2. Project Leadership
Owner
University of Illinois F&S
DIA
Construction Manager
Design Team
AECOM – Architectural
Thorton Tomasetti – Structural
Henderson Engineers – Mechanical, Electrical
ESD – Plumbing
3. Project Specifics
160 Million Renovations and Addition
New Mechanical Spaces and Systems
Reconfiguration of the arena
New Luxury Seating
New Ramps and Walks
6 phases
1,3,5 – Basketball Phases
2,4,6 – “Construction” Phases
Peak manpower for Phase 2 – 160
Peak manpower for Phase 4 – 250
5. State Farm Center12/02/2013 – 02/28/2014
Phase 1 –
Site Work
Key
Construction
No Service
Ongoing
In Use
Other
6. State Farm Center12/02/2013 – 02/28/2014
PRV Room
Demo HV-10
T/C Offices
Phase 1 –
Mechanical Level
Key
Construction
No Service
Ongoing
In Use
Other
7. State Farm CenterState Farm Center
Phase 1 Construction Logistics
December 2013 To February 2014
St. Mary’s Road
FourthStreetFourthStreet
St. Mary’s Road
Kirby Avenue Kirby Avenue
Orange Lot
No Construction
Parking
Brown Lot
No Construction
Parking
Blue Lot
No Construction
Parking
N
Relocate
Fence As
Work
Progresses
Relocate
Fence As
Work
Progresses
B
C
C
C
C
C
C
C
C
C
C
B
B
B
B
B B
P
P
-6’ High chain link fence (with posts in
ground)
-6’ High chain link fence, moveable fence
supported by bases and sandbags and/or
pins
-Primary construction truck ingress and
egress
-”B” level entrance into building via stairs
(must be maintained for ingress and egress)
-”C” level entrance into building via existing
ramps
-Maintain pedestrian access/egress into SFC
at “B” level
-Maintain pedestrian access/egress via
ramps to “C” level entrance
-Public drop off
-30’ Wide Sliding Gate
-25’ Wide Swing Gate
-25’ Wide Sliding Gate
-Masonry Silo
-800 AMP 120/208V Service for Trailers
G1
G7
G5
G4
G2
G6
G3
C
B
B
C
P
Relocate
Fence As
Work
Progresses
Relocate
Fence As
Work
Progresses
G5
G5
G5
M
TE
Dumpster
Dumpster
Dumpster
Dumpster
Dumpster
Tool Trailers – 34 Spaces
340’ x 60’
Storage/Staging
Area
Notes: Typical Work of Phase 1
1) U.G. Utility Contractor shall provide, install,
maintain, and reposition moveable chain link fence
around all excavations, equipment, and disturbed
areas during installations.
2) Any existing roads, sidewalks or pavements shall
be restored via 3000 PSI concrete, 4 inches thick
after underground installation to allow pedestrian
or vehicle traffic.
3) U.G. Utility Contractor to provide and maintain
steel road plates over areas where pavement can
not be replaced to allow access to SFC.
4) U.G. Utility Contractor to schedule and
coordinate work to always provide ingress and
egress to the SFC “B” Level entrances and ramps to
the “C” Level entrances.
B
West Construction Staging Area Construction Road
G8
G9 Plywood
Canopy
Protection
*Trades Men
Parking For Phase 1
Only
G1
1
G1
1
Service Level
Dock Below
Construction Field
Office and Staging
RED PARKING LOT
Temporary
Fence Panels
12. State Farm CenterState Farm Center
St. Mary’s Road
FourthStreet
Kirby Avenue Kirby Avenue
Orange Lot
No Construction
Parking
Brown Lot
Construction Parking
(Phase 2 Only)
Blue Lot
No Construction
Parking
-6’ High chain link fence (with posts in
ground)
-6’ High chain link fence, moveable
fence supported by bases and sandbags
and/or pins
-Primary construction truck ingress and
egress
-Public drop off
-Earth Retention
-30’ Wide Sliding Gate
-25’ Wide Swing Gate
-25’ Wide Sliding Gate
-Masonry Silo
-800 AMP 120/208V Service for Trailers
-30’ Wide Swing Gate
P
Crane
Pad
Plywood
Canopy
Protection
Crane Pad
50’ x 100’
STAGING AREA
FOR WEST
STAGING AREA
FOR NORTH
STAGING AREA FOR SOUTH
STAGING AREA FOR EAST
FourthStreet
St. Mary’s Road
G1
G7
G2
G3
Dumpster
Dumpster
Dumpster
Dumpster
Dumpster
Tool Trailers – 34 Spaces
340’ x 60’
Storage/Staging
Area
G5
G5
G5
M
TE
G5
30’ Wide Road< Ramp <
There will be no
ramp to service
level
Contractor must
provide their own
cranes for hoisting
Construction
hoisting access to
service level after
concrete floor at
Level B is poured
West Construction Staging Area
New
Road
Phase 2 Construction Logistics
March 2014 To November 2014
Crane Pads to be constructed
of CA-A plus 6” of CA-6 with
top elevation@ 749’
G13
G5
G6
G1
2
G1
0
G1
1
G1
0
G9
G4
G8
G9
*No Construction
Parking
East Staging Area
50’ x 200’
Crane Pad
50’ x 100’
Crane
Pad
New U.G. electrical
ductbank, water
main, and steam
installations in this
area.
G1
1
G1
1
G8
G9
Access to loading dock
at event level
Service Level
Dock Below
N
13. 03/01/2014 – 10/31/2014
BTN Work Room
Loading Dock Walk
Shops
Security
Phase 2 –
Service Level
Key
Construction
No Service
Ongoing
In Use
Other
East Mechanical
West Mechanical
Micro Piles from Above
15. 03/01/2014 – 10/31/2014
Operations Offices
Substation A & B
Tunnel Abatement
Phase 2 –
Mechanical Level
Key
Construction
No Service
Ongoing
In Use
Abatement
Chilled Water Main to AHU 18
Demo Chiller
Generator Base
PRV Room
East Mechanical Tunnel
West Mechanical Tunnel
Micro Piles from Above
23. Remove Insulrock
East Addition
03/01/2014 – 10/31/2014
Phase 2 –
B Level Concourse
Key
Construction
No Service
Ongoing
In Use
Other
Abate Office Areas
Demo Office Areas
Demo Toilet Lids
Domestic Water Loop
West Addition
Fit Out (No Service)
South Ramps and Plaza
Demo Stair Over
Substation A & B
28. 03/01/2014 – 10/31/2014
Bowl Retention Piles
New Tunnel Piles
Raker Duct Lining
Phase 2 –
Event Bowl
Key
Construction
No Service
Ongoing
In Use
Preparation
Booth Exterior
Vom. Infills
C-Level Seating
Provide Raker Access
Prepare Catwalk for Phase 6
32. 03/01/2014 – 10/31/2014
Temporary Stairs
Demolition of Stairs at Substation
5 Portables
2 ADA Ramps
East Addition
Phase 2 –
C Level Concourse
Key
Construction
No Service
Ongoing
In Use
Temporary
South Ramps
& Plaza
West Addition
35. Phase 3 – Basketball Season
• Work continues on the East and West Addition
Service Level Fitout
• Closeout of the Bid Package 1 Contractors
• EXTENSIVE scheduling and pre-planning session for
Phase 4
45. Project Challenges
Aggressive design schedule and even more
aggressive construction schedule
Public client with state procurement limitations
Renovation of a 50 year old building
Finding qualified local manpower to be able to support
a project of this magnitude
Despite all the challenges so far the project remains
on schedule and within budget.