SlideShare a Scribd company logo
1 of 27
Types
of
Estimate
 Rough Estimate
• Assembly Estimate
• Parametric Estimate
• Model Estimate
• Project Comparison Estimate
 Detailed Estimate
Types Of Estimates
There are two main types of estimates:-
1 Rough cost estimate.
2 Detailed estimate.
Depending upon the purpose of estimate, some types
of detailed estimate are as follows:-
a) Contractor's estimate
b) Engineer's estimate
c) Progress estimate
Types Of Estimates
• Estimation of cost before construction from plans or
architectural drawings of the project scheme, when even
detailed or structural design has not been carried out, is called
Rough cost estimate.
• These estimates are used for obtaining Administrative Approval
from the concerning Authorities.
• Sometimes, on the basis of rough cost estimates, a proposal
may be dropped altogether.
Rough Cost Estimate
• Unit cost is worked out for projects similar to the
project under consideration carried out recently in
nearly the same site conditions.
• Unit cost means cost of execution of a unit quantity of
the work.
Rough Cost Estimate (-Ctd-)
• To find rough cost of any project, this worked average unit cost is
multiplied with total quantity of the present work in the same units.
• For example, in case of a building, plinth area (sq. ft.) of the
proposed building is worked out, which is then multiplied by the
cost per unit area (Rs. /ft2) of similar building actually constructed
in the near past in nearly the same site conditions, to find out the
rough cost estimate of the building.
• This cost is sometimes adjusted by the average percentage rise in
the cost of materials and wages.
Rough Cost Estimate (-Ctd-)
 The rough cost estimate may be prepared on the following basis for different
types of projects:
1. Cost per square foot of covered area (plinth area) is the most commonly
adopted criterion for preparing rough cost estimate for most of the residential
buildings.
2. For public buildings, cost. Per person (cost per capita) is used. For example,
Students hostel ———————— Cost per student
Hospitals ———————— Cost per bed
Hotel ———————— Cost per Guest
Rough Cost Estimate
Rough Cost Estimate
3. Cost per cubic foot is particularly suitable for commercial
offices, shopping centers, and factory buildings, etc.
4. For water tank/reservoir, cost may be worked out on the basis
of capacity in gallons of water stored.
5. For roads and railways, cost may be found out per
mile/kilometer of length.
6. For streets, cost may be per hundred feet/meters of length.
7. In case of bridges, cost per foot/meter of clear span may be
calculated.
 Calculate the total rough cost estimate and cost per
flat for a multi-story (4-story) building consisting of
40 residential flats. Other details are given in the
table:
Example 1
Sr.No PORTION
AREA
(sq. ft)
UNIT COST (Rs./sq.ft.)
Building
Works
Sanitary
Works
Electric
Services
Sui Gas
Services
1
Main Flat Area
(i) Ground Floor
(ii) Ist Floor
(iii) 2nd Floor
(iv) 3rd Floor
20030
20030
20030
20030
1800
1500
1650
1800
130
130
130
130
100
100
100
100
60
60
60
60
2 Park Area at G. Floor 75,800 800 -------- 40 -------
3
Circulation Area in all 4
floors
1936 1050 -------- 70 -------
4
Covered Shopping Area at
G. Floor
920 950 -------- 70 -------
5 Attached Servant Quarters 2112 1150 55 70 40
1- Road and Walkways = 15,00,000/-
2- Land Scapping = 12,00,000/-
3- External Sewerage = 7,00,000/-
4- External Water Supply, Overhead and Underground Water
Tanks with pumping machinery for each set of Flats =
19,00,000/-
5- External Electricity = 3,00,000/-
6- Boundary Wall = 6,00,000/-
7- Miscellaneous unforeseen items = 8,00,000/-
8- Add 6 % development charges.
9- Add 3 % consultancy charges
Add the following costs as Lump Sum :
 Prepare a Rough-cost Estimate of a residential building project
with a total plinth area of all building of 1500 sq.m. given that:
 Plinth Area Rate = Rs: 950.00 / sq. ft.
 Extra for special architectural treatment = 1.5 % of the building cost.
 Extra for water supply and sanitary installations = 5 % of the building cost.
 Extra for internal installations = 14 % of the building cost
 Extra for Electric & Sui gas services = 16 % of building cost
 Contingencies = 3 % overall
 Supervision charges = 8 % overall
 Design charges = 2 % overall
Example 2
Prepare a Rough-cost Estimate based on unit cost, of a four story office
building having a carpet area of 2000 sq.m. for obtaining the
administrative approval of the Government. It may be assumed that 30 %
of the built up area will be taken by the corridors, verandas, lavatories,
staircase, etc. and 10 % of built up area will be occupied by walls. The
following data is given:
 Super-Built Area Rate = Rs: 1100.00 / sq. ft.
 Extra for special architectural treatment = 0.5 % of the building cost.
 Extra for water supply and sanitary installations = 6 % of the building
cost.
Example 3
 Extra for internal installations = 14 % of the building cost
 Extra for electric services = 12.5 % of building cost
 Extra for sui gas services = 6 % of building cost
 Extra due to deep foundations at site = 1.0 % of building cost
 Contingencies = 2.5 % overall
 Supervision charges = 8 % overall
 Design charges = 2.5 % overall
Example 3
Prepare a Rough-cost Estimate for obtaining the administrative
approval of the Government for a hospital project to serve both indoor
and outdoor patients in an important rural area. The hospital will
consist of the following:
 Main administrative office with dispensing operations, etc.
 Two general wards, each of 20 general beds.
 Superintendent Doctor’s Residence.
 Two Assistant Doctor’s Residences.
 Eight single Nurses Quarters.
 Four Compounder’s Quarters.
 Twelve lower staff’s Quarters.
Example 4
• Detailed estimates are prepared by carefully and separately
calculating in detail, the costs of various items of the work that
constitute the whole project from the detailed working drawings
after the design has been finalized.
• The mistakes, if any, in the rough cost estimate are eliminated in
the detailed estimate.
• Detailed estimates are submitted to the competent authorities for
obtaining technical sanction.
Detailed Estimate
 The whole project is sub-divided into different items of work or
activities. The quantity for each item is then calculated separately
from the drawings as accurately as possible. The procedure is
known as "taking out of quantities".
 The quantities for each item may be estimated and shown in the
pattern which is called "Bill of quantities."
 The unit, in which each item of the wok is to be calculated, should
be according to the prevailing practice as followed in various
departments of the country.
Detailed Estimate
Bill Of Quantities
Sr. No
Description
of item
No
Measurements
Quantity
Total
Quantity
Remarks
Length Breadth Height
Priced Bill Of Quantities
Sr. No Description of Item Unit Quantity Rate Cost Remarks
 Each item of the work is then multiplied by its estimated current rate
calculated by a fixed procedure to find out cost of the item.
 At the end, a total of all items of the work are made to get the total
estimated cost.
 The rates are usually as per Schedule of Rates for the locality plus a
premium to allow for rise in labor and material rates over and above the
schedule of rates.
 A percentage, usually 5% is also provided on the total estimated cost for
the work to allow for the possible contingencies due to unforeseen items
or expenditure or other causes, besides 2% establishment charges.
Detailed Estimate
 Besides drawings and details of measurements and calculation of
quantities (Bill of Quantities), the following documents are also usually
submitted with the detailed estimate for obtaining Technical Sanction:
1. A report explaining History, necessity, scope and main features of the
project, its design, and estimate, etc.
2. Specifications lying down the nature and class of work and material to be
used in various parts of the work.
3. The abstract of cost (priced Bill of Quantities) showing the total
quantities under each sub-head, rate per unit of measurement, and cost.
4. Calculation sheets showing calculations for important parts of the
structure. In fact, in estimating the art and skill lies only in the
computation of details without any omissions, of all parts of the building
or work.
Detailed Estimate
Classification Depending Upon Purpose Of
Detailed Estimate
1- Contractor Estimate
It is made by the contractor for determining the price or prices to
be bid.
It is usually a carefully prepared detailed estimate.
2- Engineer’s Estimate
This type of estimate is made by the Engineer (Consultant) usually
for the purposes of financing the work and for checking bids and
running bills submitted by contractors.
3- Progress Estimate
• These are made by the Engineer at regular intervals for the
completed parts of the project during the progress of the work for
determining the amounts of partial payments to be made to the
contractor.
• On large contracts, such estimates are commonly made each month
and, hence, are frequently called monthly estimates.
Classification Depending Upon Purpose Of
Detailed Estimate
 Carpet Area: Total usable area within the four walls of an apartment
or a commercial space, as the case may be. In other words, it refers
to the area for which a carpet can be laid if required by the owners.
 Plinth Area: The entire carpet area along with the thickness of the
external walls of the apartment. It obviously includes the thickness of
the internal walls and the columns, if any, lying within the four walls
of an apartment. The commercial space is not taken into account in
calculating the plinth area.
 Super Built-up Area: The plinth area of an apartment or a
commercial unit as added by the balconies and other common areas
like corridors, staircase, lift room, motor room, security room,
meeting hall, gymnasium and an area reserved for indoor games.
Basic Terms
Lec05.pptx
Lec05.pptx

More Related Content

Similar to Lec05.pptx

estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for buildingHimani762003
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxrikeshbisen
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIALNat Rice
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptBALAMURUGANR53
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdfBSuresh26
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxcricketreview
 
2# types of estimate
2# types of estimate2# types of estimate
2# types of estimateLIJI A
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdfDeepak37004
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptSOUMITRAMUDI
 
Estimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresEstimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresAyan Sengupta
 

Similar to Lec05.pptx (20)

estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptx
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Ecv
EcvEcv
Ecv
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdf
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
 
2# types of estimate
2# types of estimate2# types of estimate
2# types of estimate
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation_and_Costing.ppt
Estimation_and_Costing.pptEstimation_and_Costing.ppt
Estimation_and_Costing.ppt
 
Estimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresEstimating & costing of civil engineering structures
Estimating & costing of civil engineering structures
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Lec05.pptx

  • 1.
  • 3.  Rough Estimate • Assembly Estimate • Parametric Estimate • Model Estimate • Project Comparison Estimate  Detailed Estimate Types Of Estimates
  • 4. There are two main types of estimates:- 1 Rough cost estimate. 2 Detailed estimate. Depending upon the purpose of estimate, some types of detailed estimate are as follows:- a) Contractor's estimate b) Engineer's estimate c) Progress estimate Types Of Estimates
  • 5. • Estimation of cost before construction from plans or architectural drawings of the project scheme, when even detailed or structural design has not been carried out, is called Rough cost estimate. • These estimates are used for obtaining Administrative Approval from the concerning Authorities. • Sometimes, on the basis of rough cost estimates, a proposal may be dropped altogether. Rough Cost Estimate
  • 6. • Unit cost is worked out for projects similar to the project under consideration carried out recently in nearly the same site conditions. • Unit cost means cost of execution of a unit quantity of the work. Rough Cost Estimate (-Ctd-)
  • 7. • To find rough cost of any project, this worked average unit cost is multiplied with total quantity of the present work in the same units. • For example, in case of a building, plinth area (sq. ft.) of the proposed building is worked out, which is then multiplied by the cost per unit area (Rs. /ft2) of similar building actually constructed in the near past in nearly the same site conditions, to find out the rough cost estimate of the building. • This cost is sometimes adjusted by the average percentage rise in the cost of materials and wages. Rough Cost Estimate (-Ctd-)
  • 8.  The rough cost estimate may be prepared on the following basis for different types of projects: 1. Cost per square foot of covered area (plinth area) is the most commonly adopted criterion for preparing rough cost estimate for most of the residential buildings. 2. For public buildings, cost. Per person (cost per capita) is used. For example, Students hostel ———————— Cost per student Hospitals ———————— Cost per bed Hotel ———————— Cost per Guest Rough Cost Estimate
  • 9. Rough Cost Estimate 3. Cost per cubic foot is particularly suitable for commercial offices, shopping centers, and factory buildings, etc. 4. For water tank/reservoir, cost may be worked out on the basis of capacity in gallons of water stored. 5. For roads and railways, cost may be found out per mile/kilometer of length. 6. For streets, cost may be per hundred feet/meters of length. 7. In case of bridges, cost per foot/meter of clear span may be calculated.
  • 10.  Calculate the total rough cost estimate and cost per flat for a multi-story (4-story) building consisting of 40 residential flats. Other details are given in the table: Example 1
  • 11. Sr.No PORTION AREA (sq. ft) UNIT COST (Rs./sq.ft.) Building Works Sanitary Works Electric Services Sui Gas Services 1 Main Flat Area (i) Ground Floor (ii) Ist Floor (iii) 2nd Floor (iv) 3rd Floor 20030 20030 20030 20030 1800 1500 1650 1800 130 130 130 130 100 100 100 100 60 60 60 60 2 Park Area at G. Floor 75,800 800 -------- 40 ------- 3 Circulation Area in all 4 floors 1936 1050 -------- 70 ------- 4 Covered Shopping Area at G. Floor 920 950 -------- 70 ------- 5 Attached Servant Quarters 2112 1150 55 70 40
  • 12. 1- Road and Walkways = 15,00,000/- 2- Land Scapping = 12,00,000/- 3- External Sewerage = 7,00,000/- 4- External Water Supply, Overhead and Underground Water Tanks with pumping machinery for each set of Flats = 19,00,000/- 5- External Electricity = 3,00,000/- 6- Boundary Wall = 6,00,000/- 7- Miscellaneous unforeseen items = 8,00,000/- 8- Add 6 % development charges. 9- Add 3 % consultancy charges Add the following costs as Lump Sum :
  • 13.  Prepare a Rough-cost Estimate of a residential building project with a total plinth area of all building of 1500 sq.m. given that:  Plinth Area Rate = Rs: 950.00 / sq. ft.  Extra for special architectural treatment = 1.5 % of the building cost.  Extra for water supply and sanitary installations = 5 % of the building cost.  Extra for internal installations = 14 % of the building cost  Extra for Electric & Sui gas services = 16 % of building cost  Contingencies = 3 % overall  Supervision charges = 8 % overall  Design charges = 2 % overall Example 2
  • 14. Prepare a Rough-cost Estimate based on unit cost, of a four story office building having a carpet area of 2000 sq.m. for obtaining the administrative approval of the Government. It may be assumed that 30 % of the built up area will be taken by the corridors, verandas, lavatories, staircase, etc. and 10 % of built up area will be occupied by walls. The following data is given:  Super-Built Area Rate = Rs: 1100.00 / sq. ft.  Extra for special architectural treatment = 0.5 % of the building cost.  Extra for water supply and sanitary installations = 6 % of the building cost. Example 3
  • 15.  Extra for internal installations = 14 % of the building cost  Extra for electric services = 12.5 % of building cost  Extra for sui gas services = 6 % of building cost  Extra due to deep foundations at site = 1.0 % of building cost  Contingencies = 2.5 % overall  Supervision charges = 8 % overall  Design charges = 2.5 % overall Example 3
  • 16. Prepare a Rough-cost Estimate for obtaining the administrative approval of the Government for a hospital project to serve both indoor and outdoor patients in an important rural area. The hospital will consist of the following:  Main administrative office with dispensing operations, etc.  Two general wards, each of 20 general beds.  Superintendent Doctor’s Residence.  Two Assistant Doctor’s Residences.  Eight single Nurses Quarters.  Four Compounder’s Quarters.  Twelve lower staff’s Quarters. Example 4
  • 17. • Detailed estimates are prepared by carefully and separately calculating in detail, the costs of various items of the work that constitute the whole project from the detailed working drawings after the design has been finalized. • The mistakes, if any, in the rough cost estimate are eliminated in the detailed estimate. • Detailed estimates are submitted to the competent authorities for obtaining technical sanction. Detailed Estimate
  • 18.  The whole project is sub-divided into different items of work or activities. The quantity for each item is then calculated separately from the drawings as accurately as possible. The procedure is known as "taking out of quantities".  The quantities for each item may be estimated and shown in the pattern which is called "Bill of quantities."  The unit, in which each item of the wok is to be calculated, should be according to the prevailing practice as followed in various departments of the country. Detailed Estimate
  • 19. Bill Of Quantities Sr. No Description of item No Measurements Quantity Total Quantity Remarks Length Breadth Height
  • 20. Priced Bill Of Quantities Sr. No Description of Item Unit Quantity Rate Cost Remarks
  • 21.  Each item of the work is then multiplied by its estimated current rate calculated by a fixed procedure to find out cost of the item.  At the end, a total of all items of the work are made to get the total estimated cost.  The rates are usually as per Schedule of Rates for the locality plus a premium to allow for rise in labor and material rates over and above the schedule of rates.  A percentage, usually 5% is also provided on the total estimated cost for the work to allow for the possible contingencies due to unforeseen items or expenditure or other causes, besides 2% establishment charges. Detailed Estimate
  • 22.  Besides drawings and details of measurements and calculation of quantities (Bill of Quantities), the following documents are also usually submitted with the detailed estimate for obtaining Technical Sanction: 1. A report explaining History, necessity, scope and main features of the project, its design, and estimate, etc. 2. Specifications lying down the nature and class of work and material to be used in various parts of the work. 3. The abstract of cost (priced Bill of Quantities) showing the total quantities under each sub-head, rate per unit of measurement, and cost. 4. Calculation sheets showing calculations for important parts of the structure. In fact, in estimating the art and skill lies only in the computation of details without any omissions, of all parts of the building or work. Detailed Estimate
  • 23. Classification Depending Upon Purpose Of Detailed Estimate 1- Contractor Estimate It is made by the contractor for determining the price or prices to be bid. It is usually a carefully prepared detailed estimate. 2- Engineer’s Estimate This type of estimate is made by the Engineer (Consultant) usually for the purposes of financing the work and for checking bids and running bills submitted by contractors.
  • 24. 3- Progress Estimate • These are made by the Engineer at regular intervals for the completed parts of the project during the progress of the work for determining the amounts of partial payments to be made to the contractor. • On large contracts, such estimates are commonly made each month and, hence, are frequently called monthly estimates. Classification Depending Upon Purpose Of Detailed Estimate
  • 25.  Carpet Area: Total usable area within the four walls of an apartment or a commercial space, as the case may be. In other words, it refers to the area for which a carpet can be laid if required by the owners.  Plinth Area: The entire carpet area along with the thickness of the external walls of the apartment. It obviously includes the thickness of the internal walls and the columns, if any, lying within the four walls of an apartment. The commercial space is not taken into account in calculating the plinth area.  Super Built-up Area: The plinth area of an apartment or a commercial unit as added by the balconies and other common areas like corridors, staircase, lift room, motor room, security room, meeting hall, gymnasium and an area reserved for indoor games. Basic Terms