RUNWAY DESIGN
Change in direction of runway
It may not be always possible to orient the runway exactly
along the direction as determined from the wind rose. Slight
adjustment in the directions may be imperative because of the
following reasons.
1. Obstructions
2. Excessive grading
3. Noise nuisance
Basic runway length
It is the length of the runway under the following assumed
conditions at the airport
1) Airport altitude is at sea level
2) Temperature at the Airport is standard (15’C)
3) Runway is levelled in the longitudinal direction
4) No wind is blowing on runway
5) Aircraft is loaded to its full loading capacity
6) There is no wind blowing enroute to the destination
7) Enroute temperature is standard
Basic runway length
The basic runway length is determined from the performance
characteristics of the aircrafts using the airport. The following
cases are usually considered
īƒŧ Normal landing case
īƒŧ Normal take-off case
īƒŧ Engine failure case
īļ For jet engine aircrafts all 3 cases are considered
īļ For the piston engine aircraft only 1st and 3rd cases are considered
īą The case which works out the longest runway length is finally
adopted.
1) Normal landing case
The landing case requires that aircraft should come to stop within
60% of the landing distance. The runway of full strength
pavement is provided for the entire landing distance.
2) Normal take-off case
īƒŧ The normal take-off case requires a clearway which is an area beyond the
runway and is in alignment with the centre of runway.
īƒŧ The width of clearway should not be less than 150 m and is also kept free from
obstructions.
stopway clearway
3) Engine failure case
īƒŧ The engine failure case may require either a clearway or a stopway, or both.
īƒŧ Stopway is described as an area beyond the runway and centrally located in
alignment with the centre of runway.
īƒŧ It is used for decelerating during an aborted (terminated) take-off.
īƒŧ The strength of stopway pavement should be just sufficient to carry the
weight of aircraft without causing any structural damage to the designated
engine failure speed, the pilot decelerate the aircraft and makes use of the
stopway.
Correction for Elevation, Temperature & Gradient
1) Correction for elevation:-
As the elevation increases, the air density reduces. This in turn reduces the
lift on the wings of the aircraft and the aircraft requires greater ground speed
before it can rise into the air.
To achieve greater speed, longer length of runway is required.
ICAO recommends that the basic runway length should be increased at the
rate of 7% per 300 m rise in elevation above the mean sea level.
2) Correction for temperature:-
Airport reference temperature
Where Ta- Average daily temperature
Tm- Maximum daily temperature
ICAO recommends that the basic runway length after having been corrected
for elevation, should be further increased at the rate 1% for every 1oc rise of
airport reference temperature above the standard atmospheric temperature at
the elevation.
3) Check for the total correction for the elevation plus temperature
īƒŧ ICAO further recommends that's, if total corrections exceeds 35% of the basic
runway length, these corrections should be further checked up by conducting
specific studies at the site by model tests.
īƒŧ Steeper gradient results in greater consumption of energy & as such longer
length of runway is required to attain the desired ground speed.
īƒŧ ICAO does not recommends any specification for the correction of gradients.
īƒŧ FAA recommends that the runway length after having been corrected for
elevation & temperature should be further increased at the rate of 20% for
every 1% of effective gradients.
4) Corrections for gradients:-
Runway Geometric Design
ICAO gives various geometric standards for the airport design.
1) Runway length
2) Runway width
3) Width & length of safety area
4) Transverse gradients
5) Longitudinal & effective gradient
6) Sight distance
Runway Geometric Design
1) Runway length
The basic runway length as recommended by ICAO for different types of
airport are there. To obtain the actual length of runway, corrections for
elevation, temperature & gradient are applied to the basic runway length.
2) Runway width
īƒŧ ICAO recommends the pavement width varying from 45 m - 18 m for
different types of aircraft.
īƒŧ The aircraft traffic is more concentrated in the central 24m width of the
runway pavement.
3) Width & Length Of Safety Area
īƒŧ safety area consists of the runway, which is paved area plus the shoulder on
either side of runway plus the area is cleared, graded & drained as shown in
fig.
īƒŧ The shoulder are usually unpaved as they are used during emergency.
īƒŧ ICAO recommends.
Types of airport Width of safety area
Non-instrumental runway A,B&C
D&E
150 m
78 m
Instrumental runway A,B,C,D&E Mini. 300 m
Typical C/S of runway for ILS approach is shown below
(Instrumental Landing Systems)
(Instrumental Landing Systems)
4) Transverse gradient
īƒŧ Transverse gradient is essential for quick drainage of surface water. If
surface water is allowed to pond on the runway, the aircraft can meet severe
hazards.
īƒŧ ICAO recommends that the transverse gradient of runway pavement should
not exceed 1.5% for A,B, C & D 2 % for D & E types.
īƒŧ ICAO does not recommends that the minimum transverse gradient of
runway pavement but it should not greater then 0.5 %.
5) Longitudinal & Effective Gradients.
īƒŧ The longitudinal gradient of runway increases the required runway length.
īƒŧ ICAO recommendation as follows
Types of
airport
Longitudinal
gradient
Effective
gradient
A,B & C 1.5 % 1 %
D & E 2 % 2 %
6) Sight distance (is the length of roadway visible to a driver)
īƒŧ Two runways or a runway & taxiway intersect each other, there are chances of
collision of aircraft, if sufficient sight distance are not available.
īƒŧ ICAO recommends that for A,B & C types of airports, any two points 3 m above the
surface of runway should be mutually visible from a distance equal to ÂŊ the runway
length.
īƒŧ For D & E types of runway there should be unobstructed line of sight from any point
3 m above runway and to all other point 2.1 m above runway within a distance of at
least ÂŊ the length of runway.
TAXIWAY
TAXIWAY
The main function of the taxiway is the inter connection between runway and
loading apron or service hanger
Following consideration decide the layout of taxiway.
īļ Not interfere with the landing and take-off aircrafts
īļ At busy airports, taxiway should be located at various points along the runway
so that the landing aircraft leaves the runway as early as possible and keeps it
clear for use by other aircrafts. Such taxiway are called exit taxiways
īļ The route for taxiway should be so selected that it provides the shortest
distance from the apron to the runway end.
īļ As for as possible the intersection of taxiway and runway should be avoided.
īļ Exit taxiways should be designed for high turn-off speed.
Taxiway Geometric Design
ICAO gives various geometric standards for the airport design.
1) Taxiway length
2) Taxiway width
3) Width & length of safety area
4) Transverse gradients
5) Longitudinal & effective gradient
6) Sight distance
7) Turning radius
ī‘ Taxiway Geometric Designâ€Ļ
ī‘ Length of taxiway:
ī‘ As short as possible.
ī‘Increased number of taxiways have to be provided along the
runway.
ī‘Width of taxiway:
ī‘ It is observed that the width of a taxiway is much lower than
the runway width, as aircraft is not airborne and speeds are
small.
ī‘Varies between 22.5 m & 7.5 m
ī‘ Taxiway Geometric Designâ€Ļ
ī‘Width of taxiway:
ī‘ Width of taxiway (ICAO)
ī‘Longitudinal gradient:
ī‘ Level taxiway are operationally more desirable.
ī‘If gradient is steep, it affects fuel consumption.
ī‘ As per ICAO, maximum longitudinal gradient is 1.5% for
A&B type of airports & 3.0% for C,D&E type of airports.
Airport Code Taxiway width
A 22.5 m
B 22.5 m
C 15.0 m
D 9.9 m
E 7.5m
ī‘ Taxiway Geometric Designâ€Ļ
ī‘ Rate of change of longitudinal gradient:
ī‘ Available sight distance on the pavements is affected by the
rate of change of longitudinal gradient.
ī‘As per ICAO, the maximum change in pavement longitudinal
gradient is 4% for A&B category of airport & 3.33% for C,D&E
category of airports.
ī‘ Sight distance:
ī‘ As speed of aircraft on taxiway is lower than the speed on
runway, the smaller value of sight distance will be sufficient on
the taxiway.
ī‘Sight distance:
ī‘ICAO recommended that the surface of taxiway must be
visible at least up to a distance of X- from any point at a height
of Y above the taxiway surface.
ī‘ Transverse gradient:
ī‘ Adopted same as recommended for runway.
ī‘Transverse gradient is essential for quick drainage of surface
water.
Airport Code Y X
A 1.5 m 150 m
B 2.0 m 200 m
C,D&E 3.0 m 300 m
ī‘ Transverse gradient:
ī‘ ICAO recommended that the transverse gradient of runway
pavement should not exceed 1.5% for A,B&C & 2% for D&E
types. Shoulder are usually provided with steeper gradients.
ī‘Width of safety area:
ī‘ Safety area is made up to partially paved shoulders on either
side plus the area which is graded & drained.
ī‘ Turning radius:
ī‘ Change in aircraft path is done by providing a horizontal
curve.
ī‘The design should be such that the aircraft can negotiate the
curve without significantly reducing the speed.
ī‘Circular curve of large radius is provided.
ī‘Recommended radii corresponding of taxing speeds of small,
subsonic & supersonic airplanes is 60 m, 135 m & 240 m
respectively.
R2= V2/125f,
Where, R=radius in meter, V=speed in KMPhr
F=Friction btw tire and pavement
Exit Taxiways
Location of exit taxiway
īļThis depends upon several factors
īļ Number of exit taxiways
īļ Exit speed
īļ Types of aircrafts
īļ Weather conditions
īļ Topographical features
īļ Pilot variability
Exit Taxiways
Location of exit taxiway
īļThis depends upon several factors
īļ Number of exit taxiways: the number of taxiways to be provided decides
their location. If there are only two exit taxiways they should be provided
at the runway ends. If there are more than it should be ditributed along the
runway length.
īļ Exit speed: the maximum speed with which an aircraft can take a turn and
enter the exit taxiway is limited for each aircraft. The aircraft requires
certain length of runway to reduce its speed from the landing speed to the
turnoff speed. Thus this affects the location of taxiway.
īļ Types of aircrafts: different types of aircraft lands at different speed.
Therefore the distance required by different aircrafts, to reduce their speed
to the exit speed value, varies with the type of the aircraft, Thus in turn
affects the location of taxiway.
īļ Weather conditions
īļ Topographical features
īļ Pilot variability
DESIGN OF EXIT TAXIWAY CONNECTING RUNWAY & PARALLEL
TAXIWAY
1) The most significant factor is the exit speed of aircraft.
2) Slightly widened entrance of 30 m will be provide.
3) Total angle of turn is 3 300c-
4) The turning radius should be calculated by the following formula
5) A high turn-off speeds of 65-95 kmph a compound curve is necessary to
minimize the tire wear on the nose gear.
6) The length of longer radius curve can be roughly obtained by
valve of C=0.39
7) Stopping distance (SD)
Where d- deceleration distance
300-450
R=
VISUAL AIDS: A device which improves vision
NECESSITY OF VISUAL AIDS :-
īļ The pilots needs visual aids while landing or taking-off during all weather and
at every time.
īļ The pilots usually takes helps of the perspective view of the runway & other
ground reference marks during the landing operation.
īļ Runway thresholds, runway edges and the runway centre line are the most
essential items which should be clearly visible to the pilot. (lighting)
īļ In order to enhance the day time visibility runways, taxiways and allied
structures are marked with lines & numbers. (marking)
Airport Marking
Airport area is marked in a simple manner so that the pilots can easily
spot & recognize to the various airport elements.
The airport markings are divided into the following
īƒŧ Runway marking
īƒŧ Taxiway marking
īƒŧ Runway & taxiway shoulder marking
īƒŧ Apron marking
īƒŧ Wind direction indicator
īƒŧ Landing direction indicator
Airport Markings
Airport Lighting
In the day time during poor weather conditions, or at night, the visibility
reduces considerably. It is essential to provide adequate lighting. the colour &
general pattern of lights used in airport lighting are standardized for all civil
airports.
The airport lightings are divided into the following elements
īƒŧ Runway lighting
īƒŧ Taxiway lighting
īƒŧ Apron & hanger lighting
īƒŧ Lighting of Wind direction indicator
īƒŧ Lighting of Landing direction indicator
Wind direction indicator

More Related Content

What's hot

Airport capacity and airport marking
Airport capacity and airport markingAirport capacity and airport marking
Airport capacity and airport markingIsmailQubaisMotiya
 
Runway orientation
Runway orientationRunway orientation
Runway orientationjagadish108
 
Airport engineering
Airport engineering Airport engineering
Airport engineering Jaspreet singh
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristicssrinivas2036
 
Classification of airport
Classification of airportClassification of airport
Classification of airportIsmailQubaisMotiya
 
Airport drainage
Airport drainageAirport drainage
Airport drainagesrinivas2036
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport EngineeringFirasath Ali
 
1.introduction
1.introduction1.introduction
1.introductionMani Vel
 
Airport presentation 5th unit
Airport presentation 5th unitAirport presentation 5th unit
Airport presentation 5th unitT.Naga Anusha
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristicsAbhishek Kumar
 
Airport planning and design
Airport planning and designAirport planning and design
Airport planning and designRAMPRASAD KUMAWAT
 
Taxiway design perfect ppt
Taxiway design perfect pptTaxiway design perfect ppt
Taxiway design perfect pptVijay Reddy
 
Airfield pavements
Airfield pavementsAirfield pavements
Airfield pavementsBhavya Jaiswal
 
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERINGTRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERINGGovindaRajuluBadana1
 
Factors influence site selection of an airport
Factors influence site selection of an airportFactors influence site selection of an airport
Factors influence site selection of an airportMaddelaSiddhardha
 
Factors in Airport site selection PART-2
Factors in Airport site selection PART-2Factors in Airport site selection PART-2
Factors in Airport site selection PART-2RAMPRASAD KUMAWAT
 
Airport planning - Railways, airports, docks and harbour engineering (RAHE)
Airport planning - Railways, airports, docks and harbour engineering  (RAHE)Airport planning - Railways, airports, docks and harbour engineering  (RAHE)
Airport planning - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
 

What's hot (20)

Basic runway length
Basic runway lengthBasic runway length
Basic runway length
 
Airport capacity and airport marking
Airport capacity and airport markingAirport capacity and airport marking
Airport capacity and airport marking
 
Runway orientation
Runway orientationRunway orientation
Runway orientation
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
Airport engineering
Airport engineering Airport engineering
Airport engineering
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristics
 
Classification of airport
Classification of airportClassification of airport
Classification of airport
 
Airport drainage
Airport drainageAirport drainage
Airport drainage
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
 
Runways
RunwaysRunways
Runways
 
1.introduction
1.introduction1.introduction
1.introduction
 
Airport presentation 5th unit
Airport presentation 5th unitAirport presentation 5th unit
Airport presentation 5th unit
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristics
 
Airport planning and design
Airport planning and designAirport planning and design
Airport planning and design
 
Taxiway design perfect ppt
Taxiway design perfect pptTaxiway design perfect ppt
Taxiway design perfect ppt
 
Airfield pavements
Airfield pavementsAirfield pavements
Airfield pavements
 
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERINGTRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
TRANSPORTATION ENGINEERING - II - AIRPORT ENGINEERING
 
Factors influence site selection of an airport
Factors influence site selection of an airportFactors influence site selection of an airport
Factors influence site selection of an airport
 
Factors in Airport site selection PART-2
Factors in Airport site selection PART-2Factors in Airport site selection PART-2
Factors in Airport site selection PART-2
 
Airport planning - Railways, airports, docks and harbour engineering (RAHE)
Airport planning - Railways, airports, docks and harbour engineering  (RAHE)Airport planning - Railways, airports, docks and harbour engineering  (RAHE)
Airport planning - Railways, airports, docks and harbour engineering (RAHE)
 

Viewers also liked

Pavement Products PPT (October 2014)
Pavement Products PPT (October 2014)Pavement Products PPT (October 2014)
Pavement Products PPT (October 2014)The D.S. Brown Company
 
Pkqa iso 17025 requirements
Pkqa iso 17025 requirementsPkqa iso 17025 requirements
Pkqa iso 17025 requirementsPat Kilbane
 
Airport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneAirport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneNIKHIL PAKWANNE
 
Distresses in flexible pavements by water
Distresses in flexible pavements by waterDistresses in flexible pavements by water
Distresses in flexible pavements by waterammar rasheed
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniquesNayana 54321
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESMalay Talaviya
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavementRandhir Kumar
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavementRafi Khan
 
Annex 14 ppt cheng
Annex 14 ppt chengAnnex 14 ppt cheng
Annex 14 ppt chengguestb793fe2
 
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESCASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESPrabhu Saran
 
Flexible pavement failure
Flexible pavement failureFlexible pavement failure
Flexible pavement failureNabaraj Poudel
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentationPawan Kumar
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Designsrinivas2036
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT Amol Pawar
 

Viewers also liked (19)

Pavement Products PPT (October 2014)
Pavement Products PPT (October 2014)Pavement Products PPT (October 2014)
Pavement Products PPT (October 2014)
 
Pkqa iso 17025 requirements
Pkqa iso 17025 requirementsPkqa iso 17025 requirements
Pkqa iso 17025 requirements
 
Airport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneAirport runway By Nikhil Pakwanne
Airport runway By Nikhil Pakwanne
 
Iso 17025 nabl implementation steps lakshy rev00-240914
Iso 17025 nabl  implementation steps lakshy rev00-240914Iso 17025 nabl  implementation steps lakshy rev00-240914
Iso 17025 nabl implementation steps lakshy rev00-240914
 
Distresses in flexible pavements by water
Distresses in flexible pavements by waterDistresses in flexible pavements by water
Distresses in flexible pavements by water
 
Airports presentation
Airports presentationAirports presentation
Airports presentation
 
Pdce
PdcePdce
Pdce
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniques
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
 
TOP DOWN CRACKING IN FLEXIBLE PAVEMENTS
TOP DOWN CRACKING  IN FLEXIBLE PAVEMENTSTOP DOWN CRACKING  IN FLEXIBLE PAVEMENTS
TOP DOWN CRACKING IN FLEXIBLE PAVEMENTS
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
Annex 14 ppt cheng
Annex 14 ppt chengAnnex 14 ppt cheng
Annex 14 ppt cheng
 
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESCASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
 
Flexible pavement failure
Flexible pavement failureFlexible pavement failure
Flexible pavement failure
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
 
Airport Layout
Airport LayoutAirport Layout
Airport Layout
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 

Similar to Air port presentation 6th unit

runway orientation.pdf
runway orientation.pdfrunway orientation.pdf
runway orientation.pdfMargaretAbrahamCE
 
Airport layout
Airport layoutAirport layout
Airport layoutArmanAnsari37
 
Lecture 7 (1).pptx
Lecture 7 (1).pptxLecture 7 (1).pptx
Lecture 7 (1).pptxWhUllahWa
 
Airport Design RHTA - VTU Module 5
Airport Design RHTA - VTU Module 5Airport Design RHTA - VTU Module 5
Airport Design RHTA - VTU Module 5AJEETH B
 
IRJET- Design of Runway for Navi-Mumbai International Airport
IRJET-  	  Design of Runway for Navi-Mumbai International AirportIRJET-  	  Design of Runway for Navi-Mumbai International Airport
IRJET- Design of Runway for Navi-Mumbai International AirportIRJET Journal
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
Circular Runway
Circular RunwayCircular Runway
Circular RunwayIRJET Journal
 
Airport Engineering
Airport Engineering Airport Engineering
Airport Engineering Abhishek Pandey
 
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...irjes
 
Lecture 9.pdf
Lecture 9.pdfLecture 9.pdf
Lecture 9.pdfShashankSR6
 
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptxAIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptxAnujyadav514462
 
Taneja Aerospace and Aviation limied
Taneja Aerospace and Aviation limiedTaneja Aerospace and Aviation limied
Taneja Aerospace and Aviation limieddarshakb
 
Proposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIAProposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIAKozarni Koko
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport EngineeringBecky Gilbert
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bayssrinivas2036
 
ThunderCats_Revised_2
ThunderCats_Revised_2ThunderCats_Revised_2
ThunderCats_Revised_2Michael Benassi
 
AIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANAIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANNiranjan Varma
 

Similar to Air port presentation 6th unit (20)

runway orientation.pdf
runway orientation.pdfrunway orientation.pdf
runway orientation.pdf
 
Airport layout
Airport layoutAirport layout
Airport layout
 
Lecture 7 (1).pptx
Lecture 7 (1).pptxLecture 7 (1).pptx
Lecture 7 (1).pptx
 
Airport Design RHTA - VTU Module 5
Airport Design RHTA - VTU Module 5Airport Design RHTA - VTU Module 5
Airport Design RHTA - VTU Module 5
 
IRJET- Design of Runway for Navi-Mumbai International Airport
IRJET-  	  Design of Runway for Navi-Mumbai International AirportIRJET-  	  Design of Runway for Navi-Mumbai International Airport
IRJET- Design of Runway for Navi-Mumbai International Airport
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
 
Circular Runway
Circular RunwayCircular Runway
Circular Runway
 
Airport Engineering
Airport Engineering Airport Engineering
Airport Engineering
 
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
 
Lecture 9.pdf
Lecture 9.pdfLecture 9.pdf
Lecture 9.pdf
 
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptxAIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
 
Air traffic management
Air traffic managementAir traffic management
Air traffic management
 
Airport
AirportAirport
Airport
 
Taneja Aerospace and Aviation limied
Taneja Aerospace and Aviation limiedTaneja Aerospace and Aviation limied
Taneja Aerospace and Aviation limied
 
Proposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIAProposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIA
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bays
 
Airports
AirportsAirports
Airports
 
ThunderCats_Revised_2
ThunderCats_Revised_2ThunderCats_Revised_2
ThunderCats_Revised_2
 
AIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANAIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJAN
 

Recently uploaded

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube ExchangerAnamika Sarkar
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 

Air port presentation 6th unit

  • 2. Change in direction of runway It may not be always possible to orient the runway exactly along the direction as determined from the wind rose. Slight adjustment in the directions may be imperative because of the following reasons. 1. Obstructions 2. Excessive grading 3. Noise nuisance
  • 3. Basic runway length It is the length of the runway under the following assumed conditions at the airport 1) Airport altitude is at sea level 2) Temperature at the Airport is standard (15’C) 3) Runway is levelled in the longitudinal direction 4) No wind is blowing on runway 5) Aircraft is loaded to its full loading capacity 6) There is no wind blowing enroute to the destination 7) Enroute temperature is standard
  • 4. Basic runway length The basic runway length is determined from the performance characteristics of the aircrafts using the airport. The following cases are usually considered īƒŧ Normal landing case īƒŧ Normal take-off case īƒŧ Engine failure case īļ For jet engine aircrafts all 3 cases are considered īļ For the piston engine aircraft only 1st and 3rd cases are considered īą The case which works out the longest runway length is finally adopted.
  • 5. 1) Normal landing case The landing case requires that aircraft should come to stop within 60% of the landing distance. The runway of full strength pavement is provided for the entire landing distance.
  • 6. 2) Normal take-off case īƒŧ The normal take-off case requires a clearway which is an area beyond the runway and is in alignment with the centre of runway. īƒŧ The width of clearway should not be less than 150 m and is also kept free from obstructions.
  • 8. 3) Engine failure case īƒŧ The engine failure case may require either a clearway or a stopway, or both. īƒŧ Stopway is described as an area beyond the runway and centrally located in alignment with the centre of runway. īƒŧ It is used for decelerating during an aborted (terminated) take-off. īƒŧ The strength of stopway pavement should be just sufficient to carry the weight of aircraft without causing any structural damage to the designated engine failure speed, the pilot decelerate the aircraft and makes use of the stopway.
  • 9. Correction for Elevation, Temperature & Gradient 1) Correction for elevation:- As the elevation increases, the air density reduces. This in turn reduces the lift on the wings of the aircraft and the aircraft requires greater ground speed before it can rise into the air. To achieve greater speed, longer length of runway is required. ICAO recommends that the basic runway length should be increased at the rate of 7% per 300 m rise in elevation above the mean sea level. 2) Correction for temperature:- Airport reference temperature Where Ta- Average daily temperature Tm- Maximum daily temperature ICAO recommends that the basic runway length after having been corrected for elevation, should be further increased at the rate 1% for every 1oc rise of airport reference temperature above the standard atmospheric temperature at the elevation.
  • 10.
  • 11. 3) Check for the total correction for the elevation plus temperature īƒŧ ICAO further recommends that's, if total corrections exceeds 35% of the basic runway length, these corrections should be further checked up by conducting specific studies at the site by model tests. īƒŧ Steeper gradient results in greater consumption of energy & as such longer length of runway is required to attain the desired ground speed. īƒŧ ICAO does not recommends any specification for the correction of gradients. īƒŧ FAA recommends that the runway length after having been corrected for elevation & temperature should be further increased at the rate of 20% for every 1% of effective gradients. 4) Corrections for gradients:-
  • 12. Runway Geometric Design ICAO gives various geometric standards for the airport design. 1) Runway length 2) Runway width 3) Width & length of safety area 4) Transverse gradients 5) Longitudinal & effective gradient 6) Sight distance
  • 13. Runway Geometric Design 1) Runway length The basic runway length as recommended by ICAO for different types of airport are there. To obtain the actual length of runway, corrections for elevation, temperature & gradient are applied to the basic runway length. 2) Runway width īƒŧ ICAO recommends the pavement width varying from 45 m - 18 m for different types of aircraft. īƒŧ The aircraft traffic is more concentrated in the central 24m width of the runway pavement.
  • 14. 3) Width & Length Of Safety Area īƒŧ safety area consists of the runway, which is paved area plus the shoulder on either side of runway plus the area is cleared, graded & drained as shown in fig. īƒŧ The shoulder are usually unpaved as they are used during emergency. īƒŧ ICAO recommends. Types of airport Width of safety area Non-instrumental runway A,B&C D&E 150 m 78 m Instrumental runway A,B,C,D&E Mini. 300 m
  • 15.
  • 16. Typical C/S of runway for ILS approach is shown below (Instrumental Landing Systems)
  • 18. 4) Transverse gradient īƒŧ Transverse gradient is essential for quick drainage of surface water. If surface water is allowed to pond on the runway, the aircraft can meet severe hazards. īƒŧ ICAO recommends that the transverse gradient of runway pavement should not exceed 1.5% for A,B, C & D 2 % for D & E types. īƒŧ ICAO does not recommends that the minimum transverse gradient of runway pavement but it should not greater then 0.5 %.
  • 19. 5) Longitudinal & Effective Gradients. īƒŧ The longitudinal gradient of runway increases the required runway length. īƒŧ ICAO recommendation as follows Types of airport Longitudinal gradient Effective gradient A,B & C 1.5 % 1 % D & E 2 % 2 %
  • 20. 6) Sight distance (is the length of roadway visible to a driver) īƒŧ Two runways or a runway & taxiway intersect each other, there are chances of collision of aircraft, if sufficient sight distance are not available. īƒŧ ICAO recommends that for A,B & C types of airports, any two points 3 m above the surface of runway should be mutually visible from a distance equal to ÂŊ the runway length. īƒŧ For D & E types of runway there should be unobstructed line of sight from any point 3 m above runway and to all other point 2.1 m above runway within a distance of at least ÂŊ the length of runway.
  • 22. TAXIWAY The main function of the taxiway is the inter connection between runway and loading apron or service hanger Following consideration decide the layout of taxiway. īļ Not interfere with the landing and take-off aircrafts īļ At busy airports, taxiway should be located at various points along the runway so that the landing aircraft leaves the runway as early as possible and keeps it clear for use by other aircrafts. Such taxiway are called exit taxiways īļ The route for taxiway should be so selected that it provides the shortest distance from the apron to the runway end. īļ As for as possible the intersection of taxiway and runway should be avoided. īļ Exit taxiways should be designed for high turn-off speed.
  • 23. Taxiway Geometric Design ICAO gives various geometric standards for the airport design. 1) Taxiway length 2) Taxiway width 3) Width & length of safety area 4) Transverse gradients 5) Longitudinal & effective gradient 6) Sight distance 7) Turning radius
  • 24. ī‘ Taxiway Geometric Designâ€Ļ ī‘ Length of taxiway: ī‘ As short as possible. ī‘Increased number of taxiways have to be provided along the runway. ī‘Width of taxiway: ī‘ It is observed that the width of a taxiway is much lower than the runway width, as aircraft is not airborne and speeds are small. ī‘Varies between 22.5 m & 7.5 m
  • 25. ī‘ Taxiway Geometric Designâ€Ļ ī‘Width of taxiway: ī‘ Width of taxiway (ICAO) ī‘Longitudinal gradient: ī‘ Level taxiway are operationally more desirable. ī‘If gradient is steep, it affects fuel consumption. ī‘ As per ICAO, maximum longitudinal gradient is 1.5% for A&B type of airports & 3.0% for C,D&E type of airports. Airport Code Taxiway width A 22.5 m B 22.5 m C 15.0 m D 9.9 m E 7.5m
  • 26. ī‘ Taxiway Geometric Designâ€Ļ ī‘ Rate of change of longitudinal gradient: ī‘ Available sight distance on the pavements is affected by the rate of change of longitudinal gradient. ī‘As per ICAO, the maximum change in pavement longitudinal gradient is 4% for A&B category of airport & 3.33% for C,D&E category of airports. ī‘ Sight distance: ī‘ As speed of aircraft on taxiway is lower than the speed on runway, the smaller value of sight distance will be sufficient on the taxiway.
  • 27. ī‘Sight distance: ī‘ICAO recommended that the surface of taxiway must be visible at least up to a distance of X- from any point at a height of Y above the taxiway surface. ī‘ Transverse gradient: ī‘ Adopted same as recommended for runway. ī‘Transverse gradient is essential for quick drainage of surface water. Airport Code Y X A 1.5 m 150 m B 2.0 m 200 m C,D&E 3.0 m 300 m
  • 28. ī‘ Transverse gradient: ī‘ ICAO recommended that the transverse gradient of runway pavement should not exceed 1.5% for A,B&C & 2% for D&E types. Shoulder are usually provided with steeper gradients. ī‘Width of safety area: ī‘ Safety area is made up to partially paved shoulders on either side plus the area which is graded & drained.
  • 29. ī‘ Turning radius: ī‘ Change in aircraft path is done by providing a horizontal curve. ī‘The design should be such that the aircraft can negotiate the curve without significantly reducing the speed. ī‘Circular curve of large radius is provided. ī‘Recommended radii corresponding of taxing speeds of small, subsonic & supersonic airplanes is 60 m, 135 m & 240 m respectively. R2= V2/125f, Where, R=radius in meter, V=speed in KMPhr F=Friction btw tire and pavement
  • 30.
  • 31. Exit Taxiways Location of exit taxiway īļThis depends upon several factors īļ Number of exit taxiways īļ Exit speed īļ Types of aircrafts īļ Weather conditions īļ Topographical features īļ Pilot variability
  • 32. Exit Taxiways Location of exit taxiway īļThis depends upon several factors īļ Number of exit taxiways: the number of taxiways to be provided decides their location. If there are only two exit taxiways they should be provided at the runway ends. If there are more than it should be ditributed along the runway length. īļ Exit speed: the maximum speed with which an aircraft can take a turn and enter the exit taxiway is limited for each aircraft. The aircraft requires certain length of runway to reduce its speed from the landing speed to the turnoff speed. Thus this affects the location of taxiway. īļ Types of aircrafts: different types of aircraft lands at different speed. Therefore the distance required by different aircrafts, to reduce their speed to the exit speed value, varies with the type of the aircraft, Thus in turn affects the location of taxiway. īļ Weather conditions īļ Topographical features īļ Pilot variability
  • 33. DESIGN OF EXIT TAXIWAY CONNECTING RUNWAY & PARALLEL TAXIWAY 1) The most significant factor is the exit speed of aircraft. 2) Slightly widened entrance of 30 m will be provide. 3) Total angle of turn is 3 300c- 4) The turning radius should be calculated by the following formula 5) A high turn-off speeds of 65-95 kmph a compound curve is necessary to minimize the tire wear on the nose gear. 6) The length of longer radius curve can be roughly obtained by valve of C=0.39 7) Stopping distance (SD) Where d- deceleration distance 300-450 R=
  • 34.
  • 35.
  • 36.
  • 37. VISUAL AIDS: A device which improves vision NECESSITY OF VISUAL AIDS :- īļ The pilots needs visual aids while landing or taking-off during all weather and at every time. īļ The pilots usually takes helps of the perspective view of the runway & other ground reference marks during the landing operation. īļ Runway thresholds, runway edges and the runway centre line are the most essential items which should be clearly visible to the pilot. (lighting) īļ In order to enhance the day time visibility runways, taxiways and allied structures are marked with lines & numbers. (marking)
  • 38. Airport Marking Airport area is marked in a simple manner so that the pilots can easily spot & recognize to the various airport elements. The airport markings are divided into the following īƒŧ Runway marking īƒŧ Taxiway marking īƒŧ Runway & taxiway shoulder marking īƒŧ Apron marking īƒŧ Wind direction indicator īƒŧ Landing direction indicator
  • 40. Airport Lighting In the day time during poor weather conditions, or at night, the visibility reduces considerably. It is essential to provide adequate lighting. the colour & general pattern of lights used in airport lighting are standardized for all civil airports. The airport lightings are divided into the following elements īƒŧ Runway lighting īƒŧ Taxiway lighting īƒŧ Apron & hanger lighting īƒŧ Lighting of Wind direction indicator īƒŧ Lighting of Landing direction indicator