2. Rehabilitation of Vani Water Supply System (EIB/WIMP/W/ICB/12-L2)
Installation of Distribution Network, 1,720m of PE100 Pipe (OD110, OD90 & OD63), 467nr House Connections and associated 3,341m of PE100 Pipe (OD63 & OD25).
Installation of SCADA System including 2nr Ultrasonic Flow Meters, 2nr Residual Chlorine Monitoring Devices, 3nr Actuated Valves, 1nr Pressure Reducing Valve & Pump Control.
Contract Value 320,000GEL (€135,000), FIDIC Red Book MDB 2006
Commencement Date – 23rd April 2012
Completion Date – 10th November 2012
3. 3,341M OF PE100 PIPE (OD63 & OD25)
1,720M OF PE100 PIPE (OD110, OD90 & OD63)
4. PVC WATER METER BOXES
WATER METER BOX FITTINGS
(1ST VALVE, FILTER, WATER METER, CONNECTION FITTINGS)
5. CROSSING THE BRIDGE
(26TH MAY STREET, PE100, PN10, DN110, L=380M)
CROSSING THE MAGISTERIAL ROAD
(TAMAR MEPE STREET PE100, PN10, DN90)
6. SECONDARY PIPELINE
(TAMAR MEPE STREET PE100, PN10, DN63)
PE EF PIPE SADDLE FOR HOUSE CONNECTION SERVICE LINE