - Pedestrian Bridge as Public Art: Detailing in Exposed SteelICSA 2016 - Pedestrian Bridge as Public Art: Detailing in Exposed Steel
ICSA 2016 - Pedestrian Bridge as Public Art: Detailing in Exposed SteelTerri Meyer Boake
 
Beijing Urban Planning Issues
Beijing Urban Planning IssuesBeijing Urban Planning Issues
Beijing Urban Planning IssuesJoe Carter
 
Kenzo Tange - Architecture
Kenzo Tange - ArchitectureKenzo Tange - Architecture
Kenzo Tange - ArchitectureMansi Pushpakar
 
Graduation Project Thesis. Youth Empowerment Center. Haneen Fraihat
Graduation Project Thesis. Youth Empowerment Center. Haneen FraihatGraduation Project Thesis. Youth Empowerment Center. Haneen Fraihat
Graduation Project Thesis. Youth Empowerment Center. Haneen FraihatHaneen Fraihat
 
Theorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention CentreTheorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention CentreDexter Ng
 
London aquatic center Case study
London aquatic center Case studyLondon aquatic center Case study
London aquatic center Case studyrohan joshi
 
Suzhou Museum Analysis
Suzhou Museum AnalysisSuzhou Museum Analysis
Suzhou Museum AnalysisTay Jit Ying
 
Cept case study
Cept case studyCept case study
Cept case studyAlmas Khan
 
KENZO TANGE
KENZO TANGEKENZO TANGE
KENZO TANGEAmal Raj
 
supreme court additonal complex project
supreme court additonal complex projectsupreme court additonal complex project
supreme court additonal complex projectAbhishek singh
 
University Case Study Bangladesh
University Case Study BangladeshUniversity Case Study Bangladesh
University Case Study Bangladeshomorfarukparveztopu
 
Landscape architecture
Landscape architectureLandscape architecture
Landscape architectureSheau Hui Tan
 
Waterfront development
Waterfront developmentWaterfront development
Waterfront developmentmisschand
 

What's hot (20)

Institut du Monde Arabe By Jean Nouvel
Institut du Monde Arabe By Jean NouvelInstitut du Monde Arabe By Jean Nouvel
Institut du Monde Arabe By Jean Nouvel
 
ICSA 2016 - Pedestrian Bridge as Public Art: Detailing in Exposed Steel
ICSA 2016 - Pedestrian Bridge as Public Art: Detailing in Exposed SteelICSA 2016 - Pedestrian Bridge as Public Art: Detailing in Exposed Steel
ICSA 2016 - Pedestrian Bridge as Public Art: Detailing in Exposed Steel
 
Bernard tsumi 3
Bernard tsumi 3Bernard tsumi 3
Bernard tsumi 3
 
Beijing Urban Planning Issues
Beijing Urban Planning IssuesBeijing Urban Planning Issues
Beijing Urban Planning Issues
 
Kenzo Tange - Architecture
Kenzo Tange - ArchitectureKenzo Tange - Architecture
Kenzo Tange - Architecture
 
Graduation Project Thesis. Youth Empowerment Center. Haneen Fraihat
Graduation Project Thesis. Youth Empowerment Center. Haneen FraihatGraduation Project Thesis. Youth Empowerment Center. Haneen Fraihat
Graduation Project Thesis. Youth Empowerment Center. Haneen Fraihat
 
Theorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention CentreTheorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention Centre
 
London aquatic center Case study
London aquatic center Case studyLondon aquatic center Case study
London aquatic center Case study
 
Nakagin Capsule Tower
Nakagin Capsule TowerNakagin Capsule Tower
Nakagin Capsule Tower
 
Suzhou Museum Analysis
Suzhou Museum AnalysisSuzhou Museum Analysis
Suzhou Museum Analysis
 
Cept case study
Cept case studyCept case study
Cept case study
 
Sasaki Bridgeport Parks Master Plan Final Presentation
Sasaki Bridgeport Parks Master Plan Final PresentationSasaki Bridgeport Parks Master Plan Final Presentation
Sasaki Bridgeport Parks Master Plan Final Presentation
 
Bernard Tschumi
Bernard TschumiBernard Tschumi
Bernard Tschumi
 
City Museum
City MuseumCity Museum
City Museum
 
KENZO TANGE
KENZO TANGEKENZO TANGE
KENZO TANGE
 
supreme court additonal complex project
supreme court additonal complex projectsupreme court additonal complex project
supreme court additonal complex project
 
Hotel tassel
Hotel tasselHotel tassel
Hotel tassel
 
University Case Study Bangladesh
University Case Study BangladeshUniversity Case Study Bangladesh
University Case Study Bangladesh
 
Landscape architecture
Landscape architectureLandscape architecture
Landscape architecture
 
Waterfront development
Waterfront developmentWaterfront development
Waterfront development
 

Viewers also liked

CMAA April Luncheon - Focal Point
CMAA April Luncheon - Focal PointCMAA April Luncheon - Focal Point
CMAA April Luncheon - Focal PointAusrine Rakauskaite
 
State_Farm_Campaign
State_Farm_CampaignState_Farm_Campaign
State_Farm_Campaignkels
 
State Farm presentation at the Chief Analytics Officer Forum East Coast USA (...
State Farm presentation at the Chief Analytics Officer Forum East Coast USA (...State Farm presentation at the Chief Analytics Officer Forum East Coast USA (...
State Farm presentation at the Chief Analytics Officer Forum East Coast USA (...Chief Analytics Officer Forum
 
State farm idea management
State farm idea managementState farm idea management
State farm idea managementSIKM
 
FAQs About State Farm Agency Opportunity
FAQs About State Farm Agency OpportunityFAQs About State Farm Agency Opportunity
FAQs About State Farm Agency Opportunitylesley_postle
 
AAF State Farm Campaign 2010
AAF State Farm Campaign 2010AAF State Farm Campaign 2010
AAF State Farm Campaign 2010jnoelles
 
State Farm Presentation
State Farm PresentationState Farm Presentation
State Farm Presentationkels
 
Analysis state farm
Analysis state farmAnalysis state farm
Analysis state farmCubeyou Inc
 
State Farm Plans Book Ucla 2010
State Farm Plans Book Ucla 2010State Farm Plans Book Ucla 2010
State Farm Plans Book Ucla 2010Karla Liu
 

Viewers also liked (9)

CMAA April Luncheon - Focal Point
CMAA April Luncheon - Focal PointCMAA April Luncheon - Focal Point
CMAA April Luncheon - Focal Point
 
State_Farm_Campaign
State_Farm_CampaignState_Farm_Campaign
State_Farm_Campaign
 
State Farm presentation at the Chief Analytics Officer Forum East Coast USA (...
State Farm presentation at the Chief Analytics Officer Forum East Coast USA (...State Farm presentation at the Chief Analytics Officer Forum East Coast USA (...
State Farm presentation at the Chief Analytics Officer Forum East Coast USA (...
 
State farm idea management
State farm idea managementState farm idea management
State farm idea management
 
FAQs About State Farm Agency Opportunity
FAQs About State Farm Agency OpportunityFAQs About State Farm Agency Opportunity
FAQs About State Farm Agency Opportunity
 
AAF State Farm Campaign 2010
AAF State Farm Campaign 2010AAF State Farm Campaign 2010
AAF State Farm Campaign 2010
 
State Farm Presentation
State Farm PresentationState Farm Presentation
State Farm Presentation
 
Analysis state farm
Analysis state farmAnalysis state farm
Analysis state farm
 
State Farm Plans Book Ucla 2010
State Farm Plans Book Ucla 2010State Farm Plans Book Ucla 2010
State Farm Plans Book Ucla 2010
 

Similar to State Farm Center Renovation Project

Substantial Completion: Lorton Road Project
Substantial Completion: Lorton Road ProjectSubstantial Completion: Lorton Road Project
Substantial Completion: Lorton Road ProjectFairfax County
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipmentBashirul Islam
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Fairfax County Old Courthouse Road Walkway Improvements August 2020
Fairfax County Old Courthouse Road Walkway Improvements August 2020Fairfax County Old Courthouse Road Walkway Improvements August 2020
Fairfax County Old Courthouse Road Walkway Improvements August 2020Fairfax County
 
Lee Highway, U.S. Route 29 Phase III Widening
Lee Highway, U.S. Route 29 Phase III WideningLee Highway, U.S. Route 29 Phase III Widening
Lee Highway, U.S. Route 29 Phase III WideningFairfax County
 
Sound Transit 6/17/09 Noise And Construction Meeting
Sound Transit 6/17/09 Noise And Construction MeetingSound Transit 6/17/09 Noise And Construction Meeting
Sound Transit 6/17/09 Noise And Construction Meetingjseattle
 
Portland Place Phase II
Portland Place Phase IIPortland Place Phase II
Portland Place Phase IIFairfax County
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road RealignmentFairfax County
 
Canalside board update dec 2015
Canalside board update dec 2015Canalside board update dec 2015
Canalside board update dec 2015MetroPR
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road WalkwayFairfax County
 
Biomed realty-emeryville-center-innovation
Biomed realty-emeryville-center-innovationBiomed realty-emeryville-center-innovation
Biomed realty-emeryville-center-innovationE'ville Eye
 
Newington Forest Ave Walkway from Hooes Road to Treasure Tree Court
Newington Forest Ave Walkway from Hooes Road to Treasure Tree CourtNewington Forest Ave Walkway from Hooes Road to Treasure Tree Court
Newington Forest Ave Walkway from Hooes Road to Treasure Tree CourtFairfax County
 
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docxDESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docxcarolinef5
 
Pohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian ImprovementsPohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian ImprovementsFairfax County
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Fairfax County
 

Similar to State Farm Center Renovation Project (20)

Substantial Completion: Lorton Road Project
Substantial Completion: Lorton Road ProjectSubstantial Completion: Lorton Road Project
Substantial Completion: Lorton Road Project
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Fairfax County Old Courthouse Road Walkway Improvements August 2020
Fairfax County Old Courthouse Road Walkway Improvements August 2020Fairfax County Old Courthouse Road Walkway Improvements August 2020
Fairfax County Old Courthouse Road Walkway Improvements August 2020
 
SECTIONAL DIAGRAM
SECTIONAL DIAGRAMSECTIONAL DIAGRAM
SECTIONAL DIAGRAM
 
Lee Highway, U.S. Route 29 Phase III Widening
Lee Highway, U.S. Route 29 Phase III WideningLee Highway, U.S. Route 29 Phase III Widening
Lee Highway, U.S. Route 29 Phase III Widening
 
Sound Transit 6/17/09 Noise And Construction Meeting
Sound Transit 6/17/09 Noise And Construction MeetingSound Transit 6/17/09 Noise And Construction Meeting
Sound Transit 6/17/09 Noise And Construction Meeting
 
Portland Place Phase II
Portland Place Phase IIPortland Place Phase II
Portland Place Phase II
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road Realignment
 
Canalside board update dec 2015
Canalside board update dec 2015Canalside board update dec 2015
Canalside board update dec 2015
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
Quander Road Walkway
Quander Road WalkwayQuander Road Walkway
Quander Road Walkway
 
July 21, 2021 TARC Virtual Workshop
July 21, 2021 TARC Virtual WorkshopJuly 21, 2021 TARC Virtual Workshop
July 21, 2021 TARC Virtual Workshop
 
Biomed realty-emeryville-center-innovation
Biomed realty-emeryville-center-innovationBiomed realty-emeryville-center-innovation
Biomed realty-emeryville-center-innovation
 
Technical Report
Technical ReportTechnical Report
Technical Report
 
Newington Forest Ave Walkway from Hooes Road to Treasure Tree Court
Newington Forest Ave Walkway from Hooes Road to Treasure Tree CourtNewington Forest Ave Walkway from Hooes Road to Treasure Tree Court
Newington Forest Ave Walkway from Hooes Road to Treasure Tree Court
 
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docxDESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
 
Pohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian ImprovementsPohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian Improvements
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020
 
HS2.5 RK SELRT Alt Ops Exec Report
HS2.5 RK SELRT Alt Ops Exec ReportHS2.5 RK SELRT Alt Ops Exec Report
HS2.5 RK SELRT Alt Ops Exec Report
 

More from Ausrine Rakauskaite

Kaplan Institute Constuction - Illinois Tech
Kaplan Institute Constuction - Illinois TechKaplan Institute Constuction - Illinois Tech
Kaplan Institute Constuction - Illinois TechAusrine Rakauskaite
 
Project Delivery and Best Practices
Project Delivery and Best PracticesProject Delivery and Best Practices
Project Delivery and Best PracticesAusrine Rakauskaite
 
UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...Ausrine Rakauskaite
 
Clark Construction/PD3 Presentation - McCormick HQ
Clark Construction/PD3 Presentation - McCormick HQClark Construction/PD3 Presentation - McCormick HQ
Clark Construction/PD3 Presentation - McCormick HQAusrine Rakauskaite
 
CMAA January Luncheon - Illinois Tollway
CMAA January Luncheon - Illinois TollwayCMAA January Luncheon - Illinois Tollway
CMAA January Luncheon - Illinois TollwayAusrine Rakauskaite
 
ACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD PresentationACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD PresentationAusrine Rakauskaite
 
CMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement ProgramCMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement ProgramAusrine Rakauskaite
 
CMAA Presentation Final Cook County
CMAA Presentation Final Cook CountyCMAA Presentation Final Cook County
CMAA Presentation Final Cook CountyAusrine Rakauskaite
 

More from Ausrine Rakauskaite (12)

Kaplan Institute Constuction - Illinois Tech
Kaplan Institute Constuction - Illinois TechKaplan Institute Constuction - Illinois Tech
Kaplan Institute Constuction - Illinois Tech
 
Project Delivery and Best Practices
Project Delivery and Best PracticesProject Delivery and Best Practices
Project Delivery and Best Practices
 
Capital Programs - O'Hare 21
Capital Programs - O'Hare 21 Capital Programs - O'Hare 21
Capital Programs - O'Hare 21
 
UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...
 
Clark Construction/PD3 Presentation - McCormick HQ
Clark Construction/PD3 Presentation - McCormick HQClark Construction/PD3 Presentation - McCormick HQ
Clark Construction/PD3 Presentation - McCormick HQ
 
CMAA Riverwalk Presentation
CMAA Riverwalk PresentationCMAA Riverwalk Presentation
CMAA Riverwalk Presentation
 
CMAA January Luncheon - Illinois Tollway
CMAA January Luncheon - Illinois TollwayCMAA January Luncheon - Illinois Tollway
CMAA January Luncheon - Illinois Tollway
 
ACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD PresentationACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD Presentation
 
CMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement ProgramCMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement Program
 
CMAA Presentation Final Cook County
CMAA Presentation Final Cook CountyCMAA Presentation Final Cook County
CMAA Presentation Final Cook County
 
November 2014 CCM Newsletter
November 2014 CCM NewsletterNovember 2014 CCM Newsletter
November 2014 CCM Newsletter
 
The State of Rail in Illinois
The State of Rail in IllinoisThe State of Rail in Illinois
The State of Rail in Illinois
 

Recently uploaded

भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 

Recently uploaded (20)

भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 

State Farm Center Renovation Project

  • 1. State Farm Center Renovation and Addition Project
  • 2. Project Leadership  Owner  University of Illinois F&S  DIA  Construction Manager  Design Team  AECOM – Architectural  Thorton Tomasetti – Structural  Henderson Engineers – Mechanical, Electrical  ESD – Plumbing
  • 3. Project Specifics  160 Million Renovations and Addition  New Mechanical Spaces and Systems  Reconfiguration of the arena  New Luxury Seating  New Ramps and Walks  6 phases  1,3,5 – Basketball Phases  2,4,6 – “Construction” Phases  Peak manpower for Phase 2 – 160  Peak manpower for Phase 4 – 250
  • 5. State Farm Center12/02/2013 – 02/28/2014 Phase 1 – Site Work Key Construction No Service Ongoing In Use Other
  • 6. State Farm Center12/02/2013 – 02/28/2014 PRV Room Demo HV-10 T/C Offices Phase 1 – Mechanical Level Key Construction No Service Ongoing In Use Other
  • 7. State Farm CenterState Farm Center Phase 1 Construction Logistics December 2013 To February 2014 St. Mary’s Road FourthStreetFourthStreet St. Mary’s Road Kirby Avenue Kirby Avenue Orange Lot No Construction Parking Brown Lot No Construction Parking Blue Lot No Construction Parking N Relocate Fence As Work Progresses Relocate Fence As Work Progresses B C C C C C C C C C C B B B B B B P P -6’ High chain link fence (with posts in ground) -6’ High chain link fence, moveable fence supported by bases and sandbags and/or pins -Primary construction truck ingress and egress -”B” level entrance into building via stairs (must be maintained for ingress and egress) -”C” level entrance into building via existing ramps -Maintain pedestrian access/egress into SFC at “B” level -Maintain pedestrian access/egress via ramps to “C” level entrance -Public drop off -30’ Wide Sliding Gate -25’ Wide Swing Gate -25’ Wide Sliding Gate -Masonry Silo -800 AMP 120/208V Service for Trailers G1 G7 G5 G4 G2 G6 G3 C B B C P Relocate Fence As Work Progresses Relocate Fence As Work Progresses G5 G5 G5 M TE Dumpster Dumpster Dumpster Dumpster Dumpster Tool Trailers – 34 Spaces 340’ x 60’ Storage/Staging Area Notes: Typical Work of Phase 1 1) U.G. Utility Contractor shall provide, install, maintain, and reposition moveable chain link fence around all excavations, equipment, and disturbed areas during installations. 2) Any existing roads, sidewalks or pavements shall be restored via 3000 PSI concrete, 4 inches thick after underground installation to allow pedestrian or vehicle traffic. 3) U.G. Utility Contractor to provide and maintain steel road plates over areas where pavement can not be replaced to allow access to SFC. 4) U.G. Utility Contractor to schedule and coordinate work to always provide ingress and egress to the SFC “B” Level entrances and ramps to the “C” Level entrances. B West Construction Staging Area Construction Road G8 G9 Plywood Canopy Protection *Trades Men Parking For Phase 1 Only G1 1 G1 1 Service Level Dock Below Construction Field Office and Staging RED PARKING LOT Temporary Fence Panels
  • 12. State Farm CenterState Farm Center St. Mary’s Road FourthStreet Kirby Avenue Kirby Avenue Orange Lot No Construction Parking Brown Lot Construction Parking (Phase 2 Only) Blue Lot No Construction Parking -6’ High chain link fence (with posts in ground) -6’ High chain link fence, moveable fence supported by bases and sandbags and/or pins -Primary construction truck ingress and egress -Public drop off -Earth Retention -30’ Wide Sliding Gate -25’ Wide Swing Gate -25’ Wide Sliding Gate -Masonry Silo -800 AMP 120/208V Service for Trailers -30’ Wide Swing Gate P Crane Pad Plywood Canopy Protection Crane Pad 50’ x 100’ STAGING AREA FOR WEST STAGING AREA FOR NORTH STAGING AREA FOR SOUTH STAGING AREA FOR EAST FourthStreet St. Mary’s Road G1 G7 G2 G3 Dumpster Dumpster Dumpster Dumpster Dumpster Tool Trailers – 34 Spaces 340’ x 60’ Storage/Staging Area G5 G5 G5 M TE G5 30’ Wide Road< Ramp < There will be no ramp to service level Contractor must provide their own cranes for hoisting Construction hoisting access to service level after concrete floor at Level B is poured West Construction Staging Area New Road Phase 2 Construction Logistics March 2014 To November 2014 Crane Pads to be constructed of CA-A plus 6” of CA-6 with top elevation@ 749’ G13 G5 G6 G1 2 G1 0 G1 1 G1 0 G9 G4 G8 G9 *No Construction Parking East Staging Area 50’ x 200’ Crane Pad 50’ x 100’ Crane Pad New U.G. electrical ductbank, water main, and steam installations in this area. G1 1 G1 1 G8 G9 Access to loading dock at event level Service Level Dock Below N
  • 13. 03/01/2014 – 10/31/2014 BTN Work Room Loading Dock Walk Shops Security Phase 2 – Service Level Key Construction No Service Ongoing In Use Other East Mechanical West Mechanical Micro Piles from Above
  • 15. 03/01/2014 – 10/31/2014 Operations Offices Substation A & B Tunnel Abatement Phase 2 – Mechanical Level Key Construction No Service Ongoing In Use Abatement Chilled Water Main to AHU 18 Demo Chiller Generator Base PRV Room East Mechanical Tunnel West Mechanical Tunnel Micro Piles from Above
  • 16. Earth Retention – Additions
  • 18. Earth Retention – Soil Nail Wall
  • 19. Earth Retention – Soil Nail Wall
  • 20. Earth Retention – Soil Nail Wall
  • 21. Earth Retention – Soil Nail Wall
  • 22. Earth Retention – Soil Nail Wall
  • 23. Remove Insulrock East Addition 03/01/2014 – 10/31/2014 Phase 2 – B Level Concourse Key Construction No Service Ongoing In Use Other Abate Office Areas Demo Office Areas Demo Toilet Lids Domestic Water Loop West Addition Fit Out (No Service) South Ramps and Plaza Demo Stair Over Substation A & B
  • 28. 03/01/2014 – 10/31/2014 Bowl Retention Piles New Tunnel Piles Raker Duct Lining Phase 2 – Event Bowl Key Construction No Service Ongoing In Use Preparation Booth Exterior Vom. Infills C-Level Seating Provide Raker Access Prepare Catwalk for Phase 6
  • 32. 03/01/2014 – 10/31/2014 Temporary Stairs Demolition of Stairs at Substation 5 Portables 2 ADA Ramps East Addition Phase 2 – C Level Concourse Key Construction No Service Ongoing In Use Temporary South Ramps & Plaza West Addition
  • 35. Phase 3 – Basketball Season • Work continues on the East and West Addition Service Level Fitout • Closeout of the Bid Package 1 Contractors • EXTENSIVE scheduling and pre-planning session for Phase 4
  • 36.
  • 37.
  • 38.
  • 39. Phase 4 Arena Bowl Demolition Day 1
  • 40. Phase 4 Arena Bowl Demolition Day 6
  • 42. Tie Backs for the NE Tunnel
  • 43. Load Transfer Beam Placement
  • 45. Project Challenges  Aggressive design schedule and even more aggressive construction schedule  Public client with state procurement limitations  Renovation of a 50 year old building  Finding qualified local manpower to be able to support a project of this magnitude  Despite all the challenges so far the project remains on schedule and within budget.