SlideShare a Scribd company logo
LEADERS IN SAFETY AND ISO CERTIFICATIONS
JSA Title:
ISO 45001:2018 & ISO 9001:2015 Certified body
European Safety Council, AOSH-UK, Bharat Sevak Semaj Accredited Centre
OTHM,UK Approved Training Provider
Expert Trainers Academy is a world-renowned provider of safety training and
ISO certifications, and its services are available all around the globe. We offer more than
180 international certifications in Safety, ISO and Management certifications
To get Site safety documents preparation tips, PLEASE FOLLOW THE LINK below
https://www.linkedin.com/company/expert-trainers-academy/
For more details please contact +966-581502680 (International), +91 93460 90241(India)
JOB SAFETY ANALYSIS
JSA Title HEAVY LIFTING OF VESSEL
Personal Protective Equipment
Required
Minimum PPE’s “Safety Helmet, Safety Shoes, Safety Glass (dark &
clear glasses), Long sleeves shirt” & Ready to use / wear working gloves,
ear plug, and approved full body harness with double lanyards equipped
with shock absorber.
BASIC JOB STEPS POTENTIAL HAZARDS RECOMMENDATIONS
1. Pre-Commencement Activities (Preparation
and planning of Work, work site, equipment &
tools)
1.1. Human Injury due to lack of communication
and information
1.1.1. Barricade the working area (site temporary
Fabrication)
1.1.2. Toolbox meeting using TAL-STARRT Form
1.1.3. Preparation of timber (de-nailed) to use for ground
protection
1.1.4. Placement of required warning signs
1.2. Personal injury due to lack of experience and
training.
1.2.1. Only experience personnel are allowed to do the
task
1.2.2. A particular training if requires (Fall Protection
Training, Confined Space Entry Training)
General Instruction:
“If there is any doubt, don’t hesitate to ask!”
1.3. Equipment may have a harmful effect on
environment.
1.3.1. All equipment shall be inspected prior to entrance to
site by the GAMA and TAL HSE Dept.
1.3.2. Validity of TAL Inspection Stickers (if necessary)
1.3.3. Daily operator’s checklist must be completed
1.3.4. Report all environmental spill to the GAMA-HSE
1.3.5. Tanks and Vessels must be purge or keep
ventilated due to anti-corrosion gas
1.4. Personal injury due to not being aware of
the activities.
1.4.1. TAL - Permit for requires for more than
twenty (20) ton or Tandem lifting
1.4.2. Everyday TBT shall be conducted regarding the
daily activities (TAL-STARRT Form for critical
work)
1.4.3. JSA’s must be posted at site for safety
awareness and reference
1.4.4. Only authorized person is allowed in the area
1.5. Personal injuries due to usage of unfit
equipment.
1.5.1. Supervisors should have a Daily routine checks
or Prior to use inspection on equipments and
tools.
1.5.2. Colour coding for all electrical equipment and
tools
General Instruction:
“Defective tools should immediately removed
from site”
1.6. Damage equipment due to Poor
supervision
1.6.1. Close supervision of all work activities at all times
1.6.2. Daily inspection / checklist required equipment
should be forwarded to GAMA-HSE Dept. for
documentation
1.6.3. Foreman will inspect all hand-tools prior to use
1.7. Illegal operation, No communication with
area authorities, Clash of Activities
1.7.1. The required Permit to Work (use of man basket,
removal/opening of gratings, hot work permit)
shall be obtained and kept at work area at all
times along with the JSA
1.7.2. Strict compliance to all written procedures from
method statements (Rigging Plan, Lifting Plan
and other site safety procedures)
1.8. Dust Control 1.8.1. Provision of dust masks for workers and ensure
their use
1.8.2. Provide dust mitigation by spreading water (be
aware of lying cables) “all cables must be treated
as live”
2. Mobilize materials, tools, vessel, and
equipment to worksite. Area Preparation and
selection of proper tools, lifting tackles and
suitable equipment necessary for the task.
2.1. Unsafe condition and Unsafe act. Back injury
(manual handling)
2.1.1. Manual handling shall be covered in daily TBT and
be implemented on site
2.1.2. Buddy-buddy system may apply
2.1.3. Use of mechanical lift if possible
2.2. Traffic (wheels stuck including out rigger of
the crane to tip over due to un-compacted and
uneven soil) and pedestrians (Worker hit by a
moving machine)
2.2.1. Approved engineering ground compaction
2.2.2. Prevention to tip over the crane the Safe Working
Range and Safe Working Load has to be determined
before the lift
2.2.3. Distribution of load use of out rigging mats
2.2.4. Audible reversing alarms shall be installed on
equipment / vehicles
2.2.5. Pedestrian safety precautions shall be discussed in
daily TBT
2.2.6. All traffic rules and signs should be followed (on site
speed limit is 25-km/h)
2.2.7. Only approved routes shall be used for access to
and egress from the site and fabrication
2.2.8. The drivers shall be made aware of the approved
routes
2.2.9. Trained banks-men with high-visibility vests shall
accompany the work activities near traffic/roads
2.3. Overturning of vehicle / Crash injuries 2.3.1. All drivers shall have valid Saudi driving licenses
2.3.2. The areas where heavy equipment are working shall
be clearly marked on site
2.3.3. Safe access shall be maintained at site for vehicles
and equipment
2.3.4. Use of seatbelts shall be mandatory
2.4. Slips / Trips / Falls 2.4.1. Equipment saddles must be properly installed to a
compacted ground level.
2.4.2. Housekeeping shall be discussed in daily TBT and
be implemented on site on a daily basis
2.4.3. Provide safe access / emergency walkways (free
from any materials)
3. Unloading of Vessel, Tanks, Equipment,
Structures and materials use of Lifting
equipment / tackle (Mobile Crane, Tower
Crane, Gantry Crane, Boom truck, Fork lift)
3.1. Material Falls; Damage to the equipment and
property due unprepared area and incorrect gear
(SWL); Environmental hazard cause by equipment
3.1.1. Use Approved lifting equipment and gear with daily
checklist (operator’s inspection)
3.1.2. Check ground to make sure it is stable and place
approved out rigger pads.
3.1.3. Use softener (protection pad) to protect the sling to
damage from sharp edge materials
3.1.4. Use slings and shackles of the correct SWL for
unloading. Lifting gear to have the current quarterly
colour code displayed
3.1.5. Check SWL and SWR for cranes to be use
3.1.6. Crane operation to be barricaded, restricted access
to unauthorized personnel
3.1.7. Two (2) tag lines are required for High Vessel lifting
3.1.8. Provide lifting safety sign boards
3.1.9. Provide approved Temporary Structural and vessel
supports
3.1.10. Provide stopper to prevent the vessel to roll-over
3.1.11. Only assigned rigger can give the signal for
lifting
3.1.12. Report all environmental spills to GAMA-HSE Dept.
Position the correct cranes into position to do the
lifting and check free slew motion
3.2. Person can be trapped between counterweight
and tracks; Struck by a moving cranes.
Damage buildings, facilities and lines (existing
fence, light pole, u/g lines, etc.) struck or run over
by the moving crane
3.2.1. Riggers to check clearance around cranes to ensure every
body out of striking distance.
3.2.2. Riggers to check safe clearance between existing facilities
and lines.
3.2.3. Area to be barricaded around cranes, roads & working
area closed and marked. Signed accordingly.
3.2.4. 360 degrees visibility for the crane operator
Assemble all equipment, vessel, and structures
use of Mechanical lifting
4.1. Physical Injury, Falling materials, damage to
equipment, and Environmental hazard
4.1.1. STARRT meeting to be conducted, form filled in and
displayed at the working location,
4.1.2. Use Approved lifting machine and spreader beam
with 3rd
party and site inspections
4.1.3. Experienced and certified crane operator to operate the
crane
4.1.4. Use softener (protection pad) for slings when necessary
to protect from damage
4.1.5. All rigging/lifting equipment to be inspected and display
current colour code
4.1.6. Only trained and certified riggers to work with the crane,
tag lines to be used to control the load
4.1.7. Work area to be fully barricaded, access restricted
authorized personnel only
4.1.8. Full time Competent Personnel to supervise and give
instruction (Visible on the area) while work is carried out
4.1.9. Report all environmental spills to GAMA HSE
General Instruction:
- Only approved equipment to be used (crane, ,etc)
- No standing under a suspended load(including riggers)
Communication between Operators and rigger 4.2. Wrong signal / action or misunderstanding
can cause catastrophic accident.
4.1.10. Rigger must position visible to the operator
4.1.11. Use radio communication
4.1.12. Good communication, and know how - what is
planned to avoid misunderstanding
5. Assemble equipment, vessel, and structure by
Manual Lifting and engineering strategies
5.1. Physical injuries (Back injury, struck by two
solid objects, etc.)
5.1.1. Proper Manual lifting and handling shall be covered
in daily TBT and be implemented on site
5.1.2. Buddy-buddy system may apply
5.1.3. Use of mechanical lifting if possible
5.1.4. Manual strategy system must be properly plan and
supervised
5.1.5. Use only approved and inspected tools and lifter
(chain block, chain puller, tagger, etc.)
6. Possibility to use of Grinding and cutting of
Steel use of Grinder
6.4.Fire and Burns 6.1.1. Hot Work Permit acquire from TAL
6.1.2. Inspected and colour coded grinder (bull, baby and
pencil) including all electrical extension cable
6.1.3. Only experienced and trained pipe-fitter/fabricators
are required for the task
6.1.4. Use all the necessary PPE for grinding
6.1.5. No combustible material near the work place
6.1.6. Fire blanket or equivalent, fire extinguisher
6.2. Electrocution 6.2.1. Use all necessary requirements including PPE for
the task
6.2.2. Use only approved extension cables with quarterly
colour coding
6.2.3. Know the cable management (above 2 meters in
high, with flagging, avoid contact to any electrical
conductive materials)
Use of Cutting of steel using Gas cutting
machine
6.3. Fire and Burns 6.3.1. Hot Work Permit acquire from TAL
6.3.2. Oxy-acetylene Equipment Inspection checklist
should be administer on site
6.3.3. Only experienced and trained pipe-fitter /
Fabricators are required for the task
6.3.4. Use all the necessary PPE for gas cutting
6.3.5. No combustible material near the work place
6.3.6. Fire blanket or equivalent, fire extinguisher
Welding Works 6.4. Fire and Burns and environmental Hazards 6.4.1. Inspected and colour coded welding equipment
and cables
6.4.2. Only qualified welders is required for the task
6.4.3. Use all the necessary PPE for welding
6.4.4. No combustible material near the work place
6.4.5. No combustible material under the work place
when working at heights
6.4.6. Fire blanket or equivalent, fire extinguisher
6.4.7. Provide bucket or can for welding rod butts and
report to GAMA-HSE Department for
documentation
7. Scaffolding Erection 7.1. Unsafe scaffolding, Hazard to fall 7.1.1. Scaffold must be erect as per standard/ client
requirements
7.1.2. Scaffolding Foreman must prepare a STARRT Form
before the erection of any more than 6 meters above
7.1.3. All Scaffolders should wear full body harness
equipped with two (2) LANYARD (inspected and
approved “colour coded”)
7.1.4. All Scaffolders must have a Fall Protection Training
identification stick on their helmets
General Instruction:
More than four (4) meters high work must comply with the
standard – Full body harness with shock absorber attached
is required.
Scaffolding as working platform 7.2. Hazard to fall 7.2.1. Wear fall protection
7.2.2. Inspection Tag signed and revalidate every week
7.2.3. Ensure the 100% tie off (double lanyard)
Note:
-All designed erected scaffoldings are in yellow tag which
requires wearing full body harness double lanyard equipped
with shock absorber.
-Only Scaffolders are allowed to alter or rectify scaffolding)
8. Lifting and positioning of vessel, machine, or
equipment to the foundation in a vertical or
horizontal position and tightening of nuts
8.1. Uncontrolled lifting 8.1.1. Site review of Lifting Plan
8.1.2. General isolation (clear of any persons) of the area,
swing radius, includes the area where vessel,
equipment, or machine has to install.
8.1.3. Only assigned rigger to give signals to crane
operator
8.1.4. No passing underneath the lifting structure, no
holding / touching the lifting structure
8.1.5. Attach / use two tag lines to the bottom for
controlling the load
9. Removal of lifting tackles to the top of the
vessel by the use of Man lift – basket and or
Mobile Man lifter
9.1. Hazard to fall, Falling hazards, Mobile man
lift Tip over
9.1.1. Third party inspection is required both for Man
Basket and Mobile Man lifter
9.1.2. Only trained or qualified personnel to operate, ride
or use the lifter
9.1.3. Properly position the Mobile man lift to a stable
ground level
9.1.4. Use Full Body Harness
9.1.5. FPT – Fall Protection Training requires
9.1.6. Use appropriate Tag lines (2) attached to the
bottom for Man Basket control
9.1.7. Use approved crane
9.1.8. Proper anchorage in using man basket
9.1.9. Wear hand gloves
9.1.10. Secure / Tie all hand tools to prevent falling
Use of Ladder as an access / ladder used
to climb
9.2 Slip, Trip and Fall due to not 100% tie-off 9.2.1. Use Approved and inspected ladders, displaying
the current quarterly colour code
9.2.2. Proper installation of ladders according to heights
and first step/rung to be reach evenly.
9.2.3. Ladder must be 100 percent tied-off
9.2.4. Use (3) three points system, when climbing a
ladders (hands are free from materials)
9.2.5. Additional materials required at heights should be
lifted correctly (using ropes or crane lifts)
9.2.6. One worker at a time on climbing a ladder
9.2.7. 100 % tying in the rungs must be imposed on FPT
and before climbing up
9.2.8. As an access to climb-assigned helper to hold the
ladder on the ground
9.2.9. As an access to climb-Ladder must be
immediately secure at the top
9.2.10. Ladder should stand only in a firm and balance
position
9.2.11. Ladder must no position against moving structure
9.2.12. Do not throw materials from the top
9.2.13. Restriction (Barricade and safety sign boards)
10. Tandem Lift 10.1. Loss of control causing injury or property
damage
10.1.1. TAL – STARRT Form application (critical work)
10.1.2. TAL-Permit applications
10.1.3. Approved Lifting Plan
10.1.4. Approved Rigging Plan
10.1.5. Mechanical Transport Supervisor or rigging
supervisor to be present at all times to ensure correct
and safe lifting
11. Demobilization 11.1. Work completion; Clutter/Rubbish 11.1.1. Workforce shall be alerted about the work
completion
11.1.2. Removal of all woods, palettes, creates, and steel
saddles used as a base support
11.1.3. Arrangement of all lifting tackles (shackles, slings,
rope, etc.)
11.1.4. Good housekeeping practice shall be implemented
throughout the day

More Related Content

What's hot

Flagman-Training.ppt
Flagman-Training.pptFlagman-Training.ppt
Flagman-Training.ppt
Imran Khan
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
Azmeel Contracting Company
 
Risk Assessment in a Workplace Transport /Risk assessment for a road haulage ...
Risk Assessment in a Workplace Transport /Risk assessment for a road haulage ...Risk Assessment in a Workplace Transport /Risk assessment for a road haulage ...
Risk Assessment in a Workplace Transport /Risk assessment for a road haulage ...
Tarun Kumar Cheddy
 
NGI-Safety Induction-English
NGI-Safety Induction-EnglishNGI-Safety Induction-English
NGI-Safety Induction-Englishlifecombo
 
Bloqueo y etiquetado de energia (loto)
Bloqueo y etiquetado de energia (loto)Bloqueo y etiquetado de energia (loto)
Bloqueo y etiquetado de energia (loto)
jacobo_et
 
Haad height aware - eng
Haad   height aware - engHaad   height aware - eng
Haad height aware - eng
Mumtaz A. Khan CMIOSH, IDipNEBOSH
 
HSE Management Plan
HSE Management PlanHSE Management Plan
HSE Management Plan
Philip Hà
 
Manual para trabajos de alto riesgo
Manual para trabajos de alto riesgoManual para trabajos de alto riesgo
Manual para trabajos de alto riesgo
VICTOR CESAR TURRIN LLEELLISH
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Hse alert 43 forklift safety
Hse alert 43 forklift safetyHse alert 43 forklift safety
Hse alert 43 forklift safety
Dwarika Bhushan Sharma
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
Dwarika Bhushan Sharma
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates
Dwarika Bhushan Sharma
 
Job safety analysis
Job safety analysis Job safety analysis
Job safety analysis
soumenmakar
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
BalamuruganD26
 
Lighting risk assessment
Lighting risk assessmentLighting risk assessment
Lighting risk assessment
mediageek5
 
Nebosh International Diploma unit A questions matrix
Nebosh International Diploma unit A questions matrixNebosh International Diploma unit A questions matrix
Nebosh International Diploma unit A questions matrix
Ciske Berrington
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
Dwarika Bhushan Sharma
 
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
MAVILA ELIZABETH ROJAS SILVA
 

What's hot (20)

Flagman-Training.ppt
Flagman-Training.pptFlagman-Training.ppt
Flagman-Training.ppt
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
Risk Assessment in a Workplace Transport /Risk assessment for a road haulage ...
Risk Assessment in a Workplace Transport /Risk assessment for a road haulage ...Risk Assessment in a Workplace Transport /Risk assessment for a road haulage ...
Risk Assessment in a Workplace Transport /Risk assessment for a road haulage ...
 
NGI-Safety Induction-English
NGI-Safety Induction-EnglishNGI-Safety Induction-English
NGI-Safety Induction-English
 
Bloqueo y etiquetado de energia (loto)
Bloqueo y etiquetado de energia (loto)Bloqueo y etiquetado de energia (loto)
Bloqueo y etiquetado de energia (loto)
 
Haad height aware - eng
Haad   height aware - engHaad   height aware - eng
Haad height aware - eng
 
Hirarc
HirarcHirarc
Hirarc
 
HSE Management Plan
HSE Management PlanHSE Management Plan
HSE Management Plan
 
Manual para trabajos de alto riesgo
Manual para trabajos de alto riesgoManual para trabajos de alto riesgo
Manual para trabajos de alto riesgo
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Hse alert 43 forklift safety
Hse alert 43 forklift safetyHse alert 43 forklift safety
Hse alert 43 forklift safety
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Job safety analysis
Job safety analysis Job safety analysis
Job safety analysis
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
 
Lighting risk assessment
Lighting risk assessmentLighting risk assessment
Lighting risk assessment
 
Nebosh International Diploma unit A questions matrix
Nebosh International Diploma unit A questions matrixNebosh International Diploma unit A questions matrix
Nebosh International Diploma unit A questions matrix
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
 

Similar to JHA HEAVY LIFTING OF VESSEL.pdf

JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfJHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
Haroon AbdulRahim
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptx
ssuser926916
 
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptxSAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
Shyam Sundar Roy
 
JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building
Alvin160771
 
TBR - MSCL Piping Installation shutdown 2023.docx
TBR - MSCL Piping Installation shutdown 2023.docxTBR - MSCL Piping Installation shutdown 2023.docx
TBR - MSCL Piping Installation shutdown 2023.docx
RizalZamin
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhek
RoseGaming1
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
Change- out P119 Pulley-2
Change- out P119 Pulley-2Change- out P119 Pulley-2
Change- out P119 Pulley-2Scott Jarrold
 
fdocuments.net_lifting-devices-and-equipments-56b8523cbf6c6.ppt
fdocuments.net_lifting-devices-and-equipments-56b8523cbf6c6.pptfdocuments.net_lifting-devices-and-equipments-56b8523cbf6c6.ppt
fdocuments.net_lifting-devices-and-equipments-56b8523cbf6c6.ppt
RahulDeshpande84
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
FESTUS RICHARD SIAME
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
Dwarika Bhushan Sharma
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
Dwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
TRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docxTRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docx
PriyaRavirajan
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JESUSBASILIOANTONIO
 

Similar to JHA HEAVY LIFTING OF VESSEL.pdf (20)

JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfJHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptx
 
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptxSAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
 
JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building
 
TBR - MSCL Piping Installation shutdown 2023.docx
TBR - MSCL Piping Installation shutdown 2023.docxTBR - MSCL Piping Installation shutdown 2023.docx
TBR - MSCL Piping Installation shutdown 2023.docx
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhek
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
Change- out P119 Pulley-2
Change- out P119 Pulley-2Change- out P119 Pulley-2
Change- out P119 Pulley-2
 
fdocuments.net_lifting-devices-and-equipments-56b8523cbf6c6.ppt
fdocuments.net_lifting-devices-and-equipments-56b8523cbf6c6.pptfdocuments.net_lifting-devices-and-equipments-56b8523cbf6c6.ppt
fdocuments.net_lifting-devices-and-equipments-56b8523cbf6c6.ppt
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
update 20feb1
update 20feb1update 20feb1
update 20feb1
 
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
TRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docxTRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docx
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
 

Recently uploaded

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 

JHA HEAVY LIFTING OF VESSEL.pdf

  • 1. LEADERS IN SAFETY AND ISO CERTIFICATIONS JSA Title: ISO 45001:2018 & ISO 9001:2015 Certified body European Safety Council, AOSH-UK, Bharat Sevak Semaj Accredited Centre OTHM,UK Approved Training Provider Expert Trainers Academy is a world-renowned provider of safety training and ISO certifications, and its services are available all around the globe. We offer more than 180 international certifications in Safety, ISO and Management certifications To get Site safety documents preparation tips, PLEASE FOLLOW THE LINK below https://www.linkedin.com/company/expert-trainers-academy/ For more details please contact +966-581502680 (International), +91 93460 90241(India)
  • 2. JOB SAFETY ANALYSIS JSA Title HEAVY LIFTING OF VESSEL Personal Protective Equipment Required Minimum PPE’s “Safety Helmet, Safety Shoes, Safety Glass (dark & clear glasses), Long sleeves shirt” & Ready to use / wear working gloves, ear plug, and approved full body harness with double lanyards equipped with shock absorber. BASIC JOB STEPS POTENTIAL HAZARDS RECOMMENDATIONS 1. Pre-Commencement Activities (Preparation and planning of Work, work site, equipment & tools) 1.1. Human Injury due to lack of communication and information 1.1.1. Barricade the working area (site temporary Fabrication) 1.1.2. Toolbox meeting using TAL-STARRT Form 1.1.3. Preparation of timber (de-nailed) to use for ground protection 1.1.4. Placement of required warning signs 1.2. Personal injury due to lack of experience and training. 1.2.1. Only experience personnel are allowed to do the task 1.2.2. A particular training if requires (Fall Protection Training, Confined Space Entry Training) General Instruction: “If there is any doubt, don’t hesitate to ask!” 1.3. Equipment may have a harmful effect on environment. 1.3.1. All equipment shall be inspected prior to entrance to site by the GAMA and TAL HSE Dept. 1.3.2. Validity of TAL Inspection Stickers (if necessary) 1.3.3. Daily operator’s checklist must be completed 1.3.4. Report all environmental spill to the GAMA-HSE 1.3.5. Tanks and Vessels must be purge or keep ventilated due to anti-corrosion gas
  • 3. 1.4. Personal injury due to not being aware of the activities. 1.4.1. TAL - Permit for requires for more than twenty (20) ton or Tandem lifting 1.4.2. Everyday TBT shall be conducted regarding the daily activities (TAL-STARRT Form for critical work) 1.4.3. JSA’s must be posted at site for safety awareness and reference 1.4.4. Only authorized person is allowed in the area 1.5. Personal injuries due to usage of unfit equipment. 1.5.1. Supervisors should have a Daily routine checks or Prior to use inspection on equipments and tools. 1.5.2. Colour coding for all electrical equipment and tools General Instruction: “Defective tools should immediately removed from site” 1.6. Damage equipment due to Poor supervision 1.6.1. Close supervision of all work activities at all times 1.6.2. Daily inspection / checklist required equipment should be forwarded to GAMA-HSE Dept. for documentation 1.6.3. Foreman will inspect all hand-tools prior to use 1.7. Illegal operation, No communication with area authorities, Clash of Activities 1.7.1. The required Permit to Work (use of man basket, removal/opening of gratings, hot work permit) shall be obtained and kept at work area at all times along with the JSA 1.7.2. Strict compliance to all written procedures from method statements (Rigging Plan, Lifting Plan and other site safety procedures)
  • 4. 1.8. Dust Control 1.8.1. Provision of dust masks for workers and ensure their use 1.8.2. Provide dust mitigation by spreading water (be aware of lying cables) “all cables must be treated as live” 2. Mobilize materials, tools, vessel, and equipment to worksite. Area Preparation and selection of proper tools, lifting tackles and suitable equipment necessary for the task. 2.1. Unsafe condition and Unsafe act. Back injury (manual handling) 2.1.1. Manual handling shall be covered in daily TBT and be implemented on site 2.1.2. Buddy-buddy system may apply 2.1.3. Use of mechanical lift if possible 2.2. Traffic (wheels stuck including out rigger of the crane to tip over due to un-compacted and uneven soil) and pedestrians (Worker hit by a moving machine) 2.2.1. Approved engineering ground compaction 2.2.2. Prevention to tip over the crane the Safe Working Range and Safe Working Load has to be determined before the lift 2.2.3. Distribution of load use of out rigging mats 2.2.4. Audible reversing alarms shall be installed on equipment / vehicles 2.2.5. Pedestrian safety precautions shall be discussed in daily TBT 2.2.6. All traffic rules and signs should be followed (on site speed limit is 25-km/h) 2.2.7. Only approved routes shall be used for access to and egress from the site and fabrication 2.2.8. The drivers shall be made aware of the approved routes 2.2.9. Trained banks-men with high-visibility vests shall accompany the work activities near traffic/roads
  • 5. 2.3. Overturning of vehicle / Crash injuries 2.3.1. All drivers shall have valid Saudi driving licenses 2.3.2. The areas where heavy equipment are working shall be clearly marked on site 2.3.3. Safe access shall be maintained at site for vehicles and equipment 2.3.4. Use of seatbelts shall be mandatory 2.4. Slips / Trips / Falls 2.4.1. Equipment saddles must be properly installed to a compacted ground level. 2.4.2. Housekeeping shall be discussed in daily TBT and be implemented on site on a daily basis 2.4.3. Provide safe access / emergency walkways (free from any materials) 3. Unloading of Vessel, Tanks, Equipment, Structures and materials use of Lifting equipment / tackle (Mobile Crane, Tower Crane, Gantry Crane, Boom truck, Fork lift) 3.1. Material Falls; Damage to the equipment and property due unprepared area and incorrect gear (SWL); Environmental hazard cause by equipment 3.1.1. Use Approved lifting equipment and gear with daily checklist (operator’s inspection) 3.1.2. Check ground to make sure it is stable and place approved out rigger pads. 3.1.3. Use softener (protection pad) to protect the sling to damage from sharp edge materials 3.1.4. Use slings and shackles of the correct SWL for unloading. Lifting gear to have the current quarterly colour code displayed 3.1.5. Check SWL and SWR for cranes to be use 3.1.6. Crane operation to be barricaded, restricted access to unauthorized personnel 3.1.7. Two (2) tag lines are required for High Vessel lifting 3.1.8. Provide lifting safety sign boards 3.1.9. Provide approved Temporary Structural and vessel supports 3.1.10. Provide stopper to prevent the vessel to roll-over 3.1.11. Only assigned rigger can give the signal for lifting 3.1.12. Report all environmental spills to GAMA-HSE Dept.
  • 6. Position the correct cranes into position to do the lifting and check free slew motion 3.2. Person can be trapped between counterweight and tracks; Struck by a moving cranes. Damage buildings, facilities and lines (existing fence, light pole, u/g lines, etc.) struck or run over by the moving crane 3.2.1. Riggers to check clearance around cranes to ensure every body out of striking distance. 3.2.2. Riggers to check safe clearance between existing facilities and lines. 3.2.3. Area to be barricaded around cranes, roads & working area closed and marked. Signed accordingly. 3.2.4. 360 degrees visibility for the crane operator Assemble all equipment, vessel, and structures use of Mechanical lifting 4.1. Physical Injury, Falling materials, damage to equipment, and Environmental hazard 4.1.1. STARRT meeting to be conducted, form filled in and displayed at the working location, 4.1.2. Use Approved lifting machine and spreader beam with 3rd party and site inspections 4.1.3. Experienced and certified crane operator to operate the crane 4.1.4. Use softener (protection pad) for slings when necessary to protect from damage 4.1.5. All rigging/lifting equipment to be inspected and display current colour code 4.1.6. Only trained and certified riggers to work with the crane, tag lines to be used to control the load 4.1.7. Work area to be fully barricaded, access restricted authorized personnel only 4.1.8. Full time Competent Personnel to supervise and give instruction (Visible on the area) while work is carried out 4.1.9. Report all environmental spills to GAMA HSE General Instruction: - Only approved equipment to be used (crane, ,etc) - No standing under a suspended load(including riggers)
  • 7. Communication between Operators and rigger 4.2. Wrong signal / action or misunderstanding can cause catastrophic accident. 4.1.10. Rigger must position visible to the operator 4.1.11. Use radio communication 4.1.12. Good communication, and know how - what is planned to avoid misunderstanding 5. Assemble equipment, vessel, and structure by Manual Lifting and engineering strategies 5.1. Physical injuries (Back injury, struck by two solid objects, etc.) 5.1.1. Proper Manual lifting and handling shall be covered in daily TBT and be implemented on site 5.1.2. Buddy-buddy system may apply 5.1.3. Use of mechanical lifting if possible 5.1.4. Manual strategy system must be properly plan and supervised 5.1.5. Use only approved and inspected tools and lifter (chain block, chain puller, tagger, etc.) 6. Possibility to use of Grinding and cutting of Steel use of Grinder 6.4.Fire and Burns 6.1.1. Hot Work Permit acquire from TAL 6.1.2. Inspected and colour coded grinder (bull, baby and pencil) including all electrical extension cable 6.1.3. Only experienced and trained pipe-fitter/fabricators are required for the task 6.1.4. Use all the necessary PPE for grinding 6.1.5. No combustible material near the work place 6.1.6. Fire blanket or equivalent, fire extinguisher 6.2. Electrocution 6.2.1. Use all necessary requirements including PPE for the task 6.2.2. Use only approved extension cables with quarterly colour coding 6.2.3. Know the cable management (above 2 meters in high, with flagging, avoid contact to any electrical conductive materials)
  • 8. Use of Cutting of steel using Gas cutting machine 6.3. Fire and Burns 6.3.1. Hot Work Permit acquire from TAL 6.3.2. Oxy-acetylene Equipment Inspection checklist should be administer on site 6.3.3. Only experienced and trained pipe-fitter / Fabricators are required for the task 6.3.4. Use all the necessary PPE for gas cutting 6.3.5. No combustible material near the work place 6.3.6. Fire blanket or equivalent, fire extinguisher Welding Works 6.4. Fire and Burns and environmental Hazards 6.4.1. Inspected and colour coded welding equipment and cables 6.4.2. Only qualified welders is required for the task 6.4.3. Use all the necessary PPE for welding 6.4.4. No combustible material near the work place 6.4.5. No combustible material under the work place when working at heights 6.4.6. Fire blanket or equivalent, fire extinguisher 6.4.7. Provide bucket or can for welding rod butts and report to GAMA-HSE Department for documentation
  • 9. 7. Scaffolding Erection 7.1. Unsafe scaffolding, Hazard to fall 7.1.1. Scaffold must be erect as per standard/ client requirements 7.1.2. Scaffolding Foreman must prepare a STARRT Form before the erection of any more than 6 meters above 7.1.3. All Scaffolders should wear full body harness equipped with two (2) LANYARD (inspected and approved “colour coded”) 7.1.4. All Scaffolders must have a Fall Protection Training identification stick on their helmets General Instruction: More than four (4) meters high work must comply with the standard – Full body harness with shock absorber attached is required. Scaffolding as working platform 7.2. Hazard to fall 7.2.1. Wear fall protection 7.2.2. Inspection Tag signed and revalidate every week 7.2.3. Ensure the 100% tie off (double lanyard) Note: -All designed erected scaffoldings are in yellow tag which requires wearing full body harness double lanyard equipped with shock absorber. -Only Scaffolders are allowed to alter or rectify scaffolding) 8. Lifting and positioning of vessel, machine, or equipment to the foundation in a vertical or horizontal position and tightening of nuts 8.1. Uncontrolled lifting 8.1.1. Site review of Lifting Plan 8.1.2. General isolation (clear of any persons) of the area, swing radius, includes the area where vessel, equipment, or machine has to install. 8.1.3. Only assigned rigger to give signals to crane operator 8.1.4. No passing underneath the lifting structure, no holding / touching the lifting structure 8.1.5. Attach / use two tag lines to the bottom for controlling the load
  • 10. 9. Removal of lifting tackles to the top of the vessel by the use of Man lift – basket and or Mobile Man lifter 9.1. Hazard to fall, Falling hazards, Mobile man lift Tip over 9.1.1. Third party inspection is required both for Man Basket and Mobile Man lifter 9.1.2. Only trained or qualified personnel to operate, ride or use the lifter 9.1.3. Properly position the Mobile man lift to a stable ground level 9.1.4. Use Full Body Harness 9.1.5. FPT – Fall Protection Training requires 9.1.6. Use appropriate Tag lines (2) attached to the bottom for Man Basket control 9.1.7. Use approved crane 9.1.8. Proper anchorage in using man basket 9.1.9. Wear hand gloves 9.1.10. Secure / Tie all hand tools to prevent falling Use of Ladder as an access / ladder used to climb 9.2 Slip, Trip and Fall due to not 100% tie-off 9.2.1. Use Approved and inspected ladders, displaying the current quarterly colour code 9.2.2. Proper installation of ladders according to heights and first step/rung to be reach evenly. 9.2.3. Ladder must be 100 percent tied-off 9.2.4. Use (3) three points system, when climbing a ladders (hands are free from materials) 9.2.5. Additional materials required at heights should be lifted correctly (using ropes or crane lifts) 9.2.6. One worker at a time on climbing a ladder 9.2.7. 100 % tying in the rungs must be imposed on FPT and before climbing up 9.2.8. As an access to climb-assigned helper to hold the ladder on the ground 9.2.9. As an access to climb-Ladder must be immediately secure at the top
  • 11. 9.2.10. Ladder should stand only in a firm and balance position 9.2.11. Ladder must no position against moving structure 9.2.12. Do not throw materials from the top 9.2.13. Restriction (Barricade and safety sign boards) 10. Tandem Lift 10.1. Loss of control causing injury or property damage 10.1.1. TAL – STARRT Form application (critical work) 10.1.2. TAL-Permit applications 10.1.3. Approved Lifting Plan 10.1.4. Approved Rigging Plan 10.1.5. Mechanical Transport Supervisor or rigging supervisor to be present at all times to ensure correct and safe lifting 11. Demobilization 11.1. Work completion; Clutter/Rubbish 11.1.1. Workforce shall be alerted about the work completion 11.1.2. Removal of all woods, palettes, creates, and steel saddles used as a base support 11.1.3. Arrangement of all lifting tackles (shackles, slings, rope, etc.) 11.1.4. Good housekeeping practice shall be implemented throughout the day