Kosan Chrisplant var ”den nye dreng i klassen”, da de fik til opgave at udvikle og levere et produkt, der ikke var set før i Danmark: Et mere miljøvenligt og avanceret bunkering-anlæg til den nye gas-drevne Samsøfærge. Uden fortilfælde og standarder at skele til stillede projekt store krav til projektledelsen, stakeholder management og tæt samarbejde med bl.a. myndighederne. Hør erfaringerne og få inspiration til din projektledelse!
7. 7
• More than 2,500 plants/ larger
installations supplied since 1951
• Clients in more than 130
countries around the world,
covering large international
corporations, state-owned
enterprises, national oil and gas
companies and small and large
private businesses
Worldwide references
8. 8
Project Areas
LNG/LPG All ProSupply
The Kosan Crisplant Group is a project-oriented corporation that makes business within the LPG and
LNG/CNG industry. We supplies systems and turnkey plants for filling and maintenance of LPG
cylinders. We supply process technology, equipment and turnkey plants for LNG applications.
For both business areas, we offers after-sales and engineering services, facility management and
supply of components…….. and equal important; Know How & Know Why
24. 24
► 100% Self Sufficient with Renewable Energy
► Biomass and sunpanels for heating
► Free from Fossile Fuel in 2030
► Strong Back-up from Local Population
Samsø
29. 29
► Zero Emission
► Automatic
► Operated by only one person
► Fast
► Mobile plant
Points of difference
30. 30
► Market did not exist
► Product did not exist
► We had no experience
► Standards were not settled
= A certain degree of risk……..
Project Challenges
31. 31
► Design – Will it work ?
► Standards – Will we be able to have it approved ?
► Stakeholders – suppliers and authorities
Project Challenges
33. 33
Technical Challenges
► Gas is led back to the tank by thermal expansion
► Econimizers secure no emission during ”rest time”
► Pressure in tank remains under control
35. 35
Approvals
Storage:
50 – 200 T enviromental screening
> 200 T Full enviromental screening
Safety, fire etc: Local fire chief
Plant and installation: Ministry of works
Equipment:
ATEX: Electrical and pumps
PED: Piping and tanks
PED + ADR: Tank trailers
Design standards:
Various EU and National standards
36. 36
► Dedicated Client
► Dedicated Project Manager – willing to take responsibility
► Stakeholder Management - Teamwork
► No Counting of hours
► Constructive Approach from Authorities
Why did the Project Become a Success?
37. 37
► Project Manager is vital
► Externally: Communication and drive
► Internally: Secure back up from organisation
Learnings