SlideShare a Scribd company logo
1 of 26
Caribbean Renewable Energy Forum:
JPS - Current State and Challenges
Kelly Tomblin
President & CEO
October 18, 2016
JPS Goal: To Maintain Balance
2
Sustainability
JPS helping to
ensure a Secure,
Sustainable and
Affordable
Energy Future
Our vision is aligned to the
national goals of energy
security, affordability and
sustainability.
• Our focus has is both
short term and long term
Project Renaissance: New Power Plant
Old Harbour 190MW Combined Cycle
Power Plant
New 190 MW 3x1 CC
Power Block
Existing OH Units 1-4
4
190 MW CC power plant was awarded to JPS, replacing 40 year old plant
Project Status –
LNG Terminal
 LNG contracts to be secured within 6 months of Financial Close
 ADO expected 20 months from NTP and LNG expected 22 months from NTP.
Power Plant
 Signed EPC contract with TSK from Spain
 Modified PPA with, Emergency backup fuel ADO submitted to OUR/ESET
 EPC LNTP payment made on Sep 30
 Secured financial commitments from banks ($223M)
5
Bogue Conversion/System Stability
Fuel Diversity: Bogue Conversion
Delivering a least cost small scale gas delivery
system to Jamaica
Convert Bogue GT12 & 13 Gas
Turbines to Dual Fuel Operations
(ADO& Gas)
Have Bogue CCGT plant
operate reliably &
efficiently on gas October,
2016
Bogue CCGT JPS first gas fired
generating plant
Lowering energy prices through fuel
diversification
Bringing natural Gas to Jamaica, at
last
Bogue CCGT Gas Conversion Project
8
LNG supply line
from Port
LNG supply line on
site
Delivering Fuel Diversity
9
Fuel Diversity in Action
10
Ship to Ship Gas Transfer
11
Ship to ship Gas Transfer
Fuel Diversity
& Maintaining System Operations
Jamaica’s Installed Generation Capacity
Ocho Rios
Montego Bay
Negril
Old Harbour
Kingston
138 kV Transmission Lines
69 kV Transmission Lines
Thermal Resources
ADO
LNG
Renewable Resources
WIND
HYDRO
SOLAR
HFO
Installed Renewables-Oct 2016
80 MW Intermittent Power addition in 2016
• 24 MW Wind Power in May 2016
• 36 MW Wind Power in June 2016
• 20 MW Solar Power in May 2016
Total
• Installed Hydro Capacity - 29.12 MW
• Installed Wind Capacity - 101.3 MW
• Installed Solar Capacity - 20 MW
• Roof Top Solar - 4MW (estimated 30MW)
The Renewable Energy Capacity Penetration
Total Capacity = 1,024 MW
Existing RE capacity =150MW or 14.6%
VRR (Wind + Solar) = 120MW or 11.8%
Projected RE Capacity = 17.7%
VRR (Wind + Solar ) = 14.5%
Research indicates that in most large scale grid systems, VRR < 10% of peak capacity has little impact on system
operation. Larger Shares will present challenges for System Operators.
Wind Energy and Power Systems Operations: A review of Wind Integration Studies to Date” The Electricity Journal, Vol 22, Issue 10, 34-43.
Day Peak Min
Demand (MW) 580.0 400.0
Wind Capacity % 17..5% 25.3%
Solar Capacity % 3.4% 5.0%
TOTAL 20.9% 30.3%
P E A K MIN
17.5% 25.3%
3.4% 5.0%
20.9% 30.3%
RE CAPACITY PENETRATION AT ON-PEAK AND OFF-PEAK
Wind Capacity % Solar Capacity % TOTAL
-5
0
5
10
15
20
25
30
35
40
MW
Time
36MW Wind Farm, August 18, 2016 (6:00am - 6:30pm)
BMR
0
5
10
15
20
25
MW
Time
20MW PV Plant, August 18, 2016 (6:00am - 6:30pm)
MW
20
Short Term Plan 2016
 Declaration of Machine Availability for Spinning Reserves
 Rate of Change alarm for Renewables on the Grid, Renewable
Forecasting Improvements
 Improve Ramp Response of Machines
 Review Load Shedding Scheme
 Spinning reserve review
21
Medium to Long Term Plan
• Storage
• Smart Grid
System Operations Improvements
• High resolution visualization of grid
status and health
• Automated Demand Management
• Algorithms that identify intermittency
events and look-ahead
• Integrated forecasting software that
allows for more accurate dispatch
• Ability to manage the connection or
disconnection of micro-grids
• Work force demographics and skills
JPS Participation in Retail Renewable Energy
and Energy Efficiency
24
Retail Service Offered by Energy Services
• Energy Auditing
• Load logging services (days / weeks)
• Load breakout services (logging)
• Supply and installation of LED lights
• Wind Speed Logging
25
Renewable Energy-Customer Offerings
• Solar/Photovoltaic System
• Solar Water Heaters
26
Services Offered by Energy Services
• Supply and install variable speed drives
• Supply and install energy efficient
motors
• Power factor assessment and correction
JPS: Committed to
Jamaica’s Growth &
Prosperity
27

More Related Content

What's hot

Unlocking the Innovation Hidden within Today’s Variable-Speed Drives
Unlocking the Innovation Hidden within Today’s Variable-Speed DrivesUnlocking the Innovation Hidden within Today’s Variable-Speed Drives
Unlocking the Innovation Hidden within Today’s Variable-Speed DrivesEMEX
 
Matthias Löbermann - TenneT Germany
Matthias Löbermann - TenneT GermanyMatthias Löbermann - TenneT Germany
Matthias Löbermann - TenneT GermanyGuidoBacker1
 
Haven Energy Bridge – Electrolysing Renewable Generation to Inject Hydrogen i...
Haven Energy Bridge – Electrolysing Renewable Generation to Inject Hydrogen i...Haven Energy Bridge – Electrolysing Renewable Generation to Inject Hydrogen i...
Haven Energy Bridge – Electrolysing Renewable Generation to Inject Hydrogen i...EMEX
 
Energy Generation and Transmission
Energy Generation and Transmission Energy Generation and Transmission
Energy Generation and Transmission ascommme
 
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...IEA-ETSAP
 
Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Kachinga-Wankunda Phiri
 
Energy-Water-Land Nexus in Germany: A case study
Energy-Water-Land Nexus in Germany: A case studyEnergy-Water-Land Nexus in Germany: A case study
Energy-Water-Land Nexus in Germany: A case studyIEA-ETSAP
 
Community microgrids for renewables driven resilience
Community microgrids for renewables driven resilienceCommunity microgrids for renewables driven resilience
Community microgrids for renewables driven resilienceClean Coalition
 
In the wake of a tidal stream turbine
In the wake of a tidal stream turbineIn the wake of a tidal stream turbine
In the wake of a tidal stream turbineRobin Lovelace
 
Peter Davies & Morten Boegild - Tidal turbine array modelling, influence of w...
Peter Davies & Morten Boegild - Tidal turbine array modelling, influence of w...Peter Davies & Morten Boegild - Tidal turbine array modelling, influence of w...
Peter Davies & Morten Boegild - Tidal turbine array modelling, influence of w...Lloyd's Register Renewables
 
Island Power Generation and Demand Side Purchasing and Selling
Island Power Generation and Demand Side Purchasing and SellingIsland Power Generation and Demand Side Purchasing and Selling
Island Power Generation and Demand Side Purchasing and SellingEMEX
 
Imi remosa - Hydrogen for energy and business transition in industry (Alberto...
Imi remosa - Hydrogen for energy and business transition in industry (Alberto...Imi remosa - Hydrogen for energy and business transition in industry (Alberto...
Imi remosa - Hydrogen for energy and business transition in industry (Alberto...Sardegna Ricerche
 
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...IEA-ETSAP
 
Powering sydneys future workshop
Powering sydneys future workshopPowering sydneys future workshop
Powering sydneys future workshopTransGrid AU
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Energy Network marcus evans
 
Flinders Island Isolated Power System (IPS) Connect 2016 MASDAR
Flinders Island Isolated Power System (IPS) Connect 2016 MASDARFlinders Island Isolated Power System (IPS) Connect 2016 MASDAR
Flinders Island Isolated Power System (IPS) Connect 2016 MASDARjames hamilton
 
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...IEA-ETSAP
 
Montecito Community Microgrid: Renewables-driven resilience for critical faci...
Montecito Community Microgrid: Renewables-driven resilience for critical faci...Montecito Community Microgrid: Renewables-driven resilience for critical faci...
Montecito Community Microgrid: Renewables-driven resilience for critical faci...Clean Coalition
 
New Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
New Revenue and Cost Savings Opportunities – Realising the Value of FlexibilityNew Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
New Revenue and Cost Savings Opportunities – Realising the Value of FlexibilityEMEX
 

What's hot (20)

Unlocking the Innovation Hidden within Today’s Variable-Speed Drives
Unlocking the Innovation Hidden within Today’s Variable-Speed DrivesUnlocking the Innovation Hidden within Today’s Variable-Speed Drives
Unlocking the Innovation Hidden within Today’s Variable-Speed Drives
 
Matthias Löbermann - TenneT Germany
Matthias Löbermann - TenneT GermanyMatthias Löbermann - TenneT Germany
Matthias Löbermann - TenneT Germany
 
Haven Energy Bridge – Electrolysing Renewable Generation to Inject Hydrogen i...
Haven Energy Bridge – Electrolysing Renewable Generation to Inject Hydrogen i...Haven Energy Bridge – Electrolysing Renewable Generation to Inject Hydrogen i...
Haven Energy Bridge – Electrolysing Renewable Generation to Inject Hydrogen i...
 
Energy Generation and Transmission
Energy Generation and Transmission Energy Generation and Transmission
Energy Generation and Transmission
 
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
 
The future role of gas networks in Integrated Energy Network
The future role of gas networks in Integrated Energy NetworkThe future role of gas networks in Integrated Energy Network
The future role of gas networks in Integrated Energy Network
 
Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16
 
Energy-Water-Land Nexus in Germany: A case study
Energy-Water-Land Nexus in Germany: A case studyEnergy-Water-Land Nexus in Germany: A case study
Energy-Water-Land Nexus in Germany: A case study
 
Community microgrids for renewables driven resilience
Community microgrids for renewables driven resilienceCommunity microgrids for renewables driven resilience
Community microgrids for renewables driven resilience
 
In the wake of a tidal stream turbine
In the wake of a tidal stream turbineIn the wake of a tidal stream turbine
In the wake of a tidal stream turbine
 
Peter Davies & Morten Boegild - Tidal turbine array modelling, influence of w...
Peter Davies & Morten Boegild - Tidal turbine array modelling, influence of w...Peter Davies & Morten Boegild - Tidal turbine array modelling, influence of w...
Peter Davies & Morten Boegild - Tidal turbine array modelling, influence of w...
 
Island Power Generation and Demand Side Purchasing and Selling
Island Power Generation and Demand Side Purchasing and SellingIsland Power Generation and Demand Side Purchasing and Selling
Island Power Generation and Demand Side Purchasing and Selling
 
Imi remosa - Hydrogen for energy and business transition in industry (Alberto...
Imi remosa - Hydrogen for energy and business transition in industry (Alberto...Imi remosa - Hydrogen for energy and business transition in industry (Alberto...
Imi remosa - Hydrogen for energy and business transition in industry (Alberto...
 
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
 
Powering sydneys future workshop
Powering sydneys future workshopPowering sydneys future workshop
Powering sydneys future workshop
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
 
Flinders Island Isolated Power System (IPS) Connect 2016 MASDAR
Flinders Island Isolated Power System (IPS) Connect 2016 MASDARFlinders Island Isolated Power System (IPS) Connect 2016 MASDAR
Flinders Island Isolated Power System (IPS) Connect 2016 MASDAR
 
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
 
Montecito Community Microgrid: Renewables-driven resilience for critical faci...
Montecito Community Microgrid: Renewables-driven resilience for critical faci...Montecito Community Microgrid: Renewables-driven resilience for critical faci...
Montecito Community Microgrid: Renewables-driven resilience for critical faci...
 
New Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
New Revenue and Cost Savings Opportunities – Realising the Value of FlexibilityNew Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
New Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
 

Viewers also liked

53% dos micro e pequenos empresários estão pessimistas com o futuro da economia
53% dos micro e pequenos empresários estão pessimistas com o futuro da economia53% dos micro e pequenos empresários estão pessimistas com o futuro da economia
53% dos micro e pequenos empresários estão pessimistas com o futuro da economiaGustavo Salgado
 
51648613 aparato-digestivo-de-la-gallinaclase9
51648613 aparato-digestivo-de-la-gallinaclase951648613 aparato-digestivo-de-la-gallinaclase9
51648613 aparato-digestivo-de-la-gallinaclase9Rukkalaf Veterinaria
 
Exposicion de condensadores
Exposicion de condensadoresExposicion de condensadores
Exposicion de condensadoreseulercubas
 
Aquascape tools, Aquarium Instruments, Wave Scissors, Spatulas, Spring Action...
Aquascape tools, Aquarium Instruments, Wave Scissors, Spatulas, Spring Action...Aquascape tools, Aquarium Instruments, Wave Scissors, Spatulas, Spring Action...
Aquascape tools, Aquarium Instruments, Wave Scissors, Spatulas, Spring Action...SIMRIX SURGICAL CO
 
Real time semantic search using approximate methodology for large-scale stora...
Real time semantic search using approximate methodology for large-scale stora...Real time semantic search using approximate methodology for large-scale stora...
Real time semantic search using approximate methodology for large-scale stora...Shakas Technologies
 
Woman's empowerment presentation 2
Woman's empowerment presentation 2Woman's empowerment presentation 2
Woman's empowerment presentation 2Rebika Rani Sahu
 
Introduction to strategic mgt
Introduction to strategic mgtIntroduction to strategic mgt
Introduction to strategic mgtDr.Yaser Aref
 
History of Emoji
History of EmojiHistory of Emoji
History of Emojiadamzurn
 

Viewers also liked (17)

hudmotorsports
hudmotorsportshudmotorsports
hudmotorsports
 
BDFP Manual
BDFP Manual BDFP Manual
BDFP Manual
 
Arabic Agreement Letter
Arabic Agreement LetterArabic Agreement Letter
Arabic Agreement Letter
 
53% dos micro e pequenos empresários estão pessimistas com o futuro da economia
53% dos micro e pequenos empresários estão pessimistas com o futuro da economia53% dos micro e pequenos empresários estão pessimistas com o futuro da economia
53% dos micro e pequenos empresários estão pessimistas com o futuro da economia
 
51648613 aparato-digestivo-de-la-gallinaclase9
51648613 aparato-digestivo-de-la-gallinaclase951648613 aparato-digestivo-de-la-gallinaclase9
51648613 aparato-digestivo-de-la-gallinaclase9
 
CCCOnline Presentation
CCCOnline PresentationCCCOnline Presentation
CCCOnline Presentation
 
페이지정의
페이지정의페이지정의
페이지정의
 
Exposicion de condensadores
Exposicion de condensadoresExposicion de condensadores
Exposicion de condensadores
 
Aquascape tools, Aquarium Instruments, Wave Scissors, Spatulas, Spring Action...
Aquascape tools, Aquarium Instruments, Wave Scissors, Spatulas, Spring Action...Aquascape tools, Aquarium Instruments, Wave Scissors, Spatulas, Spring Action...
Aquascape tools, Aquarium Instruments, Wave Scissors, Spatulas, Spring Action...
 
Adjectives
AdjectivesAdjectives
Adjectives
 
idioms
idiomsidioms
idioms
 
Real time semantic search using approximate methodology for large-scale stora...
Real time semantic search using approximate methodology for large-scale stora...Real time semantic search using approximate methodology for large-scale stora...
Real time semantic search using approximate methodology for large-scale stora...
 
Babysitting Log: Egg Baby Project
Babysitting Log: Egg Baby Project Babysitting Log: Egg Baby Project
Babysitting Log: Egg Baby Project
 
Woman's empowerment presentation 2
Woman's empowerment presentation 2Woman's empowerment presentation 2
Woman's empowerment presentation 2
 
Interesting versus right
Interesting versus rightInteresting versus right
Interesting versus right
 
Introduction to strategic mgt
Introduction to strategic mgtIntroduction to strategic mgt
Introduction to strategic mgt
 
History of Emoji
History of EmojiHistory of Emoji
History of Emoji
 

Similar to Caribbean utility leaders (tomblin)

The merits of integrating renewables with smarter grid carilec
The merits of integrating renewables with smarter grid   carilecThe merits of integrating renewables with smarter grid   carilec
The merits of integrating renewables with smarter grid carilecRick Case, PMP, P.E.
 
Latest in energy storage
Latest in energy storageLatest in energy storage
Latest in energy storageLoic Charmoille
 
What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?Cedric Christensen
 
Towards Net Zero Power 04.03.2020.pptx
Towards Net Zero Power 04.03.2020.pptxTowards Net Zero Power 04.03.2020.pptx
Towards Net Zero Power 04.03.2020.pptxVaibhavHindia
 
Ips connect 2015 francisco gafaro
Ips connect 2015 francisco gafaroIps connect 2015 francisco gafaro
Ips connect 2015 francisco gafarojames_hamilton
 
Mexico's Clean Energy Transformation and Storage
Mexico's Clean Energy Transformation and StorageMexico's Clean Energy Transformation and Storage
Mexico's Clean Energy Transformation and StorageMarcelino Madrigal
 
World's Largest Solar Project
World's Largest Solar ProjectWorld's Largest Solar Project
World's Largest Solar ProjectMitchellDong
 
Renewable Energy Project Development in Off-Grid Areas - Rene Fajigalutan, RO...
Renewable Energy Project Development in Off-Grid Areas - Rene Fajigalutan, RO...Renewable Energy Project Development in Off-Grid Areas - Rene Fajigalutan, RO...
Renewable Energy Project Development in Off-Grid Areas - Rene Fajigalutan, RO...OECD Environment
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimetRick Case, PMP, P.E.
 
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENAFlinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENAjames hamilton
 
Playing Well with Others - Market for Storage Hybrids
Playing Well with Others - Market for Storage HybridsPlaying Well with Others - Market for Storage Hybrids
Playing Well with Others - Market for Storage HybridsJill Kirkpatrick
 
Wind-Plus-Storage Presentation
Wind-Plus-Storage PresentationWind-Plus-Storage Presentation
Wind-Plus-Storage PresentationNicole Green
 
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotMike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotjames hamilton
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 
L’esperienza della California, Mark Rothleder
L’esperienza della California, Mark RothlederL’esperienza della California, Mark Rothleder
L’esperienza della California, Mark RothlederTerna SpA
 
Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...IEA-ETSAP
 
A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements Iceland Geothermal
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptsomnathmahapatra6
 
Concept of the Hagersvalle Energy ParkF[1]
Concept of the Hagersvalle Energy ParkF[1]Concept of the Hagersvalle Energy ParkF[1]
Concept of the Hagersvalle Energy ParkF[1]Tomo Kalaba
 

Similar to Caribbean utility leaders (tomblin) (20)

The merits of integrating renewables with smarter grid carilec
The merits of integrating renewables with smarter grid   carilecThe merits of integrating renewables with smarter grid   carilec
The merits of integrating renewables with smarter grid carilec
 
Latest in energy storage
Latest in energy storageLatest in energy storage
Latest in energy storage
 
What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?
 
Towards Net Zero Power 04.03.2020.pptx
Towards Net Zero Power 04.03.2020.pptxTowards Net Zero Power 04.03.2020.pptx
Towards Net Zero Power 04.03.2020.pptx
 
Ips connect 2015 francisco gafaro
Ips connect 2015 francisco gafaroIps connect 2015 francisco gafaro
Ips connect 2015 francisco gafaro
 
Pcci energy committe twg on power
Pcci energy committe   twg on powerPcci energy committe   twg on power
Pcci energy committe twg on power
 
Mexico's Clean Energy Transformation and Storage
Mexico's Clean Energy Transformation and StorageMexico's Clean Energy Transformation and Storage
Mexico's Clean Energy Transformation and Storage
 
World's Largest Solar Project
World's Largest Solar ProjectWorld's Largest Solar Project
World's Largest Solar Project
 
Renewable Energy Project Development in Off-Grid Areas - Rene Fajigalutan, RO...
Renewable Energy Project Development in Off-Grid Areas - Rene Fajigalutan, RO...Renewable Energy Project Development in Off-Grid Areas - Rene Fajigalutan, RO...
Renewable Energy Project Development in Off-Grid Areas - Rene Fajigalutan, RO...
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimet
 
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENAFlinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
 
Playing Well with Others - Market for Storage Hybrids
Playing Well with Others - Market for Storage HybridsPlaying Well with Others - Market for Storage Hybrids
Playing Well with Others - Market for Storage Hybrids
 
Wind-Plus-Storage Presentation
Wind-Plus-Storage PresentationWind-Plus-Storage Presentation
Wind-Plus-Storage Presentation
 
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotMike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
L’esperienza della California, Mark Rothleder
L’esperienza della California, Mark RothlederL’esperienza della California, Mark Rothleder
L’esperienza della California, Mark Rothleder
 
Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...
 
A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
 
Concept of the Hagersvalle Energy ParkF[1]
Concept of the Hagersvalle Energy ParkF[1]Concept of the Hagersvalle Energy ParkF[1]
Concept of the Hagersvalle Energy ParkF[1]
 

More from Japan Caribbean Climate Change Partnership (10)

St lucias energy transition
St lucias energy transitionSt lucias energy transition
St lucias energy transition
 
Why we need a long term strategy for investment in clean energy (turnerjones)
Why we need a long term strategy for investment in clean energy (turnerjones)Why we need a long term strategy for investment in clean energy (turnerjones)
Why we need a long term strategy for investment in clean energy (turnerjones)
 
Cref 2016 opening keynote address (lee)
Cref 2016 opening keynote address (lee)Cref 2016 opening keynote address (lee)
Cref 2016 opening keynote address (lee)
 
Caribbean hotels and energy (gischler)
Caribbean hotels and energy (gischler)Caribbean hotels and energy (gischler)
Caribbean hotels and energy (gischler)
 
The offshore session (guerin)
The offshore session (guerin)The offshore session (guerin)
The offshore session (guerin)
 
The offshore session (acevedo imbard)
The offshore session (acevedo imbard)The offshore session (acevedo imbard)
The offshore session (acevedo imbard)
 
Project case study st. eustatius pv hybrid system (cuvalay)
Project case study st. eustatius pv hybrid system (cuvalay)Project case study st. eustatius pv hybrid system (cuvalay)
Project case study st. eustatius pv hybrid system (cuvalay)
 
Keynote &amp; on stage interview (carbo)
Keynote &amp; on stage interview (carbo)Keynote &amp; on stage interview (carbo)
Keynote &amp; on stage interview (carbo)
 
Haiti private sector investment (gischler)
Haiti private sector investment (gischler)Haiti private sector investment (gischler)
Haiti private sector investment (gischler)
 
Energy storage what weve learned from puerto ricos mtrs (saloman)
Energy storage what weve learned from puerto ricos mtrs (saloman)Energy storage what weve learned from puerto ricos mtrs (saloman)
Energy storage what weve learned from puerto ricos mtrs (saloman)
 

Recently uploaded

(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一F dds
 
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girlsMumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girlsPooja Nehwal
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BHbill846304
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...Cluster TWEED
 
See How do animals kill their prey for food
See How do animals kill their prey for foodSee How do animals kill their prey for food
See How do animals kill their prey for fooddrsk203
 
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full NightCall Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Sustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesSustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesDr. Salem Baidas
 
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...Amil baba
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...Suhani Kapoor
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Open Access Research Paper
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
VIP Call Girls Moti Ganpur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Moti Ganpur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Moti Ganpur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Moti Ganpur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...Suhani Kapoor
 

Recently uploaded (20)

Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
 
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
 
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girlsMumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BH
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
 
See How do animals kill their prey for food
See How do animals kill their prey for foodSee How do animals kill their prey for food
See How do animals kill their prey for food
 
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full NightCall Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
 
Sustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesSustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and Challenges
 
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
VIP Call Girls Moti Ganpur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Moti Ganpur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Moti Ganpur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Moti Ganpur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
 
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCREscort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
 

Caribbean utility leaders (tomblin)

  • 1. Caribbean Renewable Energy Forum: JPS - Current State and Challenges Kelly Tomblin President & CEO October 18, 2016
  • 2. JPS Goal: To Maintain Balance 2 Sustainability JPS helping to ensure a Secure, Sustainable and Affordable Energy Future Our vision is aligned to the national goals of energy security, affordability and sustainability. • Our focus has is both short term and long term
  • 4. Old Harbour 190MW Combined Cycle Power Plant New 190 MW 3x1 CC Power Block Existing OH Units 1-4 4 190 MW CC power plant was awarded to JPS, replacing 40 year old plant
  • 5. Project Status – LNG Terminal  LNG contracts to be secured within 6 months of Financial Close  ADO expected 20 months from NTP and LNG expected 22 months from NTP. Power Plant  Signed EPC contract with TSK from Spain  Modified PPA with, Emergency backup fuel ADO submitted to OUR/ESET  EPC LNTP payment made on Sep 30  Secured financial commitments from banks ($223M) 5
  • 7. Fuel Diversity: Bogue Conversion Delivering a least cost small scale gas delivery system to Jamaica Convert Bogue GT12 & 13 Gas Turbines to Dual Fuel Operations (ADO& Gas) Have Bogue CCGT plant operate reliably & efficiently on gas October, 2016 Bogue CCGT JPS first gas fired generating plant Lowering energy prices through fuel diversification Bringing natural Gas to Jamaica, at last Bogue CCGT Gas Conversion Project
  • 8. 8 LNG supply line from Port LNG supply line on site Delivering Fuel Diversity
  • 10. 10 Ship to Ship Gas Transfer
  • 11. 11 Ship to ship Gas Transfer
  • 12. Fuel Diversity & Maintaining System Operations
  • 13. Jamaica’s Installed Generation Capacity Ocho Rios Montego Bay Negril Old Harbour Kingston 138 kV Transmission Lines 69 kV Transmission Lines Thermal Resources ADO LNG Renewable Resources WIND HYDRO SOLAR HFO
  • 14. Installed Renewables-Oct 2016 80 MW Intermittent Power addition in 2016 • 24 MW Wind Power in May 2016 • 36 MW Wind Power in June 2016 • 20 MW Solar Power in May 2016 Total • Installed Hydro Capacity - 29.12 MW • Installed Wind Capacity - 101.3 MW • Installed Solar Capacity - 20 MW • Roof Top Solar - 4MW (estimated 30MW)
  • 15. The Renewable Energy Capacity Penetration Total Capacity = 1,024 MW Existing RE capacity =150MW or 14.6% VRR (Wind + Solar) = 120MW or 11.8% Projected RE Capacity = 17.7% VRR (Wind + Solar ) = 14.5% Research indicates that in most large scale grid systems, VRR < 10% of peak capacity has little impact on system operation. Larger Shares will present challenges for System Operators. Wind Energy and Power Systems Operations: A review of Wind Integration Studies to Date” The Electricity Journal, Vol 22, Issue 10, 34-43. Day Peak Min Demand (MW) 580.0 400.0 Wind Capacity % 17..5% 25.3% Solar Capacity % 3.4% 5.0% TOTAL 20.9% 30.3% P E A K MIN 17.5% 25.3% 3.4% 5.0% 20.9% 30.3% RE CAPACITY PENETRATION AT ON-PEAK AND OFF-PEAK Wind Capacity % Solar Capacity % TOTAL
  • 16.
  • 17. -5 0 5 10 15 20 25 30 35 40 MW Time 36MW Wind Farm, August 18, 2016 (6:00am - 6:30pm) BMR
  • 18. 0 5 10 15 20 25 MW Time 20MW PV Plant, August 18, 2016 (6:00am - 6:30pm) MW
  • 19. 20 Short Term Plan 2016  Declaration of Machine Availability for Spinning Reserves  Rate of Change alarm for Renewables on the Grid, Renewable Forecasting Improvements  Improve Ramp Response of Machines  Review Load Shedding Scheme  Spinning reserve review
  • 20. 21 Medium to Long Term Plan • Storage • Smart Grid
  • 21. System Operations Improvements • High resolution visualization of grid status and health • Automated Demand Management • Algorithms that identify intermittency events and look-ahead • Integrated forecasting software that allows for more accurate dispatch • Ability to manage the connection or disconnection of micro-grids • Work force demographics and skills
  • 22. JPS Participation in Retail Renewable Energy and Energy Efficiency
  • 23. 24 Retail Service Offered by Energy Services • Energy Auditing • Load logging services (days / weeks) • Load breakout services (logging) • Supply and installation of LED lights • Wind Speed Logging
  • 24. 25 Renewable Energy-Customer Offerings • Solar/Photovoltaic System • Solar Water Heaters
  • 25. 26 Services Offered by Energy Services • Supply and install variable speed drives • Supply and install energy efficient motors • Power factor assessment and correction
  • 26. JPS: Committed to Jamaica’s Growth & Prosperity 27

Editor's Notes

  1. final route
  2. Load logging services (days / weeks) Measurement of electrical parameters (kW, kVA, kWh, PF, current, voltage) for specific equipment or areas (e.g. Grinder, mixer, extractor fan, air conditioner, packing area, canteen etc.) Load breakout services (logging) Measure and show the energy contribution of various loads to total energy consumption