SlideShare a Scribd company logo
1 of 55
Presented by:
Vijayvenkatesh.C
CIVIL DEPARTMENT OF CIVIL ENGINEERING
FINAL YEAR.
ST.JOSEPHS COLLEGE OF ENGINEERING &
TECHNOLOGY.
 Highway construction can be characterized by large right-of-way having
length of considerable amount. Due to this Highway construction
constitutes materials that are needed in large quantum. Depending upon
the type of highway pavement, flexible or rigid the material required for
highway construction is decided.
 These items of major importance which are used in normal
highway construction
are:
1. Bituminous Materials
2. Soil
3. Aggregates
4. Portland Cement Concrete
5. Admixtures
6. Pavement Marking Materials
7. Structural Steel
Bituminous Materials
 Bituminous material, or bitumen in the form of asphalt, is one of
the major highway construction materials used.
 Asphalt is normally a residue product from the distillation of crude
oil and, as refined, is a heavy, viscous material that is semisolid at
normal atmospheric temperatures.
 By controlled processing or blending desired viscosity and
hardness
characteristics can be produced.
 This product is called asphalt cement and is also known as paving
grade or penetration grade asphalt.
 Bituminous Materials, of the Highway Materials Manual contains
the test procedures, sampling requirements, and test equipments.
Soils
Major works of man since the beginning of time have depended on the
use of soils.
 Not only does soil form the foundation, or supporting surface for
buildings, bridges, roadways and culverts, but it is the most common
constituent, in the form of aggregate.
 Soils are the most basic abundant material in highway engineering
and as such, are well characterized by the expression "common as
dirt."
 The steps taken to prepare foundations manipulate and transport soils
and prepare them for use as aggregates accounts for well over 70 percent
of the total cost of construction for a normal highway project.
Aggregates
 The surface, base, and sub base of pavements consist of aggregates
or a mixture of aggregates with cement and water (Portland cement
concrete) or a bituminous material (bituminous concrete).
 The strength properties of a layer are a function of both the quality
and the proportions of ingredients.
 Aggregates are hard, durable, mineral materials obtained by
mining or quarrying operations of deposits of sand, gravel, talus or
ledges, and may be defined as "granular material of mineral
composition
Portland Cement Concrete
 Portland cement concrete is a mixture of portland cement, water,
air, sand and gravel or crushed stone.
 It is formed when the cement and water (paste) combine
chemically and binds the entire mixture into a rock-like mass.
 It may be thought of as a two component material; paste and
aggregate.
 The paste is comprised of cement, water, and entrained air.
 The aggregate portion is generally composed of sand and gravel and
comprises 70 to 80 percent of the volume of the concrete.
 Aggregates both fine and course, should be selected for their quality,
strength, durability and resistance to environmental affects.
Admixtures
 Number of additives developed to improve various characteristics
of concrete in both the plastic and hardened states.Other additives
gaining in usage are known as water reducing admixtures and set
retarding admixtures.
 Water reducing additive is intended to impart more workability into a
plastic concrete with less water, thereby increasing its strength through a
reduced water/cement ratio.
 Set retarding additive is intended to slow the setting characteristics of the
mix and thereby allowing more time for placing and finishing
Pavement Marking Materials
 Pavement markings have important functions in providing guidance and
information to drivers.
Pavement markings convey important information to drivers without
diverting their attention from the road.

In some cases they supplement regulations or warnings given by other
devices. In other cases they are used alone and produce results that
cannot be obtained by any other device.

Many materials can be used for pavement marking. The choice depends
on cost, durability, reflectivity, pavement surface, and drying time.
These are Pavement Marking Materials,
Paint
Water-based paint, applied either cold or hot, is the most commonly
used pavement marking. It is low cost with a short drying time, but its
visibility on wet nights is just moderate.
Thermoplastics
These pavement-marking materials are made of thermoplastic heated to
about 400° F and spread onto the pavement surface
Epoxy
Also applied as a liquid with special equipment, epoxy has good
visibility and reflectivity, and cost is moderate. Markings remains 3 to 4
years.
 Moisture Condition Value (MCV) Test
 California Bearing Ration (CBR) Test
 Dynamic Cone Penetrometer
 Ground Penetrating Radar (GPR)
 Penetration Test on Bitumen:
 Softening Point Test on Bitumen
 Los Angles Abrasion Value Test
 Flakiness Index Test
 The California bearing ratio (CBR) is a penetration test for evaluation
of the mechanical strength of natural ground, subgrades and basecourses
beneath new carriageway construction.
 Subgrade soil is the integral part of the road pavement structure which
provides support to the pavement. The subgrade and its different
properties are very much important in the pavement design structure.
 The major function of the subgrade is to provide the support to the
pavement against traffic loading and for this the subgrade should
possess sufficient stability under adverse climate and heavy loading
conditions.
 The strength of a soil or subgrade can be determined by using a test
known as California Bearing Ratio Test which was developed in
California in the year 1930's and it is way to determine the standard
soil properties such as density
Subgrade performance
A subgrade characteristics mainly depends on the following three factors
such as,
 Load bearing capacity: The subgrade resists loads which are transmitted
from the pavement structure. Various factors such as degree of
compaction, moisture content, and nature of soil affect the load bearing
capacity of soil. A subgrade without excessive deformation sustain heavy
loading is considered good.
 Moisture content: Properties such as load bearing capacity, shrinkage and
swelling etc. are mostly affected by the variation of moisture content.
Various things such as drainage, groundwater table elevation, infiltration,
or pavement porosity etc. Influence the moisture content. Highly wet
subgrades deform more under loading..
Shrinkage and/or swelling:
 Shrinkage or swelling mainly depends on moisture content. Additionally,
in frost conditions (in northern climate) soils with excessive fine content
may be susceptible to frost heave.
 Shrinkage, swelling and frost heave are the factors whose tendency is to
deform and crack any pavement structure construed over them.
The desirable properties of sub grade soil as a highway material are
 Withstand capability (Stability)
 Ease of compaction.
 Strength permanency
 Low change in volume during adverse conditions of
weather and ground water table.
 Superior drainage
 Incompressibility
Aggregate plays an important role in pavement construction.
Aggregates influence, to a great extent, the load transfer
capability of pavements, following tests are carried out:
 Crushing test
 Abrasion test
 Impact test
 Soundness test
 Specific gravity and water absorption test
 Bitumen adhesion test
CRUSHING TEST
Crushing Test is used to determine the crushing strength of
aggregates. The aggregate crushing value provides a relative
measure of resistance to crushing under gradually applied crushing
load
ABRASION TEST
 Abrasion test is carried out to test the hardness property of
aggregates and to decide whether they are suitable for different
pavement construction works. Los Angeles abrasion test is a
preferred one for carrying out the hardness property and has
been standardized in India
IMPACT TEST
 The aggregate impact test is carried out to evaluate the resistance to
impact of aggregates. Aggregates passing 12.5 mm sieve and retained on
10 mm sieve is filled in a cylindrical steel cup of internal dia 10.2 mm
and depth 5 cm which is attached to a metal base of impact testing
machine.
 The material is filled in 3 layers where each layer is tamped for 25
numbers of blows. Metal hammer of weight 13.5 to 14 Kg is arranged to
drop with a free fall of 38.0 cm by vertical guides and the test specimen
is subjected to 15 numbers of blows.
 The crushed aggregate is allowed to pass through 2.36 mm IS sieve. And
the impact value is measured as percentage of aggregates passing sieve
(W2) to the total weight of the sample (W1).
Aggregate impact value = (W1/W2)*100
 Soundness test is intended to study the resistance of aggregates to
weathering action, by conducting accelerated weathering test cycles. The
Porous aggregates subjected to freezing and thawing is likely to
disintegrate prematurely. To ascertain the durability of such aggregates,
they are subjected to an accelerated soundness test
 Aggregates of specified size are subjected to cycles of alternate wetting
in a saturated solution of either sodium sulphate or magnesium sulphate
for 16 – 18 hours and then dried in oven at 105 to 1100C to a constant
weight. After five cycles, the loss in weight of aggregates is determined
by sieving out all undersized particles and weighing.
The loss in weight should not exceed 12 percent when tested
with sodium sulphate and 18 percent with magnesium
sulphate solution.
 The specific gravity and water absorption of aggregates are important
properties that are required for the design of concrete and bituminous
mixes. The specific gravity of a solid is the ratio of its mass to that of
an equal volume of distilled water at a specified temperature.
 Water Absorption: The difference between the apparent and bulk
specific gravities is nothing but the water permeable voids of the
aggregates. We can measure the volume of such voids by weighing the
aggregates dry and in a saturated surface dry condition, with all
permeable voids filled with water. The difference of the above two is
MW.
 MW is the weight of dry aggregates minus weight of aggregates
saturated surface dry condition. Thus,
Water Absorption = (MW/MD)*100
 Bitumen adheres well to all normal types of road aggregates provided
they are dry and free from dust. In the absence of water there is
practically no adhesion problem of bituminous construction.
 Adhesion problem occurs when the aggregate is wet and cold. This
problem can be dealt with by removing moisture from the aggregate by
drying and increasing the mixing temperature.
 Further, the presence of water causes stripping of binder from the coated
aggregates. This problem occurs when bitumen mixture is permeable to
water.
 Several laboratory tests are conducted to arbitrarily determine the
adhesion of bitumen binder to an aggregate in the presence of water.
Static immersion test is one specified by IRC and is quite simple.
 The principle of the test is by immersing aggregate fully coated with
binder in water maintained at 400C temperature for 24 hours.
 Penetration test
 Ductility test
 Softening point test
 Specific gravity test
 Viscosity test
 Flash and Fire point test
 Float test
 Water content test
 Loss on heating test
Penetration test
 It measures the hardness or softness of bitumen by measuring the depth
in tenths of a millimeter to which a standard loaded needle will penetrate
vertically in 5 seconds
 It may be noted that penetration value is largely influenced by any
inaccuracy with regards to pouring temperature, size of the needle,
weight placed on the needle and the test temperature.
 In hot climates, a lower penetration grade preferred.
DUCTILITY TEST
 Ductility is the property of bitumen that permits it to undergo great
deformation or elongation.
 Ductility is defined as the distance in cm, to which a standard
sample or briquette of the material will be elongated without
breaking.
 Dimension of the briquette thus formed is exactly 1 cm square.
The bitumen sample is heated and poured in the mould assembly
placed on a plate.
 These samples with moulds are cooled in the air and then in water
bath at 270C temperature.
 The excess bitumen is cut and the surface is leveled using a hot
knife. Then the mould with assembly containing sample is kept in
water bath of the ductility machine for about 90 minutes.
 The sides of the moulds are removed, the clips are hooked on the
machine and the machine is operated. The distance up to the point
of breaking of thread is the ductility value which is reported in cm.
 The ductility value gets affected by factors such as pouring
temperature, test temperature, rate of pulling etc.
 A minimum ductility value of 75 cm has been specified by the
BIS..
SOFTENING POINT TEST
Softening point denotes the temperature at which the bitumen
attains a particular degree of softening under the specified
condition of test.
 The test is conducted by using Ring and Ball apparatus. A brass
ring containing test sample of bitumen is suspended in liquid like
water or glycerin at a given temperature.
 A steel ball is placed upon the bitumen sample and the liquid
medium is heated at a rate of 50C per minute. Temperature is noted
when the softened bitumen touches the metal plate which is at a
specified distance below.
 Generally, higher softening point indicates lower temperature
susceptibility and is preferred in hot climates.
SPECIFIC GRAVITY TEST
 The specific gravity of bitumen is defined as the ratio of mass of given
volume of bitumen of known content to the mass of equal volume of
water at 270C.
 The specific gravity can be measured using either pycnometer or
preparing a cube specimen of bitumen in semi solid or solid state.
 In paving jobs, to classify a binder, density property is of great use. In
most cases bitumen is weighed, but when used with aggregates, the
bitumen is converted to volume using density values.
 The density of bitumen is greatly influenced by its chemical
composition. Increase in aromatic type mineral impurities cause an
increase in specific gravity.
 The specific gravity of bitumen varies from 0.97 to 1.02.
WATER CONTENT TEST
 It is desirable that the bitumen contains minimum water content to
prevent foaming of the bitumen when it is heated above the boiling
point of water.
 The water in bitumen is determined by mixing known weight of
specimen in a pure petroleum distillate free from water, heating
and distilling of the water.
 The weight of the water condensed and collected is expressed as
percentage by weight of the original sample.
 The allowable maximum water content should not be more than
0.2% by weight.
LOSS ON HEATING TEST
 When the bitumen is heated it loses the volatility and gets hardened.
About 50gm of the sample is weighed and heated to a temperature of
1630C for 5 hours in a specified oven designed for this test.
 The sample specimen is weighed again after the heating period and
loss in weight is expressed as percentage by weight of the original
sample.
 Bitumen used in pavement mixes should not indicate more than 1%
loss in weight, but for bitumen having penetration values 150-200 up
to 2% loss in weight is allowed.
What is Bitumen?
The primary use (70%) of asphalt/bitumen is in road construction,
where it is used as the glue or binder mixed with aggregate
particles to create asphalt concrete.
Preparation of the existing base course layer
 The existing surface is prepared by removing the pot holes or rust
if any. The irregularities are filled in with premix chippings at least
a week before laying surface course.
 If the existing pavement is extremely way, a bituminous leveling
course of adequate thickness is provided to lay a bituminous
concrete surface course on a binder course instead of directly
laying it on a WBM.
Application of Tuck Coat
It is desirable to lay AC layer over a bituminous base or binder
course. A tack coat of bitumen is applied at 6.0 to 7.5 kg per 10
sq.m area, this quantity may be increased to 7.5 to 10 kg for non-
bituminous base.
Preparation and placing of Premix
 The premix is prepared in a hot mix plant of a required capacity
with the desired quality control. The bitumen may be heated upto
150 – 177 deg C and the aggregate temperature should not differ
by over 14 deg C from the binder temperature.
 The hot mixed material is collected from the mixture by the
transporters, carried to the location is spread by a mechanical paver
at a temperature of 121 to 163 deg C.
 the camber and the thickness of the layer are accurately verified.
The control of the temperatures during the mixing and the
compaction are of great significance in the strength of the resulting
pavement structure.
 Rolling
 A mix after it is placed on the base course is thoroughly compacted by
rolling at a speed not more than 5km per hour.
 The initial or break down rolling is done by 8 to 12 tonnes roller
and the intermediate rolling is done with a fixed wheel pneumatic
roller of 15 to 30 tonnes having a tyre pressure of 7kg per sq.cm.
the wheels of the roller are kept damp with water.
 The number of passes required depends on the thickness of the
layer. In warm weather rolling on the next day, helps to increase
the density if the initial rolling was not adequate. The final rolling
or finishing is done by 8 to 10 tonne tandem roller.
Fig: Tandem Roller
Quality control of bituminous concrete construction
 The routine checks are carried out at site to ensure the quality of
the resulting pavement mixture and the pavement surface.
 Periodical checks are made for,
 a) Aggregate grading
 b) Grade of bitumen
 c) Temperature of aggregate
 d) Temperature of paving mix during mixing and compaction.
At least one sample for every 100 tonnes of the mix discharged by
the hot mix plant is collected and tested for above
requirements. Marshall tests are also conducted. For every 100
sq.m of the compacted surface, one test of the field density is
conducted to check whether it is atleast 95% of the density
obtained in the laboratory. The variation in the thickness allowed is
6mm per 4.5m length of construction.
Finished surface:
 The AC surface should be checked by a 3.0 m straight edge. The
longitudinal undulations should not exceed 8.0 mm and the number
of undulations higher than 6.0 mm should not exceed 10 in a length
of 300 m. The cross-traffic profile should not have undulations
exceeding 4.0mm.
 Cement concrete road construction is one of the types of low
volume road construction. We know that the construction of the
road is mostly dependent upon the factor like amount traffic that is
to be handled by the road after its completion.
 On most of the village roads connecting small villages in the rural
areas of the country, the type of vehicular traffic is quite different
from the traffic on other highways.
 The traffic passing on a road can be categorized into three
categories as light commercial traffics, medium commercial
traffics and heavy commercial traffics, but the frequency of each
class of traffic varies with the road.
Materials for concrete cement road construction
The materials for the cement concrete road construction may be
divided into two parts. These are mentioned as follows:-
 Selection of basic component materials
 Mix design and production of pavement quality concrete(PQC)
mix required to construct the cement concrete road pavement
Subgrade preparation
 Subgrade preparation involves cleaning, earthwork (excavation or
filling of soil, replacement of weak soil, soil stabilization etc.) and
compaction.
 Where the concrete layer is laid directly over the subgrade, the
subgrade is moist at the time concrete is placed. If the subgrade is
dry, water could be sprinkled over the surface before laying any
concrete course, however, care should taken so that soft patches or
water pools are not formed at the surface
Construction of Base/ Sub-base
 A base/ sub-base to the concrete pavement provides uniform and
reasonably firm support, prevents mud-pumping , and acts as
capillary cut-off.
 Sub-base for concrete pavement could be constituted with brick
flat soling, WBM, granular aggregates, crushed concrete, slag,
stabilized soil etc. sub-base could be of three types with
 (i) Granular material (for example, brick soling with one layer of
sand under it, WBM, well graded granular materials etc.)
 (ii) Stabilized soil
 (iii) Semi-rigid material, (for example, lime burnt clay pozzolana
concrete, lime fly-ash concrete, lean cement concrete roller
compacted concrete etc.).
Compaction and surface finishing
 Concrete is spread evenly and is rodded with suitable equipment
such that formation of honey-combing or voids can be avoided. At
the same time, over-compacting needs to be avoided, which can
cause segregation and loss of entrained air
Texturing
 Finished concrete has a smooth surface; texturing of concrete
surface is done to impart required skid resistance to the concrete
surface. The texturing is done by means of wire brushing or
grooving along the transverse direction. Initial texturing may be
done at the time of construction of the paver itself. Final texturing
is done no sooner the sheen of the concrete surface goes off.
Concrete curing
 Curing is a process in which requisite moisture content and
temperature is maintained so that concrete achieves its design
strength through hydration of cement
8.QUALITY CONTROL MEASURES
 Study duties responsibilities, Tender specification, standards, codes of
practice and work instruction.
 Evolve effective acceptance/rejection procedures for construction
materials in coordination with the project purchase department.
 Do proper sampling and testing of steel, cement, concrete, aggregates,
water, etc., and verify test results in view of standards and work
specifications prior to their use in construction. Also control quality of
electrodes to their use in welding.
 Set procedures to control quality at the points of storage for raw
materials, mixing and placing of concrete.
 Follow the prescribed curing and deshuttering schedules.
 Observe procedures to control quality of welded joints of structural
steel members.
 Evolve a system to check quality of workmanship in all construction
activities.
 Keep all revised Indian Standards and codes of practice available in
QC laboratory and have them handy during discussion with
client/consultant.
 Maintain sequence of construction required under any activity.
 Discuss QA/QC issues as a separate agenda during site review
meetings with staff.
 Observe regular schedule for maintenance, repairs and calibration of
plants and equipments.
 Keep spare parts/materials for laboratory equipments weigh batchers,
batching plant, etc., always keep spare vibrators ready at site.
 Carry work instruction cards in pocket while supervising/inspecting
works.
 Regularly maintain the formats prescribed under ISO 9002 Quality
assurance system
 Practice sound house keeping methods to achieve saving, safety and
quality.
9.Highway Drainage
 It’s purpose is to drain rain water from the highway into the
sewerage system. A highway drain is the pipe connecting the
highway gully to the surface water sewer.
 A soakaway is a drainage pit covered by a metal cover or
sometimes by soil. Its purpose is to allow rain water from buildings
to permeate into the surrounding subsoil. These are sometimes
used to drain the highway
Highway drainage should fulfil the following objectives:
 Prevent flooding, ponding and seepage, and keep the carriageway,
cycleway and footway as free of standing water as possible.
 Ensure surface water falling on the highway enters the drainage
system or natural watercourse as speedily as possible.
 Keep the underlying road structure as dry as possible.
 Prevent injury or damage caused by hazardous surface water.
 Prevent highway surface water flooding adjacent properties.
 Prevent blockages in associated highway drainage systems with
consequential flooding.
Highway drainage is important from various view points:
 Excess moisture in soil sub-grade causes instability under the road
surface. The pavement may fail due to sub-grade failure. In some
clayey soil variation in moisture content causes considerable
variation in volume of sub-grade. This sometimes contributes to
pavement failure.
 The waves and corrugations formed in case of flexible pavements
also play an important role in pavement failure.
 Sustained contact of water with bituminous pavements
causes failure due stripping bitumen from the aggregates
like loosening of some of the bituminous pavement layer
and formation of pot holes
 The prime cause of failures in rigid pavements by mud
pumping is due to the presence of water in fine sub-
grade soil.
Well designed and well maintained road drainage is important in
order to:
 Minimize the environmental impact of road runoff on the receiving
water environment.
 Ensure the speedy removal of surface water to enhance safety and
minimize disruption to road users.
 Maximize the longevity of the road surface and associated
infrastructures.
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE

More Related Content

What's hot

Airport obstructions
Airport obstructionsAirport obstructions
Airport obstructionssrinivas2036
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
Cement stabilization of soils ppt
Cement stabilization of soils pptCement stabilization of soils ppt
Cement stabilization of soils pptVeluppillai Mohan
 
Testing of hardened concrete
Testing of hardened concreteTesting of hardened concrete
Testing of hardened concreteJ C
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundationSourabh Jain
 
Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1GARRE RAVI KUMAR
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadampradip dangar
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenenceGhanashyam Prajapati
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPTKavin Raval
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highwayJunaid Jamadar
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavementRandhir Kumar
 
pavement materials:aggregates
pavement materials:aggregates pavement materials:aggregates
pavement materials:aggregates pradip dangar
 

What's hot (20)

Airport obstructions
Airport obstructionsAirport obstructions
Airport obstructions
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Cement stabilization of soils ppt
Cement stabilization of soils pptCement stabilization of soils ppt
Cement stabilization of soils ppt
 
Testing of hardened concrete
Testing of hardened concreteTesting of hardened concrete
Testing of hardened concrete
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 
Embankment
EmbankmentEmbankment
Embankment
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Unit 5
Unit 5Unit 5
Unit 5
 
river training work
river training workriver training work
river training work
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
pavement materials:aggregates
pavement materials:aggregates pavement materials:aggregates
pavement materials:aggregates
 

Viewers also liked

Skybus metro as a mode of transportation
Skybus metro as a mode of transportationSkybus metro as a mode of transportation
Skybus metro as a mode of transportationPramod Chinchansur
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPTVikas Sukhwal
 
Highway Construction
Highway Construction  Highway Construction
Highway Construction zapada rahul
 
JAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITYJAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITYAnkita Kolamkar
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 
Recent construction technologies
Recent construction technologiesRecent construction technologies
Recent construction technologiesChandana Yadav
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elementssubbu lakshmi
 
Under water concreting
Under water concretingUnder water concreting
Under water concretingAgnesh Shetty
 
LIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEMLIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEMAnup Kude
 
Seminar on Environmental Impact Assessment
Seminar on Environmental Impact AssessmentSeminar on Environmental Impact Assessment
Seminar on Environmental Impact Assessmentashwinpand90
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...Bharat Badre
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportBeing Deepak
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work reportAbdul rahman kureshi
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarPavan Kumar N
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance pptBeing Deepak
 
Geological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway constructionGeological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway constructionAbhinav Anand
 

Viewers also liked (20)

Skybus metro as a mode of transportation
Skybus metro as a mode of transportationSkybus metro as a mode of transportation
Skybus metro as a mode of transportation
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
 
Highway Construction
Highway Construction  Highway Construction
Highway Construction
 
JAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITYJAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITY
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
Recent construction technologies
Recent construction technologiesRecent construction technologies
Recent construction technologies
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
 
PWD, national highway
PWD, national highwayPWD, national highway
PWD, national highway
 
LIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEMLIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEM
 
Seminar on Environmental Impact Assessment
Seminar on Environmental Impact AssessmentSeminar on Environmental Impact Assessment
Seminar on Environmental Impact Assessment
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar report
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
Chapter1
Chapter1Chapter1
Chapter1
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminar
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance ppt
 
Piling of a flyover (AUST 2.2 A)
Piling of a flyover (AUST 2.2 A)Piling of a flyover (AUST 2.2 A)
Piling of a flyover (AUST 2.2 A)
 
Geological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway constructionGeological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway construction
 

Similar to HIGHWAY CONSTRUCTION MATERIAL & PRACTICE

Highway Construction Materials and Practice
Highway Construction Materials and PracticeHighway Construction Materials and Practice
Highway Construction Materials and PracticeSenthamizhan M
 
Construction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesConstruction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesRaghvendraBajpai3
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavementpokjak80
 
B-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.pptB-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.pptmosesnhidza
 
Role of water in man made rock.pptx
Role of water in man made rock.pptxRole of water in man made rock.pptx
Role of water in man made rock.pptxRiteshRajput22
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTUVATSAL PATEL
 
Weekly Report of AACRA Practice site visit.docx
Weekly Report of AACRA Practice site visit.docxWeekly Report of AACRA Practice site visit.docx
Weekly Report of AACRA Practice site visit.docxEthiopiaSelam2010
 
Mix proportioning dr. sdb.pptx
Mix proportioning dr. sdb.pptxMix proportioning dr. sdb.pptx
Mix proportioning dr. sdb.pptxnaveen kumar
 
TRANSPORTATION , HIGHWAYS MATERIALS AND ITS TEST
TRANSPORTATION , HIGHWAYS MATERIALS AND ITS TESTTRANSPORTATION , HIGHWAYS MATERIALS AND ITS TEST
TRANSPORTATION , HIGHWAYS MATERIALS AND ITS TESTMahreen Zamir Abro
 
Report in Reinforced Concrete Factory.pdf
Report in Reinforced Concrete Factory.pdfReport in Reinforced Concrete Factory.pdf
Report in Reinforced Concrete Factory.pdfAdnan Alqaramani
 
Construction Testing Cement Testing
Construction Testing  Cement TestingConstruction Testing  Cement Testing
Construction Testing Cement TestingShambhudayal
 
Gangaram yadav ppt road con....
Gangaram yadav ppt road con....Gangaram yadav ppt road con....
Gangaram yadav ppt road con....RaazYadav6
 
Lecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdfLecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdfOmarAbdi39
 
02. Concrete.pptx
02. Concrete.pptx02. Concrete.pptx
02. Concrete.pptxAQIBIMRAN3
 

Similar to HIGHWAY CONSTRUCTION MATERIAL & PRACTICE (20)

Highway materials and tests
Highway materials and testsHighway materials and tests
Highway materials and tests
 
Highway Construction Materials and Practice
Highway Construction Materials and PracticeHighway Construction Materials and Practice
Highway Construction Materials and Practice
 
highway con..pptx
highway con..pptxhighway con..pptx
highway con..pptx
 
c-4.pdf
c-4.pdfc-4.pdf
c-4.pdf
 
Construction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesConstruction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic Wastes
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavement
 
B-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.pptB-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.ppt
 
Role of water in man made rock.pptx
Role of water in man made rock.pptxRole of water in man made rock.pptx
Role of water in man made rock.pptx
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
Weekly Report of AACRA Practice site visit.docx
Weekly Report of AACRA Practice site visit.docxWeekly Report of AACRA Practice site visit.docx
Weekly Report of AACRA Practice site visit.docx
 
Mix proportioning dr. sdb.pptx
Mix proportioning dr. sdb.pptxMix proportioning dr. sdb.pptx
Mix proportioning dr. sdb.pptx
 
TRANSPORTATION , HIGHWAYS MATERIALS AND ITS TEST
TRANSPORTATION , HIGHWAYS MATERIALS AND ITS TESTTRANSPORTATION , HIGHWAYS MATERIALS AND ITS TEST
TRANSPORTATION , HIGHWAYS MATERIALS AND ITS TEST
 
Report in Reinforced Concrete Factory.pdf
Report in Reinforced Concrete Factory.pdfReport in Reinforced Concrete Factory.pdf
Report in Reinforced Concrete Factory.pdf
 
Construction Testing Cement Testing
Construction Testing  Cement TestingConstruction Testing  Cement Testing
Construction Testing Cement Testing
 
Gangaram yadav ppt road con....
Gangaram yadav ppt road con....Gangaram yadav ppt road con....
Gangaram yadav ppt road con....
 
Aggregates
AggregatesAggregates
Aggregates
 
POROUS CONCRETE B8.pptx
POROUS CONCRETE B8.pptxPOROUS CONCRETE B8.pptx
POROUS CONCRETE B8.pptx
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 
Lecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdfLecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdf
 
02. Concrete.pptx
02. Concrete.pptx02. Concrete.pptx
02. Concrete.pptx
 

Recently uploaded

VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 

HIGHWAY CONSTRUCTION MATERIAL & PRACTICE

  • 1. Presented by: Vijayvenkatesh.C CIVIL DEPARTMENT OF CIVIL ENGINEERING FINAL YEAR. ST.JOSEPHS COLLEGE OF ENGINEERING & TECHNOLOGY.
  • 2.  Highway construction can be characterized by large right-of-way having length of considerable amount. Due to this Highway construction constitutes materials that are needed in large quantum. Depending upon the type of highway pavement, flexible or rigid the material required for highway construction is decided.  These items of major importance which are used in normal highway construction are: 1. Bituminous Materials 2. Soil 3. Aggregates 4. Portland Cement Concrete 5. Admixtures 6. Pavement Marking Materials 7. Structural Steel
  • 3. Bituminous Materials  Bituminous material, or bitumen in the form of asphalt, is one of the major highway construction materials used.  Asphalt is normally a residue product from the distillation of crude oil and, as refined, is a heavy, viscous material that is semisolid at normal atmospheric temperatures.  By controlled processing or blending desired viscosity and hardness characteristics can be produced.  This product is called asphalt cement and is also known as paving grade or penetration grade asphalt.  Bituminous Materials, of the Highway Materials Manual contains the test procedures, sampling requirements, and test equipments.
  • 4. Soils Major works of man since the beginning of time have depended on the use of soils.  Not only does soil form the foundation, or supporting surface for buildings, bridges, roadways and culverts, but it is the most common constituent, in the form of aggregate.  Soils are the most basic abundant material in highway engineering and as such, are well characterized by the expression "common as dirt."  The steps taken to prepare foundations manipulate and transport soils and prepare them for use as aggregates accounts for well over 70 percent of the total cost of construction for a normal highway project. Aggregates  The surface, base, and sub base of pavements consist of aggregates or a mixture of aggregates with cement and water (Portland cement concrete) or a bituminous material (bituminous concrete).
  • 5.  The strength properties of a layer are a function of both the quality and the proportions of ingredients.  Aggregates are hard, durable, mineral materials obtained by mining or quarrying operations of deposits of sand, gravel, talus or ledges, and may be defined as "granular material of mineral composition Portland Cement Concrete  Portland cement concrete is a mixture of portland cement, water, air, sand and gravel or crushed stone.  It is formed when the cement and water (paste) combine chemically and binds the entire mixture into a rock-like mass.  It may be thought of as a two component material; paste and aggregate.  The paste is comprised of cement, water, and entrained air.
  • 6.  The aggregate portion is generally composed of sand and gravel and comprises 70 to 80 percent of the volume of the concrete.  Aggregates both fine and course, should be selected for their quality, strength, durability and resistance to environmental affects. Admixtures  Number of additives developed to improve various characteristics of concrete in both the plastic and hardened states.Other additives gaining in usage are known as water reducing admixtures and set retarding admixtures.  Water reducing additive is intended to impart more workability into a plastic concrete with less water, thereby increasing its strength through a reduced water/cement ratio.  Set retarding additive is intended to slow the setting characteristics of the mix and thereby allowing more time for placing and finishing
  • 7. Pavement Marking Materials  Pavement markings have important functions in providing guidance and information to drivers. Pavement markings convey important information to drivers without diverting their attention from the road.  In some cases they supplement regulations or warnings given by other devices. In other cases they are used alone and produce results that cannot be obtained by any other device.  Many materials can be used for pavement marking. The choice depends on cost, durability, reflectivity, pavement surface, and drying time.
  • 8. These are Pavement Marking Materials, Paint Water-based paint, applied either cold or hot, is the most commonly used pavement marking. It is low cost with a short drying time, but its visibility on wet nights is just moderate. Thermoplastics These pavement-marking materials are made of thermoplastic heated to about 400° F and spread onto the pavement surface Epoxy Also applied as a liquid with special equipment, epoxy has good visibility and reflectivity, and cost is moderate. Markings remains 3 to 4 years.
  • 9.  Moisture Condition Value (MCV) Test  California Bearing Ration (CBR) Test  Dynamic Cone Penetrometer  Ground Penetrating Radar (GPR)  Penetration Test on Bitumen:  Softening Point Test on Bitumen  Los Angles Abrasion Value Test  Flakiness Index Test
  • 10.  The California bearing ratio (CBR) is a penetration test for evaluation of the mechanical strength of natural ground, subgrades and basecourses beneath new carriageway construction.  Subgrade soil is the integral part of the road pavement structure which provides support to the pavement. The subgrade and its different properties are very much important in the pavement design structure.  The major function of the subgrade is to provide the support to the pavement against traffic loading and for this the subgrade should possess sufficient stability under adverse climate and heavy loading conditions.
  • 11.  The strength of a soil or subgrade can be determined by using a test known as California Bearing Ratio Test which was developed in California in the year 1930's and it is way to determine the standard soil properties such as density Subgrade performance A subgrade characteristics mainly depends on the following three factors such as,  Load bearing capacity: The subgrade resists loads which are transmitted from the pavement structure. Various factors such as degree of compaction, moisture content, and nature of soil affect the load bearing capacity of soil. A subgrade without excessive deformation sustain heavy loading is considered good.  Moisture content: Properties such as load bearing capacity, shrinkage and swelling etc. are mostly affected by the variation of moisture content. Various things such as drainage, groundwater table elevation, infiltration, or pavement porosity etc. Influence the moisture content. Highly wet subgrades deform more under loading..
  • 12. Shrinkage and/or swelling:  Shrinkage or swelling mainly depends on moisture content. Additionally, in frost conditions (in northern climate) soils with excessive fine content may be susceptible to frost heave.  Shrinkage, swelling and frost heave are the factors whose tendency is to deform and crack any pavement structure construed over them. The desirable properties of sub grade soil as a highway material are  Withstand capability (Stability)  Ease of compaction.  Strength permanency  Low change in volume during adverse conditions of weather and ground water table.  Superior drainage  Incompressibility
  • 13.
  • 14. Aggregate plays an important role in pavement construction. Aggregates influence, to a great extent, the load transfer capability of pavements, following tests are carried out:  Crushing test  Abrasion test  Impact test  Soundness test  Specific gravity and water absorption test  Bitumen adhesion test
  • 15. CRUSHING TEST Crushing Test is used to determine the crushing strength of aggregates. The aggregate crushing value provides a relative measure of resistance to crushing under gradually applied crushing load
  • 16. ABRASION TEST  Abrasion test is carried out to test the hardness property of aggregates and to decide whether they are suitable for different pavement construction works. Los Angeles abrasion test is a preferred one for carrying out the hardness property and has been standardized in India
  • 17. IMPACT TEST  The aggregate impact test is carried out to evaluate the resistance to impact of aggregates. Aggregates passing 12.5 mm sieve and retained on 10 mm sieve is filled in a cylindrical steel cup of internal dia 10.2 mm and depth 5 cm which is attached to a metal base of impact testing machine.  The material is filled in 3 layers where each layer is tamped for 25 numbers of blows. Metal hammer of weight 13.5 to 14 Kg is arranged to drop with a free fall of 38.0 cm by vertical guides and the test specimen is subjected to 15 numbers of blows.  The crushed aggregate is allowed to pass through 2.36 mm IS sieve. And the impact value is measured as percentage of aggregates passing sieve (W2) to the total weight of the sample (W1). Aggregate impact value = (W1/W2)*100
  • 18.
  • 19.  Soundness test is intended to study the resistance of aggregates to weathering action, by conducting accelerated weathering test cycles. The Porous aggregates subjected to freezing and thawing is likely to disintegrate prematurely. To ascertain the durability of such aggregates, they are subjected to an accelerated soundness test  Aggregates of specified size are subjected to cycles of alternate wetting in a saturated solution of either sodium sulphate or magnesium sulphate for 16 – 18 hours and then dried in oven at 105 to 1100C to a constant weight. After five cycles, the loss in weight of aggregates is determined by sieving out all undersized particles and weighing. The loss in weight should not exceed 12 percent when tested with sodium sulphate and 18 percent with magnesium sulphate solution.
  • 20.  The specific gravity and water absorption of aggregates are important properties that are required for the design of concrete and bituminous mixes. The specific gravity of a solid is the ratio of its mass to that of an equal volume of distilled water at a specified temperature.  Water Absorption: The difference between the apparent and bulk specific gravities is nothing but the water permeable voids of the aggregates. We can measure the volume of such voids by weighing the aggregates dry and in a saturated surface dry condition, with all permeable voids filled with water. The difference of the above two is MW.  MW is the weight of dry aggregates minus weight of aggregates saturated surface dry condition. Thus, Water Absorption = (MW/MD)*100
  • 21.  Bitumen adheres well to all normal types of road aggregates provided they are dry and free from dust. In the absence of water there is practically no adhesion problem of bituminous construction.  Adhesion problem occurs when the aggregate is wet and cold. This problem can be dealt with by removing moisture from the aggregate by drying and increasing the mixing temperature.  Further, the presence of water causes stripping of binder from the coated aggregates. This problem occurs when bitumen mixture is permeable to water.  Several laboratory tests are conducted to arbitrarily determine the adhesion of bitumen binder to an aggregate in the presence of water. Static immersion test is one specified by IRC and is quite simple.  The principle of the test is by immersing aggregate fully coated with binder in water maintained at 400C temperature for 24 hours.
  • 22.  Penetration test  Ductility test  Softening point test  Specific gravity test  Viscosity test  Flash and Fire point test  Float test  Water content test  Loss on heating test
  • 23. Penetration test  It measures the hardness or softness of bitumen by measuring the depth in tenths of a millimeter to which a standard loaded needle will penetrate vertically in 5 seconds  It may be noted that penetration value is largely influenced by any inaccuracy with regards to pouring temperature, size of the needle, weight placed on the needle and the test temperature.  In hot climates, a lower penetration grade preferred.
  • 24. DUCTILITY TEST  Ductility is the property of bitumen that permits it to undergo great deformation or elongation.  Ductility is defined as the distance in cm, to which a standard sample or briquette of the material will be elongated without breaking.  Dimension of the briquette thus formed is exactly 1 cm square. The bitumen sample is heated and poured in the mould assembly placed on a plate.  These samples with moulds are cooled in the air and then in water bath at 270C temperature.
  • 25.  The excess bitumen is cut and the surface is leveled using a hot knife. Then the mould with assembly containing sample is kept in water bath of the ductility machine for about 90 minutes.  The sides of the moulds are removed, the clips are hooked on the machine and the machine is operated. The distance up to the point of breaking of thread is the ductility value which is reported in cm.  The ductility value gets affected by factors such as pouring temperature, test temperature, rate of pulling etc.  A minimum ductility value of 75 cm has been specified by the BIS..
  • 26.
  • 27. SOFTENING POINT TEST Softening point denotes the temperature at which the bitumen attains a particular degree of softening under the specified condition of test.  The test is conducted by using Ring and Ball apparatus. A brass ring containing test sample of bitumen is suspended in liquid like water or glycerin at a given temperature.  A steel ball is placed upon the bitumen sample and the liquid medium is heated at a rate of 50C per minute. Temperature is noted when the softened bitumen touches the metal plate which is at a specified distance below.  Generally, higher softening point indicates lower temperature susceptibility and is preferred in hot climates.
  • 28.
  • 29. SPECIFIC GRAVITY TEST  The specific gravity of bitumen is defined as the ratio of mass of given volume of bitumen of known content to the mass of equal volume of water at 270C.  The specific gravity can be measured using either pycnometer or preparing a cube specimen of bitumen in semi solid or solid state.  In paving jobs, to classify a binder, density property is of great use. In most cases bitumen is weighed, but when used with aggregates, the bitumen is converted to volume using density values.  The density of bitumen is greatly influenced by its chemical composition. Increase in aromatic type mineral impurities cause an increase in specific gravity.  The specific gravity of bitumen varies from 0.97 to 1.02.
  • 30. WATER CONTENT TEST  It is desirable that the bitumen contains minimum water content to prevent foaming of the bitumen when it is heated above the boiling point of water.  The water in bitumen is determined by mixing known weight of specimen in a pure petroleum distillate free from water, heating and distilling of the water.  The weight of the water condensed and collected is expressed as percentage by weight of the original sample.  The allowable maximum water content should not be more than 0.2% by weight.
  • 31. LOSS ON HEATING TEST  When the bitumen is heated it loses the volatility and gets hardened. About 50gm of the sample is weighed and heated to a temperature of 1630C for 5 hours in a specified oven designed for this test.  The sample specimen is weighed again after the heating period and loss in weight is expressed as percentage by weight of the original sample.  Bitumen used in pavement mixes should not indicate more than 1% loss in weight, but for bitumen having penetration values 150-200 up to 2% loss in weight is allowed.
  • 32. What is Bitumen? The primary use (70%) of asphalt/bitumen is in road construction, where it is used as the glue or binder mixed with aggregate particles to create asphalt concrete. Preparation of the existing base course layer  The existing surface is prepared by removing the pot holes or rust if any. The irregularities are filled in with premix chippings at least a week before laying surface course.  If the existing pavement is extremely way, a bituminous leveling course of adequate thickness is provided to lay a bituminous concrete surface course on a binder course instead of directly laying it on a WBM. Application of Tuck Coat It is desirable to lay AC layer over a bituminous base or binder course. A tack coat of bitumen is applied at 6.0 to 7.5 kg per 10 sq.m area, this quantity may be increased to 7.5 to 10 kg for non- bituminous base.
  • 33. Preparation and placing of Premix  The premix is prepared in a hot mix plant of a required capacity with the desired quality control. The bitumen may be heated upto 150 – 177 deg C and the aggregate temperature should not differ by over 14 deg C from the binder temperature.  The hot mixed material is collected from the mixture by the transporters, carried to the location is spread by a mechanical paver at a temperature of 121 to 163 deg C.  the camber and the thickness of the layer are accurately verified. The control of the temperatures during the mixing and the compaction are of great significance in the strength of the resulting pavement structure.  Rolling  A mix after it is placed on the base course is thoroughly compacted by rolling at a speed not more than 5km per hour.
  • 34.  The initial or break down rolling is done by 8 to 12 tonnes roller and the intermediate rolling is done with a fixed wheel pneumatic roller of 15 to 30 tonnes having a tyre pressure of 7kg per sq.cm. the wheels of the roller are kept damp with water.  The number of passes required depends on the thickness of the layer. In warm weather rolling on the next day, helps to increase the density if the initial rolling was not adequate. The final rolling or finishing is done by 8 to 10 tonne tandem roller. Fig: Tandem Roller
  • 35. Quality control of bituminous concrete construction  The routine checks are carried out at site to ensure the quality of the resulting pavement mixture and the pavement surface.  Periodical checks are made for,  a) Aggregate grading  b) Grade of bitumen  c) Temperature of aggregate  d) Temperature of paving mix during mixing and compaction. At least one sample for every 100 tonnes of the mix discharged by the hot mix plant is collected and tested for above requirements. Marshall tests are also conducted. For every 100 sq.m of the compacted surface, one test of the field density is conducted to check whether it is atleast 95% of the density obtained in the laboratory. The variation in the thickness allowed is 6mm per 4.5m length of construction.
  • 36. Finished surface:  The AC surface should be checked by a 3.0 m straight edge. The longitudinal undulations should not exceed 8.0 mm and the number of undulations higher than 6.0 mm should not exceed 10 in a length of 300 m. The cross-traffic profile should not have undulations exceeding 4.0mm.
  • 37.  Cement concrete road construction is one of the types of low volume road construction. We know that the construction of the road is mostly dependent upon the factor like amount traffic that is to be handled by the road after its completion.  On most of the village roads connecting small villages in the rural areas of the country, the type of vehicular traffic is quite different from the traffic on other highways.  The traffic passing on a road can be categorized into three categories as light commercial traffics, medium commercial traffics and heavy commercial traffics, but the frequency of each class of traffic varies with the road.
  • 38. Materials for concrete cement road construction The materials for the cement concrete road construction may be divided into two parts. These are mentioned as follows:-  Selection of basic component materials  Mix design and production of pavement quality concrete(PQC) mix required to construct the cement concrete road pavement
  • 39. Subgrade preparation  Subgrade preparation involves cleaning, earthwork (excavation or filling of soil, replacement of weak soil, soil stabilization etc.) and compaction.  Where the concrete layer is laid directly over the subgrade, the subgrade is moist at the time concrete is placed. If the subgrade is dry, water could be sprinkled over the surface before laying any concrete course, however, care should taken so that soft patches or water pools are not formed at the surface Construction of Base/ Sub-base  A base/ sub-base to the concrete pavement provides uniform and reasonably firm support, prevents mud-pumping , and acts as capillary cut-off.
  • 40.  Sub-base for concrete pavement could be constituted with brick flat soling, WBM, granular aggregates, crushed concrete, slag, stabilized soil etc. sub-base could be of three types with  (i) Granular material (for example, brick soling with one layer of sand under it, WBM, well graded granular materials etc.)  (ii) Stabilized soil  (iii) Semi-rigid material, (for example, lime burnt clay pozzolana concrete, lime fly-ash concrete, lean cement concrete roller compacted concrete etc.). Compaction and surface finishing  Concrete is spread evenly and is rodded with suitable equipment such that formation of honey-combing or voids can be avoided. At the same time, over-compacting needs to be avoided, which can cause segregation and loss of entrained air
  • 41. Texturing  Finished concrete has a smooth surface; texturing of concrete surface is done to impart required skid resistance to the concrete surface. The texturing is done by means of wire brushing or grooving along the transverse direction. Initial texturing may be done at the time of construction of the paver itself. Final texturing is done no sooner the sheen of the concrete surface goes off.
  • 42. Concrete curing  Curing is a process in which requisite moisture content and temperature is maintained so that concrete achieves its design strength through hydration of cement
  • 43. 8.QUALITY CONTROL MEASURES  Study duties responsibilities, Tender specification, standards, codes of practice and work instruction.  Evolve effective acceptance/rejection procedures for construction materials in coordination with the project purchase department.  Do proper sampling and testing of steel, cement, concrete, aggregates, water, etc., and verify test results in view of standards and work specifications prior to their use in construction. Also control quality of electrodes to their use in welding.  Set procedures to control quality at the points of storage for raw materials, mixing and placing of concrete.  Follow the prescribed curing and deshuttering schedules.  Observe procedures to control quality of welded joints of structural steel members.  Evolve a system to check quality of workmanship in all construction activities.
  • 44.  Keep all revised Indian Standards and codes of practice available in QC laboratory and have them handy during discussion with client/consultant.  Maintain sequence of construction required under any activity.  Discuss QA/QC issues as a separate agenda during site review meetings with staff.  Observe regular schedule for maintenance, repairs and calibration of plants and equipments.  Keep spare parts/materials for laboratory equipments weigh batchers, batching plant, etc., always keep spare vibrators ready at site.  Carry work instruction cards in pocket while supervising/inspecting works.  Regularly maintain the formats prescribed under ISO 9002 Quality assurance system  Practice sound house keeping methods to achieve saving, safety and quality.
  • 45. 9.Highway Drainage  It’s purpose is to drain rain water from the highway into the sewerage system. A highway drain is the pipe connecting the highway gully to the surface water sewer.  A soakaway is a drainage pit covered by a metal cover or sometimes by soil. Its purpose is to allow rain water from buildings to permeate into the surrounding subsoil. These are sometimes used to drain the highway Highway drainage should fulfil the following objectives:  Prevent flooding, ponding and seepage, and keep the carriageway, cycleway and footway as free of standing water as possible.  Ensure surface water falling on the highway enters the drainage system or natural watercourse as speedily as possible.  Keep the underlying road structure as dry as possible.
  • 46.  Prevent injury or damage caused by hazardous surface water.  Prevent highway surface water flooding adjacent properties.  Prevent blockages in associated highway drainage systems with consequential flooding.
  • 47. Highway drainage is important from various view points:  Excess moisture in soil sub-grade causes instability under the road surface. The pavement may fail due to sub-grade failure. In some clayey soil variation in moisture content causes considerable variation in volume of sub-grade. This sometimes contributes to pavement failure.  The waves and corrugations formed in case of flexible pavements also play an important role in pavement failure.  Sustained contact of water with bituminous pavements causes failure due stripping bitumen from the aggregates like loosening of some of the bituminous pavement layer and formation of pot holes  The prime cause of failures in rigid pavements by mud pumping is due to the presence of water in fine sub- grade soil.
  • 48. Well designed and well maintained road drainage is important in order to:  Minimize the environmental impact of road runoff on the receiving water environment.  Ensure the speedy removal of surface water to enhance safety and minimize disruption to road users.  Maximize the longevity of the road surface and associated infrastructures.