SlideShare a Scribd company logo
1 of 29
Strategic Airport Management Programme
9-13 April 2007
Airport Planning and
Terminal Design
presented by
Eileen Poh
Assistant Director (ICAO Affairs)
Strategic Airport Management Programme
9-13 April 2007
Outline
C An overview of Airport Master Planning based
on ICAO planning guidelines
C What an airport master plan entail
C Emphasis on concepts and considerations
from the executives’ perspective
1
CConcept of the ultimate development of a specific
airport, graphically presented with written report
to effectively convey the research and logic from
which the plan was evolved (ICAO Manual)
CLong-term development concept of an airport; an
embodiment of the airport’s strategic framework
and concept depicted graphically and documents
the data and logic upon which the plan is based
CGuidelines for future airport development to
satisfy aviation demands in a financially feasible
manner, while addressing aviation,
environmental and socioeconomic issues in the
local community
Strategic Airport Management Programme 3
9-13 April 2007
Definition of Airport Master Plan
C Airport Master Plan serves as a guide for:
‰ Establishing short and long range policy/decision
‰ Developing physical facilities of an airport – aviation
and non-aviation
‰ Developing land uses surrounding airport
‰ Determining environmental effects of airport
construction and operation
‰ Establishing access requirements of the airport
‰ Identifying potential problems as well as opportunities
‰ Securing financial aid
‰ Establishing basis for negotiations of interests and
needs among aerodrome authority, businesses and
community
Strategic Airport Management Programme 4
9-13 April 2007
Airport Master Plan
2
Strategic Airport Management Programme
9-13 April 2007
Changi Airport Master Plan
6
9-13 April 2007
CAirports are multi-faceted facilities, impacting a
wide spectrum of people and businesses
CNeed for consultation and coordination of
planning with stakeholders concerned:
‰ Airlines
‰ National and local government planners
‰ Government control authorities (immigration, customs,
health)
‰ National and local transport authorities
‰ Aircraft and equipment manufacturers
‰ International aviation agencies and businesses
‰ Concessionaires
‰ Local businesSstrataegnicdAirproertsMiadnaegenmteinatPlrocgorammmmme unities
Stakeholders of Airport Master Plan
3
7Strategic Airport Management Programme
9-13 April 2007
CA good Airport Master Plan represents the
most efficient framework with flexibility,
expandability and optimum balance of all
individual airport facilities/services to provide
the required capacity for aircraft, pax, cargo
and vehicular movements with max
facilitation for pax, operator and staff at
lowest capital and operating costs and max
revenue
CGenerates higher capacity and efficiency
through a series of compromises than would
otherwise be attained without reconciliation of
individual facilities plans
Airport Master Planning Philosophy
8Strategic Airport Management Programme
9-13 April 2007
IN ALL CASES, COMPROMISES
DO NOT AFFECT SAFETY
Airport Master Planning Philosophy
4
9Strategic Airport Management Programme
9-13 April 2007
CInvolves preparation of broad and specific
policies, plans and programs
CGoals of Planning process to:
‰ Orderly and timely develop airport to meet present
and future air transportation needs
‰ Coordinate local, regional and national plans
‰ Protect and enhance environment (noise,
pollution)
‰ Establish effective airport organisation for
implementation
‰ Ensure compatibility with state/country aviation,
ICAO and IATA standards
Airport Master Planning Process
10Strategic Airport Management Programme
9-13 April 2007
‰ Coordinate national and regional airport systems
‰ Coordinate plans for nav. facilities, airspace and
air traffic control procedures
‰ Optimize use of land and airspace resources
CPolicy/Coordinative Planning
‰ Project goals, objectives
‰ Develop work programmes, schedules and
budgets
‰ Prepare and evaluation and decision format
‰ Establish coordination and monitoring procedures
‰ Establish data management and public
information system
Airport Master Planning Process
5
11Strategic Airport Management Programme
9-13 April 2007
CEconomic Planning
‰ Prepare analysis of aviation market characteristics
and forecasts of aviation activity
‰ Determine representative benefits and costs
associated with airport development alternatives
‰ Prepare an assessment of impact on area
economy of various alternatives
Airport Master Planning Process
12Strategic Airport Management Programme
9-13 April 2007
CPhysical Planning
‰ Airspace and air traffic control provisions
‰ Airfield configuration (including approach zones)
‰ Terminal complex
‰ Circulation, utility and communications networks
‰ Support and service facilities
‰ Ground access systems
‰ Over-all land use patterns
Airport Master Planning Process
6
13Strategic Airport Management Programme
9-13 April 2007
CEnvironmental Planning
‰ Prepare an assessment of natural environmental
conditions associated with the airport “impact”
area (plant and animal life, climate, topography
and natural resources, etc)
‰ Document present and projected development
patterns of relevance to the impact area
‰ Determine community attitudes and opinions
Airport Master Planning Process
14Strategic Airport Management Programme
9-13 April 2007
CFinancial Planning
‰ Determine airport funding source and constraints
‰ Prepare a financial feasibility study of various
airport development alternatives
‰ Prepare preliminary financial plans and
programmes for the finally agreed upon concept
Airport Master Planning Process
7
15Strategic Airport Management Programme
9-13 April 2007
CReviews
‰ Annually and adjust plans according to prevailing
conditions
‰ Thorough evaluation and modification every five
yearly or more often if changes in economic,
operational and environmental and financial
conditions dictates
Airport Master Planning Process
16Strategic Airport Management Programme
9-13 April 2007
C Prepare work program and identifyresponsibilities
C Inventory and document existingconditions
C Forecast future air trafficdemand
C Determine facility requirements and preliminarytime-
phased development
C Evaluate existing and potentialconstraints
C Prioritize considerations (constraints, airporttype)
C Developconcepts
C Assess operational, financial and environmental impact
of concepts (reiterations)
C Select most acceptable and appropriate alternatives,
modify and finalize
Steps in Planning Process
8
CForecasts parameters
‰ Annual pax, cargo, mail throughput (int’l/dom;
scheduled/ non-scheduled; arrival/departure,
transit/transhipment
‰ Typical peak hour aircraft movements and pax,
cargo, mail throughput
(arrivals/departure/combined)
‰ Average day of peak month aircraft movements and
pax, cargo, mail throughput
‰ No. of airlines, fleet mix, load factors, route
structures
‰ No. of base aircraft (scheduled/non-scheduled/GA)
‰ No. of visitors and airport workers
Strategic Airport Management Programme 17
9-13 April 2007
Air Traffic Forecasts
Strategic Airport Management Programme
9-13 April 2007
Objectives of airport
Income evaluation
Airport master plan
Traffic
forecasts
Capital and
recurrent Cost
Facility
Navaids,
Runway,
requirements Taxiway,apron
Terminal, access
system
Comparison
of results
with
Objectives
(and
Cost/benefit
analysis
Revise objectives if nec.
Revise plan if nec.
Forecast Relationship vs Master Plan
Conversion
to typical
peak hour
Aircraft
of forecasts movements
Pax, freight
and Mail
throughput
9
19Strategic Airport Management Programme
9-13 April 2007
C Informedjudgement
‰ Depends on experience and credibility of forecaster,
subjective, immediate term
CTrend extrapolation
‰ Assumes all past factors influencing aviation traffic
demand will continue to operate with same impact in
future, best fit curve, short term
Forecasts Techniques
20Strategic Airport Management Programme
9-13 April 2007
Linear projection
Time
EstimatedActivity
Parabolic projection
Time
EstimatedActivity
Exponential projection
T im e
EstimatedActivity
Gomperts projection
Time
EstimatedActivity
Y=aT+b Y=a+bT+cT²
Y=a (1+b)T
Y = ab-cT
Forecasts Techniques
10
CEconometric modelling
‰ Based on derived quantitative relationship between
traffic and important underlying factors affecting
traffic
‰ A few quantifiable major factors influencing air
transport demand can explain most of traffic
demand variation
‰ Real economic growth, real air fares, real energy
prices, tourism gorwth and consumer demographics
deemed to be most important factors impacting
aviation growth
‰ Relatively effective for short and medium term
forecasts
Strategic Airport Management Programme
9-13 April 2007
Forecasts Techniques
Strategic Airport Management Programme
9-13 April 2007
CMarket survey (Cross Classification Method)
‰ Obtains primary data from source of airport demand
‰ Surveys covering extensive user network to
eliminate bias, expensive and needs proper
structuring
‰ Assumes stable relationship between travel pattern
and socioeconomic characteristics
Forecasts Techniques
11
23Strategic Airport Management Programme
9-13 April 2007
C Economics
‰ GNP,GDP
‰ Income distribution
‰ Import/export levels
‰ Local economic activities
C Trip Purpose
‰ Business
‰ Leisure
‰ Personal
C GeographicalAttributes
‰ Distances between towns
‰ Physical and local
attractions
Forecasts Factors to Consider
C DemographicPattern
‰ Population
‰ Age
‰ Education level,
occupation
C Transportation system
‰ Competing modes
(fares,
service, freq, timing)
‰ Airport groundaccess
C Other External Factors
‰ New traffic rights/routes
‰ Government taxes +
fees
24
1
10
TripRate
UnitedStates
Germany Japan
m
France
Italy
New ZealandAustralia
Hong Kong Canada
Korea Spain
United Kingdo
Holland
Taiwan
Malaysia Portugal
Argentina
Turkey
0.1Brazil
Indonesia
India
China
0.01
-10,000 -5,000 0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000
Per capita GDP (US$)
0.001
Source: FAA, Various national statistics providers, Booz Allen Hamilton analysis
Strategic Airport Management Programme
9-13 April 2007
Forecasts Factors to Consider
12
Strategic Airport Management Programme
9-13 April 2007
CDeveloping an airport plan with a
layout that yields optimum airport
capacity within available land to
meet future demand and
international operating standards
CDelay and processing times
associated with different facilities
and components in the master
plan impact capacity
Airport Master Plan Objective
Strategic Airport Management Programme
9-13 April 2007
CFactors that affects capacity include:
‰ Airfield configuration (runway, taxiway, gates/parking
positions)
‰ Operating environment
‰ Navaids and ATC facilities (availability of navaids,
airspace, arrival and departure routes, extent of ATC
facilities approach/departure control tower)
Airport Master Plan Objective
13
Strategic Airport Management Programme
9-13 April 2007
CRunway Configuration
‰ Orientation
‰ Number of runways
CTaxiway Layout
CTerminal / Apron Area
CAircraft Parking Configuration
CCargo Terminal
Airfield Configuration
Strategic Airport Management Programme
9-13 April 2007
Runways
▪ No. of runways depends on volume of aircraft movements
▪ Orientation of runway depends on direction of prevailing
winds
▪ Runway length is influenced by temperature, runway slope,
airport altitude, MTOW, runway pavement condition,
visibility
▪ Airspace around airport should remain free of obstacles to
permit safe aircraft operations
Airfield Configuration Concept
14
Strategic Airport Management Programme
9-13 April 2007
CAircraft are not directed over populated areas and
avoid obstructions
COriented in the direction of the prevailing wind and
cross wind is not too excessive
Reference field
length
Allowable crosswind
components
> 1500 m 20 knots
1200 – 1499 m 13 knots
< 1200 m 10 knots
Runway Orientation
Strategic Airport Management Programme
9-13 April 2007
CAnnex 14 specifies that runways should be
oriented so aircraft may be able to land at least
95% of the time with cross wind components
CGood visibility
Runway Orientation
15
C Achieve safe aircraft operations,ensure:-
‰ Adequate separation between air traffic streams
‰ Obstacle clearance
‰ Crosswind provision
C Ensure least interference and delay to operations
C Avoid noise and sensitiveareas
Single runway
Hourly capacity (ops/hr)
VFR IFR
51-98 50-59
94-197 55-60
103-197 99-119
215 —761m
2 parallel runwSt
ara
yte
sgicAirport Management Programme
9-13 April 2007
> 1311m
Runway Configuration
Strategic Airport Management Programme
9-13 April 2007
Hourly capacity (ops/hr)
VFR
72-98
IFR
56-60
73-150 56-60
73-132 56-60
Cross runways
Runway Configuration
16
Strategic Airport Management Programme
9-13 April 2007
CSingle runway
‰ preferable to locate terminal equi-distance to runway
ends or shift it if there is predominant direction of
operations
C2-parallel runways (single orientation)
‰ Optimum capacity and best air traffic control efficiency
‰ Mid-field terminal between runways preferred
‰ Terminal on one side of runways lead to longer taxiing
distances and runway crossing problems
‰ Runways may be staggered
Runway Configuration
Strategic Airport Management Programme
9-13 April 2007
CRunways with 2 alignments
‰ Open configuration preferred with diverging operations
used whenever possible
‰ If intersecting configuration is unavoidable and there is
predominant direction in aircraft operations, runways
should have a rear intersection for that direction
‰ Centrally located terminal to minimize taxi distance
Runway Configuration
17
Strategic Airport Management Programme
9-13 April 2007
▪ Taxiways to be arranged to minimize interference between
landing aircraft and aircraft taxiing to takeoff
▪ Parallel taxiways increase runway capacity
▪ Shortest taxi distance from passenger terminal apron to runway
ends
Runways
Taxiways
Airfield Configuration
CEfficient connection between runways and
terminal / service areas
CAvoid conflicts between aircraft operations
‰ Arriving and departing taxi routes
‰ Holding passes and bypasses
CAvoid crossing of active taxiways over active
runways
CMinimize runway occupancy time of arriving
aircraft (eg strategically located rapid exit
taxiways enable landing aircraft to leave runway
quickly for other aircraft)
Strategic Airport Management Programme
9-13 April 2007
Taxiway Layout Guidelines
18
Strategic Airport Management Programme
9-13 April 2007
CTerminal/Apron location
‰ Minimum taxiing distance to and from runways
‰ Avoid locations under aircraft approach or departure
paths
Taxiway Layout Guidelines
Strategic Airport Management Programme
9-13 April 2007
Taxiway Layout
19
Strategic Airport Management Programme
9-13 April 2007
Typical Airport Configuration
Strategic Airport Management Programme
9-13 April 2007
Typical Airport Configuration
20
Strategic Airport Management Programme
9-13 April 2007
▪ Account for the safety procedures of aircraft manoeuvring on
the apron
▪ Allow efficient aircraft movements and dispensing apron
services
▪ Flexible to accommodate different size of aircraft types and
future expansion needs
Taxiways
Runways Aprons
Airfield Configuration
Strategic Airport Management Programme
9-13 April 2007
Parking Configuration
21
Strategic Airport Management Programme
9-13 April 2007
Parking Configuration
CDetermine purpose for which airport is required
CConsider forecast future demands (operational
and economic) and quantity and type of traffic
CDefine type of airport and operational systems for
forecast traffic
CMajor steps to consider
‰ Selection of site that provides adequate space and size
and suitable locations to serve the residents and
commerce
‰ Evaluation of feasibility of possible locations through
the forecast period from economic, geographic,
engineering and aeronautical standpoints
Strategic Airport Management Programme
9-13 April 2007
Airport Site Selection
22
Strategic Airport Management Programme
9-13 April 2007
CFactors influencing airport size:-
‰ Performance characteristics and size of aircraft
‰ Anticipated volume and character of traffic
‰ Meteorological conditions like wind and temperature
‰ Elevation of airport site
CFactors influencing airport location:-
‰ Type and development of surrounding area
‰ Atmospheric and meteorological conditions (Fog, Haze,
turbulence, heavy rainfall)
‰ Accessibility to ground transport (existing highway)
‰ Availability of land for expansion
Airport Site Selection
Strategic Airport Management Programme
9-13 April 2007
CFactors influencing airport location (con’t):-
‰ Presence of other airports and availability of airspace
‰ Traffic flow patterns of airports (restricted airspace)
‰ Surrounding obstructions (around airports particularly
for approach and departure paths, obstacle limitation
surfaces)
‰ Economy of construction
‰ Availability of utilities (electricity, fuel, water supply etc)
‰ Proximity to aeronautical demand
Airport Site Selection
23
CNoise Pollution
‰ Proper planning of land use for areas surrounding
airport
CAir Pollution
‰ Aircraft engine, exhaust, fuel venting, auxiliary paves
unit, fuel storage and ground service tanks, motor
vehicles, construction operations
CWater Pollution
‰ Sanitary wastes, storm water, maintenance wastes
and industrial wastes
‰ Waste water may be treated before discharging,
removing split oil by containment and spill recovery
(absorbent etc)
Strategic Airport Management Programme
9-13 April 2007
Environmental Studies
Strategic Airport Management Programme
9-13 April 2007
CArchaeological considerations
CSeismic considerations
CInclement weather
Environmental Studies
24
Strategic Airport Management Programme
CEconomics and Financial Feasibility
CEconomic and financials models of alternative
master plans (iterative process)
CMaster Plan should be targeted to generate
sufficient revenues to cover annual costs of
capital, traffic, operations and maintenance
expenses
CCost benefit analysis
C apital C osts Operating C osts C ommerical Revenue
9-13 April 2007
Interest Rate
Financial Plan
Strategic Airport Management Programme
ResultingROE
Financial Plan
-40% -30%
C apital C osts
-20%
ROE Spider Diagram
30.00%
25.00%
20.00%
15.00%
10.00%
5.00%
-
-10% - 10% 20% 30%
% C hange in Assumption s
Operating C osts Commerical Revenue Interest Rate
9-13 April 2007
40%
25
Strategic Airport Management Programme
9-13 April 2007
Changi Airport Terminal 3 completion - 2007
Strategic Airport Management Programme
9-13 April 2007
Megaplex
1
Airport Logistics Park
of Singapore
(ALPS)
SP ATC
CustomsChkpt
Changi Airfreight Centre Master Plan (2003)
26
Strategic Airport Management Programme
9-13 April 2007
Hong Kong International Airport
Strategic Airport Management Programme
9-13 April 2007
Heathrow Airport (Interim Master Plan Alt)
27
Strategic Airport Management Programme
9-13 April 2007
Heathrow Airport (Interim Master Plan Alt)
Strategic Airport Management Programme
9-13 April 2007
Thailand International Airport
SUVARNABHUMI
AIRPORT (BKK)
28
Strategic Airport Management Programme
9-13 April 2007
CAirport Planning Manual (Doc 9184), Part 1,
Master Planning by ICAO
CIATA Master Planning Manual
CAirport Engineering by Norman Ashford
CFAA Airport Master Plan
CFAA Airports designs
Useful Reading Material
29

More Related Content

What's hot

Layout of Airport Planning
Layout of Airport PlanningLayout of Airport Planning
Layout of Airport PlanningManoharanM12
 
Airport obstructions
Airport obstructionsAirport obstructions
Airport obstructionssrinivas2036
 
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERINGTRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERINGGovindaRajuluBadana1
 
Airport terminal planning and design
Airport terminal planning and designAirport terminal planning and design
Airport terminal planning and designJetline Marvel
 
Airport terminal design (lecture note)
Airport terminal design (lecture note)Airport terminal design (lecture note)
Airport terminal design (lecture note)Sarah Shuchi
 
Airport capacity and airport marking
Airport capacity and airport markingAirport capacity and airport marking
Airport capacity and airport markingIsmailQubaisMotiya
 
Design and planning of airport
Design and planning of airportDesign and planning of airport
Design and planning of airportHarshit P Jain
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Designsrinivas2036
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
Presentation on Airport Engineering
Presentation on Airport EngineeringPresentation on Airport Engineering
Presentation on Airport EngineeringAbhishekChavan63
 
Components of Airfield
Components of AirfieldComponents of Airfield
Components of AirfieldBhavya Jaiswal
 
Airport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneAirport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneNIKHIL PAKWANNE
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport EngineeringArbaz Kazi
 

What's hot (20)

Airport engineering PART-1
Airport engineering PART-1 Airport engineering PART-1
Airport engineering PART-1
 
Runways
RunwaysRunways
Runways
 
Layout of Airport Planning
Layout of Airport PlanningLayout of Airport Planning
Layout of Airport Planning
 
Airport obstructions
Airport obstructionsAirport obstructions
Airport obstructions
 
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERINGTRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
 
Airport layout
Airport layoutAirport layout
Airport layout
 
Airport terminal planning and design
Airport terminal planning and designAirport terminal planning and design
Airport terminal planning and design
 
Airport terminal design (lecture note)
Airport terminal design (lecture note)Airport terminal design (lecture note)
Airport terminal design (lecture note)
 
Airport capacity and airport marking
Airport capacity and airport markingAirport capacity and airport marking
Airport capacity and airport marking
 
Airpot design
Airpot designAirpot design
Airpot design
 
Airport planning and design
Airport planning and designAirport planning and design
Airport planning and design
 
Design and planning of airport
Design and planning of airportDesign and planning of airport
Design and planning of airport
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
 
Airport Layout
Airport LayoutAirport Layout
Airport Layout
 
Presentation on Airport Engineering
Presentation on Airport EngineeringPresentation on Airport Engineering
Presentation on Airport Engineering
 
Airport Engineering
Airport Engineering Airport Engineering
Airport Engineering
 
Components of Airfield
Components of AirfieldComponents of Airfield
Components of Airfield
 
Airport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneAirport runway By Nikhil Pakwanne
Airport runway By Nikhil Pakwanne
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
 

Similar to Strategic Airport Master Planning Programme

Airport Layout Plan For Efficient Airport Design
Airport Layout Plan For Efficient Airport DesignAirport Layout Plan For Efficient Airport Design
Airport Layout Plan For Efficient Airport DesignAllison Thompson
 
Update-May2007-e
Update-May2007-eUpdate-May2007-e
Update-May2007-eWJ
 
EffectiveAirportManagement-Diffs-Sols-191213.ppt
EffectiveAirportManagement-Diffs-Sols-191213.pptEffectiveAirportManagement-Diffs-Sols-191213.ppt
EffectiveAirportManagement-Diffs-Sols-191213.pptSURAJ SINGH SAINI
 
AirportCreators PTE Amsterdam 2017 - introduction
AirportCreators PTE Amsterdam 2017 - introductionAirportCreators PTE Amsterdam 2017 - introduction
AirportCreators PTE Amsterdam 2017 - introductionFrank Schellenberg
 
Modernizing Aviation to Maximize its Benefits
Modernizing Aviation to Maximize its BenefitsModernizing Aviation to Maximize its Benefits
Modernizing Aviation to Maximize its BenefitsMomina Riaz
 
India Aviation ICT Forum - P.S. Nair, CEO, Corporate, Airport Sector, GMR Air...
India Aviation ICT Forum - P.S. Nair, CEO, Corporate, Airport Sector, GMR Air...India Aviation ICT Forum - P.S. Nair, CEO, Corporate, Airport Sector, GMR Air...
India Aviation ICT Forum - P.S. Nair, CEO, Corporate, Airport Sector, GMR Air...SITA
 
India Aviation ICT Forum - P.S. Nair, CEO - Corporate, Airport Sector, GMR Ai...
India Aviation ICT Forum - P.S. Nair, CEO - Corporate, Airport Sector, GMR Ai...India Aviation ICT Forum - P.S. Nair, CEO - Corporate, Airport Sector, GMR Ai...
India Aviation ICT Forum - P.S. Nair, CEO - Corporate, Airport Sector, GMR Ai...SITA
 
Report on airport engineering
Report on airport engineeringReport on airport engineering
Report on airport engineeringAbhishekChavan63
 
Airport Planning & Terminal Building Design
Airport Planning & Terminal Building DesignAirport Planning & Terminal Building Design
Airport Planning & Terminal Building DesignSiniša Prvanov
 
The Next Generation Air Transportation System V1
The Next Generation Air Transportation System V1The Next Generation Air Transportation System V1
The Next Generation Air Transportation System V1rpearce61
 
Oct 2011 Presentation BC RTWR
Oct 2011 Presentation BC RTWROct 2011 Presentation BC RTWR
Oct 2011 Presentation BC RTWRDr. Anders Adrem
 
Airport Site Selection
Airport Site SelectionAirport Site Selection
Airport Site SelectionJulie Davis
 
Airport Collaborative Decision Making: Systems Approach
Airport Collaborative Decision Making: Systems ApproachAirport Collaborative Decision Making: Systems Approach
Airport Collaborative Decision Making: Systems ApproachEnrique Melendez, C.M., PMP
 
Robbins9 ppt09
Robbins9 ppt09Robbins9 ppt09
Robbins9 ppt09umar0007
 

Similar to Strategic Airport Master Planning Programme (20)

Modified C.V 2015-R02
Modified C.V 2015-R02Modified C.V 2015-R02
Modified C.V 2015-R02
 
Airport Layout Plan For Efficient Airport Design
Airport Layout Plan For Efficient Airport DesignAirport Layout Plan For Efficient Airport Design
Airport Layout Plan For Efficient Airport Design
 
Update-May2007-e
Update-May2007-eUpdate-May2007-e
Update-May2007-e
 
EffectiveAirportManagement-Diffs-Sols-191213.ppt
EffectiveAirportManagement-Diffs-Sols-191213.pptEffectiveAirportManagement-Diffs-Sols-191213.ppt
EffectiveAirportManagement-Diffs-Sols-191213.ppt
 
AirportCreators PTE Amsterdam 2017 - introduction
AirportCreators PTE Amsterdam 2017 - introductionAirportCreators PTE Amsterdam 2017 - introduction
AirportCreators PTE Amsterdam 2017 - introduction
 
Modernizing Aviation to Maximize its Benefits
Modernizing Aviation to Maximize its BenefitsModernizing Aviation to Maximize its Benefits
Modernizing Aviation to Maximize its Benefits
 
India Aviation ICT Forum - P.S. Nair, CEO, Corporate, Airport Sector, GMR Air...
India Aviation ICT Forum - P.S. Nair, CEO, Corporate, Airport Sector, GMR Air...India Aviation ICT Forum - P.S. Nair, CEO, Corporate, Airport Sector, GMR Air...
India Aviation ICT Forum - P.S. Nair, CEO, Corporate, Airport Sector, GMR Air...
 
India Aviation ICT Forum - P.S. Nair, CEO - Corporate, Airport Sector, GMR Ai...
India Aviation ICT Forum - P.S. Nair, CEO - Corporate, Airport Sector, GMR Ai...India Aviation ICT Forum - P.S. Nair, CEO - Corporate, Airport Sector, GMR Ai...
India Aviation ICT Forum - P.S. Nair, CEO - Corporate, Airport Sector, GMR Ai...
 
Rajesh Kumar
Rajesh KumarRajesh Kumar
Rajesh Kumar
 
Capital Programs - O'Hare 21
Capital Programs - O'Hare 21 Capital Programs - O'Hare 21
Capital Programs - O'Hare 21
 
Report on airport engineering
Report on airport engineeringReport on airport engineering
Report on airport engineering
 
Airport Planning & Terminal Building Design
Airport Planning & Terminal Building DesignAirport Planning & Terminal Building Design
Airport Planning & Terminal Building Design
 
The Next Generation Air Transportation System V1
The Next Generation Air Transportation System V1The Next Generation Air Transportation System V1
The Next Generation Air Transportation System V1
 
ts-07x01.pdf
ts-07x01.pdfts-07x01.pdf
ts-07x01.pdf
 
Oct 2011 Presentation BC RTWR
Oct 2011 Presentation BC RTWROct 2011 Presentation BC RTWR
Oct 2011 Presentation BC RTWR
 
Mike Palfrey CV15v3
Mike Palfrey CV15v3Mike Palfrey CV15v3
Mike Palfrey CV15v3
 
Airport Site Selection
Airport Site SelectionAirport Site Selection
Airport Site Selection
 
My Resume
My ResumeMy Resume
My Resume
 
Airport Collaborative Decision Making: Systems Approach
Airport Collaborative Decision Making: Systems ApproachAirport Collaborative Decision Making: Systems Approach
Airport Collaborative Decision Making: Systems Approach
 
Robbins9 ppt09
Robbins9 ppt09Robbins9 ppt09
Robbins9 ppt09
 

Recently uploaded

Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 

Recently uploaded (20)

Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 

Strategic Airport Master Planning Programme

  • 1. Strategic Airport Management Programme 9-13 April 2007 Airport Planning and Terminal Design presented by Eileen Poh Assistant Director (ICAO Affairs) Strategic Airport Management Programme 9-13 April 2007 Outline C An overview of Airport Master Planning based on ICAO planning guidelines C What an airport master plan entail C Emphasis on concepts and considerations from the executives’ perspective 1
  • 2. CConcept of the ultimate development of a specific airport, graphically presented with written report to effectively convey the research and logic from which the plan was evolved (ICAO Manual) CLong-term development concept of an airport; an embodiment of the airport’s strategic framework and concept depicted graphically and documents the data and logic upon which the plan is based CGuidelines for future airport development to satisfy aviation demands in a financially feasible manner, while addressing aviation, environmental and socioeconomic issues in the local community Strategic Airport Management Programme 3 9-13 April 2007 Definition of Airport Master Plan C Airport Master Plan serves as a guide for: ‰ Establishing short and long range policy/decision ‰ Developing physical facilities of an airport – aviation and non-aviation ‰ Developing land uses surrounding airport ‰ Determining environmental effects of airport construction and operation ‰ Establishing access requirements of the airport ‰ Identifying potential problems as well as opportunities ‰ Securing financial aid ‰ Establishing basis for negotiations of interests and needs among aerodrome authority, businesses and community Strategic Airport Management Programme 4 9-13 April 2007 Airport Master Plan 2
  • 3. Strategic Airport Management Programme 9-13 April 2007 Changi Airport Master Plan 6 9-13 April 2007 CAirports are multi-faceted facilities, impacting a wide spectrum of people and businesses CNeed for consultation and coordination of planning with stakeholders concerned: ‰ Airlines ‰ National and local government planners ‰ Government control authorities (immigration, customs, health) ‰ National and local transport authorities ‰ Aircraft and equipment manufacturers ‰ International aviation agencies and businesses ‰ Concessionaires ‰ Local businesSstrataegnicdAirproertsMiadnaegenmteinatPlrocgorammmmme unities Stakeholders of Airport Master Plan 3
  • 4. 7Strategic Airport Management Programme 9-13 April 2007 CA good Airport Master Plan represents the most efficient framework with flexibility, expandability and optimum balance of all individual airport facilities/services to provide the required capacity for aircraft, pax, cargo and vehicular movements with max facilitation for pax, operator and staff at lowest capital and operating costs and max revenue CGenerates higher capacity and efficiency through a series of compromises than would otherwise be attained without reconciliation of individual facilities plans Airport Master Planning Philosophy 8Strategic Airport Management Programme 9-13 April 2007 IN ALL CASES, COMPROMISES DO NOT AFFECT SAFETY Airport Master Planning Philosophy 4
  • 5. 9Strategic Airport Management Programme 9-13 April 2007 CInvolves preparation of broad and specific policies, plans and programs CGoals of Planning process to: ‰ Orderly and timely develop airport to meet present and future air transportation needs ‰ Coordinate local, regional and national plans ‰ Protect and enhance environment (noise, pollution) ‰ Establish effective airport organisation for implementation ‰ Ensure compatibility with state/country aviation, ICAO and IATA standards Airport Master Planning Process 10Strategic Airport Management Programme 9-13 April 2007 ‰ Coordinate national and regional airport systems ‰ Coordinate plans for nav. facilities, airspace and air traffic control procedures ‰ Optimize use of land and airspace resources CPolicy/Coordinative Planning ‰ Project goals, objectives ‰ Develop work programmes, schedules and budgets ‰ Prepare and evaluation and decision format ‰ Establish coordination and monitoring procedures ‰ Establish data management and public information system Airport Master Planning Process 5
  • 6. 11Strategic Airport Management Programme 9-13 April 2007 CEconomic Planning ‰ Prepare analysis of aviation market characteristics and forecasts of aviation activity ‰ Determine representative benefits and costs associated with airport development alternatives ‰ Prepare an assessment of impact on area economy of various alternatives Airport Master Planning Process 12Strategic Airport Management Programme 9-13 April 2007 CPhysical Planning ‰ Airspace and air traffic control provisions ‰ Airfield configuration (including approach zones) ‰ Terminal complex ‰ Circulation, utility and communications networks ‰ Support and service facilities ‰ Ground access systems ‰ Over-all land use patterns Airport Master Planning Process 6
  • 7. 13Strategic Airport Management Programme 9-13 April 2007 CEnvironmental Planning ‰ Prepare an assessment of natural environmental conditions associated with the airport “impact” area (plant and animal life, climate, topography and natural resources, etc) ‰ Document present and projected development patterns of relevance to the impact area ‰ Determine community attitudes and opinions Airport Master Planning Process 14Strategic Airport Management Programme 9-13 April 2007 CFinancial Planning ‰ Determine airport funding source and constraints ‰ Prepare a financial feasibility study of various airport development alternatives ‰ Prepare preliminary financial plans and programmes for the finally agreed upon concept Airport Master Planning Process 7
  • 8. 15Strategic Airport Management Programme 9-13 April 2007 CReviews ‰ Annually and adjust plans according to prevailing conditions ‰ Thorough evaluation and modification every five yearly or more often if changes in economic, operational and environmental and financial conditions dictates Airport Master Planning Process 16Strategic Airport Management Programme 9-13 April 2007 C Prepare work program and identifyresponsibilities C Inventory and document existingconditions C Forecast future air trafficdemand C Determine facility requirements and preliminarytime- phased development C Evaluate existing and potentialconstraints C Prioritize considerations (constraints, airporttype) C Developconcepts C Assess operational, financial and environmental impact of concepts (reiterations) C Select most acceptable and appropriate alternatives, modify and finalize Steps in Planning Process 8
  • 9. CForecasts parameters ‰ Annual pax, cargo, mail throughput (int’l/dom; scheduled/ non-scheduled; arrival/departure, transit/transhipment ‰ Typical peak hour aircraft movements and pax, cargo, mail throughput (arrivals/departure/combined) ‰ Average day of peak month aircraft movements and pax, cargo, mail throughput ‰ No. of airlines, fleet mix, load factors, route structures ‰ No. of base aircraft (scheduled/non-scheduled/GA) ‰ No. of visitors and airport workers Strategic Airport Management Programme 17 9-13 April 2007 Air Traffic Forecasts Strategic Airport Management Programme 9-13 April 2007 Objectives of airport Income evaluation Airport master plan Traffic forecasts Capital and recurrent Cost Facility Navaids, Runway, requirements Taxiway,apron Terminal, access system Comparison of results with Objectives (and Cost/benefit analysis Revise objectives if nec. Revise plan if nec. Forecast Relationship vs Master Plan Conversion to typical peak hour Aircraft of forecasts movements Pax, freight and Mail throughput 9
  • 10. 19Strategic Airport Management Programme 9-13 April 2007 C Informedjudgement ‰ Depends on experience and credibility of forecaster, subjective, immediate term CTrend extrapolation ‰ Assumes all past factors influencing aviation traffic demand will continue to operate with same impact in future, best fit curve, short term Forecasts Techniques 20Strategic Airport Management Programme 9-13 April 2007 Linear projection Time EstimatedActivity Parabolic projection Time EstimatedActivity Exponential projection T im e EstimatedActivity Gomperts projection Time EstimatedActivity Y=aT+b Y=a+bT+cT² Y=a (1+b)T Y = ab-cT Forecasts Techniques 10
  • 11. CEconometric modelling ‰ Based on derived quantitative relationship between traffic and important underlying factors affecting traffic ‰ A few quantifiable major factors influencing air transport demand can explain most of traffic demand variation ‰ Real economic growth, real air fares, real energy prices, tourism gorwth and consumer demographics deemed to be most important factors impacting aviation growth ‰ Relatively effective for short and medium term forecasts Strategic Airport Management Programme 9-13 April 2007 Forecasts Techniques Strategic Airport Management Programme 9-13 April 2007 CMarket survey (Cross Classification Method) ‰ Obtains primary data from source of airport demand ‰ Surveys covering extensive user network to eliminate bias, expensive and needs proper structuring ‰ Assumes stable relationship between travel pattern and socioeconomic characteristics Forecasts Techniques 11
  • 12. 23Strategic Airport Management Programme 9-13 April 2007 C Economics ‰ GNP,GDP ‰ Income distribution ‰ Import/export levels ‰ Local economic activities C Trip Purpose ‰ Business ‰ Leisure ‰ Personal C GeographicalAttributes ‰ Distances between towns ‰ Physical and local attractions Forecasts Factors to Consider C DemographicPattern ‰ Population ‰ Age ‰ Education level, occupation C Transportation system ‰ Competing modes (fares, service, freq, timing) ‰ Airport groundaccess C Other External Factors ‰ New traffic rights/routes ‰ Government taxes + fees 24 1 10 TripRate UnitedStates Germany Japan m France Italy New ZealandAustralia Hong Kong Canada Korea Spain United Kingdo Holland Taiwan Malaysia Portugal Argentina Turkey 0.1Brazil Indonesia India China 0.01 -10,000 -5,000 0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Per capita GDP (US$) 0.001 Source: FAA, Various national statistics providers, Booz Allen Hamilton analysis Strategic Airport Management Programme 9-13 April 2007 Forecasts Factors to Consider 12
  • 13. Strategic Airport Management Programme 9-13 April 2007 CDeveloping an airport plan with a layout that yields optimum airport capacity within available land to meet future demand and international operating standards CDelay and processing times associated with different facilities and components in the master plan impact capacity Airport Master Plan Objective Strategic Airport Management Programme 9-13 April 2007 CFactors that affects capacity include: ‰ Airfield configuration (runway, taxiway, gates/parking positions) ‰ Operating environment ‰ Navaids and ATC facilities (availability of navaids, airspace, arrival and departure routes, extent of ATC facilities approach/departure control tower) Airport Master Plan Objective 13
  • 14. Strategic Airport Management Programme 9-13 April 2007 CRunway Configuration ‰ Orientation ‰ Number of runways CTaxiway Layout CTerminal / Apron Area CAircraft Parking Configuration CCargo Terminal Airfield Configuration Strategic Airport Management Programme 9-13 April 2007 Runways ▪ No. of runways depends on volume of aircraft movements ▪ Orientation of runway depends on direction of prevailing winds ▪ Runway length is influenced by temperature, runway slope, airport altitude, MTOW, runway pavement condition, visibility ▪ Airspace around airport should remain free of obstacles to permit safe aircraft operations Airfield Configuration Concept 14
  • 15. Strategic Airport Management Programme 9-13 April 2007 CAircraft are not directed over populated areas and avoid obstructions COriented in the direction of the prevailing wind and cross wind is not too excessive Reference field length Allowable crosswind components > 1500 m 20 knots 1200 – 1499 m 13 knots < 1200 m 10 knots Runway Orientation Strategic Airport Management Programme 9-13 April 2007 CAnnex 14 specifies that runways should be oriented so aircraft may be able to land at least 95% of the time with cross wind components CGood visibility Runway Orientation 15
  • 16. C Achieve safe aircraft operations,ensure:- ‰ Adequate separation between air traffic streams ‰ Obstacle clearance ‰ Crosswind provision C Ensure least interference and delay to operations C Avoid noise and sensitiveareas Single runway Hourly capacity (ops/hr) VFR IFR 51-98 50-59 94-197 55-60 103-197 99-119 215 —761m 2 parallel runwSt ara yte sgicAirport Management Programme 9-13 April 2007 > 1311m Runway Configuration Strategic Airport Management Programme 9-13 April 2007 Hourly capacity (ops/hr) VFR 72-98 IFR 56-60 73-150 56-60 73-132 56-60 Cross runways Runway Configuration 16
  • 17. Strategic Airport Management Programme 9-13 April 2007 CSingle runway ‰ preferable to locate terminal equi-distance to runway ends or shift it if there is predominant direction of operations C2-parallel runways (single orientation) ‰ Optimum capacity and best air traffic control efficiency ‰ Mid-field terminal between runways preferred ‰ Terminal on one side of runways lead to longer taxiing distances and runway crossing problems ‰ Runways may be staggered Runway Configuration Strategic Airport Management Programme 9-13 April 2007 CRunways with 2 alignments ‰ Open configuration preferred with diverging operations used whenever possible ‰ If intersecting configuration is unavoidable and there is predominant direction in aircraft operations, runways should have a rear intersection for that direction ‰ Centrally located terminal to minimize taxi distance Runway Configuration 17
  • 18. Strategic Airport Management Programme 9-13 April 2007 ▪ Taxiways to be arranged to minimize interference between landing aircraft and aircraft taxiing to takeoff ▪ Parallel taxiways increase runway capacity ▪ Shortest taxi distance from passenger terminal apron to runway ends Runways Taxiways Airfield Configuration CEfficient connection between runways and terminal / service areas CAvoid conflicts between aircraft operations ‰ Arriving and departing taxi routes ‰ Holding passes and bypasses CAvoid crossing of active taxiways over active runways CMinimize runway occupancy time of arriving aircraft (eg strategically located rapid exit taxiways enable landing aircraft to leave runway quickly for other aircraft) Strategic Airport Management Programme 9-13 April 2007 Taxiway Layout Guidelines 18
  • 19. Strategic Airport Management Programme 9-13 April 2007 CTerminal/Apron location ‰ Minimum taxiing distance to and from runways ‰ Avoid locations under aircraft approach or departure paths Taxiway Layout Guidelines Strategic Airport Management Programme 9-13 April 2007 Taxiway Layout 19
  • 20. Strategic Airport Management Programme 9-13 April 2007 Typical Airport Configuration Strategic Airport Management Programme 9-13 April 2007 Typical Airport Configuration 20
  • 21. Strategic Airport Management Programme 9-13 April 2007 ▪ Account for the safety procedures of aircraft manoeuvring on the apron ▪ Allow efficient aircraft movements and dispensing apron services ▪ Flexible to accommodate different size of aircraft types and future expansion needs Taxiways Runways Aprons Airfield Configuration Strategic Airport Management Programme 9-13 April 2007 Parking Configuration 21
  • 22. Strategic Airport Management Programme 9-13 April 2007 Parking Configuration CDetermine purpose for which airport is required CConsider forecast future demands (operational and economic) and quantity and type of traffic CDefine type of airport and operational systems for forecast traffic CMajor steps to consider ‰ Selection of site that provides adequate space and size and suitable locations to serve the residents and commerce ‰ Evaluation of feasibility of possible locations through the forecast period from economic, geographic, engineering and aeronautical standpoints Strategic Airport Management Programme 9-13 April 2007 Airport Site Selection 22
  • 23. Strategic Airport Management Programme 9-13 April 2007 CFactors influencing airport size:- ‰ Performance characteristics and size of aircraft ‰ Anticipated volume and character of traffic ‰ Meteorological conditions like wind and temperature ‰ Elevation of airport site CFactors influencing airport location:- ‰ Type and development of surrounding area ‰ Atmospheric and meteorological conditions (Fog, Haze, turbulence, heavy rainfall) ‰ Accessibility to ground transport (existing highway) ‰ Availability of land for expansion Airport Site Selection Strategic Airport Management Programme 9-13 April 2007 CFactors influencing airport location (con’t):- ‰ Presence of other airports and availability of airspace ‰ Traffic flow patterns of airports (restricted airspace) ‰ Surrounding obstructions (around airports particularly for approach and departure paths, obstacle limitation surfaces) ‰ Economy of construction ‰ Availability of utilities (electricity, fuel, water supply etc) ‰ Proximity to aeronautical demand Airport Site Selection 23
  • 24. CNoise Pollution ‰ Proper planning of land use for areas surrounding airport CAir Pollution ‰ Aircraft engine, exhaust, fuel venting, auxiliary paves unit, fuel storage and ground service tanks, motor vehicles, construction operations CWater Pollution ‰ Sanitary wastes, storm water, maintenance wastes and industrial wastes ‰ Waste water may be treated before discharging, removing split oil by containment and spill recovery (absorbent etc) Strategic Airport Management Programme 9-13 April 2007 Environmental Studies Strategic Airport Management Programme 9-13 April 2007 CArchaeological considerations CSeismic considerations CInclement weather Environmental Studies 24
  • 25. Strategic Airport Management Programme CEconomics and Financial Feasibility CEconomic and financials models of alternative master plans (iterative process) CMaster Plan should be targeted to generate sufficient revenues to cover annual costs of capital, traffic, operations and maintenance expenses CCost benefit analysis C apital C osts Operating C osts C ommerical Revenue 9-13 April 2007 Interest Rate Financial Plan Strategic Airport Management Programme ResultingROE Financial Plan -40% -30% C apital C osts -20% ROE Spider Diagram 30.00% 25.00% 20.00% 15.00% 10.00% 5.00% - -10% - 10% 20% 30% % C hange in Assumption s Operating C osts Commerical Revenue Interest Rate 9-13 April 2007 40% 25
  • 26. Strategic Airport Management Programme 9-13 April 2007 Changi Airport Terminal 3 completion - 2007 Strategic Airport Management Programme 9-13 April 2007 Megaplex 1 Airport Logistics Park of Singapore (ALPS) SP ATC CustomsChkpt Changi Airfreight Centre Master Plan (2003) 26
  • 27. Strategic Airport Management Programme 9-13 April 2007 Hong Kong International Airport Strategic Airport Management Programme 9-13 April 2007 Heathrow Airport (Interim Master Plan Alt) 27
  • 28. Strategic Airport Management Programme 9-13 April 2007 Heathrow Airport (Interim Master Plan Alt) Strategic Airport Management Programme 9-13 April 2007 Thailand International Airport SUVARNABHUMI AIRPORT (BKK) 28
  • 29. Strategic Airport Management Programme 9-13 April 2007 CAirport Planning Manual (Doc 9184), Part 1, Master Planning by ICAO CIATA Master Planning Manual CAirport Engineering by Norman Ashford CFAA Airport Master Plan CFAA Airports designs Useful Reading Material 29