SlideShare a Scribd company logo
1 of 4
Download to read offline
Kevin Brock, PE, PMP – Mechanical Engineer & Project Manager kevin.b.brock@gmail.com
Induced Draft Fan Project
Role: Project Manager
Responsibilities: Project evaluation, justification and charter development; created technical specifications for
bid; stakeholder engagement, contractor/equipment selection; installation & construction
management personnel oversight; project closeout & documentation.
Scope: The scope of this project included replacing the fan shafts, fan housings, shaft seals, outlet
dampers, inlet and outlet expansion joints, and, inspecting and refurbishing the fan wheels for
2 ID fans.
Background
and Conditions
Flue gas from the boiler is drawn through the SCRs and precipitators by the ID fans and then
pushed through the scrubber to the stack. The fans suffered considerable degradation due to
acid corrosion as a result of the formation and deposition of H2SO4 from the flue gas onto the
steel parts of the fans, aided by poor seal design and maintenance.
Statement of
Problem/Opportunity
The ID fan shafts were near the end of their useful life. The shaft diameters had degraded
over time and were close to the minimum allowed by the OEM guideline. The fan housings
were also degraded and patching had become more and more expensive. Operating guidelines
required operation of both ID fans when the unit is online, so if one fan failed the entire unit
would be offline until repairs were completed. It would take an estimated 12 weeks to replace
a fan shaft and repair casing damage resulting from a fan shaft failure. Such an event is also a
considerable safety concern.
Key Outcomes: Project was completed under budget providing a reliable system exceeding requirements.
Drawings & Pictures:
Figure 1: Project area during construction. Note the duct,
dampers, and fan housing have been replaced. Rotor is
staged to be installed in housing and insulation and lagging
has not started.
Figure 2: Installation of one of the fans into the housing.
The fan wheels were refurbished and pressed onto new
shafts. The assembly was then balanced in the shop and
sent to the site for installation in the housing.
Kevin Brock, PE, PMP – Mechanical Engineer & Project Manager kevin.b.brock@gmail.com
Main Steam Pipe Project
Role: Project Manager
Responsibilities: Project evaluation, justification and charter development; created technical specifications for
labor and material bids; stakeholder engagement, contractor selection; installation &
construction management personnel oversight; project closeout & documentation.
Scope: The scope of this project included inspecting the high energy pipe system & replacing 32 welds
in the main steam pipe system at a coal fired power plant.
Pipe specs:
27” (nominal OD) seam less alloy steel, SA335 P22, 4.375” min wall, 18.125” min ID
21” (nominal OD) seam less alloy steel, SA335 P22, 3.375” min wall, 14.125” min ID
Elbows:
Qty 2: 90o
– 36’ & Qty: 2 90o
, 21.00” (Nominal OD), Seamless Alloy Steel, SA234 WP22, 3.375”
min wall after fabrication, 14.00” min ID , 31.5” Radius, six inch additional tangent length
Background
and Conditions
Steam from the boiler flows to the turbine through the main steam pipe system. Steam
conditions are 1005 o
F at 2400 psia.
Statement of
Problem/Opportunity
During a previous outage 14 welds in the main steam pipe system were identified to be
cracked with depths on some at 1”. To repair this condition it was decided to cut spools out
around the known cracked welds and replace with new pipe sections. Also, during this outage
the remaining welds were inspected with numerous welds found in need of replacement,
which were all addressed.
Key Outcomes: Project was completed and cracked welds were replaced.
Drawings & Pictures:
Figure 1: Working on a section of pipe.
2 fitters working each end.
Figure 2: Some of the removed pipe
pieces staged for disposal.
Kevin Brock, PE, PMP – Mechanical Engineer & Project Manager kevin.b.brock@gmail.com
Limestone Handling Project
Role: Project Manager (assigned at construction mobilization)
Responsibilities: Installation & construction management personnel oversight; stakeholder engagement;
project closeout & documentation.
Scope: The scope of this project generally included adding: an emergency reclaim feeder/breaker
(frozen lump cracker); a 500 foot reclaim conveyor w/mag separator; rail unloading hoppers
and belt feeders; stockpile pile dischargers; and, diverter gates.
Background
and Conditions
Limestone delivered by truck and rail is stocked out to a stockpile. Stone is reclaimed with the
pile dischargers which feed parallel conveyors that move the store to the lime prep building
where it is further processed for use in the scrubbers. Plant operation rules require the
scrubbers be in service anytime the generating units are operating.
Statement of
Problem/Opportunity
The limestone reclaim equipment was original to the plant and had degraded over 35 years of
operation. The limestone the plant was receiving had changed from the original design
specification and the system was experiencing plugging and issues related to handling stone in
the cold (freezing stone and flash freezing in chutes and other equipment).
Key Outcomes: Project was completed under budget providing a reliable system exceeding requirements.
Drawings & Pictures:
Figure 1: New 500’ conveyor and gallery, with emergency reclaim feeder/breaker at lower left (orange)
Figure 2: New emergency reclaim feeder/breaker Figure 3: Installation of one of the new pile dischargers
Kevin Brock, PE, PMP – Mechanical Engineer & Project Manager kevin.b.brock@gmail.com
Crusher House Retrofit & Dust Mitigation
Role: Project Manager
Responsibilities: Project justification and charter development; stakeholder engagement, engineering services
selection; contractor/equipment selection; installation & construction management personnel
oversight; project closeout & documentation.
Scope: Replace head boxes, reline surge bin, replace dynamic vibratory feeders with brute force
vibratory feeders, replace ring-hammer mills with double roll crushers; replace alloy lined
chute with ceramic lined low-dust chute and spoon; replace and extend load zone, install
chemical dust suppression/wet flow promoter/deicing system.
Background
and Conditions
Coal is reclaimed from the yard hoppers and conveyed to a bin in the Crusher House by a
parallel conveyor system. The bin has dual outlets and each is equipped with a slide gate, a
72” wide vibrating grizzly feeder, and a ring hammer mill. The mills discharge to a chute
system with crossover that charges 36” wide conveyors “A” & “B”. The mills, feeders, chutes,
and load zones are obsolete, were designed for +4” Feed, and have been a source of dust. The
Crusher House is classified as Class II, Div II, Group F area.
Statement of
Problem/Opportunity
The Crusher House equipment has been in service for over 35 years and has processed over 80
million tons of coal. Maintenance costs have been increasing and OEM support (parts) is
decreasing. The Crusher House flow capacity is lower than the rest of the coal handling
system. The Crusher House has been identified as a high priority area for new capital
equipment to meet the OSHA national emphasis program for combustible dust.
Key Outcomes: Project was completed under budget providing a reliable system exceeding requirements
Drawings & Pictures:
Figure 1: Original Crusher House equipment Figure 2: Revised Crusher House equipment

More Related Content

What's hot (20)

Mohd Mustafa CV
Mohd Mustafa CV Mohd Mustafa CV
Mohd Mustafa CV
 
KDK RES 2016 Sunoco
KDK RES 2016 SunocoKDK RES 2016 Sunoco
KDK RES 2016 Sunoco
 
Ken Edgar CV
Ken Edgar CVKen Edgar CV
Ken Edgar CV
 
resume-garychu
resume-garychuresume-garychu
resume-garychu
 
PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14
 
SUDARSAN CAUSHIK CV
SUDARSAN CAUSHIK CVSUDARSAN CAUSHIK CV
SUDARSAN CAUSHIK CV
 
Mohd Mustafa CV.
Mohd Mustafa CV.Mohd Mustafa CV.
Mohd Mustafa CV.
 
Linkedin
LinkedinLinkedin
Linkedin
 
CV_Doug_Mast
CV_Doug_MastCV_Doug_Mast
CV_Doug_Mast
 
Ernesto Bojorquez Resume Jan. 07 2017
Ernesto Bojorquez Resume Jan. 07 2017Ernesto Bojorquez Resume Jan. 07 2017
Ernesto Bojorquez Resume Jan. 07 2017
 
Check out our Oil and Gas (Fuel Storage Tanks, LPG, LPG Bullets) Slide share ...
Check out our Oil and Gas (Fuel Storage Tanks, LPG, LPG Bullets) Slide share ...Check out our Oil and Gas (Fuel Storage Tanks, LPG, LPG Bullets) Slide share ...
Check out our Oil and Gas (Fuel Storage Tanks, LPG, LPG Bullets) Slide share ...
 
madhankumar new CV 2016 june...
madhankumar new CV 2016 june...madhankumar new CV 2016 june...
madhankumar new CV 2016 june...
 
Eschenburg Resume 1
Eschenburg  Resume 1Eschenburg  Resume 1
Eschenburg Resume 1
 
Roy Ong CV (2015)
Roy Ong CV (2015)Roy Ong CV (2015)
Roy Ong CV (2015)
 
Intern report
Intern reportIntern report
Intern report
 
THARANG A KUTTY
THARANG A KUTTYTHARANG A KUTTY
THARANG A KUTTY
 
Fielding Gary CV August 2015
Fielding Gary CV August 2015Fielding Gary CV August 2015
Fielding Gary CV August 2015
 
RESUME-Latest
RESUME-LatestRESUME-Latest
RESUME-Latest
 
Viswanath_AMD
Viswanath_AMDViswanath_AMD
Viswanath_AMD
 
larry_dosher opengr resume
larry_dosher opengr resumelarry_dosher opengr resume
larry_dosher opengr resume
 

Viewers also liked

Podcast ( diana campozano)
Podcast ( diana campozano)Podcast ( diana campozano)
Podcast ( diana campozano)dianacampozano
 
Creativity in Society
Creativity in SocietyCreativity in Society
Creativity in Societytrishcoxkcb1
 
Berbakti kpd ibu bapa
Berbakti kpd ibu bapaBerbakti kpd ibu bapa
Berbakti kpd ibu bapairwansetiu
 
"Using Blockchain Technology to Maintain OERs and IPs" by Sherry Jones (April...
"Using Blockchain Technology to Maintain OERs and IPs" by Sherry Jones (April..."Using Blockchain Technology to Maintain OERs and IPs" by Sherry Jones (April...
"Using Blockchain Technology to Maintain OERs and IPs" by Sherry Jones (April...Sherry Jones
 
Smart Home, Smart Engineering
Smart Home, Smart Engineering Smart Home, Smart Engineering
Smart Home, Smart Engineering Mistral Solutions
 
Prueba de portada
Prueba de portadaPrueba de portada
Prueba de portadapatricio
 
Grafico diario del dax perfomance index para el 10 04-2013
Grafico diario del dax perfomance index para el 10 04-2013Grafico diario del dax perfomance index para el 10 04-2013
Grafico diario del dax perfomance index para el 10 04-2013Experiencia Trading
 
Mobile App Test Strategy
Mobile App Test StrategyMobile App Test Strategy
Mobile App Test Strategykraqa
 
Quiz families march 2105 quiz
Quiz families march 2105 quizQuiz families march 2105 quiz
Quiz families march 2105 quizArun Anantharaman
 
Wang - A practical model for curricular integration of information literacy i...
Wang - A practical model for curricular integration of information literacy i...Wang - A practical model for curricular integration of information literacy i...
Wang - A practical model for curricular integration of information literacy i...IL Group (CILIP Information Literacy Group)
 
Figuras literarias
Figuras literariasFiguras literarias
Figuras literariasKaren Guerra
 
How to build brands and influence people
How to build brands and influence peopleHow to build brands and influence people
How to build brands and influence peoplemattsadler
 
Universidad nacional de chimborazo
Universidad nacional de chimborazoUniversidad nacional de chimborazo
Universidad nacional de chimborazoBanesa Ruiz
 
AUS_101 Syllabus, Spring 2009
AUS_101 Syllabus, Spring 2009AUS_101 Syllabus, Spring 2009
AUS_101 Syllabus, Spring 2009Dennis Lewis, PhD
 
Grafico diario del dax perfomance index para el 12 02-2013
Grafico diario del dax perfomance index para el 12 02-2013Grafico diario del dax perfomance index para el 12 02-2013
Grafico diario del dax perfomance index para el 12 02-2013Experiencia Trading
 
コイルのスパイスモデル
コイルのスパイスモデルコイルのスパイスモデル
コイルのスパイスモデルTsuyoshi Horigome
 
Twitter - potencjał narzędziowy
Twitter - potencjał narzędziowyTwitter - potencjał narzędziowy
Twitter - potencjał narzędziowySebastian Umiński
 
Chan presentation final
Chan presentation finalChan presentation final
Chan presentation finalDaniel Chan
 

Viewers also liked (20)

Podcast ( diana campozano)
Podcast ( diana campozano)Podcast ( diana campozano)
Podcast ( diana campozano)
 
Creativity in Society
Creativity in SocietyCreativity in Society
Creativity in Society
 
Berbakti kpd ibu bapa
Berbakti kpd ibu bapaBerbakti kpd ibu bapa
Berbakti kpd ibu bapa
 
"Using Blockchain Technology to Maintain OERs and IPs" by Sherry Jones (April...
"Using Blockchain Technology to Maintain OERs and IPs" by Sherry Jones (April..."Using Blockchain Technology to Maintain OERs and IPs" by Sherry Jones (April...
"Using Blockchain Technology to Maintain OERs and IPs" by Sherry Jones (April...
 
Smart Home, Smart Engineering
Smart Home, Smart Engineering Smart Home, Smart Engineering
Smart Home, Smart Engineering
 
Prueba de portada
Prueba de portadaPrueba de portada
Prueba de portada
 
Grafico diario del dax perfomance index para el 10 04-2013
Grafico diario del dax perfomance index para el 10 04-2013Grafico diario del dax perfomance index para el 10 04-2013
Grafico diario del dax perfomance index para el 10 04-2013
 
Recycle
Recycle Recycle
Recycle
 
Mobile App Test Strategy
Mobile App Test StrategyMobile App Test Strategy
Mobile App Test Strategy
 
Quiz families march 2105 quiz
Quiz families march 2105 quizQuiz families march 2105 quiz
Quiz families march 2105 quiz
 
POS_Slide_Show
POS_Slide_ShowPOS_Slide_Show
POS_Slide_Show
 
Wang - A practical model for curricular integration of information literacy i...
Wang - A practical model for curricular integration of information literacy i...Wang - A practical model for curricular integration of information literacy i...
Wang - A practical model for curricular integration of information literacy i...
 
Figuras literarias
Figuras literariasFiguras literarias
Figuras literarias
 
How to build brands and influence people
How to build brands and influence peopleHow to build brands and influence people
How to build brands and influence people
 
Universidad nacional de chimborazo
Universidad nacional de chimborazoUniversidad nacional de chimborazo
Universidad nacional de chimborazo
 
AUS_101 Syllabus, Spring 2009
AUS_101 Syllabus, Spring 2009AUS_101 Syllabus, Spring 2009
AUS_101 Syllabus, Spring 2009
 
Grafico diario del dax perfomance index para el 12 02-2013
Grafico diario del dax perfomance index para el 12 02-2013Grafico diario del dax perfomance index para el 12 02-2013
Grafico diario del dax perfomance index para el 12 02-2013
 
コイルのスパイスモデル
コイルのスパイスモデルコイルのスパイスモデル
コイルのスパイスモデル
 
Twitter - potencjał narzędziowy
Twitter - potencjał narzędziowyTwitter - potencjał narzędziowy
Twitter - potencjał narzędziowy
 
Chan presentation final
Chan presentation finalChan presentation final
Chan presentation final
 

Similar to 4 Projects

Rocky Prosper PMP - Project Manager - June 2015
Rocky Prosper PMP - Project Manager - June 2015Rocky Prosper PMP - Project Manager - June 2015
Rocky Prosper PMP - Project Manager - June 2015Rocky Prosper
 
Roger Berryment Resume 2
Roger Berryment Resume 2Roger Berryment Resume 2
Roger Berryment Resume 2Roger Berryment
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
Project Management of M&E works at a WwTW
Project Management of M&E works at a WwTWProject Management of M&E works at a WwTW
Project Management of M&E works at a WwTWftwg
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins ResumeRusty Adkins
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptxAmirShafiq25
 
N Miksic Resume 2016
N Miksic Resume 2016N Miksic Resume 2016
N Miksic Resume 2016Norm Miksic
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland
 
Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton
 
R.muthukumar piping design engineer.doc
R.muthukumar piping design engineer.docR.muthukumar piping design engineer.doc
R.muthukumar piping design engineer.docMuthukumar RajaGounder
 
WilliamHarkabusResume
WilliamHarkabusResumeWilliamHarkabusResume
WilliamHarkabusResumeBill Harkabus
 
MW Project Experience Updated 7-24-16
MW Project Experience Updated 7-24-16MW Project Experience Updated 7-24-16
MW Project Experience Updated 7-24-16Mark Williams
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaMichaelUberti
 
Lisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -newLisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -newlisa zhang
 
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveStorm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveFairfax County
 

Similar to 4 Projects (20)

Rocky Prosper PMP - Project Manager - June 2015
Rocky Prosper PMP - Project Manager - June 2015Rocky Prosper PMP - Project Manager - June 2015
Rocky Prosper PMP - Project Manager - June 2015
 
Roger Berryment Resume 2
Roger Berryment Resume 2Roger Berryment Resume 2
Roger Berryment Resume 2
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
Project Management of M&E works at a WwTW
Project Management of M&E works at a WwTWProject Management of M&E works at a WwTW
Project Management of M&E works at a WwTW
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins Resume
 
projects
projectsprojects
projects
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
Resume M McAbee
Resume M McAbeeResume M McAbee
Resume M McAbee
 
N Miksic Resume 2016
N Miksic Resume 2016N Miksic Resume 2016
N Miksic Resume 2016
 
Nazmy Markos
Nazmy MarkosNazmy Markos
Nazmy Markos
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015
 
Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton - CV December 2016
Cameron Punton - CV December 2016
 
R.muthukumar piping design engineer.doc
R.muthukumar piping design engineer.docR.muthukumar piping design engineer.doc
R.muthukumar piping design engineer.doc
 
Abstract
AbstractAbstract
Abstract
 
WilliamHarkabusResume
WilliamHarkabusResumeWilliamHarkabusResume
WilliamHarkabusResume
 
MW Project Experience Updated 7-24-16
MW Project Experience Updated 7-24-16MW Project Experience Updated 7-24-16
MW Project Experience Updated 7-24-16
 
wsa
wsawsa
wsa
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
Lisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -newLisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -new
 
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveStorm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
 

4 Projects

  • 1. Kevin Brock, PE, PMP – Mechanical Engineer & Project Manager kevin.b.brock@gmail.com Induced Draft Fan Project Role: Project Manager Responsibilities: Project evaluation, justification and charter development; created technical specifications for bid; stakeholder engagement, contractor/equipment selection; installation & construction management personnel oversight; project closeout & documentation. Scope: The scope of this project included replacing the fan shafts, fan housings, shaft seals, outlet dampers, inlet and outlet expansion joints, and, inspecting and refurbishing the fan wheels for 2 ID fans. Background and Conditions Flue gas from the boiler is drawn through the SCRs and precipitators by the ID fans and then pushed through the scrubber to the stack. The fans suffered considerable degradation due to acid corrosion as a result of the formation and deposition of H2SO4 from the flue gas onto the steel parts of the fans, aided by poor seal design and maintenance. Statement of Problem/Opportunity The ID fan shafts were near the end of their useful life. The shaft diameters had degraded over time and were close to the minimum allowed by the OEM guideline. The fan housings were also degraded and patching had become more and more expensive. Operating guidelines required operation of both ID fans when the unit is online, so if one fan failed the entire unit would be offline until repairs were completed. It would take an estimated 12 weeks to replace a fan shaft and repair casing damage resulting from a fan shaft failure. Such an event is also a considerable safety concern. Key Outcomes: Project was completed under budget providing a reliable system exceeding requirements. Drawings & Pictures: Figure 1: Project area during construction. Note the duct, dampers, and fan housing have been replaced. Rotor is staged to be installed in housing and insulation and lagging has not started. Figure 2: Installation of one of the fans into the housing. The fan wheels were refurbished and pressed onto new shafts. The assembly was then balanced in the shop and sent to the site for installation in the housing.
  • 2. Kevin Brock, PE, PMP – Mechanical Engineer & Project Manager kevin.b.brock@gmail.com Main Steam Pipe Project Role: Project Manager Responsibilities: Project evaluation, justification and charter development; created technical specifications for labor and material bids; stakeholder engagement, contractor selection; installation & construction management personnel oversight; project closeout & documentation. Scope: The scope of this project included inspecting the high energy pipe system & replacing 32 welds in the main steam pipe system at a coal fired power plant. Pipe specs: 27” (nominal OD) seam less alloy steel, SA335 P22, 4.375” min wall, 18.125” min ID 21” (nominal OD) seam less alloy steel, SA335 P22, 3.375” min wall, 14.125” min ID Elbows: Qty 2: 90o – 36’ & Qty: 2 90o , 21.00” (Nominal OD), Seamless Alloy Steel, SA234 WP22, 3.375” min wall after fabrication, 14.00” min ID , 31.5” Radius, six inch additional tangent length Background and Conditions Steam from the boiler flows to the turbine through the main steam pipe system. Steam conditions are 1005 o F at 2400 psia. Statement of Problem/Opportunity During a previous outage 14 welds in the main steam pipe system were identified to be cracked with depths on some at 1”. To repair this condition it was decided to cut spools out around the known cracked welds and replace with new pipe sections. Also, during this outage the remaining welds were inspected with numerous welds found in need of replacement, which were all addressed. Key Outcomes: Project was completed and cracked welds were replaced. Drawings & Pictures: Figure 1: Working on a section of pipe. 2 fitters working each end. Figure 2: Some of the removed pipe pieces staged for disposal.
  • 3. Kevin Brock, PE, PMP – Mechanical Engineer & Project Manager kevin.b.brock@gmail.com Limestone Handling Project Role: Project Manager (assigned at construction mobilization) Responsibilities: Installation & construction management personnel oversight; stakeholder engagement; project closeout & documentation. Scope: The scope of this project generally included adding: an emergency reclaim feeder/breaker (frozen lump cracker); a 500 foot reclaim conveyor w/mag separator; rail unloading hoppers and belt feeders; stockpile pile dischargers; and, diverter gates. Background and Conditions Limestone delivered by truck and rail is stocked out to a stockpile. Stone is reclaimed with the pile dischargers which feed parallel conveyors that move the store to the lime prep building where it is further processed for use in the scrubbers. Plant operation rules require the scrubbers be in service anytime the generating units are operating. Statement of Problem/Opportunity The limestone reclaim equipment was original to the plant and had degraded over 35 years of operation. The limestone the plant was receiving had changed from the original design specification and the system was experiencing plugging and issues related to handling stone in the cold (freezing stone and flash freezing in chutes and other equipment). Key Outcomes: Project was completed under budget providing a reliable system exceeding requirements. Drawings & Pictures: Figure 1: New 500’ conveyor and gallery, with emergency reclaim feeder/breaker at lower left (orange) Figure 2: New emergency reclaim feeder/breaker Figure 3: Installation of one of the new pile dischargers
  • 4. Kevin Brock, PE, PMP – Mechanical Engineer & Project Manager kevin.b.brock@gmail.com Crusher House Retrofit & Dust Mitigation Role: Project Manager Responsibilities: Project justification and charter development; stakeholder engagement, engineering services selection; contractor/equipment selection; installation & construction management personnel oversight; project closeout & documentation. Scope: Replace head boxes, reline surge bin, replace dynamic vibratory feeders with brute force vibratory feeders, replace ring-hammer mills with double roll crushers; replace alloy lined chute with ceramic lined low-dust chute and spoon; replace and extend load zone, install chemical dust suppression/wet flow promoter/deicing system. Background and Conditions Coal is reclaimed from the yard hoppers and conveyed to a bin in the Crusher House by a parallel conveyor system. The bin has dual outlets and each is equipped with a slide gate, a 72” wide vibrating grizzly feeder, and a ring hammer mill. The mills discharge to a chute system with crossover that charges 36” wide conveyors “A” & “B”. The mills, feeders, chutes, and load zones are obsolete, were designed for +4” Feed, and have been a source of dust. The Crusher House is classified as Class II, Div II, Group F area. Statement of Problem/Opportunity The Crusher House equipment has been in service for over 35 years and has processed over 80 million tons of coal. Maintenance costs have been increasing and OEM support (parts) is decreasing. The Crusher House flow capacity is lower than the rest of the coal handling system. The Crusher House has been identified as a high priority area for new capital equipment to meet the OSHA national emphasis program for combustible dust. Key Outcomes: Project was completed under budget providing a reliable system exceeding requirements Drawings & Pictures: Figure 1: Original Crusher House equipment Figure 2: Revised Crusher House equipment