SlideShare a Scribd company logo
1 of 23
The Petronas
Twin Towers
AMAN SHUKLA
101116005
B.ARCH 2016-21’
NIT TRICHY
INTRODUCTION
• The Petronas Towers, also
known as the Petronas Twin
Towers (Menara Petronas, or
Menar Berkembar Petronas), are
twin skyscrapers in Kuala
Lumpur, Malaysia. According to
the Council on Tall Buildings and
Urban Habitat (CTBUH)'s official
definition and ranking, they
were the tallest buildings in the
world from 1998 to 2004 and
remain the tallest twin towers in
the world.
Quick Information
• ARCHITECT : Cesar pelli
• STRUCTURAL ENGINEER : Thornton
• thormaseti
• CONTRACTORS : TOWER 1 : Hazama corporation
• TOWER 2 : Samsung engg.& Co.
• FLOOR AREA : 3,95,000 m sq
• MATERIAL : Concrete , steel
• HEIGHT OF EACH TOWERS : 452 M above street level
• LIFTS : 29 double-decker high-speed passenger lifts in each tower.
Construction Team
• - Two separate construction teams.
• - First to use GPS (Global Positioning Satellite)
• - Built by concrete instead of conventional steel
• - 1000 people worked on each tower (3 shifts)
• - Floors up to 73rd Identical & easiest
• - 4 days to built each floor (Normal – 10 days)
TOWER 1
• Led by Japan Hazama Corporation
• Started on March 1994 (25 months & 1 week)
TOWER 2
• Led by Korea Samsung Engineering Co.
• Started on April 1994 (24 months)
Highlights
• Two 88 story towers with, a connecting bridge
• The sky bridge connecting the two structures
was also
• designed to act as a emergency escape in the
case of terroristic attacks and fires
• Pinnacles on top of the towers – design to
represent Islamic culture
• The use of glass windows
• Strive for the tallest building and originality
Foundation
The geotechnical survey discovered that the actual construction
site was situated partially over decayed limestone deposition
and rest over soft rock. foundation was rested on 1To0 4 safe
bed rock the piles were extended to depth ranging from (200-
374) feet. To reach this depth, PETRONAS Tower became the
structure having the deepest seated foundation of the world.
The piles were embedded by thick raft. This raft was 15 feet in
depth and it requires enormous amount of concrete to cast it.
This is about 4470,000 cubic feet which was the largest
continuously poured concrete until 2007. This huge quantity of
concreting for each tower required 54 hours to pour.
Design Concept
The towers evoke traditional motifs of Islamic
art, honoring the Malaysian Muslim heritage,
combined with innovative technology. Represent
a change in the style of skyscrapers built in Kuala
Lumpur, closer to traditional international style.
Pelli used an Islamic geometric design in its
plant, by interlacing two squares of gradually
decreasing size at the top, which is based on a
traditional motif in Islamic culture, a star of 12
peaks including a circle at each intersection.
Structure
Structure is the most
important element to ensure
the strength and the stability
of a building. Without a strong
structure, the buildings is not
safe to be occupied.
These pictures show the
cross section of the tower.
The cross section shows TWO
squares interlocking to each
other to form an eightpoint
star shape, which is the most
common shape design in
Islamic design.
Structure
Geometry is used as the main concept
of the design of Petronas Twin Towers.
This design means:-
Unity (Perpaduan)
Harmony (Harmoni)
Stability (Stabil)
Rationality (Rasional)
The roof uses a lot of triangular shape
structure to give a better support to the
building.
Structural System(for gravity and lateral loads):
• Structural system consists with75-by-75 foot concrete cores and an
outer ring of widely-spaced super columns.
• The core structure of each tower is composed of a ring of sixteen
cylindrical columns of high strength reinforced concrete.
• The columns vary in size from2.4in diameter at the lower areas to
1.2meters in diameter at the top ,and are placed at the outside
corners.
• The columns arel inked with a series of concrete core walls and ring
beams. These movement-resistant and damper-free structures can be
described as a pair of “soft tubes”. There are actually two concentric
pressurized cores in The structures, and the two cores unite at the
38th floor of each tower.
Skybridge
• DOUBLE DECK BRIDGE SPANNING 58.4 m
• CONNECTS TWO TOWER AT SKYLOBBY ELEVATOR
• TRANSFER STATION ON FLOOR 41 AND 42
• EASY CIRCULATION B/W UPPER TOWER FLOORS
• MINIMIZE LIFT USAGE
• REDUCES FIRE EXIT REQUIREMENT
• GREAT HEIGHT AND SPAN
• REQUIRES STEEL FOR LIGHT WEIGHT AND EASY CONST.
• TWO HINGED ARCH SUPPORTS THE SPAN
• SELF CENTRING ACTION FROM RESTRAIN AT ARCH
• CROWN AND SPHERICAL PIN AT SUPPORTS
Skybridge
• The skybridge built between the two towers
uses the combination of rectangles and
triangles structure to add more strength and
stability to the bridge
• The top view from skybridge of petronas twin
tower. It shows the landscape of roof design of
near by buildings. It portrays an interesting
symmetrical design.
Pinnacle
Material Used
• High-strength concrete was used in the central
core, perimeter columns, perimeter ring
beams and outrigger beams.
• The towers and their base are clad with
stainless steel extrusions and custommade
20.38 millimetre laminated lightgreen glass.
• The sunscreens have cast aluminium end caps
and are fixed on brackets made of extruded
aluminium and finished with oven-cured PVF2
fluorocarbon paint.
Steel Type
• Type 316 stainless steel(Ferrous) was
employed to clad the exterior of the Petronas
Towers, Malaysia (and the Jin Mao Tower in
China).
• Type 316 stainless steel is often used in
marine applications like for boat fittings, and
also used in the food and beverage industry.
Silos, cheese vats, fruit tanks and wine tanks
are also made using this type of steel.
Time
• The construction was estimated to take 8
years, however there was an eight month
delay
• It was completed in 6 years, two years under
what was predicted
• It was vital that the building was constructed
to the management plan, as it would cost
$700,000 per day after the deadline
Execution
• During the execution stage, the scope and
schedule are identified and determined.
• The schedule allowed for 4 days of
construction per floor, it initially took 8 day,
they had to construct uninterrupted, 24 hours
a day, 7 days a week
• Construction began in early 1993.
• A site establishment is conducted during this
stage, however, the engineers discovered that
there had never been a proper analysis of the
site, the site came to a standstill.
Execution
• Geologist looked for bedrock, but found that
the sitewas on declayed limestone and on the
edge of cliff
• The site was proposed to be moved 60 meters
onto the softer ground, were they could build
their own bedrock consisting of concrete
• The sky bridge connecting the two towers was
design for emergency purposes, such as a
terrorist attack, fires, and other emergencies
Constrains
• The not suitable bedrock (foundation)
• A lack of steel
• The concrete was not suitable, too soft
• They had to create a new form od concrete
that acted the same as steel; strong with a
degree of flexibility
• Flooring was time consuming
Issues during construction
• Issue One – The foundation slab
If the concrete dried unevenly, the slab would crack, thus seriously weaken
the ability to support the building above. Therefore, they decided to pour
the concrete all at the once, scheduling concrete trucks to arrive every 2,5
minutes for 52 hours, without a break.
• Issue Two – The weather
The Malaysian weather is susceptible to torrential rain, this is also
problematic to the slab, as the concrete can get too wet, and become ruined.
They covered the entire slab with canvas, the equivalent to 56 circus tents
The petronas twin towers

More Related Content

What's hot (20)

Petronas Twin Towers
Petronas Twin TowersPetronas Twin Towers
Petronas Twin Towers
 
High rise building case study
High rise building case study High rise building case study
High rise building case study
 
Shanghai tower
Shanghai towerShanghai tower
Shanghai tower
 
Taipei 101
Taipei 101Taipei 101
Taipei 101
 
BURJ AL ARAB
BURJ AL ARABBURJ AL ARAB
BURJ AL ARAB
 
Petronas towers kula lampur
Petronas towers kula lampurPetronas towers kula lampur
Petronas towers kula lampur
 
Taipei 101
Taipei 101 Taipei 101
Taipei 101
 
The Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyThe Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case Study
 
Bhurj khalifa _Net Case Study
Bhurj khalifa _Net Case StudyBhurj khalifa _Net Case Study
Bhurj khalifa _Net Case Study
 
Turning torso
Turning torsoTurning torso
Turning torso
 
The taipei 101 tower
The taipei 101 towerThe taipei 101 tower
The taipei 101 tower
 
Podium
PodiumPodium
Podium
 
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
 
Sears tower
Sears towerSears tower
Sears tower
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
Emirates towers
Emirates towersEmirates towers
Emirates towers
 
High Rise Building Research Document
High Rise Building Research DocumentHigh Rise Building Research Document
High Rise Building Research Document
 
Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.
 
Taipei 101
Taipei 101Taipei 101
Taipei 101
 
Project Taipei 101
Project Taipei 101Project Taipei 101
Project Taipei 101
 

Similar to The petronas twin towers

HIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxHIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxgoreshsaini2
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard buildingBirukYared3
 
ANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxAnshuBarmase
 
A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'Abheek Khajuria
 
Beijing National Stadium (China)
Beijing National Stadium (China)Beijing National Stadium (China)
Beijing National Stadium (China)sultanimulk796
 
Petronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabPetronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabRajat Nainwal
 
steel roof truss
steel roof trusssteel roof truss
steel roof trussRohit Dutta
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written ReportYap Xin
 
Skyscrapers ppt
Skyscrapers pptSkyscrapers ppt
Skyscrapers pptSAI KIRAN
 
Structure
StructureStructure
Structuresnarse
 
Cn tower.. a detailed study
Cn tower.. a detailed studyCn tower.. a detailed study
Cn tower.. a detailed studyMelbin Biju
 
Cn tower.. a detailed study
Cn tower.. a detailed studyCn tower.. a detailed study
Cn tower.. a detailed studyMelbin Biju
 
case study of shanghai world finance centre.
case study of shanghai world finance centre.case study of shanghai world finance centre.
case study of shanghai world finance centre.Chiranjita Jibhkate
 
High Rise Building- Taipei 101, Taiwan
High Rise Building- Taipei 101, TaiwanHigh Rise Building- Taipei 101, Taiwan
High Rise Building- Taipei 101, TaiwanPRANJAL MORE
 

Similar to The petronas twin towers (20)

HIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxHIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptx
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
ANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptx
 
KINGDOM TOWER JEDDAH TOWER
KINGDOM TOWER JEDDAH TOWERKINGDOM TOWER JEDDAH TOWER
KINGDOM TOWER JEDDAH TOWER
 
A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'
 
Skyscrapers
SkyscrapersSkyscrapers
Skyscrapers
 
Beijing National Stadium (China)
Beijing National Stadium (China)Beijing National Stadium (China)
Beijing National Stadium (China)
 
Petronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabPetronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arab
 
steel roof truss
steel roof trusssteel roof truss
steel roof truss
 
SA SEMINAR.pptx
SA SEMINAR.pptxSA SEMINAR.pptx
SA SEMINAR.pptx
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
 
Skyscrapers ppt
Skyscrapers pptSkyscrapers ppt
Skyscrapers ppt
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
Structure
StructureStructure
Structure
 
Cn tower.. a detailed study
Cn tower.. a detailed studyCn tower.. a detailed study
Cn tower.. a detailed study
 
Cn tower.. a detailed study
Cn tower.. a detailed studyCn tower.. a detailed study
Cn tower.. a detailed study
 
case study of shanghai world finance centre.
case study of shanghai world finance centre.case study of shanghai world finance centre.
case study of shanghai world finance centre.
 
Burj Al Arab
Burj Al ArabBurj Al Arab
Burj Al Arab
 
High Rise Building- Taipei 101, Taiwan
High Rise Building- Taipei 101, TaiwanHigh Rise Building- Taipei 101, Taiwan
High Rise Building- Taipei 101, Taiwan
 
Pm burj case
Pm burj casePm burj case
Pm burj case
 

Recently uploaded

main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 

Recently uploaded (20)

main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 

The petronas twin towers

  • 1. The Petronas Twin Towers AMAN SHUKLA 101116005 B.ARCH 2016-21’ NIT TRICHY
  • 2. INTRODUCTION • The Petronas Towers, also known as the Petronas Twin Towers (Menara Petronas, or Menar Berkembar Petronas), are twin skyscrapers in Kuala Lumpur, Malaysia. According to the Council on Tall Buildings and Urban Habitat (CTBUH)'s official definition and ranking, they were the tallest buildings in the world from 1998 to 2004 and remain the tallest twin towers in the world.
  • 3. Quick Information • ARCHITECT : Cesar pelli • STRUCTURAL ENGINEER : Thornton • thormaseti • CONTRACTORS : TOWER 1 : Hazama corporation • TOWER 2 : Samsung engg.& Co. • FLOOR AREA : 3,95,000 m sq • MATERIAL : Concrete , steel • HEIGHT OF EACH TOWERS : 452 M above street level • LIFTS : 29 double-decker high-speed passenger lifts in each tower.
  • 4. Construction Team • - Two separate construction teams. • - First to use GPS (Global Positioning Satellite) • - Built by concrete instead of conventional steel • - 1000 people worked on each tower (3 shifts) • - Floors up to 73rd Identical & easiest • - 4 days to built each floor (Normal – 10 days) TOWER 1 • Led by Japan Hazama Corporation • Started on March 1994 (25 months & 1 week) TOWER 2 • Led by Korea Samsung Engineering Co. • Started on April 1994 (24 months) Highlights • Two 88 story towers with, a connecting bridge • The sky bridge connecting the two structures was also • designed to act as a emergency escape in the case of terroristic attacks and fires • Pinnacles on top of the towers – design to represent Islamic culture • The use of glass windows • Strive for the tallest building and originality
  • 5. Foundation The geotechnical survey discovered that the actual construction site was situated partially over decayed limestone deposition and rest over soft rock. foundation was rested on 1To0 4 safe bed rock the piles were extended to depth ranging from (200- 374) feet. To reach this depth, PETRONAS Tower became the structure having the deepest seated foundation of the world. The piles were embedded by thick raft. This raft was 15 feet in depth and it requires enormous amount of concrete to cast it. This is about 4470,000 cubic feet which was the largest continuously poured concrete until 2007. This huge quantity of concreting for each tower required 54 hours to pour.
  • 6. Design Concept The towers evoke traditional motifs of Islamic art, honoring the Malaysian Muslim heritage, combined with innovative technology. Represent a change in the style of skyscrapers built in Kuala Lumpur, closer to traditional international style. Pelli used an Islamic geometric design in its plant, by interlacing two squares of gradually decreasing size at the top, which is based on a traditional motif in Islamic culture, a star of 12 peaks including a circle at each intersection.
  • 7. Structure Structure is the most important element to ensure the strength and the stability of a building. Without a strong structure, the buildings is not safe to be occupied. These pictures show the cross section of the tower. The cross section shows TWO squares interlocking to each other to form an eightpoint star shape, which is the most common shape design in Islamic design.
  • 8. Structure Geometry is used as the main concept of the design of Petronas Twin Towers. This design means:- Unity (Perpaduan) Harmony (Harmoni) Stability (Stabil) Rationality (Rasional) The roof uses a lot of triangular shape structure to give a better support to the building.
  • 9. Structural System(for gravity and lateral loads): • Structural system consists with75-by-75 foot concrete cores and an outer ring of widely-spaced super columns. • The core structure of each tower is composed of a ring of sixteen cylindrical columns of high strength reinforced concrete. • The columns vary in size from2.4in diameter at the lower areas to 1.2meters in diameter at the top ,and are placed at the outside corners. • The columns arel inked with a series of concrete core walls and ring beams. These movement-resistant and damper-free structures can be described as a pair of “soft tubes”. There are actually two concentric pressurized cores in The structures, and the two cores unite at the 38th floor of each tower.
  • 10.
  • 11.
  • 12.
  • 13. Skybridge • DOUBLE DECK BRIDGE SPANNING 58.4 m • CONNECTS TWO TOWER AT SKYLOBBY ELEVATOR • TRANSFER STATION ON FLOOR 41 AND 42 • EASY CIRCULATION B/W UPPER TOWER FLOORS • MINIMIZE LIFT USAGE • REDUCES FIRE EXIT REQUIREMENT • GREAT HEIGHT AND SPAN • REQUIRES STEEL FOR LIGHT WEIGHT AND EASY CONST. • TWO HINGED ARCH SUPPORTS THE SPAN • SELF CENTRING ACTION FROM RESTRAIN AT ARCH • CROWN AND SPHERICAL PIN AT SUPPORTS
  • 14. Skybridge • The skybridge built between the two towers uses the combination of rectangles and triangles structure to add more strength and stability to the bridge • The top view from skybridge of petronas twin tower. It shows the landscape of roof design of near by buildings. It portrays an interesting symmetrical design.
  • 16. Material Used • High-strength concrete was used in the central core, perimeter columns, perimeter ring beams and outrigger beams. • The towers and their base are clad with stainless steel extrusions and custommade 20.38 millimetre laminated lightgreen glass. • The sunscreens have cast aluminium end caps and are fixed on brackets made of extruded aluminium and finished with oven-cured PVF2 fluorocarbon paint.
  • 17. Steel Type • Type 316 stainless steel(Ferrous) was employed to clad the exterior of the Petronas Towers, Malaysia (and the Jin Mao Tower in China). • Type 316 stainless steel is often used in marine applications like for boat fittings, and also used in the food and beverage industry. Silos, cheese vats, fruit tanks and wine tanks are also made using this type of steel.
  • 18. Time • The construction was estimated to take 8 years, however there was an eight month delay • It was completed in 6 years, two years under what was predicted • It was vital that the building was constructed to the management plan, as it would cost $700,000 per day after the deadline
  • 19. Execution • During the execution stage, the scope and schedule are identified and determined. • The schedule allowed for 4 days of construction per floor, it initially took 8 day, they had to construct uninterrupted, 24 hours a day, 7 days a week • Construction began in early 1993. • A site establishment is conducted during this stage, however, the engineers discovered that there had never been a proper analysis of the site, the site came to a standstill.
  • 20. Execution • Geologist looked for bedrock, but found that the sitewas on declayed limestone and on the edge of cliff • The site was proposed to be moved 60 meters onto the softer ground, were they could build their own bedrock consisting of concrete • The sky bridge connecting the two towers was design for emergency purposes, such as a terrorist attack, fires, and other emergencies
  • 21. Constrains • The not suitable bedrock (foundation) • A lack of steel • The concrete was not suitable, too soft • They had to create a new form od concrete that acted the same as steel; strong with a degree of flexibility • Flooring was time consuming
  • 22. Issues during construction • Issue One – The foundation slab If the concrete dried unevenly, the slab would crack, thus seriously weaken the ability to support the building above. Therefore, they decided to pour the concrete all at the once, scheduling concrete trucks to arrive every 2,5 minutes for 52 hours, without a break. • Issue Two – The weather The Malaysian weather is susceptible to torrential rain, this is also problematic to the slab, as the concrete can get too wet, and become ruined. They covered the entire slab with canvas, the equivalent to 56 circus tents