SlideShare a Scribd company logo
1 of 54
Rehabilitation of Municipal Water Supply &
Wastewater Infrastructure in Batumi - Phase III
Lot 4-1
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 1
Project Phases:
■ The Batumi Project is divided into four phases, each of which is implemented by the Municipality of Batumi:
 Phase I consisted of rehabilitation measures for the water and sewer supply facilities in parts of the old
town of Batumi. Phase I had an investment cost of 18.5 million EUR and was implemented from 2007
until 2012.
 Phase II extends the rehabilitation measures of phase I to more parts of the city and also to nearby
coastal villages south of Batumi. This phase also builds a new waste water treatment plant for Batumi.
At a cost of 47 million EUR, phase II has been implemented between 2009 and 2013.
 .
 Phase IV concerns the rehabilitation and extension of the water supply network and the rehabilitation of
the sewer system in Batumi (new city boundaries). The Project covers the continuation of Project
Phases I-III that aim at a continuous and demand-oriented supply of the population with hygienically
sound water as well as an ecological and hygienically sound disposal and treatment of the wastewater
of Batumi. The estimated total investment cost of the Project Phase IV amount to approximately EUR
30 m.
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 2
Phase III of the Batumi municipal water project focuses on rehabilitating the rest of Batumi’s
water and sewer facilities. It continues to expand into surrounding rural coastal areas. At a
projected cost of 43.5 million EUR, phase III began in 2012 and expected to be finished in 2018.
Project Background & Scope
■ Project background - previous sewage disposal principle
comprised of individual & high rise residential buildings
being discharged to existing rainwater channels taking the
sewage directly into the Sea.
■ Project scope – environmental protection, prevention of
further Black Sea coast pollution, separation of sewage from
storm water collectors, abortion and prevention of further
sewage influx into Black Sea, improvement of quality of
coastal, bathing waters through rehabilitation and
construction of new sewerage systems within dense city
areas as well as surrounding coastal villages.
■ Lot 4-1 / Wastewater component:
 In total ~41km of sewerage pipelines, 690nr inspection
manholes, 2,190nr of house connection manholes.
 Gravity collectors L=32,8km (PP SN10, DN200-400mm, GRP
PN10 DN500, 800, 1000mm), with 661nr manholes, 2,184nr
house connection manholes.
 5.4km of pressure main (Steel PE/cem.mortar, DN1000mm)
with associated valves & washouts, combined type air valves
 One WW Shaft Pumping Station “Back Pull-Out” type (Q3=
2x57.3l/s @ 6,4m).
Section Collector
House
Connections
Manholes
(m) (pcs) (pcs)
Waste Water
Gravity Sewerage Networks
Remaining System A(RSA)
Steel (PE/cem.mort), DN250 187.00
PP SN10 (DN250-400) 12,842.00
GRP PN10, SN10,000 (DN500, 800) 482.00
Sub-total: 13,511.00 842.00 258.00
Swamp & South Swamp Area (SSA)
PP SN10 (DN200-400) 17,861.00 1,342.00 356.00
Sub-total: 17,861.00 1,342.00 356.00
Trunk Main Collectors
Collector "B"
GRP PN10, SN10 DN800-1000 2,557.00 47.00
In-lining DN1000, 1200 1,128.00
Sub-total: 3,685.00 47.00
Total - gravity sewers 35,057.00 2,184.00 661.00
Pressure Mains
Pumping Main "B"
Steel (PE/cem.mortar), DN1000 5,184.00 21.00
Total - pressure mains: 5,184.00 21.00
Total sewerage: 40,241.00 2,184.00 682.00
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 3
Objectives & Benefits
■ ObjectivesThe Batumi MunicipalWater Project aims to:
 Ensure a continuous supply of safe drinking water for the population of Batumi
 Reduce water losses and ensure efficient use of resources
 Guarantee a controlled and improved wastewater collection treatment system
 Provide regular testing and analysis of public drinking water so it is up to EU standards
 Cover operation and maintenance costs for BatumiTskali Utility by service fees
 Protect the water ecosystems of the Black Sea and Chakvi RiverWatershed
 Benefits:
 Prevents costly and pointless water loss
 Constructs a new low energyWWTP that has a solar drying system
 Achieves EU water quality standards
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 4
Lot 4-1
 Remaining System A (RSA) – dense city area
sewerage system remaining for construction
from Phase II of the Project;
 Swamp & South Swamp Area Sewage
Network (SSA) – located at the South-East
part of the city center with a high population
density, sewage previously discharged to
existing rainwater channels taking the
sewage directly into the Sea;
 Sewage Pumping Main B connecting main
WW PS B with WWTP Adlia; max. pressure 1,7
– 2,3bars.
 Collector B as trunk main is the most
important component of System B & System
C and hence its backbone as it conveys
collecting major lateral collectors and will
carry all the sewage from these areas to the
existing PS B and from there – to the WWTP
Adlia.
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 5
Remaining
SystemA (RSA)
 Covering dense city area sewerage system
remaining for construction from Phase II of
the Project:
 13,185m of sewerage city collectors (Steel
DN250mm, PP DN250-400mm, GRP
DN500-1200mm),
 258nr inspection manholes,
 842nr house connections.
 Sewage pumping station - “Back Pull-Out”
pump 2 x 57.3 l/s, H=6,4m; with double
HDPE wall housing (ID = 2,000 mm, SN4),
buoyancy preventive concrete casing.
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III /
Lot 4-1
6
RSA - Prefabricated concrete manholes:
Located at all changes of the vertical or horizontal alignment and at intervals not
exceeding 50m’ for primary & secondary sewer lines
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 7
RSA - HORIZONTAL
DRILLING:
CROSSING BELLOWTHE RAILWAY,
EXISTING STORM-WATER
CHANNELSWITH STEELCONDUIT
PIPEWITH CONCRETE SEALING
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in
Batumi - Phase III / Lot 4-1 8
RSA – Prefabricated concrete inspection manholes
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 9
RSA - Sewage
shaft PS A-1
“Back Pull-Out” pump:
 2 x 57.3 l/s, H=6,4m;
 Double HDPE wall housing;
 ID = 2,200 mm,
 OD = 2,433mm
 H=6,700mm,
 SN4,
 Buoyancy preventive concrete casing
class C25.
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III /
Lot 4-1
10
RSA - Construction phases - sewage shaft PS A-1 –
sheet piled excavation, concrete buoyancy preventive casing
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 11
RSA - Construction phases - sewage shaft PS A-1
installation of PS’ HDPE housing downstream from screen chamber with sluice gate valve
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 12
RSA - Construction phases - sewage shaft PS A-1
buoyancy preventive concrete casing surrounding HDPE PS
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 13
RSA - Construction phases - sewage PS A-1
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 14
RSA - sewage PS A-1
pumps (2 x 57.3 l/s, H=6,4m)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 15
RSA - sewage PS A-1
operation in 1+1 work regime of pumps (2 x 57.3 l/s, H=6,4m)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 16
RSA - sewage PS A-1
pumps (2 x 57.3 l/s, H=6,4m)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 17
Swamp & South
SwampArea Sewage
Network (SSA)
Located at the South-East part of the city center with a
high population density, sewage previously discharged to
existing rainwater channels taking the sewage directly
into the Sea: 17,664m of sewerage city collectors (PP
DN200-400mm), 1,424nr house connections;
New sewage network in the Swamp & South SwampArea
includes the following:
 14,223m of primary and secondary gravity sewer
collectors with diameters ranging PP DN250 –
DN400mm, with depths up to 5,0m;
 3,638m of tertiary lines (PP DN200mm);
 356nr manholes with depths up to 5,0m;
 889nr PP & 453 concrete HC manholes
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III /
Lot 4-1
18
SSA -Works
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 19
SSA –Works
Prefabricated Concrete Inspection manholes
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 20
SSA –Works
Prefabricated Concrete Inspection manholes
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 21
SSA –Works
House Connection PP-Manhole with 1 inlet / 1 outlet
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 22
SSA –Works
House Connection PP-Manhole with 3 inlets / 1 outlet
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 23
Sewage Pumping
Main B (PMB)
 Connecting main WW PS B with WWTP
Adlia;
 Steel pressure pipeline DN1000mm
(1,016X10/8.8mm), L=5,184m;
 PE coated / sulfate resistant cement
mortar lined;
 Max. pressure rating btw. pressure 1,7 –
2,3bars.
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III /
Lot 4-1
24
Sewage Pumping Main B (PMB)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 25
Sewage Pumping Main B (PMB)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 26
Sewage Pumping Main B (PMB)
Valve &Washout Manholes
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 27
Sewage Pumping Main B (PMB)
Concrete thrust blocks on DN1000mm pressure pipeline
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 28
Sewage Pumping Main B (PMB)/
Combined Air ReleaseValves
 Located on high-points of pumping mains,
designed to operate with sewage DN150,
PN10.
 Combined air valve discharges gases during the
filling or charging of the system, admits air to
the system while it is being emptied of liquid
and discharges accumulated gases from the
system while it is under pressure and
operating, combining air & vacuum.
 Additional isolating valve to permit inspection
and maintenance of the valve
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 29
Sewage Pumping Main B (PMB) – Crossing over the Mejinitskali River
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 30
SewageCollector B
Collector B (GRP DN800 - 1000mm,
L=2,557m) as trunk main is considered as
the most important component of System
B & System C and hence its backbone as it
conveys collecting major lateral collectors
and will carry all the sewage from these
areas to the existing WW PS B and from
there – over new Pumping Main B to the
WWTP Adlia.
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III /
Lot 4-1
31
Collector B
Comprises the following general issues:
Replacement of existing collector:
 Construction of 2,6 km of GRP DN800 &
DN1000mm sewer trunk main with invert
levels from 1,8m to 4,5m;
 Construction of 47 concrete manholes
with depths between 1,8 – 4,5m;
In-lining of existing collector:
 Rehabilitation of ~1,1km of existing
DN1000, 1200mm sewer trunk main by
trenchless technology with depths
varying between 4,0 & 8,0m
 Construction of 20nr manholes with
depths btw.4,0 & 8,0m
 Due to deteriorated status of existing
collector, in-lining was abandoned, new
DN1200 collector to be installed under
future project!
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 32
Sewage Collector B
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 33
Sewage Collector B
Multiple crossings with existing
installations
Collector route parallel to existing SW
channel
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 34
Collector B
Tertiary collectors – collection of HC above the trunk-collector
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 35
Sewage Collector B
Soil investigation – due to swamp area, replacement of subgrade material required below
pipe-invert level (H= 0.5 / 1,0m)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 36
Manholes
Manholes: prefabricated concrete manholes
located at all changes of the vertical or
horizontal alignment and at intervals not
exceeding 50m’ for primary & secondary
sewer lines.
In-situ concrete manholes are considered at all
changes of the vertical or horizontal
alignment and at intervals not exceeding
70m’ in straight line for theTrunk Main
Collector B.
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III /
Lot 4-1
37
Quality Control
 Trench subgrade soil analysis;
 Pipeline alignment, invert elevations;
 Pipe trench bedding & backfilling compaction
level;
 Ultrasonic testing on welded joints;
 Tightness testing of WW system (collector,
manhole, house connections);
 CCTV inspection of collectors;
 Standard concrete testing (Slump,
Compressive strength,…);
 Material inspections on delivery and
installation
Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III /
Lot 4-1
38
QC / Prefabricated concrete curing pools, compressive strength
testing
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 39
QC / material inspections on delivery
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 40
QC /Tightness testing of gravity sewers
as per EN1610
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 41
QC / CCTV Inspection
(closed circuit television) as per ATV M 14, part 2
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 42
Health & Safety
Regular Safety Patrols preventing potential accidents
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 43
Materials:
prefabricated concrete manholes / curing pools
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 44
Materials:
prefabricated concrete manholes (for collectors DN200-400)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 45
Materials:
prefabricated concrete manholes for large pipe diameters (DN500 – 1200)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 46
Materials:
prefabricated concrete manholes for connections / crossing with large pipe diameters (DN500 –
1200)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 47
Materials:
Manhole covers, dirt (sand) traps - B125, LW800-D400 (Meier Guss, Germany)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 48
Materials:
GRP Pipe material – SN10000, DN500-1200 (Superlit,Turkey);
Rehabilitation of MunicipalWater Supply &Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 49
Materials:
PP Pipe material – KG2000, SN10, DN150-400 (Wavin,Germany)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 50
Materials:
Steel pipes, Epoxy coated / sulfate resistant cement lined, (NOKSEL,Turkey)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 51
Material:
Steel pipes, Epoxy coated / sulfate resistant cement lined, (HATBORU,Turkey)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 52
Materials:
House connection manholes (Wavin, Germany)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 53
Materials:
Valves, fittings (VAG, Germany)
Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 54

More Related Content

What's hot

Water demand and factor affecting water demand
Water demand and factor affecting water demandWater demand and factor affecting water demand
Water demand and factor affecting water demandAnkit Gola
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012IAEME Publication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sectorDr Fereidoun Dejahang
 
Open channel Flow - Uniform Flow
Open channel Flow - Uniform FlowOpen channel Flow - Uniform Flow
Open channel Flow - Uniform FlowAmos David
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 finaldhanapal143
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction Thanigaivel Asokan
 
Unit III Quality and Treatment
Unit  III Quality and TreatmentUnit  III Quality and Treatment
Unit III Quality and TreatmentMadhukarJadhav8
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
pavement materials:aggregates
pavement materials:aggregates pavement materials:aggregates
pavement materials:aggregates pradip dangar
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In ConstructionIsidro Sid Calayag
 
Application of softwares in wdn design
Application of softwares in wdn designApplication of softwares in wdn design
Application of softwares in wdn designManoj Mota
 

What's hot (20)

Water demand and factor affecting water demand
Water demand and factor affecting water demandWater demand and factor affecting water demand
Water demand and factor affecting water demand
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
 
Performance thrugh pim
Performance thrugh pimPerformance thrugh pim
Performance thrugh pim
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
Open channel Flow - Uniform Flow
Open channel Flow - Uniform FlowOpen channel Flow - Uniform Flow
Open channel Flow - Uniform Flow
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
 
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction
 
Unit III Quality and Treatment
Unit  III Quality and TreatmentUnit  III Quality and Treatment
Unit III Quality and Treatment
 
Qaqc in civil construction
Qaqc in civil constructionQaqc in civil construction
Qaqc in civil construction
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Irrigation canals
Irrigation canalsIrrigation canals
Irrigation canals
 
concrete mixer
concrete mixerconcrete mixer
concrete mixer
 
pavement materials:aggregates
pavement materials:aggregates pavement materials:aggregates
pavement materials:aggregates
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In Construction
 
Application of softwares in wdn design
Application of softwares in wdn designApplication of softwares in wdn design
Application of softwares in wdn design
 
Dewatering
DewateringDewatering
Dewatering
 

Similar to Rehabilitating Batumi's Water & Sewer Infrastructure

DesignCriteriaManual DesignCriteriaManual JICA.pdf
DesignCriteriaManual DesignCriteriaManual JICA.pdfDesignCriteriaManual DesignCriteriaManual JICA.pdf
DesignCriteriaManual DesignCriteriaManual JICA.pdfkahlaoui1
 
Kakanj City Waste Water Project
Kakanj City Waste Water ProjectKakanj City Waste Water Project
Kakanj City Waste Water ProjectVladimir Popovic
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Fairfax County
 
IRJET- Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
IRJET-  	  Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...IRJET-  	  Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
IRJET- Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...IRJET Journal
 
Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26Uyanga Nyamkhuu
 
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirSeismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirVladimir Popovic
 
Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosniaVladimir Popovic
 
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfChimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfAmmar475682
 
Lectre 1- Real INTRO and SEWER DESIGFN.pptx
Lectre 1- Real INTRO and SEWER DESIGFN.pptxLectre 1- Real INTRO and SEWER DESIGFN.pptx
Lectre 1- Real INTRO and SEWER DESIGFN.pptxAsnelTiffa
 
Bangalore's Water Supply situation - BWSSB
Bangalore's Water Supply situation - BWSSBBangalore's Water Supply situation - BWSSB
Bangalore's Water Supply situation - BWSSBSangeeta (San) Banerjee
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET Journal
 

Similar to Rehabilitating Batumi's Water & Sewer Infrastructure (20)

DesignCriteriaManual DesignCriteriaManual JICA.pdf
DesignCriteriaManual DesignCriteriaManual JICA.pdfDesignCriteriaManual DesignCriteriaManual JICA.pdf
DesignCriteriaManual DesignCriteriaManual JICA.pdf
 
Kakanj wastewater project
Kakanj wastewater projectKakanj wastewater project
Kakanj wastewater project
 
Kakanj City Waste Water Project
Kakanj City Waste Water ProjectKakanj City Waste Water Project
Kakanj City Waste Water Project
 
Trenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water NetworksTrenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water Networks
 
Derventa City WW Project
Derventa City WW ProjectDerventa City WW Project
Derventa City WW Project
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2
 
IRJET- Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
IRJET-  	  Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...IRJET-  	  Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
IRJET- Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
 
Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26
 
Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15
 
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirSeismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
 
Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosnia
 
Mumbai sewage
Mumbai sewageMumbai sewage
Mumbai sewage
 
Ded butets english
Ded butets englishDed butets english
Ded butets english
 
Sanipor
SaniporSanipor
Sanipor
 
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfChimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
 
Lectre 1- Real INTRO and SEWER DESIGFN.pptx
Lectre 1- Real INTRO and SEWER DESIGFN.pptxLectre 1- Real INTRO and SEWER DESIGFN.pptx
Lectre 1- Real INTRO and SEWER DESIGFN.pptx
 
Bangalore's Water Supply situation - BWSSB
Bangalore's Water Supply situation - BWSSBBangalore's Water Supply situation - BWSSB
Bangalore's Water Supply situation - BWSSB
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
 
CV William 2016
CV William 2016CV William 2016
CV William 2016
 

More from Vladimir Popovic

Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Vladimir Popovic
 
Tightness testing of gravity pipelines
Tightness testing of gravity pipelinesTightness testing of gravity pipelines
Tightness testing of gravity pipelinesVladimir Popovic
 
3-Days Construction Schedule
3-Days Construction Schedule3-Days Construction Schedule
3-Days Construction ScheduleVladimir Popovic
 
Water Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesWater Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesVladimir Popovic
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsVladimir Popovic
 
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsVladimir Popovic
 
Sealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesSealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesVladimir Popovic
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESVladimir Popovic
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopVladimir Popovic
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Vladimir Popovic
 
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionMan Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionVladimir Popovic
 
Standard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsStandard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsVladimir Popovic
 
Ozurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectOzurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectVladimir Popovic
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Vladimir Popovic
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Vladimir Popovic
 
Man Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresMan Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresVladimir Popovic
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingVladimir Popovic
 
Kostajnica City - WS/WW Project
Kostajnica City - WS/WW ProjectKostajnica City - WS/WW Project
Kostajnica City - WS/WW ProjectVladimir Popovic
 
Derventa City Water Supply Project
Derventa City Water Supply ProjectDerventa City Water Supply Project
Derventa City Water Supply ProjectVladimir Popovic
 
Lanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewLanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewVladimir Popovic
 

More from Vladimir Popovic (20)

Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
 
Tightness testing of gravity pipelines
Tightness testing of gravity pipelinesTightness testing of gravity pipelines
Tightness testing of gravity pipelines
 
3-Days Construction Schedule
3-Days Construction Schedule3-Days Construction Schedule
3-Days Construction Schedule
 
Water Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesWater Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing Examples
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
 
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
 
Sealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesSealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod Holes
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-Stop
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
 
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionMan Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
 
Standard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsStandard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elements
 
Ozurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectOzurgeti City / Water Supply Project
Ozurgeti City / Water Supply Project
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
 
Man Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresMan Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor Structures
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
 
Kostajnica City - WS/WW Project
Kostajnica City - WS/WW ProjectKostajnica City - WS/WW Project
Kostajnica City - WS/WW Project
 
Derventa City Water Supply Project
Derventa City Water Supply ProjectDerventa City Water Supply Project
Derventa City Water Supply Project
 
Lanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewLanchkhuti WS Project Overview
Lanchkhuti WS Project Overview
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 

Rehabilitating Batumi's Water & Sewer Infrastructure

  • 1. Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III Lot 4-1 Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 1
  • 2. Project Phases: ■ The Batumi Project is divided into four phases, each of which is implemented by the Municipality of Batumi:  Phase I consisted of rehabilitation measures for the water and sewer supply facilities in parts of the old town of Batumi. Phase I had an investment cost of 18.5 million EUR and was implemented from 2007 until 2012.  Phase II extends the rehabilitation measures of phase I to more parts of the city and also to nearby coastal villages south of Batumi. This phase also builds a new waste water treatment plant for Batumi. At a cost of 47 million EUR, phase II has been implemented between 2009 and 2013.  .  Phase IV concerns the rehabilitation and extension of the water supply network and the rehabilitation of the sewer system in Batumi (new city boundaries). The Project covers the continuation of Project Phases I-III that aim at a continuous and demand-oriented supply of the population with hygienically sound water as well as an ecological and hygienically sound disposal and treatment of the wastewater of Batumi. The estimated total investment cost of the Project Phase IV amount to approximately EUR 30 m. Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 2 Phase III of the Batumi municipal water project focuses on rehabilitating the rest of Batumi’s water and sewer facilities. It continues to expand into surrounding rural coastal areas. At a projected cost of 43.5 million EUR, phase III began in 2012 and expected to be finished in 2018.
  • 3. Project Background & Scope ■ Project background - previous sewage disposal principle comprised of individual & high rise residential buildings being discharged to existing rainwater channels taking the sewage directly into the Sea. ■ Project scope – environmental protection, prevention of further Black Sea coast pollution, separation of sewage from storm water collectors, abortion and prevention of further sewage influx into Black Sea, improvement of quality of coastal, bathing waters through rehabilitation and construction of new sewerage systems within dense city areas as well as surrounding coastal villages. ■ Lot 4-1 / Wastewater component:  In total ~41km of sewerage pipelines, 690nr inspection manholes, 2,190nr of house connection manholes.  Gravity collectors L=32,8km (PP SN10, DN200-400mm, GRP PN10 DN500, 800, 1000mm), with 661nr manholes, 2,184nr house connection manholes.  5.4km of pressure main (Steel PE/cem.mortar, DN1000mm) with associated valves & washouts, combined type air valves  One WW Shaft Pumping Station “Back Pull-Out” type (Q3= 2x57.3l/s @ 6,4m). Section Collector House Connections Manholes (m) (pcs) (pcs) Waste Water Gravity Sewerage Networks Remaining System A(RSA) Steel (PE/cem.mort), DN250 187.00 PP SN10 (DN250-400) 12,842.00 GRP PN10, SN10,000 (DN500, 800) 482.00 Sub-total: 13,511.00 842.00 258.00 Swamp & South Swamp Area (SSA) PP SN10 (DN200-400) 17,861.00 1,342.00 356.00 Sub-total: 17,861.00 1,342.00 356.00 Trunk Main Collectors Collector "B" GRP PN10, SN10 DN800-1000 2,557.00 47.00 In-lining DN1000, 1200 1,128.00 Sub-total: 3,685.00 47.00 Total - gravity sewers 35,057.00 2,184.00 661.00 Pressure Mains Pumping Main "B" Steel (PE/cem.mortar), DN1000 5,184.00 21.00 Total - pressure mains: 5,184.00 21.00 Total sewerage: 40,241.00 2,184.00 682.00 Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 3
  • 4. Objectives & Benefits ■ ObjectivesThe Batumi MunicipalWater Project aims to:  Ensure a continuous supply of safe drinking water for the population of Batumi  Reduce water losses and ensure efficient use of resources  Guarantee a controlled and improved wastewater collection treatment system  Provide regular testing and analysis of public drinking water so it is up to EU standards  Cover operation and maintenance costs for BatumiTskali Utility by service fees  Protect the water ecosystems of the Black Sea and Chakvi RiverWatershed  Benefits:  Prevents costly and pointless water loss  Constructs a new low energyWWTP that has a solar drying system  Achieves EU water quality standards Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 4
  • 5. Lot 4-1  Remaining System A (RSA) – dense city area sewerage system remaining for construction from Phase II of the Project;  Swamp & South Swamp Area Sewage Network (SSA) – located at the South-East part of the city center with a high population density, sewage previously discharged to existing rainwater channels taking the sewage directly into the Sea;  Sewage Pumping Main B connecting main WW PS B with WWTP Adlia; max. pressure 1,7 – 2,3bars.  Collector B as trunk main is the most important component of System B & System C and hence its backbone as it conveys collecting major lateral collectors and will carry all the sewage from these areas to the existing PS B and from there – to the WWTP Adlia. Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 5
  • 6. Remaining SystemA (RSA)  Covering dense city area sewerage system remaining for construction from Phase II of the Project:  13,185m of sewerage city collectors (Steel DN250mm, PP DN250-400mm, GRP DN500-1200mm),  258nr inspection manholes,  842nr house connections.  Sewage pumping station - “Back Pull-Out” pump 2 x 57.3 l/s, H=6,4m; with double HDPE wall housing (ID = 2,000 mm, SN4), buoyancy preventive concrete casing. Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 6
  • 7. RSA - Prefabricated concrete manholes: Located at all changes of the vertical or horizontal alignment and at intervals not exceeding 50m’ for primary & secondary sewer lines Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 7
  • 8. RSA - HORIZONTAL DRILLING: CROSSING BELLOWTHE RAILWAY, EXISTING STORM-WATER CHANNELSWITH STEELCONDUIT PIPEWITH CONCRETE SEALING Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 8
  • 9. RSA – Prefabricated concrete inspection manholes Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 9
  • 10. RSA - Sewage shaft PS A-1 “Back Pull-Out” pump:  2 x 57.3 l/s, H=6,4m;  Double HDPE wall housing;  ID = 2,200 mm,  OD = 2,433mm  H=6,700mm,  SN4,  Buoyancy preventive concrete casing class C25. Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 10
  • 11. RSA - Construction phases - sewage shaft PS A-1 – sheet piled excavation, concrete buoyancy preventive casing Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 11
  • 12. RSA - Construction phases - sewage shaft PS A-1 installation of PS’ HDPE housing downstream from screen chamber with sluice gate valve Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 12
  • 13. RSA - Construction phases - sewage shaft PS A-1 buoyancy preventive concrete casing surrounding HDPE PS Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 13
  • 14. RSA - Construction phases - sewage PS A-1 Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 14
  • 15. RSA - sewage PS A-1 pumps (2 x 57.3 l/s, H=6,4m) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 15
  • 16. RSA - sewage PS A-1 operation in 1+1 work regime of pumps (2 x 57.3 l/s, H=6,4m) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 16
  • 17. RSA - sewage PS A-1 pumps (2 x 57.3 l/s, H=6,4m) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 17
  • 18. Swamp & South SwampArea Sewage Network (SSA) Located at the South-East part of the city center with a high population density, sewage previously discharged to existing rainwater channels taking the sewage directly into the Sea: 17,664m of sewerage city collectors (PP DN200-400mm), 1,424nr house connections; New sewage network in the Swamp & South SwampArea includes the following:  14,223m of primary and secondary gravity sewer collectors with diameters ranging PP DN250 – DN400mm, with depths up to 5,0m;  3,638m of tertiary lines (PP DN200mm);  356nr manholes with depths up to 5,0m;  889nr PP & 453 concrete HC manholes Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 18
  • 19. SSA -Works Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 19
  • 20. SSA –Works Prefabricated Concrete Inspection manholes Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 20
  • 21. SSA –Works Prefabricated Concrete Inspection manholes Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 21
  • 22. SSA –Works House Connection PP-Manhole with 1 inlet / 1 outlet Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 22
  • 23. SSA –Works House Connection PP-Manhole with 3 inlets / 1 outlet Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 23
  • 24. Sewage Pumping Main B (PMB)  Connecting main WW PS B with WWTP Adlia;  Steel pressure pipeline DN1000mm (1,016X10/8.8mm), L=5,184m;  PE coated / sulfate resistant cement mortar lined;  Max. pressure rating btw. pressure 1,7 – 2,3bars. Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 24
  • 25. Sewage Pumping Main B (PMB) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 25
  • 26. Sewage Pumping Main B (PMB) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 26
  • 27. Sewage Pumping Main B (PMB) Valve &Washout Manholes Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 27
  • 28. Sewage Pumping Main B (PMB) Concrete thrust blocks on DN1000mm pressure pipeline Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 28
  • 29. Sewage Pumping Main B (PMB)/ Combined Air ReleaseValves  Located on high-points of pumping mains, designed to operate with sewage DN150, PN10.  Combined air valve discharges gases during the filling or charging of the system, admits air to the system while it is being emptied of liquid and discharges accumulated gases from the system while it is under pressure and operating, combining air & vacuum.  Additional isolating valve to permit inspection and maintenance of the valve Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 29
  • 30. Sewage Pumping Main B (PMB) – Crossing over the Mejinitskali River Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 30
  • 31. SewageCollector B Collector B (GRP DN800 - 1000mm, L=2,557m) as trunk main is considered as the most important component of System B & System C and hence its backbone as it conveys collecting major lateral collectors and will carry all the sewage from these areas to the existing WW PS B and from there – over new Pumping Main B to the WWTP Adlia. Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 31
  • 32. Collector B Comprises the following general issues: Replacement of existing collector:  Construction of 2,6 km of GRP DN800 & DN1000mm sewer trunk main with invert levels from 1,8m to 4,5m;  Construction of 47 concrete manholes with depths between 1,8 – 4,5m; In-lining of existing collector:  Rehabilitation of ~1,1km of existing DN1000, 1200mm sewer trunk main by trenchless technology with depths varying between 4,0 & 8,0m  Construction of 20nr manholes with depths btw.4,0 & 8,0m  Due to deteriorated status of existing collector, in-lining was abandoned, new DN1200 collector to be installed under future project! Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 32
  • 33. Sewage Collector B Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 33
  • 34. Sewage Collector B Multiple crossings with existing installations Collector route parallel to existing SW channel Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 34
  • 35. Collector B Tertiary collectors – collection of HC above the trunk-collector Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 35
  • 36. Sewage Collector B Soil investigation – due to swamp area, replacement of subgrade material required below pipe-invert level (H= 0.5 / 1,0m) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 36
  • 37. Manholes Manholes: prefabricated concrete manholes located at all changes of the vertical or horizontal alignment and at intervals not exceeding 50m’ for primary & secondary sewer lines. In-situ concrete manholes are considered at all changes of the vertical or horizontal alignment and at intervals not exceeding 70m’ in straight line for theTrunk Main Collector B. Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 37
  • 38. Quality Control  Trench subgrade soil analysis;  Pipeline alignment, invert elevations;  Pipe trench bedding & backfilling compaction level;  Ultrasonic testing on welded joints;  Tightness testing of WW system (collector, manhole, house connections);  CCTV inspection of collectors;  Standard concrete testing (Slump, Compressive strength,…);  Material inspections on delivery and installation Rehabilitation of Municipal Water Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 38
  • 39. QC / Prefabricated concrete curing pools, compressive strength testing Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 39
  • 40. QC / material inspections on delivery Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 40
  • 41. QC /Tightness testing of gravity sewers as per EN1610 Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 41
  • 42. QC / CCTV Inspection (closed circuit television) as per ATV M 14, part 2 Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 42
  • 43. Health & Safety Regular Safety Patrols preventing potential accidents Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 43
  • 44. Materials: prefabricated concrete manholes / curing pools Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 44
  • 45. Materials: prefabricated concrete manholes (for collectors DN200-400) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 45
  • 46. Materials: prefabricated concrete manholes for large pipe diameters (DN500 – 1200) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 46
  • 47. Materials: prefabricated concrete manholes for connections / crossing with large pipe diameters (DN500 – 1200) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 47
  • 48. Materials: Manhole covers, dirt (sand) traps - B125, LW800-D400 (Meier Guss, Germany) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 48
  • 49. Materials: GRP Pipe material – SN10000, DN500-1200 (Superlit,Turkey); Rehabilitation of MunicipalWater Supply &Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 49
  • 50. Materials: PP Pipe material – KG2000, SN10, DN150-400 (Wavin,Germany) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 50
  • 51. Materials: Steel pipes, Epoxy coated / sulfate resistant cement lined, (NOKSEL,Turkey) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 51
  • 52. Material: Steel pipes, Epoxy coated / sulfate resistant cement lined, (HATBORU,Turkey) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 52
  • 53. Materials: House connection manholes (Wavin, Germany) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 53
  • 54. Materials: Valves, fittings (VAG, Germany) Rehabilitation of MunicipalWater Supply & Wastewater Infrastructure in Batumi - Phase III / Lot 4-1 54