 Before any activity begins related to the work of a
project, every project requires an advanced, accurate
time estimate. Without an accurate estimate, no project
can be completed within the budget and the target
completion date.
 Developing an estimate is a complex task. If the project
is large and has many stakeholders, things can be more
complex.
 Therefore, there have been many initiatives to come up
with different techniques for estimation phase of the
project in order to make the estimation more accurate.
 PERT (Program Evaluation and Review Technique) is one
of the successful and proven methods among the many
other techniques, such as, CPM, Function Point
Counting,Top-Down Estimating, WAVE, etc.
Introduction
 PERT is all about management probabilities.
 Same as most of other estimation techniques, PERT also
breaks down the tasks into detailed activities.
 In this map, a node represents each event. The activities are
represented as arrows and they are drawn from one event to
another, based on the sequence.
 Next, the Earliest Time (TE) and the Latest Time (TL) are
figured for each activity and identify the slack time for each
activity.
 When it comes to deriving the estimates, the PERT model
takes a statistical route to do that. We will cover more on this
in the next two sections.
 There are three estimation times involved in PERT;
to = Optimistic Time Estimate
tm = Most LikelyTime Estimate
tp = Pessimistic Time Estimate
 In PERT, these three estimate times are derived for each
activity. This way, a range of time is given for each
activity with the most probable value,
TheThree Chances
 Optimistic Time Estimate:
This is the fastest time an activity can be
For this, the assumption is made that all the
resources are available and all predecessor
are completed as planned.
 Most Likely Time Estimate:
Most of the times, project managers are asked
submit one estimate. In that case, this is the
that goes to the upper management.
 Pessimistic Time Estimate:
This is the maximum time required to complete
activity. In this case, it is assumed that many
wrong related to the activity. A lot of rework and
resource unavailability are assumed when this
estimation is derived.
te = (to + 4tm + tp)/6
v= (tp - to )^2/6^2
 BETA probability distribution is what works behind PERT.
The expected completion time (te) is calculated as below:
 At the same time, the possible variance (v) of the estimate is
calculated as below:
 Before these three times can be combined into a single
expression for expected time, two assumptions must be
made.
1. that the standard deviation, is one-sixth of the time
requirement range. This assumption stems from
probability theory, where the end points of a curve are
three standard deviations from the mean.
2. that the probability distribution of time required for an
activity be expressible as a beta distribution.
 Now, following is the process we follow with the two
values:
 For every activity in the critical path, E andV are calculated.
 Then, the total of all Es are taken. This is the overall
expected completion time for the project.
 Now, the corresponding V is added to each activity of the
critical path. This is the variance for the entire project. This
is done only for the activities in the critical path as only the
critical path activities can accelerate or delay the project
duration.
 Then, standard deviation of the project is calculated. This
equals to the square root of the variance (V).
 Now, the normal probability distribution is used for
calculating the project completion time with the desired
probability.
 As an example, if a = 3, b = 7, and m = 5 weeks, then the
expected time, te, would be 5 weeks.
 This value for te would then be used as the activity time
between two events in the construction of a PERT chart.
This method for obtaining best estimates contains a large
degree of uncertainty.
 If we change the variable times to a = 2, b = 12, and m = 4
weeks, then te will still be 5 weeks.
 The latter case, however, has a much higher degree of
uncertainty because of the wider spread between the
optimistic and pessimistic times.
 Care must be taken in the evaluation of risks in the
expected times
 In order to calculate the probability of completing the
project on time, the standard deviations of each activity
must be known.This can be found from the expression
 We must identify whether it is a one, two, or three sigma
limit deviation
SIGMA te= (tp - to )/6
 The total path standard deviation is calculated by the
square root of the sum of the squares of the activity
standard deviations using the following expression:
 The purpose of calculating is that it allows us to establish
a confidence interval for each activity and the critical
path.
 From statistics, using a normal distribution, we know that
there is a 68 % chance of completing the project within
one standard deviation, a 95 % chance within two
standard deviations, and a 99.73 % chance within three
standard deviations.

More Related Content

What's hot

Spm unit iii-risk-pert
Spm unit iii-risk-pertSpm unit iii-risk-pert
Spm unit iii-risk-pertKanchana Devi
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path AnalysisDavid Zaki
 
Web engineering - Measuring Effort Prediction Power and Accuracy
Web engineering - Measuring Effort Prediction Power and AccuracyWeb engineering - Measuring Effort Prediction Power and Accuracy
Web engineering - Measuring Effort Prediction Power and AccuracyNosheen Qamar
 
Keeping the Same Rule
Keeping the Same RuleKeeping the Same Rule
Keeping the Same RuleMohammed Awad
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsChethanMp7
 
Simulation Project 2
Simulation Project 2Simulation Project 2
Simulation Project 2shri1984
 
Quantitative versus qualitative approaches
Quantitative versus qualitative approachesQuantitative versus qualitative approaches
Quantitative versus qualitative approachesChris Benedict Pareja
 
Local Approximation of PageRank
Local Approximation of PageRankLocal Approximation of PageRank
Local Approximation of PageRanksjuyal
 

What's hot (11)

Ch08 pm2ndhalf
Ch08 pm2ndhalfCh08 pm2ndhalf
Ch08 pm2ndhalf
 
Spm unit iii-risk-pert
Spm unit iii-risk-pertSpm unit iii-risk-pert
Spm unit iii-risk-pert
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
Web engineering - Measuring Effort Prediction Power and Accuracy
Web engineering - Measuring Effort Prediction Power and AccuracyWeb engineering - Measuring Effort Prediction Power and Accuracy
Web engineering - Measuring Effort Prediction Power and Accuracy
 
Keeping the Same Rule
Keeping the Same RuleKeeping the Same Rule
Keeping the Same Rule
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
Pert
PertPert
Pert
 
Simulation Project 2
Simulation Project 2Simulation Project 2
Simulation Project 2
 
Quantitative versus qualitative approaches
Quantitative versus qualitative approachesQuantitative versus qualitative approaches
Quantitative versus qualitative approaches
 
Local Approximation of PageRank
Local Approximation of PageRankLocal Approximation of PageRank
Local Approximation of PageRank
 

Similar to Lec 10 pert estimating techniques

PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique) Tanoj Patidar
 
Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1M.D.Giri Reddy
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii referenceahsanrabbani
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
Pert program evaluation and preview technique, PERT
Pert program evaluation and preview technique, PERTPert program evaluation and preview technique, PERT
Pert program evaluation and preview technique, PERTBalasri Kamarapu
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpasyamputra
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review TechniqueDrAsifMohammad
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pertBhim Upadhyaya
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniquesChander Parkash
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchartlearnt
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 

Similar to Lec 10 pert estimating techniques (20)

PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pert
 
PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique)
 
Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
Cpmpert
CpmpertCpmpert
Cpmpert
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
P E R T
P E R TP E R T
P E R T
 
Pert
PertPert
Pert
 
Pert program evaluation and preview technique, PERT
Pert program evaluation and preview technique, PERTPert program evaluation and preview technique, PERT
Pert program evaluation and preview technique, PERT
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
PERT
PERTPERT
PERT
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pert
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 

More from SAJID ALI RUK

How the adoption of modern technology in manufacturing has influenced safety&...
How the adoption of modern technology in manufacturing has influenced safety&...How the adoption of modern technology in manufacturing has influenced safety&...
How the adoption of modern technology in manufacturing has influenced safety&...SAJID ALI RUK
 
Design and development of phase change material based all weather jacket
Design and development of phase change material based all weather jacketDesign and development of phase change material based all weather jacket
Design and development of phase change material based all weather jacketSAJID ALI RUK
 
Design, fabrication & simulation of mixed mode solar dehydrator for date ...
Design, fabrication & simulation of mixed mode solar dehydrator for date ...Design, fabrication & simulation of mixed mode solar dehydrator for date ...
Design, fabrication & simulation of mixed mode solar dehydrator for date ...SAJID ALI RUK
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_managementSAJID ALI RUK
 
Lec 07 kicking off_the_project
Lec 07 kicking off_the_projectLec 07 kicking off_the_project
Lec 07 kicking off_the_projectSAJID ALI RUK
 
Lec 05 wbs & obs 1
Lec 05 wbs & obs 1Lec 05 wbs & obs 1
Lec 05 wbs & obs 1SAJID ALI RUK
 
Lec 04 project organization
Lec 04 project organizationLec 04 project organization
Lec 04 project organizationSAJID ALI RUK
 
Lec 02 project management
Lec 02 project managementLec 02 project management
Lec 02 project managementSAJID ALI RUK
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
Job Responsibilities of A Maintenance Engineer
Job Responsibilities of A Maintenance EngineerJob Responsibilities of A Maintenance Engineer
Job Responsibilities of A Maintenance EngineerSAJID ALI RUK
 
Types of Maintenance Inspections and its importance for the organization
Types of Maintenance Inspections and its importance for the organizationTypes of Maintenance Inspections and its importance for the organization
Types of Maintenance Inspections and its importance for the organizationSAJID ALI RUK
 
Importance of Project Management in Mechanical Engineering
Importance of Project Management in Mechanical EngineeringImportance of Project Management in Mechanical Engineering
Importance of Project Management in Mechanical EngineeringSAJID ALI RUK
 
Mini project electronic lock
Mini project electronic lockMini project electronic lock
Mini project electronic lockSAJID ALI RUK
 
Engro fertilizer company limited
Engro fertilizer company limitedEngro fertilizer company limited
Engro fertilizer company limitedSAJID ALI RUK
 
ASME MUET SZAB CHAPTER
ASME MUET SZAB CHAPTERASME MUET SZAB CHAPTER
ASME MUET SZAB CHAPTERSAJID ALI RUK
 
Asme_muet_szab_chapter_history
Asme_muet_szab_chapter_historyAsme_muet_szab_chapter_history
Asme_muet_szab_chapter_historySAJID ALI RUK
 

More from SAJID ALI RUK (20)

How the adoption of modern technology in manufacturing has influenced safety&...
How the adoption of modern technology in manufacturing has influenced safety&...How the adoption of modern technology in manufacturing has influenced safety&...
How the adoption of modern technology in manufacturing has influenced safety&...
 
Design and development of phase change material based all weather jacket
Design and development of phase change material based all weather jacketDesign and development of phase change material based all weather jacket
Design and development of phase change material based all weather jacket
 
Design, fabrication & simulation of mixed mode solar dehydrator for date ...
Design, fabrication & simulation of mixed mode solar dehydrator for date ...Design, fabrication & simulation of mixed mode solar dehydrator for date ...
Design, fabrication & simulation of mixed mode solar dehydrator for date ...
 
Lec 12 gantt chart
Lec 12 gantt chartLec 12 gantt chart
Lec 12 gantt chart
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
 
Lec 07 kicking off_the_project
Lec 07 kicking off_the_projectLec 07 kicking off_the_project
Lec 07 kicking off_the_project
 
Lec 06 planning
Lec 06 planningLec 06 planning
Lec 06 planning
 
Lec 05 wbs & obs 1
Lec 05 wbs & obs 1Lec 05 wbs & obs 1
Lec 05 wbs & obs 1
 
Lec 04 project organization
Lec 04 project organizationLec 04 project organization
Lec 04 project organization
 
Lec 02 project management
Lec 02 project managementLec 02 project management
Lec 02 project management
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Job Responsibilities of A Maintenance Engineer
Job Responsibilities of A Maintenance EngineerJob Responsibilities of A Maintenance Engineer
Job Responsibilities of A Maintenance Engineer
 
Types of Maintenance Inspections and its importance for the organization
Types of Maintenance Inspections and its importance for the organizationTypes of Maintenance Inspections and its importance for the organization
Types of Maintenance Inspections and its importance for the organization
 
Importance of Project Management in Mechanical Engineering
Importance of Project Management in Mechanical EngineeringImportance of Project Management in Mechanical Engineering
Importance of Project Management in Mechanical Engineering
 
Mini project electronic lock
Mini project electronic lockMini project electronic lock
Mini project electronic lock
 
Engro fertilizer company limited
Engro fertilizer company limitedEngro fertilizer company limited
Engro fertilizer company limited
 
ASME MUET SZAB CHAPTER
ASME MUET SZAB CHAPTERASME MUET SZAB CHAPTER
ASME MUET SZAB CHAPTER
 
Asme_muet_szab_chapter_history
Asme_muet_szab_chapter_historyAsme_muet_szab_chapter_history
Asme_muet_szab_chapter_history
 
Motivation
Motivation Motivation
Motivation
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 

Lec 10 pert estimating techniques

  • 1. Project Management PERT Estimation TECHNIQUES By Qadir Nawaz Abbasi Mechanical Engineering Dept: MUET SZAB Campus Khairpur Mir’s July, 2018
  • 2.  Before any activity begins related to the work of a project, every project requires an advanced, accurate time estimate. Without an accurate estimate, no project can be completed within the budget and the target completion date.  Developing an estimate is a complex task. If the project is large and has many stakeholders, things can be more complex.  Therefore, there have been many initiatives to come up with different techniques for estimation phase of the project in order to make the estimation more accurate.  PERT (Program Evaluation and Review Technique) is one of the successful and proven methods among the many other techniques, such as, CPM, Function Point Counting,Top-Down Estimating, WAVE, etc. Introduction
  • 3.  PERT is all about management probabilities.  Same as most of other estimation techniques, PERT also breaks down the tasks into detailed activities.  In this map, a node represents each event. The activities are represented as arrows and they are drawn from one event to another, based on the sequence.  Next, the Earliest Time (TE) and the Latest Time (TL) are figured for each activity and identify the slack time for each activity.  When it comes to deriving the estimates, the PERT model takes a statistical route to do that. We will cover more on this in the next two sections.
  • 4.  There are three estimation times involved in PERT; to = Optimistic Time Estimate tm = Most LikelyTime Estimate tp = Pessimistic Time Estimate  In PERT, these three estimate times are derived for each activity. This way, a range of time is given for each activity with the most probable value, TheThree Chances
  • 5.  Optimistic Time Estimate: This is the fastest time an activity can be For this, the assumption is made that all the resources are available and all predecessor are completed as planned.  Most Likely Time Estimate: Most of the times, project managers are asked submit one estimate. In that case, this is the that goes to the upper management.  Pessimistic Time Estimate: This is the maximum time required to complete activity. In this case, it is assumed that many wrong related to the activity. A lot of rework and resource unavailability are assumed when this estimation is derived.
  • 6. te = (to + 4tm + tp)/6 v= (tp - to )^2/6^2  BETA probability distribution is what works behind PERT. The expected completion time (te) is calculated as below:  At the same time, the possible variance (v) of the estimate is calculated as below:  Before these three times can be combined into a single expression for expected time, two assumptions must be made. 1. that the standard deviation, is one-sixth of the time requirement range. This assumption stems from probability theory, where the end points of a curve are three standard deviations from the mean. 2. that the probability distribution of time required for an activity be expressible as a beta distribution.
  • 7.  Now, following is the process we follow with the two values:  For every activity in the critical path, E andV are calculated.  Then, the total of all Es are taken. This is the overall expected completion time for the project.  Now, the corresponding V is added to each activity of the critical path. This is the variance for the entire project. This is done only for the activities in the critical path as only the critical path activities can accelerate or delay the project duration.  Then, standard deviation of the project is calculated. This equals to the square root of the variance (V).  Now, the normal probability distribution is used for calculating the project completion time with the desired probability.
  • 8.  As an example, if a = 3, b = 7, and m = 5 weeks, then the expected time, te, would be 5 weeks.  This value for te would then be used as the activity time between two events in the construction of a PERT chart. This method for obtaining best estimates contains a large degree of uncertainty.  If we change the variable times to a = 2, b = 12, and m = 4 weeks, then te will still be 5 weeks.  The latter case, however, has a much higher degree of uncertainty because of the wider spread between the optimistic and pessimistic times.  Care must be taken in the evaluation of risks in the expected times
  • 9.  In order to calculate the probability of completing the project on time, the standard deviations of each activity must be known.This can be found from the expression  We must identify whether it is a one, two, or three sigma limit deviation SIGMA te= (tp - to )/6
  • 10.  The total path standard deviation is calculated by the square root of the sum of the squares of the activity standard deviations using the following expression:  The purpose of calculating is that it allows us to establish a confidence interval for each activity and the critical path.  From statistics, using a normal distribution, we know that there is a 68 % chance of completing the project within one standard deviation, a 95 % chance within two standard deviations, and a 99.73 % chance within three standard deviations.