SlideShare a Scribd company logo
1 of 19
Mainstreaming Renewables:
Forecasting, Scheduling and Dispatching of RE
Towards A Net Zero Energy Power Sector
04th March 2020
GUJ, MAH & MP
KAR,
TAM
& AP
RAJ
SLDC
India Power Structure Integration with
RE Rich State phenomenon
Green Energy Corridor
Category
Anticipated Capacity
(MW)
Existing Capacity
(MW)
Requirement (MW)
Wind 60000 37608 (63%) 22392 (37%)
Solar 99533 34036 (34%) 65497 (66%)
SHP 5000 4677 323
Biomass 10000 9861 139
Total 174533 86181 (49%) 88352 (51%)
GoI RE target by 2022
Targeted RE Capacity to be added by 2022
RE target of 450 MW by 2030.
 RE Rich State: Issues
• Solar Generation is highly varies during morning & evening and extremely
varies during cloud cover and monsoon.
• Wind Generation variation @ 1000 to 1500 MW is common now in a days.
• Demand variation @ 2000 to 3000MW is common now in a days.
RE Forecasting & Scheduling Challenges
RE F & S
RE Forecasting Challenges
RE Forecasting Tool
o REMC (at 11 places (1 NLDC, 3 RLDC & 7 RE Rich State)) is implemented /
under final stage.
o However, most important, error between forecast and actual data are
measured with Normalised root mean square error, which cannot be justified
with current Deviation mechanism.
o Also, need to be developed accurate forecast mechanism, where Day ahead
forecast value should be nearer to the real value.
Issues with Forecasting of RE
o Forecasting of each Forecaster is having different value, due to
o having its own model to forecast.
o sources of weather data are also differ.
RE Scheduling Challenges
RE Scheduling Tool
o Concept of unique regulation on RE frame work at central and State.
o Accurate forecasting by QCA and provision for cluster wise forecast can be
considered.
o Forecasting fees structure for QCA.
o Provision of participation of each RE generators and strong involvement and
role of State Energy Development Agency for RE generators which are not
participating.
Issues with Scheduling of RE
o Each RE rich State is having its own RE regulation.
o RE PS wise scheduling exist, group wise scheduling in some of States.
o In case of wind mills, 51% de-pooled criteria, leads other generators towards
the majority generators, without its willingness.
o Even resilient steps towards RE generators for non-adhering RE regulation,
lots RE generators are still silent.
o Error / penalty formula.
RE Dispatching of Power Challenges
Issues with Dispatching of RE
o Adequate grid infrastructure is required to transmit the RE power to the load
centre.
o Long transmission line causes constraints in the grid parameters in the form
of over voltage & voltage fluctuations.
o Transmission network developed for RE plants remains unutilized during low
RE generation / off-peak condition resulting high voltage in system.
o Very high or low RE generation resulting in over / under loading in
associated transmission elements.
RE Dispatching of Power Challenges
Requirement for smooth Dispatching of RE Power
o The connectivity / injection should be approved at higher level voltage i.e. 66
KV & above
o The developer is need to be asked to construct required capacity
transmission line up to CTU/STU grid substation.
o Necessary upward transmission strengthening is need to be carried out as
required, by CTU/STU.
o Permission of injection in the grid is to be granted on
o Approval of permission of Injection into the Grid
o Verification of ABT meter installation and data availability at control
centre
o Verification of real time data availability at control centre
RE Dispatching of Power Challenges
Requirement for smooth Dispatching of RE Power
o Support from Developer & IPP
o To adhere CEA (Technical Standards for Connectivity to the Grid)
Amendment Regulations, 2013. -Measurement of harmonic content, DC
injection and flicker shall be done at least once in a year in presence of the
parties concerned.
o LVRT / HVRT installation & Operation and intimation of all static and
operation data to SLDC.
o Single window communication from Developer.
RE (23 %)
Variable, intermittent &
uncertain energy
Coal Generation
(56 %)
Not Effective
Nuclear
Generation
(2 %)
Must Run
Hydro Generation
(12 %)
Not available in RE
Rich State & as per
need
Gas Generation
(7 %)
Costlier & not
easily available
Thermal capacity is the backbone
of balancing RE as it is available
in large quantities.
Gas plant may ramp up / down quickly.
Must Run Status
Hydro plants can quick
response.
Balancing of Power System Challenges
Coal / Tech Minimum issues
– Old Machine: Slow response in pick up / back down
– Design of machine:
» Limited ability to back-down the generation as per machine design
» Not permit to run machine below CM / TM
– Oil Support after certain minimum level:
» Heat rate increases due to running of generator below TM / CM -
costlier generation
– Seasonal efficiency constrain:
» Thermal - summer &
» Gas - winter
Thermal capacity is the backbone of balancing RE as it is available in
large quantities.
Further, gas is costlier and hydro is negligible amount in India,
particularly in RE rich State.
Mainstreaming Renewables: Challenges
Coal / Tech Minimum concerns
60 to 70 % Technical Minimum in India (50 to 60 % TM / CM in new plants,
having advance technology)
Ramp up / ramp down Issues
Low Flexibility of thermal plant to pick up & back-down frequently
To keep costly gas base generation on bar to handle RE variation leads merit
order violation resulting uneconomical system operation
Ramp up / ramp down concerns
Coal - 1MW to 5MW per minute ramp (5MW to 10MW per minute ramp in
new plants, having advance technology)
Gas - 3MW to 7MW per minute ramp (7MW to 15MW per minute ramp in new
plants, having advance technology)
Mainstreaming Renewables: Challenges
Practical problem with
Coal plant:
– How long RE generation prevail (High or low wind gen trend) ?
– Can conventional plant put on RSD ?
– Are power plant again on bar on time after shut down ?
– Hot Start Issue: may synchronized in short duration
– Cold Start Issue: takes long time to synchronization
Gas plant:
– How long high / low RE generation prevail in a day ?
– Can gas based generation carry on bar with OC or CC ?
– Availability of Gas
– Penalty for non utilization
– Advance confirmation for next days
Mainstreaming Renewables: Challenges
Hydro plants can well balance the RE generation variation due to its quick
response with high ramping of 5MW to 15MW per minute.
• Most of hydro generation available in monsoon season during low load
scenario
• Cannot be utilised as balancing every time
• In general, hydro station running with irrigation programme also
• Availability of water level
Mainstreaming Renewables: Challenges
o Constrain in managing DSM (Deviation Settlement Limit)
o Change in ISGS schedule effective from 4th time block
o Tighten band of deviation +/- 250MW at State boundary
o DSM (Fifth Amendment effective from 3rd June 2019)
o Up to 31.03.2020, the sustained deviation from schedule continues for
12th time blocks, shall attract an additional charge of 10% on the time
block DSM payable / receivable as the case may be.
o From 01.04.2020, the sustained deviation from schedule continues for
6th time blocks, shall attract an additional Charge of 3%, 5% & 10%
on daily base DSM payable / receivable as the case may be. (3% from
1st to 5th , 5% from 6th to 10th & 10% from 11th violation onwards).
Mainstreaming Renewables: DSM
Additional Charge on account of violation of deviation in sign change as per 4th Amendment
Week
Additional
Charge
in
Crore
Additional Charge on account of violation of deviation in sign change as per 5th Amendment
0
100,000
200,000
300,000
400,000
500,000
600,000
10
(03.06.19
to
…
11
12
13
14
15
16
17
18
19
20
(12.08.19
to
…
Additional
Charge
in
Lacs
0
10,000,000
20,000,000
30,000,000
40,000,000
50,000,000
60,000,000
40
(01.01.19
to
…
41
42
43
44
45
46
47
48
49
50
51
52
1
2
3
4
5
6
7
8
9
(27.05.19
to
…
Week
Case Study GJ
Mainstreaming Renewables: DSM
Current - Technological Approach
o Accurate forecasting by State & RE developer
o Special APM gas allocation to RE rich State
o Two shift operation of conventional plant
o Ancillary service at Intra-State level
o Enhance O/D & U/D limit for RE rich State
o Operative hydro stations - pooled at national level
o Operative Pump mode - pooled at national level
o Energy Banking between States
Next - Technological Approach
o Increases Technical Minimum of conventional plant (up to 30%)
o Adoption of Battery Storage & Other storage – Suitable for Micro grid
o Made Operative of Pump mode hydro power station
o Research to convert conventional hydro into Pump mode
Solution
19
Thanking you !!!

More Related Content

Similar to Towards Net Zero Power 04.03.2020.pptx

Presentation_on_DSM_and_ABTmechanisam.pptx
Presentation_on_DSM_and_ABTmechanisam.pptxPresentation_on_DSM_and_ABTmechanisam.pptx
Presentation_on_DSM_and_ABTmechanisam.pptxRuchikavanjari6thstd
 
Eskom system status presentation
Eskom system status presentationEskom system status presentation
Eskom system status presentationMatthew Le Cordeur
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimetRick Case, PMP, P.E.
 
Draft Article - V1
Draft Article - V1Draft Article - V1
Draft Article - V1Ajay Nanda
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014Headway Solar
 
Capgemini ses- smart grid operational services - the impact of renewables o...
Capgemini   ses- smart grid operational services - the impact of renewables o...Capgemini   ses- smart grid operational services - the impact of renewables o...
Capgemini ses- smart grid operational services - the impact of renewables o...Gord Reynolds
 
Choosing Green: Status and Challenges of RE based Open Access
Choosing Green: Status and Challenges of RE based Open AccessChoosing Green: Status and Challenges of RE based Open Access
Choosing Green: Status and Challenges of RE based Open AccessWRI India
 
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...IRJET Journal
 
WHY ARE GRID CODES INTERCONNECTIONS STANDARDS SO IMPORTANT
WHY ARE GRID CODES  INTERCONNECTIONS  STANDARDS SO IMPORTANTWHY ARE GRID CODES  INTERCONNECTIONS  STANDARDS SO IMPORTANT
WHY ARE GRID CODES INTERCONNECTIONS STANDARDS SO IMPORTANTPower System Operation
 
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...IRJET Journal
 
Renewable Energy Integration Limits
Renewable Energy Integration LimitsRenewable Energy Integration Limits
Renewable Energy Integration LimitsAnand SR
 
Eai presentation investment challenges in wind energy in india delhi mar 2010
Eai presentation investment challenges in wind energy in india delhi mar 2010Eai presentation investment challenges in wind energy in india delhi mar 2010
Eai presentation investment challenges in wind energy in india delhi mar 2010Renganathan M G
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.Saurabh Biswas
 
finalpresentation2.pptx
finalpresentation2.pptxfinalpresentation2.pptx
finalpresentation2.pptxNiveditaJha38
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesSaurabh Mehta
 

Similar to Towards Net Zero Power 04.03.2020.pptx (20)

Solar Presentation
Solar PresentationSolar Presentation
Solar Presentation
 
Presentation_on_DSM_and_ABTmechanisam.pptx
Presentation_on_DSM_and_ABTmechanisam.pptxPresentation_on_DSM_and_ABTmechanisam.pptx
Presentation_on_DSM_and_ABTmechanisam.pptx
 
Eskom system status presentation
Eskom system status presentationEskom system status presentation
Eskom system status presentation
 
DSM.pptx
DSM.pptxDSM.pptx
DSM.pptx
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimet
 
Draft Article - V1
Draft Article - V1Draft Article - V1
Draft Article - V1
 
SHAMS Dubai
SHAMS DubaiSHAMS Dubai
SHAMS Dubai
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014
 
Capgemini ses- smart grid operational services - the impact of renewables o...
Capgemini   ses- smart grid operational services - the impact of renewables o...Capgemini   ses- smart grid operational services - the impact of renewables o...
Capgemini ses- smart grid operational services - the impact of renewables o...
 
Choosing Green: Status and Challenges of RE based Open Access
Choosing Green: Status and Challenges of RE based Open AccessChoosing Green: Status and Challenges of RE based Open Access
Choosing Green: Status and Challenges of RE based Open Access
 
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
 
WHY ARE GRID CODES INTERCONNECTIONS STANDARDS SO IMPORTANT
WHY ARE GRID CODES  INTERCONNECTIONS  STANDARDS SO IMPORTANTWHY ARE GRID CODES  INTERCONNECTIONS  STANDARDS SO IMPORTANT
WHY ARE GRID CODES INTERCONNECTIONS STANDARDS SO IMPORTANT
 
smart grid
smart grid smart grid
smart grid
 
Caribbean utility leaders (tomblin)
Caribbean utility leaders (tomblin)Caribbean utility leaders (tomblin)
Caribbean utility leaders (tomblin)
 
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
 
Renewable Energy Integration Limits
Renewable Energy Integration LimitsRenewable Energy Integration Limits
Renewable Energy Integration Limits
 
Eai presentation investment challenges in wind energy in india delhi mar 2010
Eai presentation investment challenges in wind energy in india delhi mar 2010Eai presentation investment challenges in wind energy in india delhi mar 2010
Eai presentation investment challenges in wind energy in india delhi mar 2010
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.
 
finalpresentation2.pptx
finalpresentation2.pptxfinalpresentation2.pptx
finalpresentation2.pptx
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
 

Recently uploaded

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Towards Net Zero Power 04.03.2020.pptx

  • 1. Mainstreaming Renewables: Forecasting, Scheduling and Dispatching of RE Towards A Net Zero Energy Power Sector 04th March 2020
  • 2. GUJ, MAH & MP KAR, TAM & AP RAJ SLDC India Power Structure Integration with RE Rich State phenomenon
  • 4. Category Anticipated Capacity (MW) Existing Capacity (MW) Requirement (MW) Wind 60000 37608 (63%) 22392 (37%) Solar 99533 34036 (34%) 65497 (66%) SHP 5000 4677 323 Biomass 10000 9861 139 Total 174533 86181 (49%) 88352 (51%) GoI RE target by 2022 Targeted RE Capacity to be added by 2022 RE target of 450 MW by 2030.  RE Rich State: Issues • Solar Generation is highly varies during morning & evening and extremely varies during cloud cover and monsoon. • Wind Generation variation @ 1000 to 1500 MW is common now in a days. • Demand variation @ 2000 to 3000MW is common now in a days.
  • 5. RE Forecasting & Scheduling Challenges RE F & S
  • 6. RE Forecasting Challenges RE Forecasting Tool o REMC (at 11 places (1 NLDC, 3 RLDC & 7 RE Rich State)) is implemented / under final stage. o However, most important, error between forecast and actual data are measured with Normalised root mean square error, which cannot be justified with current Deviation mechanism. o Also, need to be developed accurate forecast mechanism, where Day ahead forecast value should be nearer to the real value. Issues with Forecasting of RE o Forecasting of each Forecaster is having different value, due to o having its own model to forecast. o sources of weather data are also differ.
  • 7. RE Scheduling Challenges RE Scheduling Tool o Concept of unique regulation on RE frame work at central and State. o Accurate forecasting by QCA and provision for cluster wise forecast can be considered. o Forecasting fees structure for QCA. o Provision of participation of each RE generators and strong involvement and role of State Energy Development Agency for RE generators which are not participating. Issues with Scheduling of RE o Each RE rich State is having its own RE regulation. o RE PS wise scheduling exist, group wise scheduling in some of States. o In case of wind mills, 51% de-pooled criteria, leads other generators towards the majority generators, without its willingness. o Even resilient steps towards RE generators for non-adhering RE regulation, lots RE generators are still silent. o Error / penalty formula.
  • 8. RE Dispatching of Power Challenges Issues with Dispatching of RE o Adequate grid infrastructure is required to transmit the RE power to the load centre. o Long transmission line causes constraints in the grid parameters in the form of over voltage & voltage fluctuations. o Transmission network developed for RE plants remains unutilized during low RE generation / off-peak condition resulting high voltage in system. o Very high or low RE generation resulting in over / under loading in associated transmission elements.
  • 9. RE Dispatching of Power Challenges Requirement for smooth Dispatching of RE Power o The connectivity / injection should be approved at higher level voltage i.e. 66 KV & above o The developer is need to be asked to construct required capacity transmission line up to CTU/STU grid substation. o Necessary upward transmission strengthening is need to be carried out as required, by CTU/STU. o Permission of injection in the grid is to be granted on o Approval of permission of Injection into the Grid o Verification of ABT meter installation and data availability at control centre o Verification of real time data availability at control centre
  • 10. RE Dispatching of Power Challenges Requirement for smooth Dispatching of RE Power o Support from Developer & IPP o To adhere CEA (Technical Standards for Connectivity to the Grid) Amendment Regulations, 2013. -Measurement of harmonic content, DC injection and flicker shall be done at least once in a year in presence of the parties concerned. o LVRT / HVRT installation & Operation and intimation of all static and operation data to SLDC. o Single window communication from Developer.
  • 11. RE (23 %) Variable, intermittent & uncertain energy Coal Generation (56 %) Not Effective Nuclear Generation (2 %) Must Run Hydro Generation (12 %) Not available in RE Rich State & as per need Gas Generation (7 %) Costlier & not easily available Thermal capacity is the backbone of balancing RE as it is available in large quantities. Gas plant may ramp up / down quickly. Must Run Status Hydro plants can quick response. Balancing of Power System Challenges
  • 12. Coal / Tech Minimum issues – Old Machine: Slow response in pick up / back down – Design of machine: » Limited ability to back-down the generation as per machine design » Not permit to run machine below CM / TM – Oil Support after certain minimum level: » Heat rate increases due to running of generator below TM / CM - costlier generation – Seasonal efficiency constrain: » Thermal - summer & » Gas - winter Thermal capacity is the backbone of balancing RE as it is available in large quantities. Further, gas is costlier and hydro is negligible amount in India, particularly in RE rich State. Mainstreaming Renewables: Challenges
  • 13. Coal / Tech Minimum concerns 60 to 70 % Technical Minimum in India (50 to 60 % TM / CM in new plants, having advance technology) Ramp up / ramp down Issues Low Flexibility of thermal plant to pick up & back-down frequently To keep costly gas base generation on bar to handle RE variation leads merit order violation resulting uneconomical system operation Ramp up / ramp down concerns Coal - 1MW to 5MW per minute ramp (5MW to 10MW per minute ramp in new plants, having advance technology) Gas - 3MW to 7MW per minute ramp (7MW to 15MW per minute ramp in new plants, having advance technology) Mainstreaming Renewables: Challenges
  • 14. Practical problem with Coal plant: – How long RE generation prevail (High or low wind gen trend) ? – Can conventional plant put on RSD ? – Are power plant again on bar on time after shut down ? – Hot Start Issue: may synchronized in short duration – Cold Start Issue: takes long time to synchronization Gas plant: – How long high / low RE generation prevail in a day ? – Can gas based generation carry on bar with OC or CC ? – Availability of Gas – Penalty for non utilization – Advance confirmation for next days Mainstreaming Renewables: Challenges
  • 15. Hydro plants can well balance the RE generation variation due to its quick response with high ramping of 5MW to 15MW per minute. • Most of hydro generation available in monsoon season during low load scenario • Cannot be utilised as balancing every time • In general, hydro station running with irrigation programme also • Availability of water level Mainstreaming Renewables: Challenges
  • 16. o Constrain in managing DSM (Deviation Settlement Limit) o Change in ISGS schedule effective from 4th time block o Tighten band of deviation +/- 250MW at State boundary o DSM (Fifth Amendment effective from 3rd June 2019) o Up to 31.03.2020, the sustained deviation from schedule continues for 12th time blocks, shall attract an additional charge of 10% on the time block DSM payable / receivable as the case may be. o From 01.04.2020, the sustained deviation from schedule continues for 6th time blocks, shall attract an additional Charge of 3%, 5% & 10% on daily base DSM payable / receivable as the case may be. (3% from 1st to 5th , 5% from 6th to 10th & 10% from 11th violation onwards). Mainstreaming Renewables: DSM
  • 17. Additional Charge on account of violation of deviation in sign change as per 4th Amendment Week Additional Charge in Crore Additional Charge on account of violation of deviation in sign change as per 5th Amendment 0 100,000 200,000 300,000 400,000 500,000 600,000 10 (03.06.19 to … 11 12 13 14 15 16 17 18 19 20 (12.08.19 to … Additional Charge in Lacs 0 10,000,000 20,000,000 30,000,000 40,000,000 50,000,000 60,000,000 40 (01.01.19 to … 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 (27.05.19 to … Week Case Study GJ Mainstreaming Renewables: DSM
  • 18. Current - Technological Approach o Accurate forecasting by State & RE developer o Special APM gas allocation to RE rich State o Two shift operation of conventional plant o Ancillary service at Intra-State level o Enhance O/D & U/D limit for RE rich State o Operative hydro stations - pooled at national level o Operative Pump mode - pooled at national level o Energy Banking between States Next - Technological Approach o Increases Technical Minimum of conventional plant (up to 30%) o Adoption of Battery Storage & Other storage – Suitable for Micro grid o Made Operative of Pump mode hydro power station o Research to convert conventional hydro into Pump mode Solution