SlideShare a Scribd company logo
1 of 24
QUANTITY SURVEYING AND
VALUATION
Department of Civil
Engineering
TAUHEED ALAM KHAN
ASSISTANT PROFESSOR
JAHANGIRABAD INSTITUTE OF TECHNOLOGY
ESTIMATION
Estimation is the scientific way of working
out the approximate cost of an n is
engineering project before execution of the
work.
 It may differ from the calculation of the exact
cost after completion of the project.
 Estimation requires a thorough Knowledge of
the construction procedures, cost of materials &
labour in addition to the skill, experience,
foresight and good judgment.
ESTIMATE
An estimate of the cost of a construction job is
the probable cost of that job as computed from
plans and specifications.
 For a good estimate the actual cost of the
proposed work after completion should not differ
by more than 5 to 10 % from its approximate
cost estimate.
UNITS OF
MEASUREMENTS
The units of measurements are mainly categorized for their nature, shape
and size and for making payments to the contractor.
a) Single units work like doors, windows etc, is expressed in
numbers.
b) Works consists linear measurements involve length like
cornice, fencing, hand rail etc., are expressed in running
meters (RM)
c) Works consists areal surface measurements like plastering,
white washing, partitions of specified thickness etc., are
expressed in square meters.
d) Works consists cubical contents which involve volume like
earth work, cement concrete, Masonry etc., are expressed in
Cubic meters.
NEED OF ESTIMATION & COSTING
1. It help to work out the approximate cost of the project in order to
decide its feasibility with respect to the cost and to ensure the
financial resources.
2. Requirements of controlled materials, such as cement and steel
can be estimated.
3. It is used for framing the tenders for the works and to check
contractor’s work during and after the its execution for the
purpose of making payments to the contractor.
4. From quantities of different items of work calculated in detailed
estimation, resources are allocated to different activities of the
project and ultimately their durations and whole planning and
scheduling of the project is carried out.
DATA REQUIRED TO PREPARE AN
ESTIMATE
1) DRAWINGS
If the drawings are not clear and without complete
dimensions the preparation of estimation become very
difficult. So, it is very essential before preparing an estimate.
2) SPECIFICATIONS
a) General Specifications:
This gives the nature, quality of work and materials in general
terms to be used in various parts of wok. It helps to form a general
idea of building.
b) Detailed Specifications:
This gives the detailed description of the various items of work
laying down the Quantities and qualities of materials, their
proportions, the method of preparation workmanship and execution
of work.
3) RATES
For preparing the estimate the unit rates of each item of work
are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labor, skilled or unskilled of masons,
carpenters, Amador, etc.,
LUMPSUM:
While preparing an estimate, it is not possible to work out in
detail in case of petty items. Items other than civil engineering
such items are called lump sum items or simply L.S.Items.
Factors to be considered for estimation
1. Each type of work requires a different method of
construction. Construction may be of an ordinary house or
office and it may also be of a Dam, Tunnel, Multistory
building, Airport, Bridge, or a Road, already in operation.
Each of these works requires totally different construction
techniques, type of machinery, and formwork.
2. Quality of labour and labour output varies in different
localities.
3. Weather conditions greatly affect the output and, hence,
the overall cost.
Factors to be considered for estimation (-ctd-)
4. Ground conditions vary and change the method of
construction. For example, excavation may be dry, wet,
hard, soft, shallow or deep requiring different efforts.
5. The source of availability of a sufficient supply of
materials of good quality.
6. The availability of construction machinery also affects
the method of construction.
7. Access to the site must be reasonable. If the access is
poor, temporary roads may be constructed.
TYPES OF ESTIMATES
There are two main types of estimates:-
 Rough (or) approximate estimate.
 Detailed estimate.
Rough (or) approximate estimate
 Preliminary or approximate estimate is required for studies of various
aspects of work of project and for its administrative approval.
 It can decide, in case of commercial projects, whether the net income
earned justifies the amount invested or not. The approximate estimate
is prepared from the practical knowledge and cost of similar works.
 The following are the methods used for preparation of approximate
estimates.
1) Plinth area method
2) Cubical contents methods
3) Unit base method.
1) Plinth area method
cost of construction = Plinth area x plinth area rate.
2) Cubical Contents Method
It is more accurate that the other two methods viz., plinth area method
and unit base method.
cost of construction = Total cubical contents x Local Cubic Rate.
3) Unit Base Method
. For public buildings, cost. Per person (cost per capita) is used. For
example,
Students hostel - cost per student
Hospital - Cost per bed
Hotel - Cost per Guest
DETAILED ESTIMATE
• Detailed estimates are prepared by carefully and
separately calculating the costs of various item of the
work that constitute the whole project from the detailed
working drawings after the design has been finalized.
• The mistakes, if any, in the rough cost estimate are
eliminated in the detailed estimate.
• Detailed estimates are submitted to the competent
authorities for obtaining technical sanction.
DETAILED ESTIMATE
 The whole project is sub-divided into different items of
work or activities. The quantity for each item is then
calculated separately from the drawings as accurately as
possible. The procedure is known as "taking out of
quantities".
 The quantities for each item may be estimated and shown
in the pattern which is called "Bill of quantities."
 The unit, in which each item of the wok is to be
calculated, should be according to the prevailing practice
as followed in various departments of the country.
BILL OF QUANTITIES
Sr. No
Description
of item
No Measurements Quantity Total
Quantity
Remarks
Length Breadth Height
PRICED BILL OF QUANTITIES
Sr. No. Description of Item Unit Quantity Rate Cost Remarks
DETAILED ESTIMATE
 Each item of the work is then multiplied by its estimated
current rate calculated by a fixed procedure to find out cost of
the item.
 At the end, a total of all items of the work are made to get the
total estimated cost.
 The rates are usually as per Schedule of Rates for the
locality plus a premium to allow for rise in labor and material
rates over and above the schedule of rates.
 A percentage, usually 5% is also provided on the total
estimated cost for the work to allow for the possible
contingencies due to unforeseen items or expenditure or
other causes, besides 2% establishment charges.
DETAILED ESTIMATE
Besides drawings and details of measurements and
calculation of quantities (Bill of Quantities), the following
documents are also usually submitted with the detailed
estimate for obtaining Technical Sanction:
1. A report explaining History, necessity, scope and main features of the
project, its design, and estimate, etc.
2. Specifications lying down the nature and class of work and material
to be used in various parts of the work.
3. The abstract of cost (priced Bill of Quantities) showing the total
quantities under each sub-head, rate per unit of measurement, and
cost.
4. Calculation sheets showing calculations for important parts of the
structure. In fact, in estimating the art and skill lies only in the
computation of details without any omissions, of all parts of the
building or work.
METHODS OF DETAILED ESTIMATE
 The dimensions, length, breadth and height or depth are to
be taken out from the working drawings (plan, elevation and
section).
 Junctions of walls, corners and the meeting points of walls
require special attention.
 For symmetrical footings, which is the usual case, earthwork
in excavation in foundations, foundation concrete, brickwork
in foundation and plinth, and brickwork in superstructure may
be estimated by either of the two methods:
(1) LONG WALL & SHORT WALL METHOD
(2) CENTER LINE METHOD
LONG WALL & SHORT WALL METHOD (or)
SEPARATE WALL METHOD
• The walls running in one direction are termed as
"long walls” and the walls running in the
transverse direction, as "Short walls.
• Lengths of long walls are measured or found
"Out-to out" and those of short walls as "In-to-
in".
• Different quantities are calculated by multiplying
the length by the breadth and the height of the
wall.
LONG WALL & SHORT WALL METHOD
• Long wall length out-to-out
= Center to center length + half breadth on one Side
+ half breadth on other side.
= Center to center length + one breadth
• Short wall length in-to-in
= Center to Center length - one breadth.
CENTER LINE METHOD
 In this method, total length of center lines of walls, long
and short, has to be found out.
 In this method, the length will remain the same for
excavation in foundations, for concrete in foundations,
for all footings, and for superstructure (with slight
difference when there are cross walls or number of
junctions).
 This method is quicker but requires special attention
and considerations at the junctions, meeting points of
partition or cross walls.
CENTER LINE METHOD
For rectangular, circular polygonal (hexagonal,
octagonal etc.,) buildings having no inter or cross
walls, this method is quite simple.
For buildings having cross or partition walls, for every
junction, half breadth of the respective item or footing
is to be deducted from the total center length.
Thus in the case of a building with one partition wall or
cross wall having two junctions, deduct one breadth of
the respective item of work from the total center
length.
References:
 Dutta, B.N., “Estimating and Costing in Civil Engineering”,
UBS Publishers & Distributors Pvt. Ltd., New Delhi, 2003.
 https://www.wikipedia.org/
 https://nptel.ac.in/course.php
 https://www.vidyarthiplus.com/studymaterials.php

More Related Content

What's hot

Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
TEST ON HARDENED CONCRETE
TEST ON HARDENED CONCRETETEST ON HARDENED CONCRETE
TEST ON HARDENED CONCRETEJaswanth J
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundationSourabh Jain
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18SANJEEV Wazir
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concreteKaran Patel
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorAshwiniChaudhari13
 
Maintenance and repair of buildings.
Maintenance and repair of buildings.Maintenance and repair of buildings.
Maintenance and repair of buildings.Satyaki Sikdar
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1ArunRavi43
 
UNIT-1 PSC.pptx
UNIT-1 PSC.pptxUNIT-1 PSC.pptx
UNIT-1 PSC.pptxjairam131
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-convertedNigitha rajan
 
Planning of materials in Construction Project management
Planning of materials in Construction Project managementPlanning of materials in Construction Project management
Planning of materials in Construction Project managementAravind Samala
 
Construction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationConstruction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationSagar Radadiya
 

What's hot (20)

Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
TEST ON HARDENED CONCRETE
TEST ON HARDENED CONCRETETEST ON HARDENED CONCRETE
TEST ON HARDENED CONCRETE
 
Special Concretes
Special Concretes Special Concretes
Special Concretes
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimator
 
Earth pressure
Earth pressureEarth pressure
Earth pressure
 
Maintenance and repair of buildings.
Maintenance and repair of buildings.Maintenance and repair of buildings.
Maintenance and repair of buildings.
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 
UNIT-1 PSC.pptx
UNIT-1 PSC.pptxUNIT-1 PSC.pptx
UNIT-1 PSC.pptx
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-converted
 
Planning of materials in Construction Project management
Planning of materials in Construction Project managementPlanning of materials in Construction Project management
Planning of materials in Construction Project management
 
Construction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationConstruction equipments - Introduction and Classification
Construction equipments - Introduction and Classification
 

Similar to Quantity Surveying & valuation.ppt

Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Padmasinh Patil
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for buildingHimani762003
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptBALAMURUGANR53
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).pptNaumanIjaz12
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notesDr.K.Mohan Das
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptSOUMITRAMUDI
 
CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdfhitusp
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing2cd
 
Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Padmasinh Patil
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfsuchitamantry2002
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdfDeepak37004
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingila vamsi krishna
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 

Similar to Quantity Surveying & valuation.ppt (20)

Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Ecv
EcvEcv
Ecv
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notes
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation_and_Costing.ppt
Estimation_and_Costing.pptEstimation_and_Costing.ppt
Estimation_and_Costing.ppt
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdf
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing
 
Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 

Quantity Surveying & valuation.ppt

  • 1. QUANTITY SURVEYING AND VALUATION Department of Civil Engineering TAUHEED ALAM KHAN ASSISTANT PROFESSOR JAHANGIRABAD INSTITUTE OF TECHNOLOGY
  • 2. ESTIMATION Estimation is the scientific way of working out the approximate cost of an n is engineering project before execution of the work.  It may differ from the calculation of the exact cost after completion of the project.  Estimation requires a thorough Knowledge of the construction procedures, cost of materials & labour in addition to the skill, experience, foresight and good judgment.
  • 3. ESTIMATE An estimate of the cost of a construction job is the probable cost of that job as computed from plans and specifications.  For a good estimate the actual cost of the proposed work after completion should not differ by more than 5 to 10 % from its approximate cost estimate.
  • 4. UNITS OF MEASUREMENTS The units of measurements are mainly categorized for their nature, shape and size and for making payments to the contractor. a) Single units work like doors, windows etc, is expressed in numbers. b) Works consists linear measurements involve length like cornice, fencing, hand rail etc., are expressed in running meters (RM) c) Works consists areal surface measurements like plastering, white washing, partitions of specified thickness etc., are expressed in square meters. d) Works consists cubical contents which involve volume like earth work, cement concrete, Masonry etc., are expressed in Cubic meters.
  • 5. NEED OF ESTIMATION & COSTING 1. It help to work out the approximate cost of the project in order to decide its feasibility with respect to the cost and to ensure the financial resources. 2. Requirements of controlled materials, such as cement and steel can be estimated. 3. It is used for framing the tenders for the works and to check contractor’s work during and after the its execution for the purpose of making payments to the contractor. 4. From quantities of different items of work calculated in detailed estimation, resources are allocated to different activities of the project and ultimately their durations and whole planning and scheduling of the project is carried out.
  • 6. DATA REQUIRED TO PREPARE AN ESTIMATE 1) DRAWINGS If the drawings are not clear and without complete dimensions the preparation of estimation become very difficult. So, it is very essential before preparing an estimate. 2) SPECIFICATIONS a) General Specifications: This gives the nature, quality of work and materials in general terms to be used in various parts of wok. It helps to form a general idea of building. b) Detailed Specifications: This gives the detailed description of the various items of work laying down the Quantities and qualities of materials, their proportions, the method of preparation workmanship and execution of work.
  • 7. 3) RATES For preparing the estimate the unit rates of each item of work are required. 1. For arriving at the unit rates of each item. 2. The rates of various materials to be used in the construction. 3. The cost of transport materials. 4. The wages of labor, skilled or unskilled of masons, carpenters, Amador, etc., LUMPSUM: While preparing an estimate, it is not possible to work out in detail in case of petty items. Items other than civil engineering such items are called lump sum items or simply L.S.Items.
  • 8. Factors to be considered for estimation 1. Each type of work requires a different method of construction. Construction may be of an ordinary house or office and it may also be of a Dam, Tunnel, Multistory building, Airport, Bridge, or a Road, already in operation. Each of these works requires totally different construction techniques, type of machinery, and formwork. 2. Quality of labour and labour output varies in different localities. 3. Weather conditions greatly affect the output and, hence, the overall cost.
  • 9. Factors to be considered for estimation (-ctd-) 4. Ground conditions vary and change the method of construction. For example, excavation may be dry, wet, hard, soft, shallow or deep requiring different efforts. 5. The source of availability of a sufficient supply of materials of good quality. 6. The availability of construction machinery also affects the method of construction. 7. Access to the site must be reasonable. If the access is poor, temporary roads may be constructed.
  • 10. TYPES OF ESTIMATES There are two main types of estimates:-  Rough (or) approximate estimate.  Detailed estimate.
  • 11. Rough (or) approximate estimate  Preliminary or approximate estimate is required for studies of various aspects of work of project and for its administrative approval.  It can decide, in case of commercial projects, whether the net income earned justifies the amount invested or not. The approximate estimate is prepared from the practical knowledge and cost of similar works.  The following are the methods used for preparation of approximate estimates. 1) Plinth area method 2) Cubical contents methods 3) Unit base method.
  • 12. 1) Plinth area method cost of construction = Plinth area x plinth area rate. 2) Cubical Contents Method It is more accurate that the other two methods viz., plinth area method and unit base method. cost of construction = Total cubical contents x Local Cubic Rate. 3) Unit Base Method . For public buildings, cost. Per person (cost per capita) is used. For example, Students hostel - cost per student Hospital - Cost per bed Hotel - Cost per Guest
  • 13. DETAILED ESTIMATE • Detailed estimates are prepared by carefully and separately calculating the costs of various item of the work that constitute the whole project from the detailed working drawings after the design has been finalized. • The mistakes, if any, in the rough cost estimate are eliminated in the detailed estimate. • Detailed estimates are submitted to the competent authorities for obtaining technical sanction.
  • 14. DETAILED ESTIMATE  The whole project is sub-divided into different items of work or activities. The quantity for each item is then calculated separately from the drawings as accurately as possible. The procedure is known as "taking out of quantities".  The quantities for each item may be estimated and shown in the pattern which is called "Bill of quantities."  The unit, in which each item of the wok is to be calculated, should be according to the prevailing practice as followed in various departments of the country.
  • 15. BILL OF QUANTITIES Sr. No Description of item No Measurements Quantity Total Quantity Remarks Length Breadth Height
  • 16. PRICED BILL OF QUANTITIES Sr. No. Description of Item Unit Quantity Rate Cost Remarks
  • 17. DETAILED ESTIMATE  Each item of the work is then multiplied by its estimated current rate calculated by a fixed procedure to find out cost of the item.  At the end, a total of all items of the work are made to get the total estimated cost.  The rates are usually as per Schedule of Rates for the locality plus a premium to allow for rise in labor and material rates over and above the schedule of rates.  A percentage, usually 5% is also provided on the total estimated cost for the work to allow for the possible contingencies due to unforeseen items or expenditure or other causes, besides 2% establishment charges.
  • 18. DETAILED ESTIMATE Besides drawings and details of measurements and calculation of quantities (Bill of Quantities), the following documents are also usually submitted with the detailed estimate for obtaining Technical Sanction: 1. A report explaining History, necessity, scope and main features of the project, its design, and estimate, etc. 2. Specifications lying down the nature and class of work and material to be used in various parts of the work. 3. The abstract of cost (priced Bill of Quantities) showing the total quantities under each sub-head, rate per unit of measurement, and cost. 4. Calculation sheets showing calculations for important parts of the structure. In fact, in estimating the art and skill lies only in the computation of details without any omissions, of all parts of the building or work.
  • 19. METHODS OF DETAILED ESTIMATE  The dimensions, length, breadth and height or depth are to be taken out from the working drawings (plan, elevation and section).  Junctions of walls, corners and the meeting points of walls require special attention.  For symmetrical footings, which is the usual case, earthwork in excavation in foundations, foundation concrete, brickwork in foundation and plinth, and brickwork in superstructure may be estimated by either of the two methods: (1) LONG WALL & SHORT WALL METHOD (2) CENTER LINE METHOD
  • 20. LONG WALL & SHORT WALL METHOD (or) SEPARATE WALL METHOD • The walls running in one direction are termed as "long walls” and the walls running in the transverse direction, as "Short walls. • Lengths of long walls are measured or found "Out-to out" and those of short walls as "In-to- in". • Different quantities are calculated by multiplying the length by the breadth and the height of the wall.
  • 21. LONG WALL & SHORT WALL METHOD • Long wall length out-to-out = Center to center length + half breadth on one Side + half breadth on other side. = Center to center length + one breadth • Short wall length in-to-in = Center to Center length - one breadth.
  • 22. CENTER LINE METHOD  In this method, total length of center lines of walls, long and short, has to be found out.  In this method, the length will remain the same for excavation in foundations, for concrete in foundations, for all footings, and for superstructure (with slight difference when there are cross walls or number of junctions).  This method is quicker but requires special attention and considerations at the junctions, meeting points of partition or cross walls.
  • 23. CENTER LINE METHOD For rectangular, circular polygonal (hexagonal, octagonal etc.,) buildings having no inter or cross walls, this method is quite simple. For buildings having cross or partition walls, for every junction, half breadth of the respective item or footing is to be deducted from the total center length. Thus in the case of a building with one partition wall or cross wall having two junctions, deduct one breadth of the respective item of work from the total center length.
  • 24. References:  Dutta, B.N., “Estimating and Costing in Civil Engineering”, UBS Publishers & Distributors Pvt. Ltd., New Delhi, 2003.  https://www.wikipedia.org/  https://nptel.ac.in/course.php  https://www.vidyarthiplus.com/studymaterials.php