3. Architecture + Engineering + Environmental + Planning | ISGInc.com
Firm Overview
Business Units
Commercial
Education
Food
+ Industrial
Government
+ Cultural
Healthcare
Housing
Mining
PublicWorks
Sports
+ Recreation
Telecommunications
+ Energy
Transportation
Water
450+ Multi-Disciplinary Professionals
11 Midwest Offices
4. Architecture + Engineering + Environmental + Planning | ISGInc.com
Case Study Challenges
Nutrient
Loss
Lost
Production
Aging
Infrastructure
Case Study Conditions:
• Large multi-landowner
systems with a county-level
board
• Drainage coefficient
unsuitable for modern farming
practices
• No water quality regulations
• Multiple stakeholder groups
6. Architecture + Engineering + Environmental + Planning | ISGInc.com
Case Study Locations
BuenaVista County
Kossuth County
Osceola County
Site Locations
7. Architecture + Engineering + Environmental + Planning | ISGInc.com
Site 1: BuenaVista County
• “Youngest” System
~100 years old
• FiveTotal Districts
• Four Interior Districts
• Restricted Outlets
8. Architecture + Engineering + Environmental + Planning | ISGInc.com
Existing Conditions
Summer 2013
July 2015
May 2016
April 2018
9. Architecture + Engineering + Environmental + Planning | ISGInc.com
Project Alternatives
Standard Drainage Solutions
Limitations
• Ditch grade
• Cost
• Stakeholder engagement
Hybrid Solution
Limitations
• Stakeholder engagement
• Funding
Main Open
Ditch Extension
Open Ditch
Cleanout
10. Architecture + Engineering + Environmental + Planning | ISGInc.com
Site 2: Kossuth County Drainage District No. 75
• Des Moines Lobe
• ~1,600 Ac Watershed
• Originally constructed in 1913
• Outlets to East Fork Des Moines
River floodplain
• ~19% of 1/2” Dc at outlet,
20-30% throughout system
• USFWS property
• Engaged landowners
11. Architecture + Engineering + Environmental + Planning | ISGInc.com
Tile Improvements + Design Options
Tile Improvements + Design Options
• 1/2” or 3/4” Dc
• Open ditch outlet
• MainTile and Lateral 1
• Additional lateral improvements
• Opportunities for water quality
improvement and alternative
design
Design Alternative:
Nutrient Reduction Wetland
• Breakpoint-style wetland
• Outlet district tiles
• Surface drainage channel
• Topographic limitations
13. Architecture + Engineering + Environmental + Planning | ISGInc.com
Alternative Project Funding
Multiple entities
involved
Anticipated low
interest
• Compared to
Drainage Bonds (5%)
Finance district
drainage and
wetland costs
District
investment
in wetland
• Alternative funding
for remainder
Up to 20-year loan
payback
Construction and
interest savings
Up to $480K in
potential savings
14. Architecture + Engineering + Environmental + Planning | ISGInc.com
Site 3: Osceola County JDD3 Branch 152
• ~4,400 Ac Watershed
• Originally constructed in 1917
• Historical Chain Lake basin
• ~20-30% of recommended capacity
throughout system
• Multiple branches considered
• Significant drown outs
• Engaged landowners
15. Architecture + Engineering + Environmental + Planning | ISGInc.com
Drainage Improvements + Challenges
• Large tile sizes
• Ditch not feasible
• Extremely high cost (>$1,200/AC)
• Grade available
• Higher coefficients considered
Quick overview of landforms: the blue area is the Des Moines Lobe which is characterized as a prairie pothole landscape- poorly drainage glacial till soils; extensive drainage. The area was formerly prairie and is now primarily row crops with extensive publicly owned drainage infrastructure (Drainage Districts). This has resulted in less than 1% of the Iowa prairie landscape remaining.
Project discussion order: start from the bottom and work our way to the top
Summer 2013 photo- NE corner had been placed into CRP (perennial vegetation) by that time but was for sure cropped through 2011