HIRARC: INSTALLATION OF MSCL PIPING
Organization: PERSADA SATRIA (M) SDN BHD Conducted By:
Position:
Revised By:
Mohd Rizal bin Zamin
Site Safety Supervisor
Mohd Rizal Zamin (SSS), Fakhrul Nizzam (Project Engineer), Lau
Wai Hong (TBR Engineering)
Activity: MSCL Piping installation
Approved By:
Designation:
Ir. Nasiruddin bin Shawal Hamid
Project Manager
Date:
Revision Date:
12 May,2022
30 May, 2023
Validation Date: 23-25 August, 2022
15 – 23 June, 2023
1. Hazard Identification 2. Risk Evaluation 3. Risk Control Steps
No Activity Hazard Cause Risk Control
Conse-
quences
Like-
lihood
Overall Risk Safety Measures Taken
1. Pre-work
confirmation
Existing services, facilities
and slopes.
Interruption of services,
Eelctrocution and minor
landslides.
- Supervision and
communication 5 1 5 (Medium)
1. Supervisor to follow instructions
given during pre-inspection and
to constantly monitor the work
2. Cordon off
work area
- Unwanted people at work
area
Bodily injury - Administrative
controls
- Supervision and
communication
3 2 8 (Medium)
1. Plan work area. Divert existing
access if affected.
2. Use barriers, warning tapes and
proper signage to inform others.
3. Road cutting - Working without proper
PPE
- Road cutting machine
Broken cutting disc mau
couse bodily harm
PPE and
Administrative
controls
2 4 8 (Medium)
1. Use proper PPE (Safety boots,
safety goggles)
4. Pipe fitting - Hot work (Angle
grinder)
Broken and flying cutting
disc
Supervision,
Administration and
3 4 12
(Medium)
1. Check equipments beforehand.
2. Use safety guard for all grinders.
- Hot Work (Welding) Infra red radiation ,
scalded skni
PPE 3. Use proper PPE (welding
goggles,good welding gloves)
4. Use competent welders
5. Machinery at
site
Lorry and backhoe at site Bodily injury, blind spots
incidents
Supervision and
administrative
control
4 3
12
(Medium)
1. Full time supervisor and sufficient
traffic controllers if needed.
2. Reminder during safety toolbox
meeting.
1.
6. Lifting load Swinging, unstable load Bodily injury Supervision and
Engineering control
4 2 8 (Medium)
1. Supervisor to monitor load lifting
2. Remote control method to control
the load from afar like tag line.
7. Extended
working hours
Low lighting Trip and fall and poor
workmanship
Engineering control
4 2 8 (Medium)
Install adequate spotlights
8. Movement of
machineries /
vehicles
(Ingress /
egress)
Machineries / vehicles
going in and out of site
Bodily injury, blind spots
incidents
Supervision and
administrative
control
4 3
12
(Medium)
1. Sufficient traffic controllers are
needed with full PPE, high
visibility vest and whistles.
2. Lead escort to be vigilant and pay
extra attention to little kids.
3. Try to direct visitors to one side of
the road to help the driver to
focus on.
2.
1. Hazard Identification 2. Risk Evaluation 3. Risk Control Steps
Table 1 : Risk Evaluation Chart
PERSADA SATRIA (M)
SDN BHD
CADANGAN PINDAAN DAN TAMBAHAN BANGUNAN
STESEN ATAS 1 TINGKAT SEDIA ADA KEPADA
2 TINGKAT, DI ATAS LOT 250,
BANDAR BUKIT BENDERA, DAERAH TIMUR LAUT
PULAU PINANG
SOP FOR PIPING INSTALLATION
1) Supervisor (compulsory) and traffic controllers (if needed) need to be present during
work.
2) Work area to be cordon off to avoid unwanted personnel. Appropriate signage are to be
put at strategic and visible locations.
3) PPE to be supplied and used on all work activities.
4) All tools to be inspected beforehand and faulty tools to be replaced or repaired.
5) Utilise competent skill workers for welding and fitting works to ensure safety and
acceptable workmanship.
6) Machineries at site need to be operated with caution. Supervisor need to be vigilant.
7) All vehicles / machineries going in and out need to be escorted by 2 or more traffic
controllers with complete PPE, high visibility vests and whistles to promote awareness.
8) Machinery operator to be careful and to be aware of their surroundings and other workers
safety. All workers also to pay attention of machinery movement near them.
9) Loads to be lift with remote control method like tag line.
10) Extra lighting sources to be provided if working time extended after dark to ensure safety
of all workers.
PREPARED BY: APPROVED BY:
MOHD RIZAL BIN ZAMIN IR. NASIRUDDIN BIN SHAWAL HAMID
(SITE SAFETY SUPERVISOR) (PROJECT MANAGER)

More Related Content

Similar to TBR - MSCL Piping Installation shutdown 2023.docx

25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 

Similar to TBR - MSCL Piping Installation shutdown 2023.docx (20)

25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 
ehs
ehsehs
ehs
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
 
cpwd training
cpwd trainingcpwd training
cpwd training
 
FARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docxFARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docx
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
17 traffic operations working on live roads risk assessment templates
17 traffic operations   working on live roads risk assessment templates17 traffic operations   working on live roads risk assessment templates
17 traffic operations working on live roads risk assessment templates
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
JSA of Radiography for Boiler A - Copy.pdf
JSA of Radiography for Boiler A - Copy.pdfJSA of Radiography for Boiler A - Copy.pdf
JSA of Radiography for Boiler A - Copy.pdf
 
Mawaz CV
Mawaz CVMawaz CV
Mawaz CV
 
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
 
Core Risk Assessment for Office work.docx
Core  Risk Assessment for Office work.docxCore  Risk Assessment for Office work.docx
Core Risk Assessment for Office work.docx
 

Recently uploaded

Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
IJECEIAES
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
drjose256
 

Recently uploaded (20)

Interfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfInterfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdf
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Students
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
 
Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...
 
The Entity-Relationship Model(ER Diagram).pptx
The Entity-Relationship Model(ER Diagram).pptxThe Entity-Relationship Model(ER Diagram).pptx
The Entity-Relationship Model(ER Diagram).pptx
 
Software Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdfSoftware Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdf
 
History of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & ModernizationHistory of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & Modernization
 
engineering chemistry power point presentation
engineering chemistry  power point presentationengineering chemistry  power point presentation
engineering chemistry power point presentation
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
 
Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) ppt
 
Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptx
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
 
handbook on reinforce concrete and detailing
handbook on reinforce concrete and detailinghandbook on reinforce concrete and detailing
handbook on reinforce concrete and detailing
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.ppt
 

TBR - MSCL Piping Installation shutdown 2023.docx

  • 1. HIRARC: INSTALLATION OF MSCL PIPING Organization: PERSADA SATRIA (M) SDN BHD Conducted By: Position: Revised By: Mohd Rizal bin Zamin Site Safety Supervisor Mohd Rizal Zamin (SSS), Fakhrul Nizzam (Project Engineer), Lau Wai Hong (TBR Engineering) Activity: MSCL Piping installation Approved By: Designation: Ir. Nasiruddin bin Shawal Hamid Project Manager Date: Revision Date: 12 May,2022 30 May, 2023 Validation Date: 23-25 August, 2022 15 – 23 June, 2023 1. Hazard Identification 2. Risk Evaluation 3. Risk Control Steps No Activity Hazard Cause Risk Control Conse- quences Like- lihood Overall Risk Safety Measures Taken 1. Pre-work confirmation Existing services, facilities and slopes. Interruption of services, Eelctrocution and minor landslides. - Supervision and communication 5 1 5 (Medium) 1. Supervisor to follow instructions given during pre-inspection and to constantly monitor the work 2. Cordon off work area - Unwanted people at work area Bodily injury - Administrative controls - Supervision and communication 3 2 8 (Medium) 1. Plan work area. Divert existing access if affected. 2. Use barriers, warning tapes and proper signage to inform others. 3. Road cutting - Working without proper PPE - Road cutting machine Broken cutting disc mau couse bodily harm PPE and Administrative controls 2 4 8 (Medium) 1. Use proper PPE (Safety boots, safety goggles) 4. Pipe fitting - Hot work (Angle grinder) Broken and flying cutting disc Supervision, Administration and 3 4 12 (Medium) 1. Check equipments beforehand. 2. Use safety guard for all grinders.
  • 2. - Hot Work (Welding) Infra red radiation , scalded skni PPE 3. Use proper PPE (welding goggles,good welding gloves) 4. Use competent welders 5. Machinery at site Lorry and backhoe at site Bodily injury, blind spots incidents Supervision and administrative control 4 3 12 (Medium) 1. Full time supervisor and sufficient traffic controllers if needed. 2. Reminder during safety toolbox meeting. 1. 6. Lifting load Swinging, unstable load Bodily injury Supervision and Engineering control 4 2 8 (Medium) 1. Supervisor to monitor load lifting 2. Remote control method to control the load from afar like tag line. 7. Extended working hours Low lighting Trip and fall and poor workmanship Engineering control 4 2 8 (Medium) Install adequate spotlights 8. Movement of machineries / vehicles (Ingress / egress) Machineries / vehicles going in and out of site Bodily injury, blind spots incidents Supervision and administrative control 4 3 12 (Medium) 1. Sufficient traffic controllers are needed with full PPE, high visibility vest and whistles. 2. Lead escort to be vigilant and pay extra attention to little kids. 3. Try to direct visitors to one side of the road to help the driver to focus on. 2. 1. Hazard Identification 2. Risk Evaluation 3. Risk Control Steps
  • 3. Table 1 : Risk Evaluation Chart
  • 4. PERSADA SATRIA (M) SDN BHD CADANGAN PINDAAN DAN TAMBAHAN BANGUNAN STESEN ATAS 1 TINGKAT SEDIA ADA KEPADA 2 TINGKAT, DI ATAS LOT 250, BANDAR BUKIT BENDERA, DAERAH TIMUR LAUT PULAU PINANG SOP FOR PIPING INSTALLATION 1) Supervisor (compulsory) and traffic controllers (if needed) need to be present during work. 2) Work area to be cordon off to avoid unwanted personnel. Appropriate signage are to be put at strategic and visible locations. 3) PPE to be supplied and used on all work activities. 4) All tools to be inspected beforehand and faulty tools to be replaced or repaired. 5) Utilise competent skill workers for welding and fitting works to ensure safety and acceptable workmanship. 6) Machineries at site need to be operated with caution. Supervisor need to be vigilant. 7) All vehicles / machineries going in and out need to be escorted by 2 or more traffic controllers with complete PPE, high visibility vests and whistles to promote awareness. 8) Machinery operator to be careful and to be aware of their surroundings and other workers safety. All workers also to pay attention of machinery movement near them. 9) Loads to be lift with remote control method like tag line. 10) Extra lighting sources to be provided if working time extended after dark to ensure safety of all workers. PREPARED BY: APPROVED BY: MOHD RIZAL BIN ZAMIN IR. NASIRUDDIN BIN SHAWAL HAMID (SITE SAFETY SUPERVISOR) (PROJECT MANAGER)