1. Slip-Lining with Fusible PVC
to Rehabilitate Large Diameter
Water Mains
OAWWA – State Conference – September 17, 2015
2. City of Elyria, Ohio
22 MGD WTP (1902-Lorain)
– Customers
• Amherst
• North Ridgeville
• Northern Ohio Rural Water
Distribution System
– 300 miles total
– 18 miles transmission
• PCCP (C301)
– 4 miles 48”
– 4 miles 36”
• Steel Pipe
– 10 miles 30”
3. 30” Steel Transmission Water Main (1937)
2,100 ft; Spiral Welded; 7/16-inch thick
Coating
– Bituminous exterior/interior (cement mortar)
American Rolling Mills Co.
– Middletown, Ohio
– ARMCO (1978); AK Steel 1993)
Feeds North and Central sections (60 psi)
Failures = exterior pin holes
6. Lake Shore Electric (LSE) Railway (RW)
1901 - LSE Interurban RW
1902 - Elyria WTP built
1906 - Lorain to Elyria
1937 - 30” Transmission Main
1938 - Last LSE RW run
7. Site Constraints
Modular Home Community
– Move 45 structures?
– Temporary relocation for residents?
– Valve vault under home
Pavement and MOT
Located along bank of detention basin
Deflections?
Open-Cut Excavation vs. Trenchless?
11. Preliminary Design Considerations
Minimize “headaches”!
– Time pipe is out of service
– Disturbances to residents
– Pavement restoration & MOT
Rehabilitation Goals
– Quick/simple installation
– Jointless
– Good corrosion resistivity = long life
– Known/Familiar material
12. Rehabilitation Method
Trenchless Method
– HDPE (slip-lining or “swagelining”)
– FPVC (slip-lining)
– CIPP (inversion & cure)
Selection Criteria
– Staging area(s) & access
– New pipe is “stand-alone” – minimal reliance on host pipe
– Installation of valves & fittings
– Allows use of known/familiar material
– Resultant interior pipe diameter
– Cost
13. Slip-Lining
New pipe pulled inside existing host pipe
Smaller ID required for new pipe (4” diam reduction typ.)
Grout annular space (stabilize; minimize thermal expansion)
14. HDPE or Fusible PVC?
24” DR21 C905 Fusible PVC (FPVC) selected
– Stronger (2x greater tensile strength)
– Lighter weight (2/3)
– Utilize standard DIP/MJ fittings (known/familiar)
– Larger ID (23.19” vs. 19.72”)
15. Hydraulic Impacts
Modeling to determine acceptable impacts (AWWA M32)
Pikewood Manor Water Main Headloss Table
Pipe
Flow
(gpm)
C
Pipe Size
(in)
Pipe
Inside
Diam. (in)
L (ft) K
V
(fps)
Headloss
(ft)
Headloss
Gradient
(ft/ft)
Hydraulic
HP (HP)
Hydraulic
HP
(KW-h)
Cost($)
KW-h
Cost($)
KW-day
FPVC
DR 21
C-905
2,300 120 20 19.42 2,100 1.5 2.5 3.20 0.0014 1.86 1.39 $0.14 $1.11
FPVC
DR 21
C-905
2,600 120 24 23.19 2,100 1.5 2.0 1.71 0.0007 1.12 0.84 $0.08 $0.67
Steel
Pipe
2,700 120 30 29.25 2,100 1.5 1.3 0.60 0.0003 0.41 0.30 $0.03 $0.24
Notes: 1. A cost of 10 cents per KW-hr is assumed.
16. Design Considerations
Pre-installation explorations
– Visual observation
– CCTV inspection w/inclinometer
– Test pull 40-ft section FPVC
– Project team consensus
PCCP reconnection
– Coordination with Hanson
Host pipe annular space
– Low density cellular grout
220 miles (3.5 hrs) from Elyria
Between Dayton and Cinci, off US75
Steel plate welded over plug….got to point where city would have 2 custom fabricated plates sitting ready for use.
1900s-1950s = Interurban or radial railway era. The rise of the automobile and the creation of roads paid for by public vs. railways that were privately funded/taxed, ended the interurban era. 1938 last run was between Cleveland and Lorain.
Looking North – approx 15’ width between basin and homes
Approx 6 feet still under the home.
Based on above the project team is beginning to realize that “Trenchless” will likely be the installation method…
Based on costs, ease of installation, and level of comfort – slip-lining is selected by the project team.
So what is slip-lining? Generic pulling rig shown, multiple options to pull pipe….contractor on this project used a HDD rig.
FPVC offered the least reduction in ID using standard sizes with a material that the City was familiar and comfortable with in terms of fittings/connections.
So to backtrack just a little,
Insert cut pipe pics and test pull pics
10% thickness surface gouging depth allowed, typ for sliplining projects.
Ended up with long/extended length transition coupling