This document provides a job safety analysis for heavy lifting of a vessel. It identifies potential hazards at each step of the process and recommendations to control the hazards. The key steps involve pre-commencement activities, mobilizing equipment, unloading the vessel using lifting equipment, assembling the vessel, scaffolding erection, lifting and positioning the vessel, removing lifting tackles using a man lift, using ladders for access, and tandem lifting. Hazards include falls, struck by objects, fires, electrocutions, and loss of control. Recommendations focus on permits, inspections, PPE, barricades, communication, training, and fall protection.
15 Formwork (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Material delivery to work area;
Formwork installation
(Classified as Temporary Structures)
Housekeeping when erecting formwork
Dismantling of form-work
Maintenance of Formwork
Worker exposure to direct sun whist working on formwork
(as applicable)
Lifting operation, as a huge and complicated systems engineering, involves every aspects of enterprise production. This paper will briefly introduce some common problems and control procedures during operation for occupational safety and health .
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
14 Use of Plant- Graders and road rollers Risk Assessment Templates
Grader /Roller checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
Grader and Roller operation
(Plant Operator) • Operator competency;
• Plant / pedestrian interaction;
• Operator visibility; • Incident due to use of defective plant or associated equipment;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of plant by untrained personnel;
• Collision with plant and live traffic within site boundary;
• Workers struck by working plant, very high risk of fatality;
Plant operation supervision • Plant operations around workers;
• Workers in plant operating radius;
• Reversing vehicles; • Worker struck by vehicle;
• Plant operator unable to see task – screen covered;
•
15 Formwork (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Material delivery to work area;
Formwork installation
(Classified as Temporary Structures)
Housekeeping when erecting formwork
Dismantling of form-work
Maintenance of Formwork
Worker exposure to direct sun whist working on formwork
(as applicable)
Lifting operation, as a huge and complicated systems engineering, involves every aspects of enterprise production. This paper will briefly introduce some common problems and control procedures during operation for occupational safety and health .
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
14 Use of Plant- Graders and road rollers Risk Assessment Templates
Grader /Roller checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
Grader and Roller operation
(Plant Operator) • Operator competency;
• Plant / pedestrian interaction;
• Operator visibility; • Incident due to use of defective plant or associated equipment;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of plant by untrained personnel;
• Collision with plant and live traffic within site boundary;
• Workers struck by working plant, very high risk of fatality;
Plant operation supervision • Plant operations around workers;
• Workers in plant operating radius;
• Reversing vehicles; • Worker struck by vehicle;
• Plant operator unable to see task – screen covered;
•
Overhead crane, crane safety, lifting operation, EHS, Safety, Testing of Crane, Commissioning of Cranes,
for soft copy please email me at dawoodibrar@hotmail.com
Forklifts are extremely useful workplace vehicles, as long as they are used safely and properly by operators who have been trained and are deemed competent to use them. Forklifts are dangerous: they account for 25% of injuries at work. Many workplace accidents involve people being hit or run over by forklift trucks (typically when the forklift is reversing). Forklift accidents can cause serious injury, death, property and product damage. Accidents can be prevented if risk assessment are conducted, safe work procedures are followed, regular Tool Box Talks are conducted and HSE continuous surveillance observations of work tasks are performed periodically.
Common Forklift Hazards:
• Overloading
• Unsafe Stacking
• Speeding
• Unauthorized operation of forklift
• Untrained forklift operators.
• Pedestrians and forklifts moving in the same place.
• Obstruction in the path e.g. overhead, uneven ground surfaces, blind corners etc.
• Reversing
Common Safe Practices:
• Prior to use, forklifts must be inspected by a competent person, & inspection sticker should be posted on it.
• Only trained and authorized operators can operate a forklift.
• Carry out daily forklift pre-operation checks using checklist.
• Report to supervisor any forklift damage or problem.
• Don’t use a forklift to lift a worker.
• Check the load loads carefully before moving them for stability and damage.
• Slow down and sound the horn at crossings, and locations where view is blocked.
• Do not authorize anyone to stand or walk under the load or forklift machinery.
• Be aware of the height of the load, mast and overhead guard of the forklift when entering or existing buildings.
• Don’t handle loads that are above the weight capacity of the forklift.
• Follow the speed limit.
• Flagmen must be available while forklift is in operation.
• Focus on the travelling path and keep a clear view of it.
• When leaving a forklift, pull the parking brake, lower the forks and neutralize the controls.
• Don’t drive and raise load at the same time
• Don’t make sudden sharp turns
• Don’t brake suddenly when the forklift is loaded.
• Watch out for overhead structures (e.g. pipes & beams)
• Follow traffic management.
• Use rear view mirrors and camera while reversing.
2 Fire Risk Assessment Template Risk Assessment Templates
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment;
2. Use of Portable gas heating or cutting equipment.
(all areas)
3. Electrical equipment (portable and fixed installation)
4. Smoking prevention, controls and arrangements within the Project
5. Hot Works activity controls
(Grinding, Welding, Cutting etc.)
6. Waste disposal: Combustible materials controlled and disposed of correctly.
(E.g. paper, cardboard plastics or wood.)
7. Storage of Flammable Gas within the project
(Acetylene, propane, butane, LPG etc.)
8. Flammable or highly flammable materials or substances on site and point of use.
(e.g. solvents, paints, adhesives, aerosols etc.)
9. Steps to reduce the potential sources of oxygen to a fire.
10. Any operations (or proposed) that may affect the Fire risk assessment
11. Clear access to electrical components and equipment.
12. Suspended ceilings within temporary buildings
(Offices, cabins etc.)
13. Alterations to structure and installations designed to prevent fire spread
14. Arson Prevention
(including security)
15. Smoke/heat detectors installed in high risk areas
16. Fire call points (break glass) installation.
17. Audible/visual fire alarms.
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates
MEWP checks on arrival to site
PRIOR TO SITE ACCESS • Use of Access plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
MEWP operation
(Operator) • Operator competency;
• Plant / pedestrian interaction;
• Work at Height; • Incident due to use of defective plant or associated equipment;
• MEWP overturning;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of MEWP by untrained personnel;
• Operators climbing onto hand rails;
• Collision with other plant and live traffic within site boundary;
• Workers struck by working MEWP, very high risk of fatality;
• Falling materials;
MEWP operation (supervision) • MEWP operations around workers;
• Workers in MEWP operating radius;
• Reversing vehicles; • Worker struck by vehicle;•
What is JSA?
A Job Safety Analysis is a task-oriented risk assessment used to review the hazards associated with a particular work task, and to verify that adequate safeguards are in place to control those hazards.
JSAs are known by a variety of terms, including Job Hazard Analysis (JHA), Job Risk Assessment (JRA), Task Risk Assessment (TRA), Safe Job Analysis (SJA).
Job Safety Analysis and its Implementation
INVOLVE employees in the development
KEEP written JSA short and simple
ILLUSTRATE safe practices
ASSIGN responsibility of JSA
TRAIN all employees and supervisors
EXPLAIN the use of JSA to employees
IMPLEMENT safe work practices
REVIEW JSA when equipment or process changes or new information becomes available regarding potential hazards associated with the job.
9 Lifting Operations with Tower crane Risk Assessment Templates
Access of Tower crane sections to work areas
Tower crane foundations
Siting, setting up and testing of Tower crane
Lifting of equipment and material
(Tower crane Operator)
Tower Crane supervision
Jumping and dismantling of Tower Crane
Overhead crane, crane safety, lifting operation, EHS, Safety, Testing of Crane, Commissioning of Cranes,
for soft copy please email me at dawoodibrar@hotmail.com
Forklifts are extremely useful workplace vehicles, as long as they are used safely and properly by operators who have been trained and are deemed competent to use them. Forklifts are dangerous: they account for 25% of injuries at work. Many workplace accidents involve people being hit or run over by forklift trucks (typically when the forklift is reversing). Forklift accidents can cause serious injury, death, property and product damage. Accidents can be prevented if risk assessment are conducted, safe work procedures are followed, regular Tool Box Talks are conducted and HSE continuous surveillance observations of work tasks are performed periodically.
Common Forklift Hazards:
• Overloading
• Unsafe Stacking
• Speeding
• Unauthorized operation of forklift
• Untrained forklift operators.
• Pedestrians and forklifts moving in the same place.
• Obstruction in the path e.g. overhead, uneven ground surfaces, blind corners etc.
• Reversing
Common Safe Practices:
• Prior to use, forklifts must be inspected by a competent person, & inspection sticker should be posted on it.
• Only trained and authorized operators can operate a forklift.
• Carry out daily forklift pre-operation checks using checklist.
• Report to supervisor any forklift damage or problem.
• Don’t use a forklift to lift a worker.
• Check the load loads carefully before moving them for stability and damage.
• Slow down and sound the horn at crossings, and locations where view is blocked.
• Do not authorize anyone to stand or walk under the load or forklift machinery.
• Be aware of the height of the load, mast and overhead guard of the forklift when entering or existing buildings.
• Don’t handle loads that are above the weight capacity of the forklift.
• Follow the speed limit.
• Flagmen must be available while forklift is in operation.
• Focus on the travelling path and keep a clear view of it.
• When leaving a forklift, pull the parking brake, lower the forks and neutralize the controls.
• Don’t drive and raise load at the same time
• Don’t make sudden sharp turns
• Don’t brake suddenly when the forklift is loaded.
• Watch out for overhead structures (e.g. pipes & beams)
• Follow traffic management.
• Use rear view mirrors and camera while reversing.
2 Fire Risk Assessment Template Risk Assessment Templates
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment;
2. Use of Portable gas heating or cutting equipment.
(all areas)
3. Electrical equipment (portable and fixed installation)
4. Smoking prevention, controls and arrangements within the Project
5. Hot Works activity controls
(Grinding, Welding, Cutting etc.)
6. Waste disposal: Combustible materials controlled and disposed of correctly.
(E.g. paper, cardboard plastics or wood.)
7. Storage of Flammable Gas within the project
(Acetylene, propane, butane, LPG etc.)
8. Flammable or highly flammable materials or substances on site and point of use.
(e.g. solvents, paints, adhesives, aerosols etc.)
9. Steps to reduce the potential sources of oxygen to a fire.
10. Any operations (or proposed) that may affect the Fire risk assessment
11. Clear access to electrical components and equipment.
12. Suspended ceilings within temporary buildings
(Offices, cabins etc.)
13. Alterations to structure and installations designed to prevent fire spread
14. Arson Prevention
(including security)
15. Smoke/heat detectors installed in high risk areas
16. Fire call points (break glass) installation.
17. Audible/visual fire alarms.
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates
MEWP checks on arrival to site
PRIOR TO SITE ACCESS • Use of Access plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
MEWP operation
(Operator) • Operator competency;
• Plant / pedestrian interaction;
• Work at Height; • Incident due to use of defective plant or associated equipment;
• MEWP overturning;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of MEWP by untrained personnel;
• Operators climbing onto hand rails;
• Collision with other plant and live traffic within site boundary;
• Workers struck by working MEWP, very high risk of fatality;
• Falling materials;
MEWP operation (supervision) • MEWP operations around workers;
• Workers in MEWP operating radius;
• Reversing vehicles; • Worker struck by vehicle;•
What is JSA?
A Job Safety Analysis is a task-oriented risk assessment used to review the hazards associated with a particular work task, and to verify that adequate safeguards are in place to control those hazards.
JSAs are known by a variety of terms, including Job Hazard Analysis (JHA), Job Risk Assessment (JRA), Task Risk Assessment (TRA), Safe Job Analysis (SJA).
Job Safety Analysis and its Implementation
INVOLVE employees in the development
KEEP written JSA short and simple
ILLUSTRATE safe practices
ASSIGN responsibility of JSA
TRAIN all employees and supervisors
EXPLAIN the use of JSA to employees
IMPLEMENT safe work practices
REVIEW JSA when equipment or process changes or new information becomes available regarding potential hazards associated with the job.
9 Lifting Operations with Tower crane Risk Assessment Templates
Access of Tower crane sections to work areas
Tower crane foundations
Siting, setting up and testing of Tower crane
Lifting of equipment and material
(Tower crane Operator)
Tower Crane supervision
Jumping and dismantling of Tower Crane
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptxShyam Sundar Roy
Safety is of paramount importance in the construction industry, particularly when it comes to the use of machinery and equipment. Construction sites are inherently hazardous environments, and the improper use of machinery can result in severe injuries, property damage, and even loss of life. This presentation aims to emphasize the significance of safety practices and provide essential guidelines for ensuring the safe use of construction machinery and equipment.
Hirarc for water pipe installation. The installation took place on Penang Hill, Penang. One of the busiest tourist attraction in Malaysia. Luckily, the job was carried out during shutdown period. It is the time for the funicular train to do major maintenance and repair and the area was unaccessible by train. We still have visitors coming in thru Jeep Track which means the area not fully closed and still have public safety issues.
This is the Hirarc for the job and it was carried out safely as planned.
8 Lifting Operations with mobile crane Risk Assessment Templates.docxDwarika Bhushan Sharma
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Lifting operations using mobile crane within site boundary Relevant Applicable MAS:
• 01412 – Lifting Operations;
• 00941 – Lifting equipment Additional Training required:
Riggers / Slingers NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Crane checks on arrival to site
PRIOR TO USE • Use of mobile crane • Unauthorized operation of the mobile crane resulting in incident;
• Failure due to use of un-certificated crane;
3 4 12
HIGH i. All cranes to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Crane load indicator to be installed and functioning correctly;
iv. Visual inspection of crane undertaken by competent person; Documentation unavailable for review Crane quarantined until evidence provided Low
2 Access of crane to work areas
• Plant and workers in same working area; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Uncontrolled crane reversing; i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the project;
iii. Flagmen to be used to control crane movements;
iv. The Logistics plan shall clearly illustrate crane access and egress points; Workers not complying with flagmen Regular topic in TBT’s Low
3 Siti
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Temporary Falsework for formwork support. Classed as Temporary Works Relevant Applicable MAS:
• 01411 – MEWP’s;
• 00236 - Housekeeping Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Access to work areas by personnel and plant.
Material delivery to work area;
• Vehicles and workers in same working area;
• Storage of materials for falsework;
• Use of plant – forklift etc.; • Collision with plant or vehicles and live traffic;ac
• Workers struck by plant, very high risk of fatality;
• Workers struck by plant;
• Poor or unsafe storage, collapse;
• Untrained operators; 4 5 20
HIGH i. Worker pedestrian routes to be designed and implemented with clear signage;
ii. Instruction to workers at induction on use of access routes around the project;
iii. All plant and operators to be Third Party certificated by approved body;
iv. Flagmen to be used to control personnel (only on roads below 80kph);
v. Falsework materials stored correctly, no more than 2 pallets high and banded together when transporting;
vi. In traffic enclosed areas suitable welfare and first aid facilities shall be implemented to minimized worker movements;
vii. The Logistics plan shall clearly illustrate access and egress points; Workers not complying with controls All supervision to monitor operation;
Regular topic in TBT’s Low
2 Use of powered access equipment for assembly of false-work (if required) • Use of MEWP
(Mobile Elevated
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Scaffold for work access. Classed as Temporary Works Relevant Applicable MAS:
• 00245 – Mobile scaffold towers
• 00236 - Housekeeping Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Access to work areas by personnel and plant.
Scaffold Material delivery to work area;
• Vehicles and workers in same working area;
• Storage of materials for scaffold;
• Use of plant – forklift etc.; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Workers struck by plant;
• Poor or unsafe storage, collapse;
• Untrained operators; 4 4 16
HIGH i. Worker pedestrian routes to be designed and implemented with clear signage;
ii. Instruction to workers at induction on use of access routes around the project;
iii. All plant and operators to be Third Party certificated by approved body;
iv. Flagmen to be used to control personnel (only on roads below 80kph);
v. Scaffold materials stored correctly, no more than 2 pallets high and banded together when transporting;
vi. In traffic enclosed areas suitable welfare and first aid facilities shall be implemented to minimized worker movements;
vii. The Logistics plan shall clearly illustrate access and egress points; Workers not complying with controls All supervision to monitor operation;
Regular topic in TBT’s Low
2 Scaffold design and erection standards
(Classified as Temporary Structure) • Trained personnel req
16 Scaffolding (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Scaffold Material delivery to work area;
Scaffold design and erection standards
(Classified as Temporary Structure)
Scaffold erection
(Classified as Temporary Structure)
Dismantling of scaffold
Maintenance of Scaffold
Worker exposure to direct sun whist working on scaffold
(as applicable)
8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
7 Falsework (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Material delivery to work area;
Use of powered access equipment for assembly of false-work (if required)
Falsework installation
(Classified as Temporary Structures)
Dismantling of false-work
Maintenance of Falsework
Worker exposure to direct sun whist working on falsework
(as applicable)
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...Dwarika Bhushan Sharma
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Use of Suspended access cradles and platforms
Relevant Applicable MAS:
• 0242 – Suspended access cradles and platforms Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Cradle checks on arrival to site
PRIOR TO USE • Use of Access equipment • Failure due to use of un-certificated plant;
3 4 12
HIGH i. All plant to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site (6 monthly check);
ii. Visual inspection of MEWP undertaken by competent person; Documentation unavailable for review Plant quarantined until evidence provided Low
2 Pre-use checks of suspended access cradle or platform • Work at Height; • Collapse of cradle through damage or failure of equipment;
• Falling materials;
4 5 20 HIGH i. Method statements and risk assessments to be submitted and adhered to;
ii. The safe working load must be clearly marked on the cradle and shall not be exceeded;
iii. It is erected and installed by a competent person, following the manufacturer’s instructions;
iv. An independent life line rope/wire and rope grabbing device installed;
v. All safety devices and controls are operating correctly;
vi. There are no visible signs of damage to the cradle and corresponding supports, tracks/runways;
vii. The ropes are free from damage and are correctly weaved through the drum and pulleys;
viii. Floors and guard rails are rigid and free from defects;
ix. All landing wheels must be attached and intact;
x. A
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Piling operations using mobile rig and rebar installation within site boundary. Use in conjunction with RA012 - Use of Mobile Crane and RA014 – Use of Concrete Pump. Relevant Applicable MAS:
• 01412 – Lifting Operations;
• 00941 – Lifting equipment Additional Training required:
Noise monitoring NOC’s Required for task:
Underground utility provider
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Piling Rig checks on arrival to site
PRIOR TO USE • Use of Piling Rig • Unauthorized operation of the mobile rig resulting in incident;
• Failure due to use of un-certificated rig;
3 4 12
HIGH i. All Piling rigs to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Rig load indicator to be installed and functioning correctly;
iv. Visual inspection of rig undertaken by competent person; Documentation unavailable for review Rig quarantined until evidence provided Low
2 Access of rig and delivery vehicles to work areas
• Plant and workers in same working area; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Uncontrolled rig movements; i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the project;
iii. Flagmen to be used to control rig movements;
iv.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
1. LEADERS IN SAFETY AND ISO CERTIFICATIONS
JSA Title:
ISO 45001:2018 & ISO 9001:2015 Certified body
European Safety Council, AOSH-UK, Bharat Sevak Semaj Accredited Centre
OTHM,UK Approved Training Provider
Expert Trainers Academy is a world-renowned provider of safety training and
ISO certifications, and its services are available all around the globe. We offer more than
180 international certifications in Safety, ISO and Management certifications
To get Site safety documents preparation tips, PLEASE FOLLOW THE LINK below
https://www.linkedin.com/company/expert-trainers-academy/
For more details please contact +966-581502680 (International), +91 93460 90241(India)
2. JOB SAFETY ANALYSIS
JSA Title HEAVY LIFTING OF VESSEL
Personal Protective Equipment
Required
Minimum PPE’s “Safety Helmet, Safety Shoes, Safety Glass (dark &
clear glasses), Long sleeves shirt” & Ready to use / wear working gloves,
ear plug, and approved full body harness with double lanyards equipped
with shock absorber.
BASIC JOB STEPS POTENTIAL HAZARDS RECOMMENDATIONS
1. Pre-Commencement Activities (Preparation
and planning of Work, work site, equipment &
tools)
1.1. Human Injury due to lack of communication
and information
1.1.1. Barricade the working area (site temporary
Fabrication)
1.1.2. Toolbox meeting using TAL-STARRT Form
1.1.3. Preparation of timber (de-nailed) to use for ground
protection
1.1.4. Placement of required warning signs
1.2. Personal injury due to lack of experience and
training.
1.2.1. Only experience personnel are allowed to do the
task
1.2.2. A particular training if requires (Fall Protection
Training, Confined Space Entry Training)
General Instruction:
“If there is any doubt, don’t hesitate to ask!”
1.3. Equipment may have a harmful effect on
environment.
1.3.1. All equipment shall be inspected prior to entrance to
site by the GAMA and TAL HSE Dept.
1.3.2. Validity of TAL Inspection Stickers (if necessary)
1.3.3. Daily operator’s checklist must be completed
1.3.4. Report all environmental spill to the GAMA-HSE
1.3.5. Tanks and Vessels must be purge or keep
ventilated due to anti-corrosion gas
3. 1.4. Personal injury due to not being aware of
the activities.
1.4.1. TAL - Permit for requires for more than
twenty (20) ton or Tandem lifting
1.4.2. Everyday TBT shall be conducted regarding the
daily activities (TAL-STARRT Form for critical
work)
1.4.3. JSA’s must be posted at site for safety
awareness and reference
1.4.4. Only authorized person is allowed in the area
1.5. Personal injuries due to usage of unfit
equipment.
1.5.1. Supervisors should have a Daily routine checks
or Prior to use inspection on equipments and
tools.
1.5.2. Colour coding for all electrical equipment and
tools
General Instruction:
“Defective tools should immediately removed
from site”
1.6. Damage equipment due to Poor
supervision
1.6.1. Close supervision of all work activities at all times
1.6.2. Daily inspection / checklist required equipment
should be forwarded to GAMA-HSE Dept. for
documentation
1.6.3. Foreman will inspect all hand-tools prior to use
1.7. Illegal operation, No communication with
area authorities, Clash of Activities
1.7.1. The required Permit to Work (use of man basket,
removal/opening of gratings, hot work permit)
shall be obtained and kept at work area at all
times along with the JSA
1.7.2. Strict compliance to all written procedures from
method statements (Rigging Plan, Lifting Plan
and other site safety procedures)
4. 1.8. Dust Control 1.8.1. Provision of dust masks for workers and ensure
their use
1.8.2. Provide dust mitigation by spreading water (be
aware of lying cables) “all cables must be treated
as live”
2. Mobilize materials, tools, vessel, and
equipment to worksite. Area Preparation and
selection of proper tools, lifting tackles and
suitable equipment necessary for the task.
2.1. Unsafe condition and Unsafe act. Back injury
(manual handling)
2.1.1. Manual handling shall be covered in daily TBT and
be implemented on site
2.1.2. Buddy-buddy system may apply
2.1.3. Use of mechanical lift if possible
2.2. Traffic (wheels stuck including out rigger of
the crane to tip over due to un-compacted and
uneven soil) and pedestrians (Worker hit by a
moving machine)
2.2.1. Approved engineering ground compaction
2.2.2. Prevention to tip over the crane the Safe Working
Range and Safe Working Load has to be determined
before the lift
2.2.3. Distribution of load use of out rigging mats
2.2.4. Audible reversing alarms shall be installed on
equipment / vehicles
2.2.5. Pedestrian safety precautions shall be discussed in
daily TBT
2.2.6. All traffic rules and signs should be followed (on site
speed limit is 25-km/h)
2.2.7. Only approved routes shall be used for access to
and egress from the site and fabrication
2.2.8. The drivers shall be made aware of the approved
routes
2.2.9. Trained banks-men with high-visibility vests shall
accompany the work activities near traffic/roads
5. 2.3. Overturning of vehicle / Crash injuries 2.3.1. All drivers shall have valid Saudi driving licenses
2.3.2. The areas where heavy equipment are working shall
be clearly marked on site
2.3.3. Safe access shall be maintained at site for vehicles
and equipment
2.3.4. Use of seatbelts shall be mandatory
2.4. Slips / Trips / Falls 2.4.1. Equipment saddles must be properly installed to a
compacted ground level.
2.4.2. Housekeeping shall be discussed in daily TBT and
be implemented on site on a daily basis
2.4.3. Provide safe access / emergency walkways (free
from any materials)
3. Unloading of Vessel, Tanks, Equipment,
Structures and materials use of Lifting
equipment / tackle (Mobile Crane, Tower
Crane, Gantry Crane, Boom truck, Fork lift)
3.1. Material Falls; Damage to the equipment and
property due unprepared area and incorrect gear
(SWL); Environmental hazard cause by equipment
3.1.1. Use Approved lifting equipment and gear with daily
checklist (operator’s inspection)
3.1.2. Check ground to make sure it is stable and place
approved out rigger pads.
3.1.3. Use softener (protection pad) to protect the sling to
damage from sharp edge materials
3.1.4. Use slings and shackles of the correct SWL for
unloading. Lifting gear to have the current quarterly
colour code displayed
3.1.5. Check SWL and SWR for cranes to be use
3.1.6. Crane operation to be barricaded, restricted access
to unauthorized personnel
3.1.7. Two (2) tag lines are required for High Vessel lifting
3.1.8. Provide lifting safety sign boards
3.1.9. Provide approved Temporary Structural and vessel
supports
3.1.10. Provide stopper to prevent the vessel to roll-over
3.1.11. Only assigned rigger can give the signal for
lifting
3.1.12. Report all environmental spills to GAMA-HSE Dept.
6. Position the correct cranes into position to do the
lifting and check free slew motion
3.2. Person can be trapped between counterweight
and tracks; Struck by a moving cranes.
Damage buildings, facilities and lines (existing
fence, light pole, u/g lines, etc.) struck or run over
by the moving crane
3.2.1. Riggers to check clearance around cranes to ensure every
body out of striking distance.
3.2.2. Riggers to check safe clearance between existing facilities
and lines.
3.2.3. Area to be barricaded around cranes, roads & working
area closed and marked. Signed accordingly.
3.2.4. 360 degrees visibility for the crane operator
Assemble all equipment, vessel, and structures
use of Mechanical lifting
4.1. Physical Injury, Falling materials, damage to
equipment, and Environmental hazard
4.1.1. STARRT meeting to be conducted, form filled in and
displayed at the working location,
4.1.2. Use Approved lifting machine and spreader beam
with 3rd
party and site inspections
4.1.3. Experienced and certified crane operator to operate the
crane
4.1.4. Use softener (protection pad) for slings when necessary
to protect from damage
4.1.5. All rigging/lifting equipment to be inspected and display
current colour code
4.1.6. Only trained and certified riggers to work with the crane,
tag lines to be used to control the load
4.1.7. Work area to be fully barricaded, access restricted
authorized personnel only
4.1.8. Full time Competent Personnel to supervise and give
instruction (Visible on the area) while work is carried out
4.1.9. Report all environmental spills to GAMA HSE
General Instruction:
- Only approved equipment to be used (crane, ,etc)
- No standing under a suspended load(including riggers)
7. Communication between Operators and rigger 4.2. Wrong signal / action or misunderstanding
can cause catastrophic accident.
4.1.10. Rigger must position visible to the operator
4.1.11. Use radio communication
4.1.12. Good communication, and know how - what is
planned to avoid misunderstanding
5. Assemble equipment, vessel, and structure by
Manual Lifting and engineering strategies
5.1. Physical injuries (Back injury, struck by two
solid objects, etc.)
5.1.1. Proper Manual lifting and handling shall be covered
in daily TBT and be implemented on site
5.1.2. Buddy-buddy system may apply
5.1.3. Use of mechanical lifting if possible
5.1.4. Manual strategy system must be properly plan and
supervised
5.1.5. Use only approved and inspected tools and lifter
(chain block, chain puller, tagger, etc.)
6. Possibility to use of Grinding and cutting of
Steel use of Grinder
6.4.Fire and Burns 6.1.1. Hot Work Permit acquire from TAL
6.1.2. Inspected and colour coded grinder (bull, baby and
pencil) including all electrical extension cable
6.1.3. Only experienced and trained pipe-fitter/fabricators
are required for the task
6.1.4. Use all the necessary PPE for grinding
6.1.5. No combustible material near the work place
6.1.6. Fire blanket or equivalent, fire extinguisher
6.2. Electrocution 6.2.1. Use all necessary requirements including PPE for
the task
6.2.2. Use only approved extension cables with quarterly
colour coding
6.2.3. Know the cable management (above 2 meters in
high, with flagging, avoid contact to any electrical
conductive materials)
8. Use of Cutting of steel using Gas cutting
machine
6.3. Fire and Burns 6.3.1. Hot Work Permit acquire from TAL
6.3.2. Oxy-acetylene Equipment Inspection checklist
should be administer on site
6.3.3. Only experienced and trained pipe-fitter /
Fabricators are required for the task
6.3.4. Use all the necessary PPE for gas cutting
6.3.5. No combustible material near the work place
6.3.6. Fire blanket or equivalent, fire extinguisher
Welding Works 6.4. Fire and Burns and environmental Hazards 6.4.1. Inspected and colour coded welding equipment
and cables
6.4.2. Only qualified welders is required for the task
6.4.3. Use all the necessary PPE for welding
6.4.4. No combustible material near the work place
6.4.5. No combustible material under the work place
when working at heights
6.4.6. Fire blanket or equivalent, fire extinguisher
6.4.7. Provide bucket or can for welding rod butts and
report to GAMA-HSE Department for
documentation
9. 7. Scaffolding Erection 7.1. Unsafe scaffolding, Hazard to fall 7.1.1. Scaffold must be erect as per standard/ client
requirements
7.1.2. Scaffolding Foreman must prepare a STARRT Form
before the erection of any more than 6 meters above
7.1.3. All Scaffolders should wear full body harness
equipped with two (2) LANYARD (inspected and
approved “colour coded”)
7.1.4. All Scaffolders must have a Fall Protection Training
identification stick on their helmets
General Instruction:
More than four (4) meters high work must comply with the
standard – Full body harness with shock absorber attached
is required.
Scaffolding as working platform 7.2. Hazard to fall 7.2.1. Wear fall protection
7.2.2. Inspection Tag signed and revalidate every week
7.2.3. Ensure the 100% tie off (double lanyard)
Note:
-All designed erected scaffoldings are in yellow tag which
requires wearing full body harness double lanyard equipped
with shock absorber.
-Only Scaffolders are allowed to alter or rectify scaffolding)
8. Lifting and positioning of vessel, machine, or
equipment to the foundation in a vertical or
horizontal position and tightening of nuts
8.1. Uncontrolled lifting 8.1.1. Site review of Lifting Plan
8.1.2. General isolation (clear of any persons) of the area,
swing radius, includes the area where vessel,
equipment, or machine has to install.
8.1.3. Only assigned rigger to give signals to crane
operator
8.1.4. No passing underneath the lifting structure, no
holding / touching the lifting structure
8.1.5. Attach / use two tag lines to the bottom for
controlling the load
10. 9. Removal of lifting tackles to the top of the
vessel by the use of Man lift – basket and or
Mobile Man lifter
9.1. Hazard to fall, Falling hazards, Mobile man
lift Tip over
9.1.1. Third party inspection is required both for Man
Basket and Mobile Man lifter
9.1.2. Only trained or qualified personnel to operate, ride
or use the lifter
9.1.3. Properly position the Mobile man lift to a stable
ground level
9.1.4. Use Full Body Harness
9.1.5. FPT – Fall Protection Training requires
9.1.6. Use appropriate Tag lines (2) attached to the
bottom for Man Basket control
9.1.7. Use approved crane
9.1.8. Proper anchorage in using man basket
9.1.9. Wear hand gloves
9.1.10. Secure / Tie all hand tools to prevent falling
Use of Ladder as an access / ladder used
to climb
9.2 Slip, Trip and Fall due to not 100% tie-off 9.2.1. Use Approved and inspected ladders, displaying
the current quarterly colour code
9.2.2. Proper installation of ladders according to heights
and first step/rung to be reach evenly.
9.2.3. Ladder must be 100 percent tied-off
9.2.4. Use (3) three points system, when climbing a
ladders (hands are free from materials)
9.2.5. Additional materials required at heights should be
lifted correctly (using ropes or crane lifts)
9.2.6. One worker at a time on climbing a ladder
9.2.7. 100 % tying in the rungs must be imposed on FPT
and before climbing up
9.2.8. As an access to climb-assigned helper to hold the
ladder on the ground
9.2.9. As an access to climb-Ladder must be
immediately secure at the top
11. 9.2.10. Ladder should stand only in a firm and balance
position
9.2.11. Ladder must no position against moving structure
9.2.12. Do not throw materials from the top
9.2.13. Restriction (Barricade and safety sign boards)
10. Tandem Lift 10.1. Loss of control causing injury or property
damage
10.1.1. TAL – STARRT Form application (critical work)
10.1.2. TAL-Permit applications
10.1.3. Approved Lifting Plan
10.1.4. Approved Rigging Plan
10.1.5. Mechanical Transport Supervisor or rigging
supervisor to be present at all times to ensure correct
and safe lifting
11. Demobilization 11.1. Work completion; Clutter/Rubbish 11.1.1. Workforce shall be alerted about the work
completion
11.1.2. Removal of all woods, palettes, creates, and steel
saddles used as a base support
11.1.3. Arrangement of all lifting tackles (shackles, slings,
rope, etc.)
11.1.4. Good housekeeping practice shall be implemented
throughout the day