SlideShare a Scribd company logo
1 of 15
Date: December /2014.
Name : Umer Nazir
Date of birth : 01/11/1979
Nationality : Pakistani
Current Position : Senior Survey inspector.
Experience : 15 years.
Contact : 00966 59 22 12 783
Pakistan : 0092 334 508 4728,
Skype: umer.nazir16
Email : Sheikhs440@gmail.com
Qualification:
Education :
Passed Intermediate & secondary education examination for Azad Jammu Kashmir
Mirpur, Kashmir, Pakistan.
- FSC for (faculty ofscience in pre engineering) from Rawalakot Degree College for
Azad Jammu Kashmir board of Education Mirpur, Pakistan. Mirpur, Pakistan,
Year 1999.
- Diploma in surveying Punjab board of technical education Lahore, Pakistan,
Year 2000.
- Tow year’sdiplomainsurveyengineeringfrom modern institute of informatics and
management MIIM Islamabad, for Punjab board of technical education Lahore,
Pakistan, 2012.
-
Training :
Course name, Period Year
- Advance diplomaininformation technology. 250 hours 2002
- AUTO CAD 2004. Six months 2006
- Microsoft Office 200x (Professional Edition). 2 days 2006
- Civil 3D land desktop 2009. 3 days 2009
- Eagle point survey software. 3 days 2010
oto
Experience : 15 years.
1) Position : Land Surveyor (Supervision) Duration : Nov 2011 to 17Nov 2014
Employer : Dar-Al-RiyadhConsultantengineeringarchitect.
Projects : Ministryof Housing,Infrastructure ConstructionSupervision Consultant,
(MOH),KSA.
1- Projectname : MOH baldingandInfrastructure,Rafha,ksa.
Duration : 2 years
Type of project : MOH Infrastructure
Client : Ministryof Housing
ProjectValue : 83 MillionSR
Role inthis
project
: Land Surveyor.
Infrastructure.
- Provide assistance to the Resident Engineer/Project Engineer with
- Serve as the site person responsible for coordinating the daily site
survey works.
- Prepare responses to the Contractors when required.
- Submitdailyreportonsite surveyactivitiesasdirectedbythe Resident
Engineer / Project Manager.
- Supervise and remain vigilant regarding all aspects of the survey
works.
- Respond with appropriate and necessary levels of survey works to
provide quality assurance in accordance with Contract Documents.
- Assist the contractor on required survey procedures.
- Coordinate with the contractor for any survey works.
- Observe the safety procedures followed by the contractor.
- Review the adequacy and accuracy of the survey records,
Topographical Survey.
- Traversing Survey.
- Layout pipe line at tender drawing
- Calculation of vertical & horizontal alignment
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical
control Surveys.
- Topographic surveys, Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land
planning Survey.
- Staking Global Positioning.
2- Projectname : KINGABDULLA FINANCIALDISTRICT(KAFD)
Duration : From: 2011 To: Sept2013 (2 Years)
Type of project : Building.
Client : RIC,Riyadh.
ProjectValue 7.8 billion USDollar
Contract value :
Scope of work : The financial sector and related industries, hosting the head quarters of
the Capital Market Authority, the Stock Exchange, banks, financial
institutions and other service providers such as accountants, auditors,
lawyers,analysts, rating agencies, consultants, and IT providers. The King
Abdullah Financial District provides the next generation of development
and will ensure the sustained dominance of Saudi Arabia as the largest
economy and financial centre within the region.
(KAFD) isa new development under construction near King Fahad Road in
the Asahafa area of Riyadh, Saudi Arabia being undertaken by the Riyadh
Investment Corporation[3]
on behalf of the Pension Authority of
the Kingdom of Saudi Arabia, consisting of 34 towers in an area of 1.6
millionsquare meters.Itwill provide more than3millionsquare meters of
space for various uses, 62,000 parking spaces and accommodation for
12,000 residents. In 2011 it was the largest project in the world seeking
green building accreditation. Bombardier won a $241m USD contract to
buildanautomated monorail forthe development.The districtisdesigned
to keep it isolated from close contact with the strictly monitored Riyadh
society.[7]
The design guidelines do not separate the sexes in the
district. The KAFD master plan was designed and overseen by Danish
Architects Henning Larsen Henning Larsen Architects.
Role inthis
project
: Surveyor (Supervision)
- Provide assistance tothe ResidentEngineer/Project Engineer with
prompt exchange of correspondence, submittals and RFI's to all
relevantparties. Dealingwithsubcontractors,client & consultant.
- Serve asthe site person responsibleforcoordinating the daily site
survey works. Staking Global Positioning.
- Submit daily report on site survey activities as directed by the
Resident Engineer / Project Manager.
- Supervise and remain vigilant regarding all aspects of the survey
works. Topographic surveys, Building Location Surveys, Land
Development.
- Respondwithappropriate andnecessarylevels of survey works to
provide qualityassurance inaccordance withContract Documents.
- Assist the contractor on required survey procedures.
- Coordinate with the contractor for any survey works.
- Observe the safety procedures followed by the contractor.
- Review the adequacy and accuracy of the survey records,
- Traversing Survey, Topographical Survey.
- Layout of substation, water pipe line, link roads to substation.
2) Position : Chiefsurveyor Duration : Feb 2011 to Nov 2011
Employer : Saudi Landscape & Contracting(SALCO)
1- Projects : (KAPSARC)
Type of project : Hardscape,Landscape and Irrigation.
Client : Armco.
ProjectValue Hole project2 billion USDollar
Contract value :
Scope of work : King Abdullah Petroleum Studies and Research Centre (KAPSARC) is a
future-oriented research and policy centre Committed to energy and
environmental exploration and production and analysis. The 887,000 sq
feet KAPSARC campus is Located in Riyadh, Saudi Arabia. The Entire
complex will be LEED Platinum Rated upon completion, which is the
highestLevel achievable underU.S. Green Building Council specifications.
SAS Global’sinvolvement in this project has been to supply HSE & QA/QC
management staff, Commercial teams, MEP & Commissioning staff &
Interior design project management staff.
- Provide assistance site Engineer/ site surveyors and report Project
manager with prompt exchange of correspondence, submittals and
RFI's to all relevant parties.
- Serve as the site person responsible for coordinating the daily site
survey works.
- Prepare responses to the sub Contractors when required.
- Submit daily report on site survey activities as directed to Project
Manager.
- Supervise and remain vigilant regarding all aspects of the survey
works.
- Coordinate with the consultant for any survey works.
- Observe the safetyproceduresfollowedbythe Client and consultants.
- Traversing Survey, Topographical Survey.
- Calculation of vertical & horizontal alignment
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical
control Surveys. Land planning Survey.
- Land Development Surveys, staking Global Positioning.
2- Projects : The Main Linesof Sewage Systems
Projectname : Sewage Network Al Ula.
Duration : Sept 2010 To: Feb2011
Type of project : Infrastructure.
Client : Ministryof Water and Electricity
Contract value : 16,926,933 SR.
Role inthis
project
: Chief Surveyor
- All kind of survey work traversing Survey, sating out & calculations.
- Layout pipe line attenderdrawing, Layoutpipe line attenderdrawing,
supervision & control Surveyors team.
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys.
- Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land
planning Survey.
- Serve as the site person responsible for coordinating the daily site
survey works.
- Prepare responses to the Contractors when required.
- Submitdailyreportonsite surveyactivitiesasdirectedbythe Resident
Engineer / Project Manager.
- Supervise and remain vigilant regarding all aspects of the survey
works.
- Respond with appropriate and necessary levels of survey works to
provide quality assurance in accordance with Contract Documents.
- Assist the contractor on required survey procedures.
- Coordinate with the consultant for any survey works.
- Observe the safety procedures followed by the consultant.
- Layout pipe line at tender drawing
- Layout of substation, water pipe line, link roads to substation.
- Topographic surveys, Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land
planning Survey.
3- Projectname : Rehabilitation of King Fahd Park and Palm Area
Duration : Sept2010 To: March 2011.
Type of project : SoftAndHard Landscape Works.
Client : Al Madinah Regional Municipality
Contract value : 46,766,989.00 SR.
Scope of work :
The central garden of Al Madina Al Munawarah is located at a distance of
five kilometers in the south of the Prophet’s Mosque, and on the borders
of the second circular road in Quba area which is famous of abundance of
groundwater and density of palm farms therein. It is bordered by the
district of Prince Naif from the north ,and Al Shabebah district from the
west,and a plot of land related to the Department of Water and Sanitary
Drainage inAl Madinah Munawarahfrom the eastand south,and the total
area of the garden amounts to (4.3) m2.
Also,a numberof entertainmentparkshave been established throughout
Al Madinah Al Munawarahincluding:Bae’ganpark situated in universities
road near Prince Muhammad Bin Abdul Aziz‘s Sports City.
Role inthis :
Project.
- All kind of survey work traversing Survey, sating out & calculations.
- Layout pipe line at tender drawing, supervision & control Surveyors team.
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical control
Surveys.
- Topographic surveys, Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land planning
Survey.
- Road and utility design surveys, Subdivision.
- Surveys, construction staking Global Positioning.
- Provide assistance site Engineer/ site surveyors and report Project
manager.
- Calculate levels and coordinates prepare necessary site repots and
calculations for site surveyors.
4- Project name : Civil constructionwork,Roadbuildingpipelinedeferentpositionin Madina
region.
Duration : From: September2010 To: March 2011.
Type of project : Civil constructionwork.
Client : Al Madinah Regional Municipality
Contract value : Multiple positionsdifferentvalue foreachproject.
Role in this
project
: Chief Surveyor.
- All kind of survey work traversing Survey, sating out & calculations.
- Layout pipe line attenderdrawing,Layoutpipe line attenderdrawing,
supervision & control Surveyors team.
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical
control Surveys.
- Topographic surveys, Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land
planning Survey.
- Road and utility design surveys, Subdivision.
- Surveys, construction staking Global Positioning.
- Provide assistance site Engineer/ site surveyors and report Project
manager.
- Calculate levels and coordinates prepare necessary site repots and
calculations for site surveyors.
5
- Project name : TabukSewage project.
Duration : From: May 2009 To: Jul 2010.
Type of project : Infrastructure.
Client : Ministryof Water and Electricity.
Contract value : 52,641,034 SR
Scope of work : The implementation and completion of a series of infrastructure and
utilityservicesprojectsinTabuk region. The projects include construction
of new residential majorand secondaryroads. These includedthe cost of
studies, construction and supervision of water and sewage projects at a
cost of million, flood protection walls around water treatment plants in
Tabuk.
Role in this
project
: Chief Surveyor
- All kind of survey work traversing Survey, sating out & calculations.
- Layout pipe line at tender drawing
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical
control Surveys.
- Topographic surveys, Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land
planning Survey.
- Road and utility design surveys, Subdivision.
- Surveys, construction staking Global Positioning.
- Provide assistance site Engineer/ site surveyors and report Project
manager.
- Calculate levels and coordinates prepare necessary site repots and
calculations for site surveyors.
3) Position : Senior land surveyor Duration : Jan2006- May 2008
Employer : Al Jabar and partner,Qatar.
Projects : Qatari Diar, Lusail City
1-
Project name : Infrastructure of the Safe Lusail North and Water front Commercial districts of Lusail
City.
Duration : From: Jun2007 To: May 2008.
Type of project : Infrastructure.
Client : Qatari Diar real estate investmentcompanyLusail DohaQatar
Contract value :
Scope of work : More than 200,000 residentswilllive in Lusail’s scenic surroundings, with
170,000 people expected to work in the city’s different districts, and
80,000 expectedtovisit its entertainment and recreation facilities. Lusail
City’s 19 districts will encompass not only new residential, commercial,
hospitality,and retail opportunities, but a full array of community needs,
complete withschools,mosques, medical facilities, sport, entertainment
and shopping centers.
Role in this
project
: Senior land Surveyor.
- All kind of survey work traversing Survey, sating out & calculations.
- Layout pipe line at tender drawing
- Calculation of vertical & horizontal alignment
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical
control Surveys.
- Topographic surveys, Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land
planning Survey.
- Road and utility design surveys, Subdivision.
- Land DevelopmentSurveys,hydrographicsurveys,constructionstaking
Global Positioning.
- Engineering Design Surveys, Construction layouts, Industrial
development Surveys.
2- Project name : Integrated Gas and Gas to Liquids project.
Duration : From: Jan2006 To: Jun2007.
Type of project : Oil and Gas industry.
Client : DevelopmentandProduction SharingAgreementwith Government of the
State Qatar, 100% Shell funding.
Project Value : Value of hole project $18 billion-$19billion
Scope of work : Pearl GTL is a world-scale project located in Ras Laffan Industrial City, 80
km north of Doha, Qatar. With full ramp-up achieved towards the end of
2012, Pearl GTL is the world’s largest source of gas-to-liquids (GTL)
products, capable of producing 140,000 barrels of GTL products each day.
The plant alsoproduces120,000 barrelsof oil perday of natural gas liquids
and ethane.
Role in this
project
: SeniorlandSurveyor
- All kind of survey work traversing Survey, sating out & calculations.
- Layout pipe line at tender drawing
- Calculation of vertical & horizontal alignment
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical
control Surveys.
- Topographic surveys, Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land
planning Survey.
- Road and utility design surveys, Subdivision.
- Land DevelopmentSurveys,hydrographicsurveys,constructionstaking
Global Positioning.
- Engineering Design Surveys, Construction layouts, Industrial
development Surveys.
4) Position : Senior land surveyor Duration : Feb 2004- may 2006
Employer : National survey engineering, U.A.E.
Projects : Burj Khalifah(Burj Dubai).
1- Project name : Worldtower, Burj Dubai.
Duration : From: Jun2007 To: may 2008
Type of project : MixedUse
Client : Emaar PropertiesPJSC
Contract value : 1.5bn USD
Scope of work : Burj Khalifah(Burj Dubai) isthe tallestman-made structure everbuilt.The building
is part of the 2 km2 development called Downtown Dubai. The mixed use
development will include residential units, offices, hotels and residential
apartments.The toweris composed of three elements arranged around a central
core.As it rises from the flat desert base, each element is set back in an upward-
spiralinghelical pattern,decreasingthe massof the toweras it reachestowardthe
sky and thereby decreasing the wind effects.
Role in this project : Senior land Surveyor
- All kind of survey work traversing Survey, sating out & calculations.
- Layout pipe line at tender drawing
- Calculation of vertical & horizontal alignment
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical control
Surveys, Topographic surveys, Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land planning
Survey.
- Road and utility design surveys, Subdivision.
- Land DevelopmentSurveys,hydrographicsurveys,constructionstaking Global
Positioning.
- Engineering Design Surveys, Construction layouts, Industrial development
Surveys.
2- Project name : Pam Jumeirah IslandU.A.E
Duration : From: Mar 2003To: May 2006
Type of project : MixedUse
Client : Nakheel
Project Value : Hole project,Itcost about 12.9 BillionUSD.
Contract value :
Scope of work :
The Palm Jumeirah is an artificial archipelago created using land
reclamation by Nakheel, a company owned by the Dubai government in United
Arab Emirates and was designed and developed by HHCP architects. It is one of
three planned islands called the Palm Islands (Palm Jumeirah, Palm Jebel
Ali andPalm Deira) which would have extended into the Persian Gulf, increasing
Dubai's shoreline by a total of 520 kilometers (320 mi). The Palm Jumeirah is the
smallest and the original of three Palm Islands originally under development
by Nakheel. It is located on the Jumeirah coastal area of the emirate of Dubai, in
the UnitedArab Emirates (UAE).PalmJumeirah is the largest man-made island of
the world for which construction was started in June 2001. More than 40000
workers from South Asia were involved in the construction work of the island,
whichwasa mammothtask involving new techniques. The island was created by
pouring in several million tons of sand into the deep sea bed with the help of
dredgers.A special technique known as “rain bowing” was used in the process of
reclamation of the land. Natural rock has been used in the creation of a natural
breakwater in the island, which was created mainly to encourage sea life
habitations. The total estimates cost involved in the project are almost US$12.3
billion.The firstresidentialunitswere handedovertothe proudresidents in 2006.
Today, nearly 500 families are already residing here and enjoying in one of the
dream destinations of the world. It is expected that by the end of the year 2009,
28 hotels in the Crescent will open their doors to welcome the tourists. Palm
Jumeirahisset to become a tourist hot-spot in just a few years. To visit this most
beautiful man-made island in the world.
Role in this project : SeniorlandSurveyor.
- Provide assistance to the Resident Engineer/Project Engineer with
- Serve as the site person responsible for coordinating the daily site survey
works.
- Prepare responses to the Contractors when required.
- Submit daily report on site survey activities as directed by the Resident
Engineer / Project Manager.
- Supervise and remain vigilant regarding all aspects of the survey works.
Topographical Survey.
- Respond with appropriate and necessary levels of survey works to
provide quality assurance in accordance with Contract Documents.
- Assist the consultant on required survey procedures.
- Coordinate with the consultant for any survey works.
- Observe the safety procedures followed by the contractor.
- Review the adequacy and accuracy of the survey records,
- Traversing Survey.
- Layout pipe line at tender drawing
- Calculation of vertical & horizontal alignment
- Layout of substation, water pipe line, link roads to substation.
- Dealing with sub contractors, client & consultant.
- The land title surveys, Boundary Surveys, horizontal and vertical control
Surveys.
- Topographic surveys, Building Location Surveys.
- Planning Survey. Staking Global Positioning. Traversing Survey.
- Layout of substation, water pipe line, link roads to substation.
- Location Survey Levels.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land planning
Survey.
- Road and utility design surveys, Subdivision.
- Land DevelopmentSurveys,hydrographicsurveys,constructionstaking Global
Positioning.
- Engineering Design Surveys, Construction layouts, Industrial development
Surveys.
5) Position : Land surveyor. Duration : Dec 2001 - Mar 2003.
Employer : Al Nasar Contracting Company LL.C.
Projects : MixedUse
1- Project name : ShuweihatWaterTransmissionScheme - LotC
Duration : 2 years
Type of project : Water works/pumpingstation/ infrastructure/complete Civil andBuilding
Works.
Client : AbuDhabi Water & electricityAuthority(ADWEA).
Project Value (by US Dollar)
Contract value : (by US Dollar)
Scope of work : The Shuweihat Water Transmission Scheme consists of mussaffah and
Mirfa pumping stations, plus a parallel double pipeline 1600mm dia,
250kms in length, with a transfer capacity of 100 million gallons of water
per day. The capacity of the system will be increased from 100 million
gallons a day (MGD) to 180 million gallons a day (MGD) to facilitate water
transmission from the Shuweihat Phase 2 independent water and power
project. Al Nasr Contracting Co was awarded with The Subcontract Scope
of Workscomprise the complete Civil and Building Works associated with
the Mirfa Pumping Station as per the specifications, drawings and BOQ.
Role in this
project
: Land surveyor
- All kind of survey work traversing Survey, sating out & calculations.
- Layout pipe line at tender drawing
- Calculation of vertical & horizontal alignment
- Layout of substation, water pipe line, link roads to substation.
- The land title surveys, Boundary Surveys, Topographic surveys,
Building Location Surveys.
- Foundation Location Surveys, Utility and Pipeline Surveys, Land
planning Survey. Leveling setting out and established control points.
- Road and utility design surveys, Subdivision.
6) Position : land surveyor Duration : Apr 2001-Dec 2001
Employer : Habib Rafiq (Pvt.) Limited
Projects : Workedas a civil surveyorLahore,Pakistan.
1- Project name : Lahore International Airport.
Duration : From: Jun2007 To: may 2008
Type of project : MixedUse
Client : CAA
Contract value :
Scope of work : Allama Iqbal International Airport (AIIAP) (formerly known as Lahore
International Airport) is the second largest, and third busiest, airport in
Pakistan. The airport handles an average of 75–80 flights each day, but the
number of flights increases during the Hajj season and the airport handles
about four million passengers a year.
The completion of the new air terminal complex and its subsequent opening
in March 2003 increased the capacity with the aim of accommodating up to
6.5 million passengers a year by 2015.
Role in this
project
: Land surveyor.
- Survey, sating out & calculations.
- Layout pipe line
- Calculation of vertical & horizontal alignment.
- Layout of substation, water pipe line, link roads to substation.
- The land title surveys, Boundary Surveys, horizontal and vertical
control Surveys.
- Topographic surveys, Building Location Surveys.

More Related Content

What's hot

Azem Al-Kurdi CV - 4.9.2016
Azem Al-Kurdi CV - 4.9.2016Azem Al-Kurdi CV - 4.9.2016
Azem Al-Kurdi CV - 4.9.2016Azem Al Kurdi
 
ALI FAKHIR IBRAHEEM - C.V
ALI FAKHIR IBRAHEEM -  C.VALI FAKHIR IBRAHEEM -  C.V
ALI FAKHIR IBRAHEEM - C.VAli Fakhir
 
CIRRICULUM VITAE - PelisP
CIRRICULUM VITAE - PelisPCIRRICULUM VITAE - PelisP
CIRRICULUM VITAE - PelisPPeter Pelis
 
RMJugueta Resume 01172016
RMJugueta Resume 01172016RMJugueta Resume 01172016
RMJugueta Resume 01172016Ronaldo Jugueta
 
Cirriculum vitae pelis2
Cirriculum vitae  pelis2Cirriculum vitae  pelis2
Cirriculum vitae pelis2Peter Pelis
 
Salem mohamed curriculum vitae
Salem mohamed curriculum vitaeSalem mohamed curriculum vitae
Salem mohamed curriculum vitaeSALEM MOHAMMED
 
Moustapha El Gharbawy Resume March 2015
Moustapha El Gharbawy Resume March 2015Moustapha El Gharbawy Resume March 2015
Moustapha El Gharbawy Resume March 2015Moustapha El Gharbawy
 
Imteyaz ahmad 12 yrs exp in MEP (Site / Project Management)
Imteyaz ahmad   12 yrs exp in MEP (Site / Project Management)Imteyaz ahmad   12 yrs exp in MEP (Site / Project Management)
Imteyaz ahmad 12 yrs exp in MEP (Site / Project Management)Imteyaz Ahmad
 
CV Osama Hamad_Aug 2016
CV Osama Hamad_Aug 2016CV Osama Hamad_Aug 2016
CV Osama Hamad_Aug 2016Osama Hamad
 

What's hot (20)

Azem Al-Kurdi CV - 4.9.2016
Azem Al-Kurdi CV - 4.9.2016Azem Al-Kurdi CV - 4.9.2016
Azem Al-Kurdi CV - 4.9.2016
 
ALI FAKHIR IBRAHEEM - C.V
ALI FAKHIR IBRAHEEM -  C.VALI FAKHIR IBRAHEEM -  C.V
ALI FAKHIR IBRAHEEM - C.V
 
Muneer CV 2016
Muneer CV 2016Muneer CV 2016
Muneer CV 2016
 
CIRRICULUM VITAE - PelisP
CIRRICULUM VITAE - PelisPCIRRICULUM VITAE - PelisP
CIRRICULUM VITAE - PelisP
 
RMJugueta Resume 01172016
RMJugueta Resume 01172016RMJugueta Resume 01172016
RMJugueta Resume 01172016
 
Curriculum Vitae QS
Curriculum Vitae QSCurriculum Vitae QS
Curriculum Vitae QS
 
Survey Engr
Survey EngrSurvey Engr
Survey Engr
 
Abo-Eldardaa_CV_2015 & Duties
Abo-Eldardaa_CV_2015 & DutiesAbo-Eldardaa_CV_2015 & Duties
Abo-Eldardaa_CV_2015 & Duties
 
2015 CV
2015 CV 2015 CV
2015 CV
 
Cirriculum vitae pelis2
Cirriculum vitae  pelis2Cirriculum vitae  pelis2
Cirriculum vitae pelis2
 
Salem mohamed curriculum vitae
Salem mohamed curriculum vitaeSalem mohamed curriculum vitae
Salem mohamed curriculum vitae
 
Subhash CV Dec 2016
Subhash CV Dec 2016Subhash CV Dec 2016
Subhash CV Dec 2016
 
Adly CV111
Adly CV111Adly CV111
Adly CV111
 
Moustapha El Gharbawy Resume March 2015
Moustapha El Gharbawy Resume March 2015Moustapha El Gharbawy Resume March 2015
Moustapha El Gharbawy Resume March 2015
 
Hassan youssef c vs
Hassan youssef c vsHassan youssef c vs
Hassan youssef c vs
 
Imteyaz ahmad 12 yrs exp in MEP (Site / Project Management)
Imteyaz ahmad   12 yrs exp in MEP (Site / Project Management)Imteyaz ahmad   12 yrs exp in MEP (Site / Project Management)
Imteyaz ahmad 12 yrs exp in MEP (Site / Project Management)
 
Siemer_June 2016_updated
Siemer_June 2016_updatedSiemer_June 2016_updated
Siemer_June 2016_updated
 
SAQIB (2) (1)
SAQIB (2) (1)SAQIB (2) (1)
SAQIB (2) (1)
 
UPDATE CV 2015
UPDATE CV 2015UPDATE CV 2015
UPDATE CV 2015
 
CV Osama Hamad_Aug 2016
CV Osama Hamad_Aug 2016CV Osama Hamad_Aug 2016
CV Osama Hamad_Aug 2016
 

Viewers also liked

Viewers also liked (6)

Zafarullah CV.doc-001
Zafarullah CV.doc-001Zafarullah CV.doc-001
Zafarullah CV.doc-001
 
RAJESH RAMU CV
RAJESH RAMU CVRAJESH RAMU CV
RAJESH RAMU CV
 
LAND SURVEYOR Resume 2013 legat
LAND SURVEYOR Resume 2013 legatLAND SURVEYOR Resume 2013 legat
LAND SURVEYOR Resume 2013 legat
 
Surveyor cv
Surveyor cvSurveyor cv
Surveyor cv
 
Senior Surveyor CV
Senior Surveyor CV Senior Surveyor CV
Senior Surveyor CV
 
Land Surveyor Updated CV
Land Surveyor Updated CVLand Surveyor Updated CV
Land Surveyor Updated CV
 

Similar to Umer CV (20)

Umer CV
Umer CVUmer CV
Umer CV
 
hidayath cv 2016
hidayath cv 2016hidayath cv 2016
hidayath cv 2016
 
cv
cvcv
cv
 
new cv ali - Copy
new cv ali - Copynew cv ali - Copy
new cv ali - Copy
 
new cv ali - Copy
new cv ali - Copynew cv ali - Copy
new cv ali - Copy
 
CV Template mohamed1
CV Template mohamed1CV Template mohamed1
CV Template mohamed1
 
Naveed Asif C.V Updated
Naveed Asif C.V UpdatedNaveed Asif C.V Updated
Naveed Asif C.V Updated
 
inayat ur rahman cv 1
inayat ur rahman cv 1inayat ur rahman cv 1
inayat ur rahman cv 1
 
Bill resume
Bill resumeBill resume
Bill resume
 
CV Senior Quantity Surveyor(CIVIL)
CV Senior Quantity Surveyor(CIVIL)CV Senior Quantity Surveyor(CIVIL)
CV Senior Quantity Surveyor(CIVIL)
 
shafaqat cv 1
shafaqat cv 1shafaqat cv 1
shafaqat cv 1
 
CV mohamed
CV mohamedCV mohamed
CV mohamed
 
C.V E. Mahmoud -
C.V E. Mahmoud -C.V E. Mahmoud -
C.V E. Mahmoud -
 
Cv civil engineer ahmed mansour
Cv civil engineer ahmed mansourCv civil engineer ahmed mansour
Cv civil engineer ahmed mansour
 
cv civil ahmed mansour
cv civil ahmed mansourcv civil ahmed mansour
cv civil ahmed mansour
 
Cv civil ahmed mansour
Cv civil ahmed mansourCv civil ahmed mansour
Cv civil ahmed mansour
 
mohammad fathi cv2017
mohammad fathi cv2017mohammad fathi cv2017
mohammad fathi cv2017
 
Dnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CVDnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CV
 
mohammad fathi cv2017
mohammad fathi cv2017mohammad fathi cv2017
mohammad fathi cv2017
 
CV-Atif_Ashraf-4
CV-Atif_Ashraf-4CV-Atif_Ashraf-4
CV-Atif_Ashraf-4
 

Umer CV

  • 1. Date: December /2014. Name : Umer Nazir Date of birth : 01/11/1979 Nationality : Pakistani Current Position : Senior Survey inspector. Experience : 15 years. Contact : 00966 59 22 12 783 Pakistan : 0092 334 508 4728, Skype: umer.nazir16 Email : Sheikhs440@gmail.com Qualification: Education : Passed Intermediate & secondary education examination for Azad Jammu Kashmir Mirpur, Kashmir, Pakistan. - FSC for (faculty ofscience in pre engineering) from Rawalakot Degree College for Azad Jammu Kashmir board of Education Mirpur, Pakistan. Mirpur, Pakistan, Year 1999. - Diploma in surveying Punjab board of technical education Lahore, Pakistan, Year 2000. - Tow year’sdiplomainsurveyengineeringfrom modern institute of informatics and management MIIM Islamabad, for Punjab board of technical education Lahore, Pakistan, 2012. - Training : Course name, Period Year - Advance diplomaininformation technology. 250 hours 2002 - AUTO CAD 2004. Six months 2006 - Microsoft Office 200x (Professional Edition). 2 days 2006 - Civil 3D land desktop 2009. 3 days 2009 - Eagle point survey software. 3 days 2010 oto
  • 2. Experience : 15 years. 1) Position : Land Surveyor (Supervision) Duration : Nov 2011 to 17Nov 2014 Employer : Dar-Al-RiyadhConsultantengineeringarchitect. Projects : Ministryof Housing,Infrastructure ConstructionSupervision Consultant, (MOH),KSA. 1- Projectname : MOH baldingandInfrastructure,Rafha,ksa. Duration : 2 years Type of project : MOH Infrastructure Client : Ministryof Housing ProjectValue : 83 MillionSR Role inthis project : Land Surveyor. Infrastructure. - Provide assistance to the Resident Engineer/Project Engineer with - Serve as the site person responsible for coordinating the daily site survey works. - Prepare responses to the Contractors when required. - Submitdailyreportonsite surveyactivitiesasdirectedbythe Resident Engineer / Project Manager. - Supervise and remain vigilant regarding all aspects of the survey works. - Respond with appropriate and necessary levels of survey works to provide quality assurance in accordance with Contract Documents. - Assist the contractor on required survey procedures. - Coordinate with the contractor for any survey works. - Observe the safety procedures followed by the contractor. - Review the adequacy and accuracy of the survey records, Topographical Survey. - Traversing Survey. - Layout pipe line at tender drawing - Calculation of vertical & horizontal alignment - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. - Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Staking Global Positioning.
  • 3. 2- Projectname : KINGABDULLA FINANCIALDISTRICT(KAFD) Duration : From: 2011 To: Sept2013 (2 Years) Type of project : Building. Client : RIC,Riyadh. ProjectValue 7.8 billion USDollar Contract value : Scope of work : The financial sector and related industries, hosting the head quarters of the Capital Market Authority, the Stock Exchange, banks, financial institutions and other service providers such as accountants, auditors, lawyers,analysts, rating agencies, consultants, and IT providers. The King Abdullah Financial District provides the next generation of development and will ensure the sustained dominance of Saudi Arabia as the largest economy and financial centre within the region. (KAFD) isa new development under construction near King Fahad Road in the Asahafa area of Riyadh, Saudi Arabia being undertaken by the Riyadh Investment Corporation[3] on behalf of the Pension Authority of the Kingdom of Saudi Arabia, consisting of 34 towers in an area of 1.6 millionsquare meters.Itwill provide more than3millionsquare meters of space for various uses, 62,000 parking spaces and accommodation for 12,000 residents. In 2011 it was the largest project in the world seeking green building accreditation. Bombardier won a $241m USD contract to buildanautomated monorail forthe development.The districtisdesigned to keep it isolated from close contact with the strictly monitored Riyadh society.[7] The design guidelines do not separate the sexes in the district. The KAFD master plan was designed and overseen by Danish Architects Henning Larsen Henning Larsen Architects. Role inthis project : Surveyor (Supervision) - Provide assistance tothe ResidentEngineer/Project Engineer with prompt exchange of correspondence, submittals and RFI's to all relevantparties. Dealingwithsubcontractors,client & consultant. - Serve asthe site person responsibleforcoordinating the daily site survey works. Staking Global Positioning. - Submit daily report on site survey activities as directed by the Resident Engineer / Project Manager. - Supervise and remain vigilant regarding all aspects of the survey works. Topographic surveys, Building Location Surveys, Land Development. - Respondwithappropriate andnecessarylevels of survey works to provide qualityassurance inaccordance withContract Documents. - Assist the contractor on required survey procedures. - Coordinate with the contractor for any survey works. - Observe the safety procedures followed by the contractor. - Review the adequacy and accuracy of the survey records, - Traversing Survey, Topographical Survey. - Layout of substation, water pipe line, link roads to substation.
  • 4. 2) Position : Chiefsurveyor Duration : Feb 2011 to Nov 2011 Employer : Saudi Landscape & Contracting(SALCO) 1- Projects : (KAPSARC) Type of project : Hardscape,Landscape and Irrigation. Client : Armco. ProjectValue Hole project2 billion USDollar Contract value : Scope of work : King Abdullah Petroleum Studies and Research Centre (KAPSARC) is a future-oriented research and policy centre Committed to energy and environmental exploration and production and analysis. The 887,000 sq feet KAPSARC campus is Located in Riyadh, Saudi Arabia. The Entire complex will be LEED Platinum Rated upon completion, which is the highestLevel achievable underU.S. Green Building Council specifications. SAS Global’sinvolvement in this project has been to supply HSE & QA/QC management staff, Commercial teams, MEP & Commissioning staff & Interior design project management staff. - Provide assistance site Engineer/ site surveyors and report Project manager with prompt exchange of correspondence, submittals and RFI's to all relevant parties. - Serve as the site person responsible for coordinating the daily site survey works. - Prepare responses to the sub Contractors when required. - Submit daily report on site survey activities as directed to Project Manager. - Supervise and remain vigilant regarding all aspects of the survey works. - Coordinate with the consultant for any survey works. - Observe the safetyproceduresfollowedbythe Client and consultants. - Traversing Survey, Topographical Survey. - Calculation of vertical & horizontal alignment - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. Land planning Survey. - Land Development Surveys, staking Global Positioning.
  • 5. 2- Projects : The Main Linesof Sewage Systems Projectname : Sewage Network Al Ula. Duration : Sept 2010 To: Feb2011 Type of project : Infrastructure. Client : Ministryof Water and Electricity Contract value : 16,926,933 SR. Role inthis project : Chief Surveyor - All kind of survey work traversing Survey, sating out & calculations. - Layout pipe line attenderdrawing, Layoutpipe line attenderdrawing, supervision & control Surveyors team. - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys. - Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Serve as the site person responsible for coordinating the daily site survey works. - Prepare responses to the Contractors when required. - Submitdailyreportonsite surveyactivitiesasdirectedbythe Resident Engineer / Project Manager. - Supervise and remain vigilant regarding all aspects of the survey works. - Respond with appropriate and necessary levels of survey works to provide quality assurance in accordance with Contract Documents. - Assist the contractor on required survey procedures. - Coordinate with the consultant for any survey works. - Observe the safety procedures followed by the consultant. - Layout pipe line at tender drawing - Layout of substation, water pipe line, link roads to substation. - Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey.
  • 6. 3- Projectname : Rehabilitation of King Fahd Park and Palm Area Duration : Sept2010 To: March 2011. Type of project : SoftAndHard Landscape Works. Client : Al Madinah Regional Municipality Contract value : 46,766,989.00 SR. Scope of work : The central garden of Al Madina Al Munawarah is located at a distance of five kilometers in the south of the Prophet’s Mosque, and on the borders of the second circular road in Quba area which is famous of abundance of groundwater and density of palm farms therein. It is bordered by the district of Prince Naif from the north ,and Al Shabebah district from the west,and a plot of land related to the Department of Water and Sanitary Drainage inAl Madinah Munawarahfrom the eastand south,and the total area of the garden amounts to (4.3) m2. Also,a numberof entertainmentparkshave been established throughout Al Madinah Al Munawarahincluding:Bae’ganpark situated in universities road near Prince Muhammad Bin Abdul Aziz‘s Sports City. Role inthis : Project. - All kind of survey work traversing Survey, sating out & calculations. - Layout pipe line at tender drawing, supervision & control Surveyors team. - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. - Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Road and utility design surveys, Subdivision. - Surveys, construction staking Global Positioning. - Provide assistance site Engineer/ site surveyors and report Project manager. - Calculate levels and coordinates prepare necessary site repots and calculations for site surveyors.
  • 7. 4- Project name : Civil constructionwork,Roadbuildingpipelinedeferentpositionin Madina region. Duration : From: September2010 To: March 2011. Type of project : Civil constructionwork. Client : Al Madinah Regional Municipality Contract value : Multiple positionsdifferentvalue foreachproject. Role in this project : Chief Surveyor. - All kind of survey work traversing Survey, sating out & calculations. - Layout pipe line attenderdrawing,Layoutpipe line attenderdrawing, supervision & control Surveyors team. - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. - Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Road and utility design surveys, Subdivision. - Surveys, construction staking Global Positioning. - Provide assistance site Engineer/ site surveyors and report Project manager. - Calculate levels and coordinates prepare necessary site repots and calculations for site surveyors.
  • 8. 5 - Project name : TabukSewage project. Duration : From: May 2009 To: Jul 2010. Type of project : Infrastructure. Client : Ministryof Water and Electricity. Contract value : 52,641,034 SR Scope of work : The implementation and completion of a series of infrastructure and utilityservicesprojectsinTabuk region. The projects include construction of new residential majorand secondaryroads. These includedthe cost of studies, construction and supervision of water and sewage projects at a cost of million, flood protection walls around water treatment plants in Tabuk. Role in this project : Chief Surveyor - All kind of survey work traversing Survey, sating out & calculations. - Layout pipe line at tender drawing - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. - Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Road and utility design surveys, Subdivision. - Surveys, construction staking Global Positioning. - Provide assistance site Engineer/ site surveyors and report Project manager. - Calculate levels and coordinates prepare necessary site repots and calculations for site surveyors.
  • 9. 3) Position : Senior land surveyor Duration : Jan2006- May 2008 Employer : Al Jabar and partner,Qatar. Projects : Qatari Diar, Lusail City 1- Project name : Infrastructure of the Safe Lusail North and Water front Commercial districts of Lusail City. Duration : From: Jun2007 To: May 2008. Type of project : Infrastructure. Client : Qatari Diar real estate investmentcompanyLusail DohaQatar Contract value : Scope of work : More than 200,000 residentswilllive in Lusail’s scenic surroundings, with 170,000 people expected to work in the city’s different districts, and 80,000 expectedtovisit its entertainment and recreation facilities. Lusail City’s 19 districts will encompass not only new residential, commercial, hospitality,and retail opportunities, but a full array of community needs, complete withschools,mosques, medical facilities, sport, entertainment and shopping centers. Role in this project : Senior land Surveyor. - All kind of survey work traversing Survey, sating out & calculations. - Layout pipe line at tender drawing - Calculation of vertical & horizontal alignment - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. - Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Road and utility design surveys, Subdivision. - Land DevelopmentSurveys,hydrographicsurveys,constructionstaking Global Positioning. - Engineering Design Surveys, Construction layouts, Industrial development Surveys.
  • 10. 2- Project name : Integrated Gas and Gas to Liquids project. Duration : From: Jan2006 To: Jun2007. Type of project : Oil and Gas industry. Client : DevelopmentandProduction SharingAgreementwith Government of the State Qatar, 100% Shell funding. Project Value : Value of hole project $18 billion-$19billion Scope of work : Pearl GTL is a world-scale project located in Ras Laffan Industrial City, 80 km north of Doha, Qatar. With full ramp-up achieved towards the end of 2012, Pearl GTL is the world’s largest source of gas-to-liquids (GTL) products, capable of producing 140,000 barrels of GTL products each day. The plant alsoproduces120,000 barrelsof oil perday of natural gas liquids and ethane. Role in this project : SeniorlandSurveyor - All kind of survey work traversing Survey, sating out & calculations. - Layout pipe line at tender drawing - Calculation of vertical & horizontal alignment - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. - Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Road and utility design surveys, Subdivision. - Land DevelopmentSurveys,hydrographicsurveys,constructionstaking Global Positioning. - Engineering Design Surveys, Construction layouts, Industrial development Surveys.
  • 11. 4) Position : Senior land surveyor Duration : Feb 2004- may 2006 Employer : National survey engineering, U.A.E. Projects : Burj Khalifah(Burj Dubai). 1- Project name : Worldtower, Burj Dubai. Duration : From: Jun2007 To: may 2008 Type of project : MixedUse Client : Emaar PropertiesPJSC Contract value : 1.5bn USD Scope of work : Burj Khalifah(Burj Dubai) isthe tallestman-made structure everbuilt.The building is part of the 2 km2 development called Downtown Dubai. The mixed use development will include residential units, offices, hotels and residential apartments.The toweris composed of three elements arranged around a central core.As it rises from the flat desert base, each element is set back in an upward- spiralinghelical pattern,decreasingthe massof the toweras it reachestowardthe sky and thereby decreasing the wind effects. Role in this project : Senior land Surveyor - All kind of survey work traversing Survey, sating out & calculations. - Layout pipe line at tender drawing - Calculation of vertical & horizontal alignment - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys, Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Road and utility design surveys, Subdivision. - Land DevelopmentSurveys,hydrographicsurveys,constructionstaking Global Positioning. - Engineering Design Surveys, Construction layouts, Industrial development Surveys.
  • 12. 2- Project name : Pam Jumeirah IslandU.A.E Duration : From: Mar 2003To: May 2006 Type of project : MixedUse Client : Nakheel Project Value : Hole project,Itcost about 12.9 BillionUSD. Contract value : Scope of work : The Palm Jumeirah is an artificial archipelago created using land reclamation by Nakheel, a company owned by the Dubai government in United Arab Emirates and was designed and developed by HHCP architects. It is one of three planned islands called the Palm Islands (Palm Jumeirah, Palm Jebel Ali andPalm Deira) which would have extended into the Persian Gulf, increasing Dubai's shoreline by a total of 520 kilometers (320 mi). The Palm Jumeirah is the smallest and the original of three Palm Islands originally under development by Nakheel. It is located on the Jumeirah coastal area of the emirate of Dubai, in the UnitedArab Emirates (UAE).PalmJumeirah is the largest man-made island of the world for which construction was started in June 2001. More than 40000 workers from South Asia were involved in the construction work of the island, whichwasa mammothtask involving new techniques. The island was created by pouring in several million tons of sand into the deep sea bed with the help of dredgers.A special technique known as “rain bowing” was used in the process of reclamation of the land. Natural rock has been used in the creation of a natural breakwater in the island, which was created mainly to encourage sea life habitations. The total estimates cost involved in the project are almost US$12.3 billion.The firstresidentialunitswere handedovertothe proudresidents in 2006. Today, nearly 500 families are already residing here and enjoying in one of the dream destinations of the world. It is expected that by the end of the year 2009, 28 hotels in the Crescent will open their doors to welcome the tourists. Palm Jumeirahisset to become a tourist hot-spot in just a few years. To visit this most beautiful man-made island in the world. Role in this project : SeniorlandSurveyor. - Provide assistance to the Resident Engineer/Project Engineer with - Serve as the site person responsible for coordinating the daily site survey works. - Prepare responses to the Contractors when required. - Submit daily report on site survey activities as directed by the Resident Engineer / Project Manager. - Supervise and remain vigilant regarding all aspects of the survey works. Topographical Survey. - Respond with appropriate and necessary levels of survey works to provide quality assurance in accordance with Contract Documents. - Assist the consultant on required survey procedures. - Coordinate with the consultant for any survey works. - Observe the safety procedures followed by the contractor. - Review the adequacy and accuracy of the survey records,
  • 13. - Traversing Survey. - Layout pipe line at tender drawing - Calculation of vertical & horizontal alignment - Layout of substation, water pipe line, link roads to substation. - Dealing with sub contractors, client & consultant. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. - Topographic surveys, Building Location Surveys. - Planning Survey. Staking Global Positioning. Traversing Survey. - Layout of substation, water pipe line, link roads to substation. - Location Survey Levels. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. - Road and utility design surveys, Subdivision. - Land DevelopmentSurveys,hydrographicsurveys,constructionstaking Global Positioning. - Engineering Design Surveys, Construction layouts, Industrial development Surveys.
  • 14. 5) Position : Land surveyor. Duration : Dec 2001 - Mar 2003. Employer : Al Nasar Contracting Company LL.C. Projects : MixedUse 1- Project name : ShuweihatWaterTransmissionScheme - LotC Duration : 2 years Type of project : Water works/pumpingstation/ infrastructure/complete Civil andBuilding Works. Client : AbuDhabi Water & electricityAuthority(ADWEA). Project Value (by US Dollar) Contract value : (by US Dollar) Scope of work : The Shuweihat Water Transmission Scheme consists of mussaffah and Mirfa pumping stations, plus a parallel double pipeline 1600mm dia, 250kms in length, with a transfer capacity of 100 million gallons of water per day. The capacity of the system will be increased from 100 million gallons a day (MGD) to 180 million gallons a day (MGD) to facilitate water transmission from the Shuweihat Phase 2 independent water and power project. Al Nasr Contracting Co was awarded with The Subcontract Scope of Workscomprise the complete Civil and Building Works associated with the Mirfa Pumping Station as per the specifications, drawings and BOQ. Role in this project : Land surveyor - All kind of survey work traversing Survey, sating out & calculations. - Layout pipe line at tender drawing - Calculation of vertical & horizontal alignment - Layout of substation, water pipe line, link roads to substation. - The land title surveys, Boundary Surveys, Topographic surveys, Building Location Surveys. - Foundation Location Surveys, Utility and Pipeline Surveys, Land planning Survey. Leveling setting out and established control points. - Road and utility design surveys, Subdivision.
  • 15. 6) Position : land surveyor Duration : Apr 2001-Dec 2001 Employer : Habib Rafiq (Pvt.) Limited Projects : Workedas a civil surveyorLahore,Pakistan. 1- Project name : Lahore International Airport. Duration : From: Jun2007 To: may 2008 Type of project : MixedUse Client : CAA Contract value : Scope of work : Allama Iqbal International Airport (AIIAP) (formerly known as Lahore International Airport) is the second largest, and third busiest, airport in Pakistan. The airport handles an average of 75–80 flights each day, but the number of flights increases during the Hajj season and the airport handles about four million passengers a year. The completion of the new air terminal complex and its subsequent opening in March 2003 increased the capacity with the aim of accommodating up to 6.5 million passengers a year by 2015. Role in this project : Land surveyor. - Survey, sating out & calculations. - Layout pipe line - Calculation of vertical & horizontal alignment. - Layout of substation, water pipe line, link roads to substation. - The land title surveys, Boundary Surveys, horizontal and vertical control Surveys. - Topographic surveys, Building Location Surveys.