Hirarc for water pipe installation. The installation took place on Penang Hill, Penang. One of the busiest tourist attraction in Malaysia. Luckily, the job was carried out during shutdown period. It is the time for the funicular train to do major maintenance and repair and the area was unaccessible by train. We still have visitors coming in thru Jeep Track which means the area not fully closed and still have public safety issues.
This is the Hirarc for the job and it was carried out safely as planned.
Passive Air Cooling System and Solar Water Heater.ppt
TBR - MSCL Piping Installation shutdown 2023.docx
1. HIRARC: INSTALLATION OF MSCL PIPING
Organization: PERSADA SATRIA (M) SDN BHD Conducted By:
Position:
Revised By:
Mohd Rizal bin Zamin
Site Safety Supervisor
Mohd Rizal Zamin (SSS), Fakhrul Nizzam (Project Engineer), Lau
Wai Hong (TBR Engineering)
Activity: MSCL Piping installation
Approved By:
Designation:
Ir. Nasiruddin bin Shawal Hamid
Project Manager
Date:
Revision Date:
12 May,2022
30 May, 2023
Validation Date: 23-25 August, 2022
15 – 23 June, 2023
1. Hazard Identification 2. Risk Evaluation 3. Risk Control Steps
No Activity Hazard Cause Risk Control
Conse-
quences
Like-
lihood
Overall Risk Safety Measures Taken
1. Pre-work
confirmation
Existing services, facilities
and slopes.
Interruption of services,
Eelctrocution and minor
landslides.
- Supervision and
communication 5 1 5 (Medium)
1. Supervisor to follow instructions
given during pre-inspection and
to constantly monitor the work
2. Cordon off
work area
- Unwanted people at work
area
Bodily injury - Administrative
controls
- Supervision and
communication
3 2 8 (Medium)
1. Plan work area. Divert existing
access if affected.
2. Use barriers, warning tapes and
proper signage to inform others.
3. Road cutting - Working without proper
PPE
- Road cutting machine
Broken cutting disc mau
couse bodily harm
PPE and
Administrative
controls
2 4 8 (Medium)
1. Use proper PPE (Safety boots,
safety goggles)
4. Pipe fitting - Hot work (Angle
grinder)
Broken and flying cutting
disc
Supervision,
Administration and
3 4 12
(Medium)
1. Check equipments beforehand.
2. Use safety guard for all grinders.
2. - Hot Work (Welding) Infra red radiation ,
scalded skni
PPE 3. Use proper PPE (welding
goggles,good welding gloves)
4. Use competent welders
5. Machinery at
site
Lorry and backhoe at site Bodily injury, blind spots
incidents
Supervision and
administrative
control
4 3
12
(Medium)
1. Full time supervisor and sufficient
traffic controllers if needed.
2. Reminder during safety toolbox
meeting.
1.
6. Lifting load Swinging, unstable load Bodily injury Supervision and
Engineering control
4 2 8 (Medium)
1. Supervisor to monitor load lifting
2. Remote control method to control
the load from afar like tag line.
7. Extended
working hours
Low lighting Trip and fall and poor
workmanship
Engineering control
4 2 8 (Medium)
Install adequate spotlights
8. Movement of
machineries /
vehicles
(Ingress /
egress)
Machineries / vehicles
going in and out of site
Bodily injury, blind spots
incidents
Supervision and
administrative
control
4 3
12
(Medium)
1. Sufficient traffic controllers are
needed with full PPE, high
visibility vest and whistles.
2. Lead escort to be vigilant and pay
extra attention to little kids.
3. Try to direct visitors to one side of
the road to help the driver to
focus on.
2.
1. Hazard Identification 2. Risk Evaluation 3. Risk Control Steps
4. PERSADA SATRIA (M)
SDN BHD
CADANGAN PINDAAN DAN TAMBAHAN BANGUNAN
STESEN ATAS 1 TINGKAT SEDIA ADA KEPADA
2 TINGKAT, DI ATAS LOT 250,
BANDAR BUKIT BENDERA, DAERAH TIMUR LAUT
PULAU PINANG
SOP FOR PIPING INSTALLATION
1) Supervisor (compulsory) and traffic controllers (if needed) need to be present during
work.
2) Work area to be cordon off to avoid unwanted personnel. Appropriate signage are to be
put at strategic and visible locations.
3) PPE to be supplied and used on all work activities.
4) All tools to be inspected beforehand and faulty tools to be replaced or repaired.
5) Utilise competent skill workers for welding and fitting works to ensure safety and
acceptable workmanship.
6) Machineries at site need to be operated with caution. Supervisor need to be vigilant.
7) All vehicles / machineries going in and out need to be escorted by 2 or more traffic
controllers with complete PPE, high visibility vests and whistles to promote awareness.
8) Machinery operator to be careful and to be aware of their surroundings and other workers
safety. All workers also to pay attention of machinery movement near them.
9) Loads to be lift with remote control method like tag line.
10) Extra lighting sources to be provided if working time extended after dark to ensure safety
of all workers.
PREPARED BY: APPROVED BY:
MOHD RIZAL BIN ZAMIN IR. NASIRUDDIN BIN SHAWAL HAMID
(SITE SAFETY SUPERVISOR) (PROJECT MANAGER)