Rehabilitation of the Urban Water Supply and Sanitation in the Sava River Basin in Bosnia and Herzegovina, (BMZ ID 2002 65 876). Rehabilitation of Urban Water Supply Una-Sana region, Consulting Services (Part A).
2. Rehabilitation of the UrbanWater Supply & Sanitation in Sava River Basin (BMZ ID 2002 65 876)
Project Scope – due to frequent pipe bursting and significant water loss a replacement of existing asbestos cement and zinc
Pipelines has been defined through 7nr priority sectors / zones:
Lot A1 - a part of the existing asbestos cement pressure transmission main, which conveys the water from the well field
“Korace” to the reservoir “Bijelo Brdo”, was to be replaced.
Lot A2 - two sections of the asbestos cement gravity transmission main, which conveys water from the reservoir “Bijelo Brdo”
to the reservoir “Babino Brdo” was to be replaced.
Lot A3 - The gravity asbestos cement transmission main, which conveys water from the reservoir Babino Brdo“ to the reservoir
„Gakovac”, shall be partly replaced. The other gravity asbestos cement transmission main, which delivers water from the
reservoir “Babino Brdo“ to the Water Supply Zone 1 in the city of “Derventa”, was also to be partly replaced.
Lot A4 - the Reservoir “Gakovac”- City Network Feeder Line located in Stevana Nemanje Street was to be replaced.
Lot A5 - a distribution asbestos cement pipes which are located in “Srpske Vojske”street was to be replaced, new house
connections installed
Lot A6 – a distribution asbestos cement pipeline in “Stefana Nemanje Street” with belonging house connections were to be
replaced.
Lot A7 – The distribution Zinc-pipes which are located in “Radnička street” together with belonging house connections were to
be replaced.
Lot A8 – Provision and installation of SCADA System with associated software, equipments, ultrasonic flow meters, pressure
reducing valves on critical locations, integration into the SCADA System.
Lot A9 – provision of Water Meters, PE Shafts and associated fittings for Water Utility “Komunalac”
In total - 12,630.52m of DI & PE Pipelines have been installed under the Project, 309nr of house connections, 14nr of supporting
concrete manholes. From remaining budget – several pipelines were extended (Lot A3, A5, A6, A7).
Project Budget – 2,000,000.00EUR
4. WS PIPE MATERIAL – DUCTILE IRON “PAM” NATURAL PIPES
, TYTON-SIT JOINTS
WS PIPE MATERIAL – HDPE100, SDR11-17, PN10, PN16
“PIPELIFE” PIPES
5. LOT A-1
(Transmission Main DI
DN300; L = 2.207,80m)
A part of the existing asbestos cement
pressure transmission main, which
conveys the water from the well field
“Korace” to the reservoir “Bijelo
Brdo”, was to be replaced.
Pipe material:
DI DN300, PN16 in 2,207.80m Length
with 1nr new Mud Outlet Valve Shaft.
Considering this previously war-
affected area has present mine fields,
it was required that demining of pipe
route corridor is conducted prior of
any construction works.
12. LotA2
Transmission main
HDPE DN300
Two sections of the asbestos cement
gravity transmission main, which
conveys water from the reservoir
“Bijelo Brdo” to the reservoir “Babino
Brdo” was to be replaced.
Pipe material:
HDPE100, PN10, SDR17, OD315mm,
L=843.10m with 2nr House
Connections
15. REPLACEMENT OF VALVES, FITTINGS AT EXISTING MUD
OUTLET VALVE MANHOLE
REPLACEMENT OF AIR VALVE AT EXISTING AIR VALVE
MANHOLE
16. REPLACEMENT OF AIR VALVE AT EXISTING AIR VALVE
MANHOLE
REPLACEMENT OF AIR VALVE AT EXISTING AIR VALVE
MANHOLE
17. LotA3
Transmission Main
The gravity asbestos cement
transmission main, which conveys
water from the reservoir Babino Brdo“
to the reservoir „Gakovac”, shall be
partly replaced.
The other gravity asbestos cement
transmission main, which delivers
water from the reservoir “Babino
Brdo“ to the Water Supply Zone 1 in
the city of “Derventa”, was also to be
partly replaced
Extension of City Network:
Pipe Material:
DI DN400, PN16 – L=253m;
DI DN300, PN16 – L=485m;
HDPE ID315, PN16 – 1,760m;
3nr new Shafts – 2 Mud Outlets, 1nr
Air Valves
18. PIPE ROUTE CORRIDOR DEMINED BY BHMAC
REGARDLESS, UNEXPLODED MINE ENCOUNTERED DURING
TRENCH EXCAVATION WORKS, WORKS ABORTED UNTIL
DEMINING COMPLETION
19. DI DN300 PIPE CONNECTION TO RESERVOIR “BABNO BRDO” DOWNSTREAM PIPE ROUTE
26. TRANSITION TO HDPE OD315, PN16 EXTENSION OF TRANSMISSION MAIN HDPE OD315, PN16
27. LotA4
Feeder Line
The Reservoir “Gakovac”- City
Network Feeder Line located in
Stevana Nemanje Street was to be
replaced
Pipe material:
HDPE PN10, PN16:
OD315 – L=577m
1nr Air Valve Shaft
1nr Flow Meter Shaft (Lot A8)
28. HDPE OD315, PN16 PIPE CONNECTION TO “GAKOVAC”
WATER RESERVOIR
HDPE OD315, PN16 PIPE CONNECTION TO “GAKOVAC”
WATER RESERVOIR
32. LotA5
Distribution Pipeline
The distribution asbestos cement
pipes which are located in “Srpske
Vojske”street shall be replaced, new
house connections installed
Distribution Pipeline:
HDPE OD180, PN10 – 1,502m;
House Connections – 46nr
35. LotA6
Distribution Pipeline
Distribution asbestos cement pipeline
in “Stefana Nemanje Street” with
belonging house connections to be
replaced:
Pipe material – HDPE PN16:
OD125 – 3,224m;
OD63-282m;
House Connections – 188nr;
2nr new shafts
45. LotA7
Distribution Pipeline
The distribution Zinc-pipes which are
located in “Radnička street” together
with belonging house connections
were to be replaced.
Pipe Material -HDPE PN16:
OD125 – L=1,022m;
OD63 – L=474m;
House Connections – 73nr;
1nr Pressure Reducing Valve Shaft