Risk Assessment
Work (PROJECT):
RISK ANALYSIS
Contractor (COMPANY):
pagina 1 of 5
OPERATING MODE N°21 REVISION N°00
OPERATIVE MODE No .
Name of the company: EMIS/SIMI  Holder Subcontractor  (subcontratada)
Company Name:
Description of the operation: Montagem dos Suportes TAD – 4G1. TD01/B
Operation description:
Transaction details
Location:Area 6
Start date: 23/03/2022 Duration: 6 months Workforce: 20
Inspection
Carried out?
Permit
lifting?
Permit
of deposit
required?
Permit
search required?
Permit
to penetrate
required?
Fire permit
required?
Permit
of consignment
/ deconsignment
required?
Knowledge
underground
networks
Controlled?
yes No yes No yes No yes No yes No yes No yes No yes No
X X X X X X
X
X
Prepared by:(Executing Entity)
Data: ____/____/____
Ass.:
Verified by: (Responsible Technical/Direction
Work)
Data: ____/____/____
Ass.:
Approved by: (Safety Coordinator)
Date: ____/____/____
Ass.:
OSH tkIS
Name and Visa :
Date:
This document is associated with METHOD STATEMENT No. 4G1. TD01/B REVISION N°0
Risk Assessment
Work (PROJECT):
RISK ANALYSIS
Contractor (COMPANY):
pagina 2 of 5
Risk Assessment
Work (PROJECT):
RISK ANALYSIS
Contractor (COMPANY):
pagina 3 of 5
Danger Risk
Evaluation Severity
Level
(PxG)
Classification
Risk
Preventive Measures
Residual Risk Assessment
Accountable
Evaluation Severi
ty
Level
(PxG)
Risk
Rating
P G P G
Fire
Explosion
Burn
Death
B II 3
Medium
Risk
Ensure continuous monitoring of explosive atmospheres;
Place fire extinguisher in the workplace (ABC - 6 Kg);
All workers are informed of the risks inherent in the work and their prevention
measures. (Toolbox);
A II 1
Very low
risk
,
Team Leader
and/or
Safety
technician
Particle
Projection
Gas Release
Injuries
Contamination
Asphyxia
B II 1
Very low
risk
All workers are informed of the risks inherent in the work and their prevention
measures.
Workers must use defined PPE (visors, masks, etc.)
Monitoring of potentially explosive atmospheres (if necessary) and use confined
space procedures
A II 1
Very low
risk
Team Leader
and/or
Safety
technician
Collision
Hit-and-run
Rollover
Entalamento
Contusion
Crushing
B II 1
Very low
risk
Ensure that the equipment to be used is properly authorized, inspected and in good
condition, in accordance with the legislation in force and internal regulations of
Secil;
Only workers qualified to do so may be allowed to manoeuvre equipment.
Comply with the rules of use of theequipment in accordance with the requirements
of Secil;
All equipment is checked according to DL 50/2005;
Drivers must strictly comply with internal traffic rules in Secil;
Stabilise the multifunction/telescopic stacker/crane taking into account the route to
be carried out during thehandling of loads, and ensure that thesupport structurehas
the necessary resistance;
Never start a lifting operation without checking that you have the stabilizer arms
open and properly levelled;
Ensure the positioning of the equipment in relation to the execution of thetask, in a
safe way, preventing the collision with existing structures or workers;
A II 1
Very low
risk
Responsible da
AREA,
Team Leader
and/or
Safety
technician
Risk Assessment
Work (PROJECT):
RISK ANALYSIS
Contractor (COMPANY):
pagina 4 of 5
Use of signaller for execution of maneuvers, and use of radio in the coordination of
work (if necessary);
No worker may be within the range of action of the equipment;
Restrict the numberof workers in the radius of influence of the multifunction/
telescopic stacker to the essential for the proper development of the work;
Thesound beacons of theequipment must always berespected and always connected
during the operations of cargo movements;
Ensure the delimitation of the area for the execution of the task, in order to
permanently safeguard circulation paths and emergency situations.
Noise
Decreased
hearing C I 1
Very low
risk
All equipment must be checked according to DL 50/2005 before leaving the tooling.
Use of Headsets (whenever necessary)
B I 1
Very low
risk
Tooland/or
Safety
technician
Drop of
suspended loads
Collision with
structures
Injuring
Contusion
Crushing
B III 2
Slight
risk
The person responsiblefor themaneuver will be the RIGER who will be identified
with the ORANGE vest
Workers must keep away fromtheequipment, safeguarding theentirerange of action
where the load will pass;
It is forbidden to stay or pass persons under suspended loads;
The entire area corresponding to the radius of action where the load will pass must
be sealed/flagged. In this impossibility, to place a person with signaller functions to
swipe and prevent the passage of people.
Hooks have to have safety tabs;
It is forbidden to remain or pass under the suspended loads and the signaling
tape;
Check thesafety tabs of the chains to be used and ensure that theload is packed and
secured before lifting;
In the unloading operation, only two employees will be allowed on top of the truck
to sling and tietheguide ropethat after completing theseoperations must comedown
The guide rope will always be used to assist the movement of materials
B II 1
Very low
risk
Responsible da
AREA,
Team Leader
and/or
Safety
technician
Risk Assessment
Work (PROJECT):
RISK ANALYSIS
Contractor (COMPANY):
pagina 5 of 5
Falling objects
Fall in height
Injuring
Contusion
Fracture
C III 3
Average
risk
Existing structures (e.g. varandins, etc.) and/or other parts to be removed should be
removed only after secure access is ensured for workers involved in the operation.
No worker may be at risk of fall in height during the handling of loads;
All work at height (in places above 1.80 meters) require mandatory use of francalete
on the protective helmet;
In the absence of collective protections above 1.80 metres in height, the use of
safety harness properly tied to lifelines or sufficiently solid/resistant
locations is mandatory.
Theuseof sailor ladders requires theuseof a harness with adouble mooring harness,
so that the worker is never free of protection against fall at height;
The permanence or movement of persons under suspended loads and in the
area of action of the equipment shall be prohibited;
Overlappingwork may only be allowed, provided that therisk of falling objects from
work at thehigher level is physically impossible. To this end, theperson responsible
must assess in advance of the initiation of theoperations all available physicalmeans
(e.g. protectiveblankets, sheds, etc.). In theimpossibility of performing work under
safety conditions at different levels, overlapping work cannot be carried out.
Use scaffolding (assembled, verified and approved by a competent person)
B III 3
Slight
risk
Responsible da
AREA,
Team Leader
and/or
Safety
technician
Fall to the same
level
Sprain
Wound
Contusion
B I 1
Very low
risk
It is forbidden to place materials next to secil hydrants and emergency equipment;
Keep the drive area tidy;
Ensure and identify safe paths of movement.
Do not leave the work areas with tools and materials scattered.
A I 1
Very low
risk
Team Leader
and/or
Safety
technician

More Related Content

Similar to Risk assessment for assembly of TAD supports - 4G1

11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docxDwarika Bhushan Sharma
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templatesDwarika Bhushan Sharma
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docxDwarika Bhushan Sharma
 
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...Dwarika Bhushan Sharma
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templatesDwarika Bhushan Sharma
 
DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxAamirAbbas75
 
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...Dwarika Bhushan Sharma
 
28 edge protection to open edges, shafts and risers risk assessment templates
28 edge protection to open edges, shafts and risers risk assessment templates28 edge protection to open edges, shafts and risers risk assessment templates
28 edge protection to open edges, shafts and risers risk assessment templatesDwarika Bhushan Sharma
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfJHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfHaroon AbdulRahim
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...MohammedAliQazi
 
20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...Dwarika Bhushan Sharma
 
MEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxMEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxSyed Neyaz Ahmad
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfManoj Kumar
 

Similar to Risk assessment for assembly of TAD supports - 4G1 (20)

11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
 
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates
 
DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptx
 
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
 
28 edge protection to open edges, shafts and risers risk assessment templates
28 edge protection to open edges, shafts and risers risk assessment templates28 edge protection to open edges, shafts and risers risk assessment templates
28 edge protection to open edges, shafts and risers risk assessment templates
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfJHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 
20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...
 
MEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxMEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptx
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdf
 

Recently uploaded

(办理学位证)(Rice毕业证)莱斯大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Rice毕业证)莱斯大学毕业证成绩单修改留信学历认证原版一模一样(办理学位证)(Rice毕业证)莱斯大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Rice毕业证)莱斯大学毕业证成绩单修改留信学历认证原版一模一样gfghbihg
 
BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024AHOhOops1
 
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingWhat Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingEscondido German Auto
 
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样gfghbihg
 
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一fjjwgk
 
如何办理爱尔兰都柏林大学毕业证(UCD毕业证) 成绩单原版一比一
如何办理爱尔兰都柏林大学毕业证(UCD毕业证) 成绩单原版一比一如何办理爱尔兰都柏林大学毕业证(UCD毕业证) 成绩单原版一比一
如何办理爱尔兰都柏林大学毕业证(UCD毕业证) 成绩单原版一比一mjyguplun
 
(8264348440) 🔝 Call Girls In Shaheen Bagh 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Shaheen Bagh 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Shaheen Bagh 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Shaheen Bagh 🔝 Delhi NCRsoniya singh
 
Call Girl Service Global Village Dubai +971509430017 Independent Call Girls G...
Call Girl Service Global Village Dubai +971509430017 Independent Call Girls G...Call Girl Service Global Village Dubai +971509430017 Independent Call Girls G...
Call Girl Service Global Village Dubai +971509430017 Independent Call Girls G...kexey39068
 
UNIT-III-TRANSMISSION SYSTEMS REAR AXLES
UNIT-III-TRANSMISSION SYSTEMS REAR AXLESUNIT-III-TRANSMISSION SYSTEMS REAR AXLES
UNIT-III-TRANSMISSION SYSTEMS REAR AXLESDineshKumar4165
 
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHot Call Girls In Sector 58 (Noida)
 
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一meq5nzfnk
 
Russian Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
Russian  Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...Russian  Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
Russian Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...shivangimorya083
 
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607dollysharma2066
 
如何办理迈阿密大学毕业证(UM毕业证)成绩单留信学历认证原版一比一
如何办理迈阿密大学毕业证(UM毕业证)成绩单留信学历认证原版一比一如何办理迈阿密大学毕业证(UM毕业证)成绩单留信学历认证原版一比一
如何办理迈阿密大学毕业证(UM毕业证)成绩单留信学历认证原版一比一ga6c6bdl
 
Innovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC TechnologyInnovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC Technologyquickpartslimitlessm
 
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGERUNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGERDineshKumar4165
 
Call Girls Vastrapur 7397865700 Ridhima Hire Me Full Night
Call Girls Vastrapur 7397865700 Ridhima Hire Me Full NightCall Girls Vastrapur 7397865700 Ridhima Hire Me Full Night
Call Girls Vastrapur 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHERUNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHERunosafeads
 

Recently uploaded (20)

(办理学位证)(Rice毕业证)莱斯大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Rice毕业证)莱斯大学毕业证成绩单修改留信学历认证原版一模一样(办理学位证)(Rice毕业证)莱斯大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Rice毕业证)莱斯大学毕业证成绩单修改留信学历认证原版一模一样
 
BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024
 
sauth delhi call girls in Connaught Place🔝 9953056974 🔝 escort Service
sauth delhi call girls in  Connaught Place🔝 9953056974 🔝 escort Servicesauth delhi call girls in  Connaught Place🔝 9953056974 🔝 escort Service
sauth delhi call girls in Connaught Place🔝 9953056974 🔝 escort Service
 
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingWhat Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
 
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
 
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
 
如何办理爱尔兰都柏林大学毕业证(UCD毕业证) 成绩单原版一比一
如何办理爱尔兰都柏林大学毕业证(UCD毕业证) 成绩单原版一比一如何办理爱尔兰都柏林大学毕业证(UCD毕业证) 成绩单原版一比一
如何办理爱尔兰都柏林大学毕业证(UCD毕业证) 成绩单原版一比一
 
(8264348440) 🔝 Call Girls In Shaheen Bagh 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Shaheen Bagh 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Shaheen Bagh 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Shaheen Bagh 🔝 Delhi NCR
 
Call Girl Service Global Village Dubai +971509430017 Independent Call Girls G...
Call Girl Service Global Village Dubai +971509430017 Independent Call Girls G...Call Girl Service Global Village Dubai +971509430017 Independent Call Girls G...
Call Girl Service Global Village Dubai +971509430017 Independent Call Girls G...
 
UNIT-III-TRANSMISSION SYSTEMS REAR AXLES
UNIT-III-TRANSMISSION SYSTEMS REAR AXLESUNIT-III-TRANSMISSION SYSTEMS REAR AXLES
UNIT-III-TRANSMISSION SYSTEMS REAR AXLES
 
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
 
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
 
Russian Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
Russian  Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...Russian  Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
Russian Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
 
Hot Sexy call girls in Pira Garhi🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Pira Garhi🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Pira Garhi🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Pira Garhi🔝 9953056974 🔝 escort Service
 
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
 
如何办理迈阿密大学毕业证(UM毕业证)成绩单留信学历认证原版一比一
如何办理迈阿密大学毕业证(UM毕业证)成绩单留信学历认证原版一比一如何办理迈阿密大学毕业证(UM毕业证)成绩单留信学历认证原版一比一
如何办理迈阿密大学毕业证(UM毕业证)成绩单留信学历认证原版一比一
 
Innovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC TechnologyInnovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC Technology
 
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGERUNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
 
Call Girls Vastrapur 7397865700 Ridhima Hire Me Full Night
Call Girls Vastrapur 7397865700 Ridhima Hire Me Full NightCall Girls Vastrapur 7397865700 Ridhima Hire Me Full Night
Call Girls Vastrapur 7397865700 Ridhima Hire Me Full Night
 
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHERUNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
 

Risk assessment for assembly of TAD supports - 4G1

  • 1. Risk Assessment Work (PROJECT): RISK ANALYSIS Contractor (COMPANY): pagina 1 of 5 OPERATING MODE N°21 REVISION N°00 OPERATIVE MODE No . Name of the company: EMIS/SIMI  Holder Subcontractor  (subcontratada) Company Name: Description of the operation: Montagem dos Suportes TAD – 4G1. TD01/B Operation description: Transaction details Location:Area 6 Start date: 23/03/2022 Duration: 6 months Workforce: 20 Inspection Carried out? Permit lifting? Permit of deposit required? Permit search required? Permit to penetrate required? Fire permit required? Permit of consignment / deconsignment required? Knowledge underground networks Controlled? yes No yes No yes No yes No yes No yes No yes No yes No X X X X X X X X Prepared by:(Executing Entity) Data: ____/____/____ Ass.: Verified by: (Responsible Technical/Direction Work) Data: ____/____/____ Ass.: Approved by: (Safety Coordinator) Date: ____/____/____ Ass.: OSH tkIS Name and Visa : Date: This document is associated with METHOD STATEMENT No. 4G1. TD01/B REVISION N°0
  • 2. Risk Assessment Work (PROJECT): RISK ANALYSIS Contractor (COMPANY): pagina 2 of 5
  • 3. Risk Assessment Work (PROJECT): RISK ANALYSIS Contractor (COMPANY): pagina 3 of 5 Danger Risk Evaluation Severity Level (PxG) Classification Risk Preventive Measures Residual Risk Assessment Accountable Evaluation Severi ty Level (PxG) Risk Rating P G P G Fire Explosion Burn Death B II 3 Medium Risk Ensure continuous monitoring of explosive atmospheres; Place fire extinguisher in the workplace (ABC - 6 Kg); All workers are informed of the risks inherent in the work and their prevention measures. (Toolbox); A II 1 Very low risk , Team Leader and/or Safety technician Particle Projection Gas Release Injuries Contamination Asphyxia B II 1 Very low risk All workers are informed of the risks inherent in the work and their prevention measures. Workers must use defined PPE (visors, masks, etc.) Monitoring of potentially explosive atmospheres (if necessary) and use confined space procedures A II 1 Very low risk Team Leader and/or Safety technician Collision Hit-and-run Rollover Entalamento Contusion Crushing B II 1 Very low risk Ensure that the equipment to be used is properly authorized, inspected and in good condition, in accordance with the legislation in force and internal regulations of Secil; Only workers qualified to do so may be allowed to manoeuvre equipment. Comply with the rules of use of theequipment in accordance with the requirements of Secil; All equipment is checked according to DL 50/2005; Drivers must strictly comply with internal traffic rules in Secil; Stabilise the multifunction/telescopic stacker/crane taking into account the route to be carried out during thehandling of loads, and ensure that thesupport structurehas the necessary resistance; Never start a lifting operation without checking that you have the stabilizer arms open and properly levelled; Ensure the positioning of the equipment in relation to the execution of thetask, in a safe way, preventing the collision with existing structures or workers; A II 1 Very low risk Responsible da AREA, Team Leader and/or Safety technician
  • 4. Risk Assessment Work (PROJECT): RISK ANALYSIS Contractor (COMPANY): pagina 4 of 5 Use of signaller for execution of maneuvers, and use of radio in the coordination of work (if necessary); No worker may be within the range of action of the equipment; Restrict the numberof workers in the radius of influence of the multifunction/ telescopic stacker to the essential for the proper development of the work; Thesound beacons of theequipment must always berespected and always connected during the operations of cargo movements; Ensure the delimitation of the area for the execution of the task, in order to permanently safeguard circulation paths and emergency situations. Noise Decreased hearing C I 1 Very low risk All equipment must be checked according to DL 50/2005 before leaving the tooling. Use of Headsets (whenever necessary) B I 1 Very low risk Tooland/or Safety technician Drop of suspended loads Collision with structures Injuring Contusion Crushing B III 2 Slight risk The person responsiblefor themaneuver will be the RIGER who will be identified with the ORANGE vest Workers must keep away fromtheequipment, safeguarding theentirerange of action where the load will pass; It is forbidden to stay or pass persons under suspended loads; The entire area corresponding to the radius of action where the load will pass must be sealed/flagged. In this impossibility, to place a person with signaller functions to swipe and prevent the passage of people. Hooks have to have safety tabs; It is forbidden to remain or pass under the suspended loads and the signaling tape; Check thesafety tabs of the chains to be used and ensure that theload is packed and secured before lifting; In the unloading operation, only two employees will be allowed on top of the truck to sling and tietheguide ropethat after completing theseoperations must comedown The guide rope will always be used to assist the movement of materials B II 1 Very low risk Responsible da AREA, Team Leader and/or Safety technician
  • 5. Risk Assessment Work (PROJECT): RISK ANALYSIS Contractor (COMPANY): pagina 5 of 5 Falling objects Fall in height Injuring Contusion Fracture C III 3 Average risk Existing structures (e.g. varandins, etc.) and/or other parts to be removed should be removed only after secure access is ensured for workers involved in the operation. No worker may be at risk of fall in height during the handling of loads; All work at height (in places above 1.80 meters) require mandatory use of francalete on the protective helmet; In the absence of collective protections above 1.80 metres in height, the use of safety harness properly tied to lifelines or sufficiently solid/resistant locations is mandatory. Theuseof sailor ladders requires theuseof a harness with adouble mooring harness, so that the worker is never free of protection against fall at height; The permanence or movement of persons under suspended loads and in the area of action of the equipment shall be prohibited; Overlappingwork may only be allowed, provided that therisk of falling objects from work at thehigher level is physically impossible. To this end, theperson responsible must assess in advance of the initiation of theoperations all available physicalmeans (e.g. protectiveblankets, sheds, etc.). In theimpossibility of performing work under safety conditions at different levels, overlapping work cannot be carried out. Use scaffolding (assembled, verified and approved by a competent person) B III 3 Slight risk Responsible da AREA, Team Leader and/or Safety technician Fall to the same level Sprain Wound Contusion B I 1 Very low risk It is forbidden to place materials next to secil hydrants and emergency equipment; Keep the drive area tidy; Ensure and identify safe paths of movement. Do not leave the work areas with tools and materials scattered. A I 1 Very low risk Team Leader and/or Safety technician