SlideShare a Scribd company logo
1 of 45
Download to read offline
6. Project Schedule Management
“Mind Map”
3
• Essam Lotfi is ELV Projects Manager, Abu Dhabi, UAE, BSc. in
Electrical Engineering, Power Distribution through Zagazig
University, Egypt since 2001. Pursued and achieved his
certificates in Project Management (PMP®) from PMI-USA
since 2013, and certificate in Cost Management (CCP®) from
AACE International since june-2014.
• 16 years extensive hands on experience in various aspects of
projects and project management within maintenance, power
distribution networks monitoring and supervision and
construction projects as well.
• Authored, Co-Authored at PMWorld Library, PWLJ.
• Volunteered at PMI-Global Congress EMEA-2014 – Dubai, 5th
to 8th May 2014.
• Technical presentation at PMI-AGC 15th International
conference –Bahrain 19th to 21st January 2015.
• Technical presentation at 54th AACEi-SF Bay Annual Western
Winter Workshop, Lake Tahoe, Nevada, USA
• Technical presentation 55th AACEi-SF Bay Annual
Western Winter Workshop, Indian Wells, CA, USA
• Technical presentation 56th AACEi-SF Bay Annual
Western Winter Workshop, Indian Wells, CA, USA
• Independent Project Management and cost
engineering/Control Instructor.
ByEssamLotfy,PMP,CCP
6.1 Plan Schedule
management
Project management plan
Project Charter
Schedule Management plan
Expert Judgment
Tools & Techniques
Inputs
Outputs
OPA & EEF
Data Analysis
Project Schedule Management
Meetings
Who..? What..? When..? How..? How Much..?
XXXXXXX Management Plan
Scope Management Plan
Development Approach
6.1 Plan Schedule
management
Schedule Management plan
Outputs
It is a component of the project management plan that establishes
the criteria and the activities for developing, Monitoring & controlling
the schedule. The schedule management plan may be formal or
informal, highly detailed, or broadly framed based on the needs of
the project, and includes appropriate control thresholds.
Project schedule model development. The scheduling methodology and the scheduling tool to be used in
the development of the project schedule model are specified.
Release and iteration length. When using an adaptive life cycle, the time-boxed periods for releases,
waves, and iterations are specified. Time-boxed periods are durations during which the team works
steadily toward completion of a goal. Time-boxing helps to minimize scope creep as it forces the teams to
process essential features first, then other features when time permits.
Level of accuracy. The level of accuracy specifies the acceptable range used in determining realistic activity
duration estimates and may include an amount for contingencies.
Units of measure. such as staff hours, staff days, or weeks for time measures, or meters, liters, tons,
kilometers, or cubic yards for quantity measures is defined for each of the resources.
Organizational procedures links. The work breakdown structure (WBS) provides the framework for the
schedule management plan, allowing for consistency with the estimates and resulting schedules.
Rules of performance measurement. Earned value management (EVM) rules or other physical
measurement rules of performance measurement are set.
6.2 Define Activities
Project Management Plan
Scope Baseline
Activity List
Activity Attribute
Expert Judgment
Tools & Techniques
Inputs
Outputs
Milestones list
Decomposition
Rolling Wave Planning
Schedule Management plan
OPA & EEF
Meetings
PM plan Updates
Schedule Baseline
Cost Baseline
Change Requests
6.2 Define Activities
Activity List
Activity Attribute
Outputs
Milestones list
PM plan Updates
Schedule Baseline
Cost Baseline
Change Requests
Comprehensive list including all schedule activities to be performed
Significant point or event in the project:
- Mandatory which is required by the contract.
- Optional which is based upon project requirements.
Schedule baseline (sometimes referred to as a target baseline) is the
original approved project schedule, which is agreed by project
stakeholders before the project starts. ... It is a fixed measure which is
used as a planning yard mark against which the progress on the actual
project schedule can be measured.
Cost baseline is that part of the project baseline that handles the
amount of money the project is predicted to cost and on the other side
when that money will be spent. It is an approved budget usually in a
time distribution format used to estimate, monitor, and control the
overall cost performance of the project.
Activity (A) – Duration = XXS F
Activity (B) - Duration = YY
Activity (C) - Duration = ZZ
Summary Level – Rolling Up for Activities Duration & Logic
Activity (A) F
Activity (B)S
F S
Activity (A)S
Activity (B)S
S S
Activity (A) F
Activity (B) F
F F
Activity (A)S
Activity (B) F
S F
Successor
Predecessor
Activity (A) – Duration = XXS F
Activity (B) - Duration = YY
Activity (C) - Duration = ZZ
Summary Level – Rolling Up for Activities Duration & Logic
With the finish-to-start predecessor,
Activity A must be completed before
Activity B begins.
It is usually the default predecessor
type for modern project scheduling
software.
Activity (A) F
Activity (B)S
F S
Successor
Predecessor
Activity (A) – Duration = XXS F
Activity (B) - Duration = YY
Activity (C) - Duration = ZZ
Summary Level – Rolling Up for Activities Duration & Logic
With the finish-to-finish predecessor,
Activity B must finish by the time
Activity A is finished.
Use this predecessor when two or
more teams are developing
something, and all activity must finish
at the same time to be converged into
the total system.
Activity (A) F
Activity (B) F
F F
Successor
Predecessor
Activity (A) – Duration = XXS F
Activity (B) - Duration = YY
Activity (C) - Duration = ZZ
Summary Level – Rolling Up for Activities Duration & Logic
Under the start-to-start predecessor,
when Activity A starts, Activity B can
start.
Use this predecessor when multiple
activities can start simultaneously.
Activity (A)S
Activity (B)S
S S
Successor
Predecessor
Activity (A) – Duration = XXS F
Activity (B) - Duration = YY
Activity (C) - Duration = ZZ
Summary Level – Rolling Up for Activities Duration & Logic
Under the start-to-finish predecessor,
Activity B would start before Activity A
finishes.
You would use start-to-finish
predecessor in situations where the
new system must start before you
could finish (shutdown) the old
system.
One example that seems to be ideal
for this type predecessor is a project in
which you are creating a new system
to replace an existing system.
Activity (A)S
Activity (B) F
S F
Successor
Predecessor
Activity (A) – Duration = XXS F
Activity (B) - Duration = YY
Activity (C) - Duration = ZZ
Summary Level – Rolling Up for Activities Duration & Logic
Successor
Predecessor
Dependency Definition
Mandatory
(Hard Logic)
A constraint that must be completed before the subsequent items can start. You must
have the roof on before you can begin to apply shingles to it.
Discretionary
(Soft Logic)
A constraint that should be completed but is not absolutely required to be completed
before the subsequent items can start. You prefer but do not absolutely have to finish
System Testing before beginning User Acceptance Testing.
Internal
A mandatory or discretionary constraint that originates from within the project or
company. You have to wait for the power supply to complete the testing of the computer
you are designing.
External
A constraint put in place by something external to the project team or organization. The
city inspector must approve any construction before issuing a certification of occupancy
so the tenant can move in.
• The network diagram is a schematic of project activities.
• It shows how various activities are connected as a result of Sequence Activities.
• This diagram gives you a picture of how the work of the project will flow.
• It is also the tool used to evaluation schedule compression techniques such as crashing and fast
tracking.
B D
Start
CA
E
F
G Finish
• Sometimes called activity-on-node (AON), the precedence
diagramming method (PDM) is what most people use when they
use modern project management scheduling software. In this
method, the activity is in the box (sometimes called the node)
and the arrow connects the activities.
• Lead is an accelerant of an activity. You use a Lead when something
can begin before its predecessor is totally complete.
• Modification of logical relationship that allows an acceleration of
the successor activity. For example, in a Finish-to-Start dependency
with a ten day lead, the successor activity can start ten days before
the predecessor activity has finished.
• The negative lead is equal to positive lag.
• A Lag is a delay between activities. You use it where there is some
type of constraint in which something must wait before it can
continue.
• Modification of logical relationship that allows a delay of the
successor activity. For example, in a Finish-to-Start dependency with
a ten day lead, the successor activity can’t start until ten days after
the predecessor activity has finished.
6.3 Sequence Activities
Project Management Plan
Schedule Baseline
Project Schedule Network
Diagram
Project Document Update
Precedence diagramming method
Tools & Techniques
Inputs
Outputs
Activities list
Dependency Determination &
Integration
Project Documents
Activity attributes
Leads & Lags
Activity (A) – Duration = XXS F
Activity (B) - Duration = YY
Activity (C) - Duration = ZZ
Summary Level – Rolling Up for Activities Duration & Logic
Schedule Management plan
Assumptions log
Milestone list
OPA & EEF
Project Management Information
system Activity Attributes
Activities list
Assumptions log
Milestone List
Example of CPM- Precedence diagram
Example of CPM- Precedence diagram
Example of CPM- Precedence diagram
Example of CPM- Precedence diagram
Example of CPM- Precedence diagram
6.4 Estimate Activities Durations
Project Team Assignment
Resource Breakdown Structure
Durations Estimates
Basis of Estimates
Expert Judgment
Tools & Techniques
Inputs
Outputs
Analogous Estimate
Parametric Estimate
Meetings
Resource Requirements
Risk Register
EEF & OPA
Resource calendars
3 – Point Estimate
Decision making
Project Management Plan
Schedule Baseline
Activities list
Project Documents
Activity attributes
Schedule Management plan
Assumptions log
Lessons Learned Register
Milestone list
Bottom Up Estimate
Data Analysis
Alternative Analysis
Reserve Analysis
Project Documents Update
Activity Attributes
Assumptions Log
Lessons Learned Register
In many cases, the number of resources that are expected to be available
to accomplish an activity, along with the skill proficiency of those
resources, may determine the activity’s duration.
A change to a driving resource allocated to the activity will usually have
an effect on the duration, but this is not a simple “straight-line” or linear
relationship. Sometimes, the intrinsic nature of the work (i.e., constraints
imposed on the duration, effort involved, or number of resources) will
take a predetermined amount of time to complete regardless of the
resource allocation (e.g., a 24-hour stress test).
Law of diminishing returns. When one factor (e.g., resource) used
to determine the effort required to produce a unit of work is
increased while all other factors remain fixed, a point will
eventually be reached at which additions of that one factor start to
yield progressively smaller or diminishing increases in output.
Number of resources. Increasing the number of resources to twice the original number of the resources
does not always reduce the time by half, as it may increase extra duration due to risk, and at some
point adding too many resources to the activity may increase duration due to knowledge transfer,
learning curve, additional coordination, and other factors involved.
Advances in technology. This may also play an important role in determining duration estimates.
Motivation of staff. The project manager also needs to be aware of Student Syndrome—or
procrastination— when people start to apply themselves only at the last possible moment before the
deadline, and Parkinson’s Law where work expands to fill the time available for its completion.
Analogous Estimate
Tools &
Techniques
Parametric Estimate
3 – Point Estimate
Bottom Up Estimate
 Using the actual duration of a previous similar schedule activity as the
basis for estimating the duration of future activity.
 Generally less costly and less time consuming.
 Less accurate.
 Estimating the basis of activity durations can be quantitatively
determined by multiplying the quantity of the work to be performed
by the productivity rates.
• Parametric estimating uses a statistical relationship between historical
data and other variables (e.g., square footage in construction).
• higher levels of accuracy depending on the sophistication and
underlying data built into the model.
• The accuracy of single-point duration estimates may be improved by
considering estimation uncertainty and risk. Using three-point
estimates helps define an approximate range for an activity’s duration:
• Most Likely (tM)
• Optimistic (tO)
• Pessimistic (tP)
• tE = (tO + tM + tP) /3 Triangular Distribution
• A method of estimating project duration or cost by aggregating the
estimates of the lower level components of the WBS.
• These estimates are then aggregated into a total quantity for each of
the activity’s durations.
• Activities may or may not have dependencies between them that can
affect the application and use of resources. If there are dependencies,
this pattern of resource usage is reflected and documented in the
estimated requirements of the activity.
Durations Estimates
Basis of Estimates
Outputs
Duration estimates are quantitative assessments of the likely number of
time periods that are required to complete an activity, a phase, or a
project. Duration estimates do not include any lags as described in Section
6.3.2.3. Duration estimates may include some indication of the range of
possible results. For example:
• A range of 2 weeks ± 2 days, which indicates that the activity will take
at least 8 days and not more than 12 (assuming a 5-day work week); or
• A 15% probability of exceeding 3 weeks, which indicates a high
probability—85%—that the activity will take 3 weeks or less.
Supporting detail for duration estimates may include:
• Documentation of the basis of the estimate (i.e., how it was
developed),
• Documentation of all assumptions made,
• Documentation of any known constraints,
• Indication of the range of possible estimates (e.g., ±10%) to indicate
that the duration is estimated between a range of values),
• Indication of the confidence level of the final estimate, and
• Documentation of individual project risks influencing this estimate.
6.5 Develop Schedule
Project Schedule Network Diagrams
Project Team Assignments
Schedule Baseline
Project Schedule
Schedule Network Analysis
Tools & Techniques
Inputs
Outputs
Critical Path Method
Resource Optimization
AGILE RELEASE PLANNING
Resource Requirements
Risk Register
Agreements
Resource calendars
Data Analysis
Project Management Information
System
Project Management Plan
Schedule Baseline
Activities list
Project Documents
Activity attributes
Schedule Management plan
Assumptions log
Lessons Learned Register
Milestone list
What-If Scenario Analysis
Simulation
Leads & Lags
Schedule Compression
Schedule Data
Change Requests
Project Management Plan updates
Schedule Management Plan
Basis of Estimates
Duration Estimates
EEF & OPA
Cost Baseline
Assumptions Log
Project Documents
Updates
Activity attributes
Duration Estimates
Lessons Learned Register
Resource Requirements
Risk Register
Schedule Network Analysis
Tools & Techniques
Critical Path Method
Resource Optimization
AGILE RELEASE PLANNING
Data Analysis
Project Management Information
System
What-If Scenario Analysis
Simulation
Leads & Lags
Schedule Compression
• It includes several techniques to project schedule model:
• Critical Path Method.
• Resource Optimization.
• Modeling Techniques.
• Additional Analysis, such as but not limited to; Divergence &
Convergence.
• Examine the Risk levels on Critical Path.
• Implementation of Risk Responses to reduce the risk on Critical
Path.
• Critical Path Method:
• Planning the Project so that it is completed as quickly as possible.
• Identifying the activities where a delay in their execution will
affect the overall end.
• Critical path is the longest sequence of dependent activities that
leads to completion of tasks.
• Critical Path is the longest path with minimum project
possible duration.
• Resource Optimization:
• Resource Leveling.
• Resource Smoothing.
• CPM Pointers:
– Used with scheduling environments where a:
• Forward Pass is used to establish the earliest the activities can start (ES) and finish (EF)
• Backward Pass is used to establish the latest the activities can start (LS) and finish (LF)
– Allows the calculation of the critical path and the amount of slack on each activity
– Any activity on the critical path typically has zero slack
– A negative slack is possible if the project is behind schedule
– Activities on the critical path are the ones the Project Manager should put more focus on
Critical Path Method
• Slack (Also Known as Float)
– Slack is the amount of time that an activity can slip or be delayed without delaying the finish
date of the project .
– If an activity has no slack, it is on the critical path Negative or positive float can also exist.
This float is a scenario in which the project’s actual finish date extends past a targeted finish
date, or the project’s actual finish date comes before the targeted finish date.
– Free Slack: The amount of time that an activity can be delayed without delaying the
successor activity. This is calculated by subtracting EF+1 of the current activity from the ES of
the successor activity.
– Total Slack: It is the latest an activity can start without delaying the project finish date or
violating a schedule constraint. Total Slack (Float) does not get added together for the path,
but float is shared across the path.
– Project Slack: The amount of time something can be delayed without delaying the published
finish date. Note that it could be different from what the project is privately anticipating.
Start
A
B
C
D
E
F
G Finish
4
5
4
2 1
6
5
Critical Path Method
Activity Preceding Duration
in Days
A Start 4
B Start 5
C A 4
D B 2
E C, D 6
F D 1
G E, F 5
• What are the different paths and time?
• Path A,C,E,G Duration of 19
• Path B,D,E,G Duration of 18
• Path B,D,F,G Duration of 13
• What is the critical path?
• Path A,C,E,G Duration of 19
Schedule Network Analysis
Tools & Techniques
Critical Path Method
Resource Optimization
AGILE RELEASE PLANNING
Data Analysis
Project Management Information
System
What-If Scenario Analysis
Simulation
Leads & Lags
Schedule Compression
• What-if scenario analysis is the process of evaluating scenarios in
order to predict their effect, positive or negative, on project
objectives.
• This is an analysis of the question, “What if the situation represented
by scenario X happens?” A schedule network analysis is performed
using the schedule to compute the different scenarios, such as
delaying a major component delivery, extending specific engineering
durations, or introducing external factors, such as a strike or a change
in the permit process.
• The outcome of the what-if scenario analysis can be used to assess the
feasibility of the project schedule under different conditions, and in
preparing schedule reserves and response plans to address the impact
of unexpected situations.
• Simulation models the combined effects of individual project risks and
other sources of uncertainty to evaluate their potential impact on
achieving project objectives.
• The most common simulation technique is Monte Carlo analysis ,in
which risks and other sources of uncertainty are used to calculate
possible schedule outcomes for the total project.
• Simulation involves calculating multiple work package durations with
different sets of activity assumptions, constraints, risks, issues, or
scenarios using probability distributions and other representations of
uncertainty.
Schedule Network Analysis
Tools & Techniques
Critical Path Method
Resource Optimization
AGILE RELEASE PLANNING
Data Analysis
Project Management Information
System
What-If Scenario Analysis
Simulation
Leads & Lags
Schedule Compression
• Lead is an accelerant of an activity. You use a Lead when something
can begin before its predecessor is totally complete.
• Modification of logical relationship that allows an acceleration of the
successor activity. For example, in a Finish-to-Start dependency with a
ten day lead, the successor activity can start ten days before the
predecessor activity has finished.
• The negative lead is equal to positive lag.
• A Lag is a delay between activities. You use it where there is some type
of constraint in which something must wait before it can continue.
• Modification of logical relationship that allows a delay of the successor
activity. For example, in a Finish-to-Start dependency with a ten day
lead, the successor activity can’t start until ten days after the
predecessor activity has finished.
Technique
Characteristics
Key Cost Quality Additional
Crashing
Putting more
resources on
Critical Path
activities
Usually
increases
Cost
Minimal risk
exposure
(compared to
fast tracking)
Think of this as crashing a party. You
have more people than originally
planned.
Fast
Tracking
Do activities
in parallel that
would
normally be in
sequence
Flexible, but
increase cost
from
potential
rework
Additional risk
exposure
because of
possible rework
Can require additional communication
to coordinate activities
Schedule Network Analysis
Tools & Techniques
Critical Path Method
Resource Optimization
AGILE RELEASE PLANNING
Data Analysis
Project Management Information
System
What-If Scenario Analysis
Simulation
Leads & Lags
Schedule Compression
• Agile release planning provides a high-level summary timeline of the
release schedule (typically 3 to 6 months) based on the product
roadmap and the product vision for the product’s evolution.
• Agile release planning also determines the number of iterations or
sprints in the release, and allows the product owner and team to
decide how much needs to be developed and how long it will take to
have a releasable product based on business goals, dependencies, and
impediments.
• Since features represent value to the customer, the timeline provides a
more easily understood project schedule as it defines which feature
will be available at the end of each iteration, which is exactly the
depth of information the customer is looking for.
Schedule Baseline
Project Schedule
Outputs
 A schedule baseline is the approved version of a schedule model that
can be changed only through formal change control procedures and is
used as a basis for comparison to actual results.
• The project schedule is an output of a schedule model that presents
linked activities with planned dates, durations, milestones, and
resources. At a minimum, the project schedule includes a planned
start date and planned finish date for each activity.
6.6 Control Schedule
Project Schedule
Resource calendars
Work Performance Information's
Schedule Forecast
Data Analysis
Tools & Techniques
Inputs
Outputs
Earned Value Analysis
Iteration Burn Down Chart
Leads & Lags
Work Performance Data
Schedule Data
Trend Analysis
Project Management Information
System
Project Management Plan
Schedule Baseline
Project Documents
Scope Baseline
Performance Measurement Baseline
Schedule Management plan
Lessons Learned Register
Project Calendars
Variance Analysis
What If Scenario
Critical Path Method
Schedule Compression
Change Requests
Project Management Plan updates
Schedule Management Plan
Schedule Baseline
OPA
Cost Baseline
Basis of Estimates
Project Documents
Updates
Assumptions Log
Lessons Learned Register
Project Schedule
Resource Calendars
Risk Register
Recourse Optimization
Performance Measurements
Baseline
Schedule Data
• Control Schedule Considered as a part of Perform Integrated Change Control Process to:
– Determining the current status of the project schedule
– Influencing the factors that create schedule changes
– Reconsidering necessary schedule reserves
– Determining if the project schedule has changed
– Managing the actual changes if they occur
Control Schedule
• Determining the current status of the project schedule by comparing the total amount of work
delivered and accepted against the estimates of work completed for the elapsed time cycle
• Conducting retrospectives (scheduled reviews to record lessons learned) for correcting processes
and improving, if required
• Reprioritizing the remaining work plan (backlog)
• Determining the rate at which the deliverables are produced, validated, and accepted (velocity)
in the given time per iteration (agreed-upon work cycle duration, typically 2 weeks or 1 month)
• Determining that the project schedule has changed
• Managing the actual changes as they occur
If Agile Approach is used, Control schedule is concerned with:
Earned Value Analysis
Earned Value Analysis Provides organizations with the methodology needed to integrate
the management of project Scope, Schedule & cost, EVM can play a critical role in
answering management questions that are critical to the success of every project
Are we Ahead or behind schedule..?
How efficiency are we using our time ..?
When is the project likely to be completed ..?
Are we currently under or over our budget..?
How efficient are we using our resources..?
What is the remaining work likely to cost..?
What is the entire project likely to cost..?
How much the project will be under or over budget
at the end ..?
If the application of EVM to a
project reveals that the project is
behind schedule or over budget,
the project manager can use the
EVM methodology to help
identify
Where the problems are
occurring..?
Whether the problems are critical or
not..?
What it will take to get the project
back on track..?
Tools & Techniques
Iteration Burn down Chart
A burn down chart is a graphical representation of work left to do versus time. The outstanding work
(or backlog) is often on the vertical axis, with time along the horizontal. That is, it is a run chart of
outstanding work. It is useful for predicting when all of the work will be completed.
Analyze the variance with respect to an ideal burn down based on the work committed from iteration planning
Forecast trend line can be used to predict the likely variance at iteration completion and take appropriate actions
Trend line is then calculated to forecast completion based on remaining work
Tools & Techniques
Diagonal line representing the ideal burn down and daily actual remaining work is then plotted
WE COMPLETED SCHEDULE
MANAGEMENT
IT IS TIME TO REST…….

More Related Content

What's hot

Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Operation mangement vs project management
Operation mangement vs project managementOperation mangement vs project management
Operation mangement vs project managementJeet Manojit
 
مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةM Maged Hegazy, LLM, MBA, CCP, P3O
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Managing Project Execution
Managing Project ExecutionManaging Project Execution
Managing Project Executionpajames36
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
Presentation project management
Presentation project managementPresentation project management
Presentation project managementFlobz Caloy
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 

What's hot (20)

Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Operation mangement vs project management
Operation mangement vs project managementOperation mangement vs project management
Operation mangement vs project management
 
مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافية
 
Project Management
Project ManagementProject Management
Project Management
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Managing Project Execution
Managing Project ExecutionManaging Project Execution
Managing Project Execution
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
MS Project
MS Project MS Project
MS Project
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Presentation project management
Presentation project managementPresentation project management
Presentation project management
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Different project management methodologies
Different project management methodologiesDifferent project management methodologies
Different project management methodologies
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 

Similar to Introduction to schedule management

Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.pptUtkarshDwivedi74
 
Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have SusanaFurman449
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec domsBabasab Patil
 
Agile scope creep and the Golden Ratio – Balancing Project Flexibility and Co...
Agile scope creep and the Golden Ratio – Balancing Project Flexibility and Co...Agile scope creep and the Golden Ratio – Balancing Project Flexibility and Co...
Agile scope creep and the Golden Ratio – Balancing Project Flexibility and Co...Pragmatic Cohesion Consulting, LLC
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 

Similar to Introduction to schedule management (20)

6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
Project Management
Project Management Project Management
Project Management
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.ppt
 
Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
 
Agile scope creep and the Golden Ratio – Balancing Project Flexibility and Co...
Agile scope creep and the Golden Ratio – Balancing Project Flexibility and Co...Agile scope creep and the Golden Ratio – Balancing Project Flexibility and Co...
Agile scope creep and the Golden Ratio – Balancing Project Flexibility and Co...
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 

More from Essam Lotffy, PMP®, CCP®

Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plansEssam Lotffy, PMP®, CCP®
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projectsEssam Lotffy, PMP®, CCP®
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalEssam Lotffy, PMP®, CCP®
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEssam Lotffy, PMP®, CCP®
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Essam Lotffy, PMP®, CCP®
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Essam Lotffy, PMP®, CCP®
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEssam Lotffy, PMP®, CCP®
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period Essam Lotffy, PMP®, CCP®
 

More from Essam Lotffy, PMP®, CCP® (18)

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Sample cosntructability report Template
Sample cosntructability report Template Sample cosntructability report Template
Sample cosntructability report Template
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.final
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
 

Recently uploaded

Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 

Recently uploaded (20)

Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 

Introduction to schedule management

  • 1.
  • 2. 6. Project Schedule Management “Mind Map”
  • 3. 3 • Essam Lotfi is ELV Projects Manager, Abu Dhabi, UAE, BSc. in Electrical Engineering, Power Distribution through Zagazig University, Egypt since 2001. Pursued and achieved his certificates in Project Management (PMP®) from PMI-USA since 2013, and certificate in Cost Management (CCP®) from AACE International since june-2014. • 16 years extensive hands on experience in various aspects of projects and project management within maintenance, power distribution networks monitoring and supervision and construction projects as well. • Authored, Co-Authored at PMWorld Library, PWLJ. • Volunteered at PMI-Global Congress EMEA-2014 – Dubai, 5th to 8th May 2014. • Technical presentation at PMI-AGC 15th International conference –Bahrain 19th to 21st January 2015. • Technical presentation at 54th AACEi-SF Bay Annual Western Winter Workshop, Lake Tahoe, Nevada, USA • Technical presentation 55th AACEi-SF Bay Annual Western Winter Workshop, Indian Wells, CA, USA • Technical presentation 56th AACEi-SF Bay Annual Western Winter Workshop, Indian Wells, CA, USA • Independent Project Management and cost engineering/Control Instructor. ByEssamLotfy,PMP,CCP
  • 4.
  • 5. 6.1 Plan Schedule management Project management plan Project Charter Schedule Management plan Expert Judgment Tools & Techniques Inputs Outputs OPA & EEF Data Analysis Project Schedule Management Meetings Who..? What..? When..? How..? How Much..? XXXXXXX Management Plan Scope Management Plan Development Approach
  • 6.
  • 7. 6.1 Plan Schedule management Schedule Management plan Outputs It is a component of the project management plan that establishes the criteria and the activities for developing, Monitoring & controlling the schedule. The schedule management plan may be formal or informal, highly detailed, or broadly framed based on the needs of the project, and includes appropriate control thresholds. Project schedule model development. The scheduling methodology and the scheduling tool to be used in the development of the project schedule model are specified. Release and iteration length. When using an adaptive life cycle, the time-boxed periods for releases, waves, and iterations are specified. Time-boxed periods are durations during which the team works steadily toward completion of a goal. Time-boxing helps to minimize scope creep as it forces the teams to process essential features first, then other features when time permits. Level of accuracy. The level of accuracy specifies the acceptable range used in determining realistic activity duration estimates and may include an amount for contingencies. Units of measure. such as staff hours, staff days, or weeks for time measures, or meters, liters, tons, kilometers, or cubic yards for quantity measures is defined for each of the resources. Organizational procedures links. The work breakdown structure (WBS) provides the framework for the schedule management plan, allowing for consistency with the estimates and resulting schedules. Rules of performance measurement. Earned value management (EVM) rules or other physical measurement rules of performance measurement are set.
  • 8. 6.2 Define Activities Project Management Plan Scope Baseline Activity List Activity Attribute Expert Judgment Tools & Techniques Inputs Outputs Milestones list Decomposition Rolling Wave Planning Schedule Management plan OPA & EEF Meetings PM plan Updates Schedule Baseline Cost Baseline Change Requests
  • 9. 6.2 Define Activities Activity List Activity Attribute Outputs Milestones list PM plan Updates Schedule Baseline Cost Baseline Change Requests Comprehensive list including all schedule activities to be performed Significant point or event in the project: - Mandatory which is required by the contract. - Optional which is based upon project requirements. Schedule baseline (sometimes referred to as a target baseline) is the original approved project schedule, which is agreed by project stakeholders before the project starts. ... It is a fixed measure which is used as a planning yard mark against which the progress on the actual project schedule can be measured. Cost baseline is that part of the project baseline that handles the amount of money the project is predicted to cost and on the other side when that money will be spent. It is an approved budget usually in a time distribution format used to estimate, monitor, and control the overall cost performance of the project.
  • 10. Activity (A) – Duration = XXS F Activity (B) - Duration = YY Activity (C) - Duration = ZZ Summary Level – Rolling Up for Activities Duration & Logic Activity (A) F Activity (B)S F S Activity (A)S Activity (B)S S S Activity (A) F Activity (B) F F F Activity (A)S Activity (B) F S F Successor Predecessor
  • 11. Activity (A) – Duration = XXS F Activity (B) - Duration = YY Activity (C) - Duration = ZZ Summary Level – Rolling Up for Activities Duration & Logic With the finish-to-start predecessor, Activity A must be completed before Activity B begins. It is usually the default predecessor type for modern project scheduling software. Activity (A) F Activity (B)S F S Successor Predecessor
  • 12. Activity (A) – Duration = XXS F Activity (B) - Duration = YY Activity (C) - Duration = ZZ Summary Level – Rolling Up for Activities Duration & Logic With the finish-to-finish predecessor, Activity B must finish by the time Activity A is finished. Use this predecessor when two or more teams are developing something, and all activity must finish at the same time to be converged into the total system. Activity (A) F Activity (B) F F F Successor Predecessor
  • 13. Activity (A) – Duration = XXS F Activity (B) - Duration = YY Activity (C) - Duration = ZZ Summary Level – Rolling Up for Activities Duration & Logic Under the start-to-start predecessor, when Activity A starts, Activity B can start. Use this predecessor when multiple activities can start simultaneously. Activity (A)S Activity (B)S S S Successor Predecessor
  • 14. Activity (A) – Duration = XXS F Activity (B) - Duration = YY Activity (C) - Duration = ZZ Summary Level – Rolling Up for Activities Duration & Logic Under the start-to-finish predecessor, Activity B would start before Activity A finishes. You would use start-to-finish predecessor in situations where the new system must start before you could finish (shutdown) the old system. One example that seems to be ideal for this type predecessor is a project in which you are creating a new system to replace an existing system. Activity (A)S Activity (B) F S F Successor Predecessor
  • 15. Activity (A) – Duration = XXS F Activity (B) - Duration = YY Activity (C) - Duration = ZZ Summary Level – Rolling Up for Activities Duration & Logic Successor Predecessor Dependency Definition Mandatory (Hard Logic) A constraint that must be completed before the subsequent items can start. You must have the roof on before you can begin to apply shingles to it. Discretionary (Soft Logic) A constraint that should be completed but is not absolutely required to be completed before the subsequent items can start. You prefer but do not absolutely have to finish System Testing before beginning User Acceptance Testing. Internal A mandatory or discretionary constraint that originates from within the project or company. You have to wait for the power supply to complete the testing of the computer you are designing. External A constraint put in place by something external to the project team or organization. The city inspector must approve any construction before issuing a certification of occupancy so the tenant can move in.
  • 16. • The network diagram is a schematic of project activities. • It shows how various activities are connected as a result of Sequence Activities. • This diagram gives you a picture of how the work of the project will flow. • It is also the tool used to evaluation schedule compression techniques such as crashing and fast tracking.
  • 17. B D Start CA E F G Finish • Sometimes called activity-on-node (AON), the precedence diagramming method (PDM) is what most people use when they use modern project management scheduling software. In this method, the activity is in the box (sometimes called the node) and the arrow connects the activities.
  • 18. • Lead is an accelerant of an activity. You use a Lead when something can begin before its predecessor is totally complete. • Modification of logical relationship that allows an acceleration of the successor activity. For example, in a Finish-to-Start dependency with a ten day lead, the successor activity can start ten days before the predecessor activity has finished. • The negative lead is equal to positive lag. • A Lag is a delay between activities. You use it where there is some type of constraint in which something must wait before it can continue. • Modification of logical relationship that allows a delay of the successor activity. For example, in a Finish-to-Start dependency with a ten day lead, the successor activity can’t start until ten days after the predecessor activity has finished.
  • 19. 6.3 Sequence Activities Project Management Plan Schedule Baseline Project Schedule Network Diagram Project Document Update Precedence diagramming method Tools & Techniques Inputs Outputs Activities list Dependency Determination & Integration Project Documents Activity attributes Leads & Lags Activity (A) – Duration = XXS F Activity (B) - Duration = YY Activity (C) - Duration = ZZ Summary Level – Rolling Up for Activities Duration & Logic Schedule Management plan Assumptions log Milestone list OPA & EEF Project Management Information system Activity Attributes Activities list Assumptions log Milestone List
  • 20.
  • 21. Example of CPM- Precedence diagram
  • 22. Example of CPM- Precedence diagram
  • 23. Example of CPM- Precedence diagram
  • 24. Example of CPM- Precedence diagram
  • 25. Example of CPM- Precedence diagram
  • 26. 6.4 Estimate Activities Durations Project Team Assignment Resource Breakdown Structure Durations Estimates Basis of Estimates Expert Judgment Tools & Techniques Inputs Outputs Analogous Estimate Parametric Estimate Meetings Resource Requirements Risk Register EEF & OPA Resource calendars 3 – Point Estimate Decision making Project Management Plan Schedule Baseline Activities list Project Documents Activity attributes Schedule Management plan Assumptions log Lessons Learned Register Milestone list Bottom Up Estimate Data Analysis Alternative Analysis Reserve Analysis Project Documents Update Activity Attributes Assumptions Log Lessons Learned Register
  • 27.
  • 28. In many cases, the number of resources that are expected to be available to accomplish an activity, along with the skill proficiency of those resources, may determine the activity’s duration. A change to a driving resource allocated to the activity will usually have an effect on the duration, but this is not a simple “straight-line” or linear relationship. Sometimes, the intrinsic nature of the work (i.e., constraints imposed on the duration, effort involved, or number of resources) will take a predetermined amount of time to complete regardless of the resource allocation (e.g., a 24-hour stress test). Law of diminishing returns. When one factor (e.g., resource) used to determine the effort required to produce a unit of work is increased while all other factors remain fixed, a point will eventually be reached at which additions of that one factor start to yield progressively smaller or diminishing increases in output. Number of resources. Increasing the number of resources to twice the original number of the resources does not always reduce the time by half, as it may increase extra duration due to risk, and at some point adding too many resources to the activity may increase duration due to knowledge transfer, learning curve, additional coordination, and other factors involved. Advances in technology. This may also play an important role in determining duration estimates. Motivation of staff. The project manager also needs to be aware of Student Syndrome—or procrastination— when people start to apply themselves only at the last possible moment before the deadline, and Parkinson’s Law where work expands to fill the time available for its completion.
  • 29. Analogous Estimate Tools & Techniques Parametric Estimate 3 – Point Estimate Bottom Up Estimate  Using the actual duration of a previous similar schedule activity as the basis for estimating the duration of future activity.  Generally less costly and less time consuming.  Less accurate.  Estimating the basis of activity durations can be quantitatively determined by multiplying the quantity of the work to be performed by the productivity rates. • Parametric estimating uses a statistical relationship between historical data and other variables (e.g., square footage in construction). • higher levels of accuracy depending on the sophistication and underlying data built into the model. • The accuracy of single-point duration estimates may be improved by considering estimation uncertainty and risk. Using three-point estimates helps define an approximate range for an activity’s duration: • Most Likely (tM) • Optimistic (tO) • Pessimistic (tP) • tE = (tO + tM + tP) /3 Triangular Distribution • A method of estimating project duration or cost by aggregating the estimates of the lower level components of the WBS. • These estimates are then aggregated into a total quantity for each of the activity’s durations. • Activities may or may not have dependencies between them that can affect the application and use of resources. If there are dependencies, this pattern of resource usage is reflected and documented in the estimated requirements of the activity.
  • 30. Durations Estimates Basis of Estimates Outputs Duration estimates are quantitative assessments of the likely number of time periods that are required to complete an activity, a phase, or a project. Duration estimates do not include any lags as described in Section 6.3.2.3. Duration estimates may include some indication of the range of possible results. For example: • A range of 2 weeks ± 2 days, which indicates that the activity will take at least 8 days and not more than 12 (assuming a 5-day work week); or • A 15% probability of exceeding 3 weeks, which indicates a high probability—85%—that the activity will take 3 weeks or less. Supporting detail for duration estimates may include: • Documentation of the basis of the estimate (i.e., how it was developed), • Documentation of all assumptions made, • Documentation of any known constraints, • Indication of the range of possible estimates (e.g., ±10%) to indicate that the duration is estimated between a range of values), • Indication of the confidence level of the final estimate, and • Documentation of individual project risks influencing this estimate.
  • 31. 6.5 Develop Schedule Project Schedule Network Diagrams Project Team Assignments Schedule Baseline Project Schedule Schedule Network Analysis Tools & Techniques Inputs Outputs Critical Path Method Resource Optimization AGILE RELEASE PLANNING Resource Requirements Risk Register Agreements Resource calendars Data Analysis Project Management Information System Project Management Plan Schedule Baseline Activities list Project Documents Activity attributes Schedule Management plan Assumptions log Lessons Learned Register Milestone list What-If Scenario Analysis Simulation Leads & Lags Schedule Compression Schedule Data Change Requests Project Management Plan updates Schedule Management Plan Basis of Estimates Duration Estimates EEF & OPA Cost Baseline Assumptions Log Project Documents Updates Activity attributes Duration Estimates Lessons Learned Register Resource Requirements Risk Register
  • 32.
  • 33. Schedule Network Analysis Tools & Techniques Critical Path Method Resource Optimization AGILE RELEASE PLANNING Data Analysis Project Management Information System What-If Scenario Analysis Simulation Leads & Lags Schedule Compression • It includes several techniques to project schedule model: • Critical Path Method. • Resource Optimization. • Modeling Techniques. • Additional Analysis, such as but not limited to; Divergence & Convergence. • Examine the Risk levels on Critical Path. • Implementation of Risk Responses to reduce the risk on Critical Path. • Critical Path Method: • Planning the Project so that it is completed as quickly as possible. • Identifying the activities where a delay in their execution will affect the overall end. • Critical path is the longest sequence of dependent activities that leads to completion of tasks. • Critical Path is the longest path with minimum project possible duration. • Resource Optimization: • Resource Leveling. • Resource Smoothing.
  • 34. • CPM Pointers: – Used with scheduling environments where a: • Forward Pass is used to establish the earliest the activities can start (ES) and finish (EF) • Backward Pass is used to establish the latest the activities can start (LS) and finish (LF) – Allows the calculation of the critical path and the amount of slack on each activity – Any activity on the critical path typically has zero slack – A negative slack is possible if the project is behind schedule – Activities on the critical path are the ones the Project Manager should put more focus on Critical Path Method • Slack (Also Known as Float) – Slack is the amount of time that an activity can slip or be delayed without delaying the finish date of the project . – If an activity has no slack, it is on the critical path Negative or positive float can also exist. This float is a scenario in which the project’s actual finish date extends past a targeted finish date, or the project’s actual finish date comes before the targeted finish date. – Free Slack: The amount of time that an activity can be delayed without delaying the successor activity. This is calculated by subtracting EF+1 of the current activity from the ES of the successor activity. – Total Slack: It is the latest an activity can start without delaying the project finish date or violating a schedule constraint. Total Slack (Float) does not get added together for the path, but float is shared across the path. – Project Slack: The amount of time something can be delayed without delaying the published finish date. Note that it could be different from what the project is privately anticipating.
  • 35. Start A B C D E F G Finish 4 5 4 2 1 6 5 Critical Path Method Activity Preceding Duration in Days A Start 4 B Start 5 C A 4 D B 2 E C, D 6 F D 1 G E, F 5 • What are the different paths and time? • Path A,C,E,G Duration of 19 • Path B,D,E,G Duration of 18 • Path B,D,F,G Duration of 13 • What is the critical path? • Path A,C,E,G Duration of 19
  • 36. Schedule Network Analysis Tools & Techniques Critical Path Method Resource Optimization AGILE RELEASE PLANNING Data Analysis Project Management Information System What-If Scenario Analysis Simulation Leads & Lags Schedule Compression • What-if scenario analysis is the process of evaluating scenarios in order to predict their effect, positive or negative, on project objectives. • This is an analysis of the question, “What if the situation represented by scenario X happens?” A schedule network analysis is performed using the schedule to compute the different scenarios, such as delaying a major component delivery, extending specific engineering durations, or introducing external factors, such as a strike or a change in the permit process. • The outcome of the what-if scenario analysis can be used to assess the feasibility of the project schedule under different conditions, and in preparing schedule reserves and response plans to address the impact of unexpected situations. • Simulation models the combined effects of individual project risks and other sources of uncertainty to evaluate their potential impact on achieving project objectives. • The most common simulation technique is Monte Carlo analysis ,in which risks and other sources of uncertainty are used to calculate possible schedule outcomes for the total project. • Simulation involves calculating multiple work package durations with different sets of activity assumptions, constraints, risks, issues, or scenarios using probability distributions and other representations of uncertainty.
  • 37. Schedule Network Analysis Tools & Techniques Critical Path Method Resource Optimization AGILE RELEASE PLANNING Data Analysis Project Management Information System What-If Scenario Analysis Simulation Leads & Lags Schedule Compression • Lead is an accelerant of an activity. You use a Lead when something can begin before its predecessor is totally complete. • Modification of logical relationship that allows an acceleration of the successor activity. For example, in a Finish-to-Start dependency with a ten day lead, the successor activity can start ten days before the predecessor activity has finished. • The negative lead is equal to positive lag. • A Lag is a delay between activities. You use it where there is some type of constraint in which something must wait before it can continue. • Modification of logical relationship that allows a delay of the successor activity. For example, in a Finish-to-Start dependency with a ten day lead, the successor activity can’t start until ten days after the predecessor activity has finished. Technique Characteristics Key Cost Quality Additional Crashing Putting more resources on Critical Path activities Usually increases Cost Minimal risk exposure (compared to fast tracking) Think of this as crashing a party. You have more people than originally planned. Fast Tracking Do activities in parallel that would normally be in sequence Flexible, but increase cost from potential rework Additional risk exposure because of possible rework Can require additional communication to coordinate activities
  • 38. Schedule Network Analysis Tools & Techniques Critical Path Method Resource Optimization AGILE RELEASE PLANNING Data Analysis Project Management Information System What-If Scenario Analysis Simulation Leads & Lags Schedule Compression • Agile release planning provides a high-level summary timeline of the release schedule (typically 3 to 6 months) based on the product roadmap and the product vision for the product’s evolution. • Agile release planning also determines the number of iterations or sprints in the release, and allows the product owner and team to decide how much needs to be developed and how long it will take to have a releasable product based on business goals, dependencies, and impediments. • Since features represent value to the customer, the timeline provides a more easily understood project schedule as it defines which feature will be available at the end of each iteration, which is exactly the depth of information the customer is looking for.
  • 39. Schedule Baseline Project Schedule Outputs  A schedule baseline is the approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results. • The project schedule is an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources. At a minimum, the project schedule includes a planned start date and planned finish date for each activity.
  • 40. 6.6 Control Schedule Project Schedule Resource calendars Work Performance Information's Schedule Forecast Data Analysis Tools & Techniques Inputs Outputs Earned Value Analysis Iteration Burn Down Chart Leads & Lags Work Performance Data Schedule Data Trend Analysis Project Management Information System Project Management Plan Schedule Baseline Project Documents Scope Baseline Performance Measurement Baseline Schedule Management plan Lessons Learned Register Project Calendars Variance Analysis What If Scenario Critical Path Method Schedule Compression Change Requests Project Management Plan updates Schedule Management Plan Schedule Baseline OPA Cost Baseline Basis of Estimates Project Documents Updates Assumptions Log Lessons Learned Register Project Schedule Resource Calendars Risk Register Recourse Optimization Performance Measurements Baseline Schedule Data
  • 41.
  • 42. • Control Schedule Considered as a part of Perform Integrated Change Control Process to: – Determining the current status of the project schedule – Influencing the factors that create schedule changes – Reconsidering necessary schedule reserves – Determining if the project schedule has changed – Managing the actual changes if they occur Control Schedule • Determining the current status of the project schedule by comparing the total amount of work delivered and accepted against the estimates of work completed for the elapsed time cycle • Conducting retrospectives (scheduled reviews to record lessons learned) for correcting processes and improving, if required • Reprioritizing the remaining work plan (backlog) • Determining the rate at which the deliverables are produced, validated, and accepted (velocity) in the given time per iteration (agreed-upon work cycle duration, typically 2 weeks or 1 month) • Determining that the project schedule has changed • Managing the actual changes as they occur If Agile Approach is used, Control schedule is concerned with:
  • 43. Earned Value Analysis Earned Value Analysis Provides organizations with the methodology needed to integrate the management of project Scope, Schedule & cost, EVM can play a critical role in answering management questions that are critical to the success of every project Are we Ahead or behind schedule..? How efficiency are we using our time ..? When is the project likely to be completed ..? Are we currently under or over our budget..? How efficient are we using our resources..? What is the remaining work likely to cost..? What is the entire project likely to cost..? How much the project will be under or over budget at the end ..? If the application of EVM to a project reveals that the project is behind schedule or over budget, the project manager can use the EVM methodology to help identify Where the problems are occurring..? Whether the problems are critical or not..? What it will take to get the project back on track..? Tools & Techniques
  • 44. Iteration Burn down Chart A burn down chart is a graphical representation of work left to do versus time. The outstanding work (or backlog) is often on the vertical axis, with time along the horizontal. That is, it is a run chart of outstanding work. It is useful for predicting when all of the work will be completed. Analyze the variance with respect to an ideal burn down based on the work committed from iteration planning Forecast trend line can be used to predict the likely variance at iteration completion and take appropriate actions Trend line is then calculated to forecast completion based on remaining work Tools & Techniques Diagonal line representing the ideal burn down and daily actual remaining work is then plotted
  • 45. WE COMPLETED SCHEDULE MANAGEMENT IT IS TIME TO REST…….