This document provides an agenda and details for Phase II Open Houses held by WOL-JV to discuss the Silver Lake Reservoir Consolidation Project. It includes introductions from the project management team and partner organizations. Presentations will cover the project scope, details, bidding packages, and requirements. Bid Package A involves excavation, piping, and drainage work, while Bid Package B includes concrete, earthwork, electrical, HVAC, and painting. Tentative dates are provided for prequalification and bidding on each package. The event will also discuss contractor bonding and include a Q&A session. Contact information is provided for any questions.
5. STEPHAN TUCKER | Project and Construction
Management, LADWP
• LADWP Greetings
• Outreach Goals and Commitment to
Project
6. DAN RAKERS/VINCE QUINONES |
Project Director, WOL-JV
• Phase II Presentation
• Project Scope
• Project Details
• Prequalification Packages
• Subcontract Agreement
• CCIP Manual
• Additional Statement and Federal Requirements
• PLA
7. BID PACKAGE A
• Sub Drains, Onsite Piping, RSC1A West
• Excavation/Installation/Backfill 3,000 LF of 78” WSP
• Excavation/ Installation/Backfill 102 LF of 72” Overflow WSP
• 13,334 LF of 8”subdrain pipe
• 2,900 LF of 6” wall/roof drains
• 3,121 LF of 12” Collector system, including manholes and
associated miscellaneous metal items
• Survey Services
• Fee Based Proposal and Award
• Field crew rate and office engineering rate to be included
• Geomembrane Liner & Miradrain System
• Placement of 550,000 SF of BGM & 330,000 SF of Miradrain
8. TENTATIVE DATES | Package A
July 6th, 2015- Prequalification RFQ Release
August 5th, 2015- Prequalification RFQ Deadline
August 14th, 2015- RFP Release
September 25th, 2015- RFP Deadline
9. BID PACKAGE B
• Concrete
• 90,000 CY Reservoir & Inlet Vault
• Chemical Mixing System
• Miscellaneous Metals for reservoir structure, and inlet vault
• Site Earthwork
• Reservoir Backfill
• Topsoil Placement
• Grading for Site Concrete
• Electrical
• Installation of electrical equipment
• Construction of duct banks
• Installation of power and control wiring
• Function test/Check out of all Project Electrical systems
10. BID PACKAGE B
• HVAC
• Ventilation systems at Inlet Vault and Manholes
• Site Concrete
• Access Roads, Crane Pads, V Gutters, Curbs
• Painting
• Finish coating of all exposed piping, valves and equipment,
including items within buildings and vaults
11. TENTATIVE DATES | Package B
July 6th, 2015- Prequalification RFQ Release
August 5th, 2015- Prequalification RFQ Deadline
November, 2015- RFP Release
December, 2015- RFP Deadline
12. KRISTINE MENDEZ | Director, Western Region
Surety, AON Construction Services Group
• Contractor Bonding