Date 13-01-2018
Action 1. Joined WhatsApp’s chat group and shared Dropbox folder to collaborate
work with each other.
2. Created project website.
3. Drafted our initial Gantt chart.
Time Expected 2 hours
Time Taken 1.5 hours
Problems N/A
Solution N/A
Date 18-01-2018
Action Draft our initial use case diagram.
Time Expected 4 hours
Time Taken 3 hours
Problems N/A
Solution N/A
Date 19-01-2018
Action Drafted a copy of
1. Version Control
2. Project overview
3. Introduction
4. Project Introduction
Time Expected 2.5 hours
Time Taken 2 hours
Problems N/A
Solution N/A
Date 23-01-2018
Action 1. Suggested ways to improve on our project proposal on WhatsApp.
2. Edited my work on the project proposal to improve based on the
suggestions of other group members.
Time Expected 30 mins
Time Taken 1 hour
Problems N/A
Solution N/A
Date 24-01-2018
Action Created risk analysis and counter-measures plan.
Time Expected 3 hours
Time Taken 3.5 hours
Problems N/A
Solution N/A
Date 27-01-2018
Action Eliminated the project's highest-risk elements.
Time Expected 1 hours
Time Taken 30 mins
Problems N/A
Solution N/A
Date 28-01-2018
Action 1. Revise our risk list.
2. Create our business case.
Time Expected 3 hours
Time Taken 2 hours
Problems N/A
Solution N/A
Date 30-01-2018
Action Design 1st Iteration: State diagram and description table for elaboration phase.
Time Expected 3 hour
Time Taken 4 hours 15 mins
Problems N/A
Solution N/A
Date 07-02-2018
Action Design 2nd Iteration: State diagram and description table for elaboration
phase.
Time Expected 4 hour
Time Taken 4 hours 20 mins
Problems N/A
Solution N/A
Date 14-02-2018
Action Make some amendments to how RSA works into simple terms that anyone
could understand easily.
Time Expected 4 hour
Time Taken 5 hours
Problems N/A
Solution N/A
Date 12-03-2018
Action Make some amendments on our project website.
Time Expected 3 hours
Time Taken 2 hours
Problems Cheng Chao is absent as he is sick
Solution I am tasked to take over his sequence diagrams to make further improvements.
Date 15-03-2018
Action 1. Design 1st Iteration: Deployment Diagram (construction phase).
2. Design 1st Iteration: State Diagram (construction phase).
Time Expected 8 hours
Time Taken 10 hours
Problems N/A
Solution N/A
Date 18-03-2018
Action Change the website from HTTP to HTTPS to encrypt all the communication
messages between the visitors and website.
Time Expected 1 hour
Time Taken 30 mins
Problems N/A
Solution N/A
Date 21-03-2018
Action Make some amendments on state diagram and deployment diagram.
Time Expected 5.5 hours
Time Taken 4.5 hours
Problems N/A
Solution N/A
Date 23-03-2018
Action Improve on the website design.
Time Expected 5 hours
Time Taken 3.5 hours
Problems N/A
Solution N/A
Date 27-03-2018
Action Proofread all my work.
Time Expected 6 hours
Time Taken 4.5 hours
Problems N/A
Solution N/A
Date 28-03-2018
Action Create test plan design (compatibility testing, conformance testing).
Time Expected 4 hours
Time Taken 3 hours
Problems N/A
Solution N/A
Date 28-03-2018
Action Create functional testing for Bob.
Time Expected 4 hours
Time Taken 2 hours
Problems N/A
Solution N/A
Date 28-03-2018
Action Redesign the website layout.
Time Expected 2 hours
Time Taken 1 hour
Problems N/A
Solution N/A
Date 31-03-2018
Action Test our prototype in the group meeting to ensure the code works.
Time Expected 1 hour
Time Taken 2 hours
Problems N/A
Solution N/A
Date 10-04-2018
Action Prepare for prototype presentation.
Time Expected 1 hour
Time Taken 2 hours
Problems N/A
Solution N/A
Date 18-04-2018
Action 1. Design 2nd Iteration: Deployment Diagram (construction phase).
2. Design 2nd Iteration: State Diagram (construction phase).
Time Expected 4 hours
Time Taken 6 hours
Problems N/A
Solution N/A
Date 01-05-2018
Action Update test plan design (compatibility testing, conformance testing).
Time Expected 11 hours
Time Taken 12 hours
Problems N/A
Solution N/A
Date 01-05-2018
Action Finalize deployment diagram.
Time Expected 7 hr
Time Taken 8 hr 30 min
Problems N/A
Solution N/A
Date 01-05-2018
Action Update user manuals and SQL installation guide to website.
Time Expected 3 hours
Time Taken 4 hours
Problems N/A
Solution N/A
Date 02-05-2018
Action Update functional testing for Bob.
Time Expected 4 hours
Time Taken 5 hours
Problems N/A
Solution N/A
Date 03-05-2018
Action Finalize state diagram and description table.
Time Expected 7 hr
Time Taken 8 hr 30 min
Problems N/A
Solution N/A
Date 04-05-2018
Action Help out to take video for final demonstration.
Time Expected 2 hr
Time Taken 3 hr 30 min
Problems N/A
Solution N/A
Date 08-05-2018
Action Discuss about all the documents needed for final submission.
Time Expected 7 hr
Time Taken 8 hr
Problems N/A
Solution N/A
Date 08-05-2018
Action Update product features to project website.
Time Expected 1 hr
Time Taken 30 min
Problems N/A
Solution N/A
Date 09-05-2018
Action Update guide on installing SQL community server to project website.
Time Expected 1 hr
Time Taken 20 min
Problems N/A
Solution N/A
Date 09-05-2018
Action Put all my work done in Dropbox for compilation.
Time Expected 1 hr
Time Taken 2 hr
Problems N/A
Solution N/A
Date 10-05-2018
Action Update all the group members’ work diaries to project website.
Time Expected 30 mins
Time Taken 20 mins
Problems N/A
Solution N/A
Date 13-05-2018
Action Update demonstration video and mini clip to project website.
Time Expected 20 mins
Time Taken 10 mins
Problems N/A
Solution N/A
Date 16-05-2018
Action Final check on all documents prior to final submission.
Time Expected 8 hr
Time Taken 9 hr
Problems N/A
Solution N/A
Date 18-05-2018
Action Update report to project website.
Time Expected 30 mins
Time Taken 20 mins
Problems N/A
Solution N/A
Date 18-05-2018
Action Update all the download links on project website.
Time Expected 30 mins
Time Taken 20 mins
Problems N/A
Solution N/A
Date 19-05-2018
Action Submission of all the required documents.
Time Expected 3 hr
Time Taken 2 hr
Problems N/A
Solution N/A
Date 25-05-2018
Action Rehearsal for final presentation.
Time Expected 9 hr
Time Taken 8 hr
Problems N/A
Solution N/A
Date 31-05-2018
Action Final rehearsal for final presentation.
Time Expected 9 hr
Time Taken 9 hr
Problems N/A
Solution N/A

More Related Content

What's hot

Sharmila Telematics
Sharmila TelematicsSharmila Telematics
Sharmila Telematics
ramugus
 
Lab 11: Preparing Your SRL Report
Lab 11: Preparing Your SRL ReportLab 11: Preparing Your SRL Report
Lab 11: Preparing Your SRL Report
Mariel Miller
 

What's hot (11)

Using Checklists to Increase Consistency and Productivity in Communication Tasks
Using Checklists to Increase Consistency and Productivity in Communication TasksUsing Checklists to Increase Consistency and Productivity in Communication Tasks
Using Checklists to Increase Consistency and Productivity in Communication Tasks
 
Gpu portfolio
Gpu portfolioGpu portfolio
Gpu portfolio
 
Howe Street Basic Project Approach
Howe Street Basic Project ApproachHowe Street Basic Project Approach
Howe Street Basic Project Approach
 
202 - Lesson 10 - Feedback
202 - Lesson 10 - Feedback202 - Lesson 10 - Feedback
202 - Lesson 10 - Feedback
 
Sharmila Telematics
Sharmila TelematicsSharmila Telematics
Sharmila Telematics
 
Task Tracking in SharePoint
Task Tracking in SharePointTask Tracking in SharePoint
Task Tracking in SharePoint
 
Project Machine Shop
Project Machine ShopProject Machine Shop
Project Machine Shop
 
Lab 11: Preparing Your SRL Report
Lab 11: Preparing Your SRL ReportLab 11: Preparing Your SRL Report
Lab 11: Preparing Your SRL Report
 
How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?
 
4 - Updating Task Progress
4 - Updating Task Progress4 - Updating Task Progress
4 - Updating Task Progress
 
Design Preso #1
Design Preso #1Design Preso #1
Design Preso #1
 

Similar to BS - Project Work Diary

Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxHomework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
adampcarr67227
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
Captainsamcox
 
ID Task ModeTask Name Duration Start Finish Predecesso.docx
ID Task ModeTask Name Duration Start Finish Predecesso.docxID Task ModeTask Name Duration Start Finish Predecesso.docx
ID Task ModeTask Name Duration Start Finish Predecesso.docx
florriezhamphrey3065
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
Jatindra Malik
 
Development 011810
Development 011810 Development 011810
Development 011810
rohit3318
 
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 1 Week 14   Program Evaluation and Review Technique (PERT.docx 1 Week 14   Program Evaluation and Review Technique (PERT.docx
1 Week 14 Program Evaluation and Review Technique (PERT.docx
joyjonna282
 
DASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptxDASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptx
17542Saiteja
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
Deborah Obasogie
 

Similar to BS - Project Work Diary (20)

CC - Project Work Diary
CC - Project Work DiaryCC - Project Work Diary
CC - Project Work Diary
 
ZC - Project Work Diary
ZC - Project Work DiaryZC - Project Work Diary
ZC - Project Work Diary
 
ST - Project Work Diary
ST - Project Work DiaryST - Project Work Diary
ST - Project Work Diary
 
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxHomework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
 
ID Task ModeTask Name Duration Start Finish Predecesso.docx
ID Task ModeTask Name Duration Start Finish Predecesso.docxID Task ModeTask Name Duration Start Finish Predecesso.docx
ID Task ModeTask Name Duration Start Finish Predecesso.docx
 
Scrum discussion (1)
Scrum discussion (1)Scrum discussion (1)
Scrum discussion (1)
 
Reduction of Order Delivery Time of Goods.pdf
Reduction of Order Delivery Time of Goods.pdfReduction of Order Delivery Time of Goods.pdf
Reduction of Order Delivery Time of Goods.pdf
 
TEAM LEADERSHIP
TEAM LEADERSHIPTEAM LEADERSHIP
TEAM LEADERSHIP
 
Frappe Open Day - September 2018
Frappe Open Day - September 2018Frappe Open Day - September 2018
Frappe Open Day - September 2018
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Scrum and Agile: Experience growing from 2 to 15 people
Scrum and Agile: Experience growing from 2 to 15 peopleScrum and Agile: Experience growing from 2 to 15 people
Scrum and Agile: Experience growing from 2 to 15 people
 
MGMT2718 Human Resource Management.docx
MGMT2718 Human Resource Management.docxMGMT2718 Human Resource Management.docx
MGMT2718 Human Resource Management.docx
 
Fmp proposal
Fmp proposal Fmp proposal
Fmp proposal
 
Development 011810
Development 011810 Development 011810
Development 011810
 
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 1 Week 14   Program Evaluation and Review Technique (PERT.docx 1 Week 14   Program Evaluation and Review Technique (PERT.docx
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 
Bpm Camp Prashant Agile
Bpm Camp Prashant   AgileBpm Camp Prashant   Agile
Bpm Camp Prashant Agile
 
DASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptxDASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptx
 
Mech 202 Project 2 Report
Mech 202 Project 2 ReportMech 202 Project 2 Report
Mech 202 Project 2 Report
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 

Recently uploaded

會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
中 央社
 
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
中 央社
 

Recently uploaded (20)

TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 
Book Review of Run For Your Life Powerpoint
Book Review of Run For Your Life PowerpointBook Review of Run For Your Life Powerpoint
Book Review of Run For Your Life Powerpoint
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
 
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
 
Major project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesMajor project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategies
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopal
 
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
 
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
 
Mattingly "AI & Prompt Design: Named Entity Recognition"
Mattingly "AI & Prompt Design: Named Entity Recognition"Mattingly "AI & Prompt Design: Named Entity Recognition"
Mattingly "AI & Prompt Design: Named Entity Recognition"
 
Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"
 
Graduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxGraduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptx
 
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
 
Trauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesTrauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical Principles
 
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhĐề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
 
How to Send Pro Forma Invoice to Your Customers in Odoo 17
How to Send Pro Forma Invoice to Your Customers in Odoo 17How to Send Pro Forma Invoice to Your Customers in Odoo 17
How to Send Pro Forma Invoice to Your Customers in Odoo 17
 
An Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge AppAn Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge App
 
Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...
 
PSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptxPSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptx
 
8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management
 
male presentation...pdf.................
male presentation...pdf.................male presentation...pdf.................
male presentation...pdf.................
 

BS - Project Work Diary

  • 1. Date 13-01-2018 Action 1. Joined WhatsApp’s chat group and shared Dropbox folder to collaborate work with each other. 2. Created project website. 3. Drafted our initial Gantt chart. Time Expected 2 hours Time Taken 1.5 hours Problems N/A Solution N/A Date 18-01-2018 Action Draft our initial use case diagram. Time Expected 4 hours Time Taken 3 hours Problems N/A Solution N/A Date 19-01-2018 Action Drafted a copy of 1. Version Control 2. Project overview 3. Introduction 4. Project Introduction Time Expected 2.5 hours Time Taken 2 hours Problems N/A Solution N/A Date 23-01-2018 Action 1. Suggested ways to improve on our project proposal on WhatsApp. 2. Edited my work on the project proposal to improve based on the suggestions of other group members. Time Expected 30 mins Time Taken 1 hour Problems N/A Solution N/A Date 24-01-2018 Action Created risk analysis and counter-measures plan. Time Expected 3 hours Time Taken 3.5 hours Problems N/A Solution N/A Date 27-01-2018 Action Eliminated the project's highest-risk elements. Time Expected 1 hours Time Taken 30 mins
  • 2. Problems N/A Solution N/A Date 28-01-2018 Action 1. Revise our risk list. 2. Create our business case. Time Expected 3 hours Time Taken 2 hours Problems N/A Solution N/A Date 30-01-2018 Action Design 1st Iteration: State diagram and description table for elaboration phase. Time Expected 3 hour Time Taken 4 hours 15 mins Problems N/A Solution N/A Date 07-02-2018 Action Design 2nd Iteration: State diagram and description table for elaboration phase. Time Expected 4 hour Time Taken 4 hours 20 mins Problems N/A Solution N/A Date 14-02-2018 Action Make some amendments to how RSA works into simple terms that anyone could understand easily. Time Expected 4 hour Time Taken 5 hours Problems N/A Solution N/A Date 12-03-2018 Action Make some amendments on our project website. Time Expected 3 hours Time Taken 2 hours Problems Cheng Chao is absent as he is sick Solution I am tasked to take over his sequence diagrams to make further improvements. Date 15-03-2018 Action 1. Design 1st Iteration: Deployment Diagram (construction phase). 2. Design 1st Iteration: State Diagram (construction phase). Time Expected 8 hours Time Taken 10 hours Problems N/A Solution N/A
  • 3. Date 18-03-2018 Action Change the website from HTTP to HTTPS to encrypt all the communication messages between the visitors and website. Time Expected 1 hour Time Taken 30 mins Problems N/A Solution N/A Date 21-03-2018 Action Make some amendments on state diagram and deployment diagram. Time Expected 5.5 hours Time Taken 4.5 hours Problems N/A Solution N/A Date 23-03-2018 Action Improve on the website design. Time Expected 5 hours Time Taken 3.5 hours Problems N/A Solution N/A Date 27-03-2018 Action Proofread all my work. Time Expected 6 hours Time Taken 4.5 hours Problems N/A Solution N/A Date 28-03-2018 Action Create test plan design (compatibility testing, conformance testing). Time Expected 4 hours Time Taken 3 hours Problems N/A Solution N/A Date 28-03-2018 Action Create functional testing for Bob. Time Expected 4 hours Time Taken 2 hours Problems N/A Solution N/A Date 28-03-2018 Action Redesign the website layout. Time Expected 2 hours Time Taken 1 hour Problems N/A Solution N/A
  • 4. Date 31-03-2018 Action Test our prototype in the group meeting to ensure the code works. Time Expected 1 hour Time Taken 2 hours Problems N/A Solution N/A Date 10-04-2018 Action Prepare for prototype presentation. Time Expected 1 hour Time Taken 2 hours Problems N/A Solution N/A Date 18-04-2018 Action 1. Design 2nd Iteration: Deployment Diagram (construction phase). 2. Design 2nd Iteration: State Diagram (construction phase). Time Expected 4 hours Time Taken 6 hours Problems N/A Solution N/A Date 01-05-2018 Action Update test plan design (compatibility testing, conformance testing). Time Expected 11 hours Time Taken 12 hours Problems N/A Solution N/A Date 01-05-2018 Action Finalize deployment diagram. Time Expected 7 hr Time Taken 8 hr 30 min Problems N/A Solution N/A Date 01-05-2018 Action Update user manuals and SQL installation guide to website. Time Expected 3 hours Time Taken 4 hours Problems N/A Solution N/A
  • 5. Date 02-05-2018 Action Update functional testing for Bob. Time Expected 4 hours Time Taken 5 hours Problems N/A Solution N/A Date 03-05-2018 Action Finalize state diagram and description table. Time Expected 7 hr Time Taken 8 hr 30 min Problems N/A Solution N/A Date 04-05-2018 Action Help out to take video for final demonstration. Time Expected 2 hr Time Taken 3 hr 30 min Problems N/A Solution N/A Date 08-05-2018 Action Discuss about all the documents needed for final submission. Time Expected 7 hr Time Taken 8 hr Problems N/A Solution N/A Date 08-05-2018 Action Update product features to project website. Time Expected 1 hr Time Taken 30 min Problems N/A Solution N/A Date 09-05-2018 Action Update guide on installing SQL community server to project website. Time Expected 1 hr Time Taken 20 min Problems N/A Solution N/A Date 09-05-2018 Action Put all my work done in Dropbox for compilation. Time Expected 1 hr Time Taken 2 hr Problems N/A Solution N/A
  • 6. Date 10-05-2018 Action Update all the group members’ work diaries to project website. Time Expected 30 mins Time Taken 20 mins Problems N/A Solution N/A Date 13-05-2018 Action Update demonstration video and mini clip to project website. Time Expected 20 mins Time Taken 10 mins Problems N/A Solution N/A Date 16-05-2018 Action Final check on all documents prior to final submission. Time Expected 8 hr Time Taken 9 hr Problems N/A Solution N/A Date 18-05-2018 Action Update report to project website. Time Expected 30 mins Time Taken 20 mins Problems N/A Solution N/A Date 18-05-2018 Action Update all the download links on project website. Time Expected 30 mins Time Taken 20 mins Problems N/A Solution N/A Date 19-05-2018 Action Submission of all the required documents. Time Expected 3 hr Time Taken 2 hr Problems N/A Solution N/A
  • 7. Date 25-05-2018 Action Rehearsal for final presentation. Time Expected 9 hr Time Taken 8 hr Problems N/A Solution N/A Date 31-05-2018 Action Final rehearsal for final presentation. Time Expected 9 hr Time Taken 9 hr Problems N/A Solution N/A