Check out our Oil and Gas (Fuel Storage Tanks, LPG, LPG Bullets) Slide share presentation.
1.
2. RGE GROUP INCLUDES:
rg engineering inc – manufactures’s rep, general contractor
mec engineering inc – engineering, design, consulting, project management
laesa ltd – independent power producer, power plant developer and operator
with over 150 mw installed capacity
ABOUT US
1
TOTAL SOLUTIONS PROVIDER IN THE WATER, ENERGY AND UTILITIES SECTOR
FOUNDED IN 1982: 34 YEARS OF EXPERIENCE
140 EMPLOYEES INCLUDING 20 LICENSED ENGINEERS
3. RGE
2
ALFA LAVAL - CENTRIFUGES & PLATE HEAT EXCHANGERS
AREVA T&D/BASLER - PROTECTION RELAYS, PROTECTION RELAY PANELS, CONTROL PANELS, CAPACITOR BANKS,
REACTIVE COMPENSATION
BRENDFORD ENVIRONMENTAL - ON-LINE CLEANING MAJOR SEWER PIPE
BRADEN - GAS TURBINE DUCTWORK & ACCESSORIES
CHEMETRON FIRE - FIRE SUPPRESSION SYSTEMS
DOROT - WATER CONTROL VALVES
DIAMOND POWER - BOILER SOOT BLOWERS
EMERSON PROCESS CONTROL - INSTRUMENTATION & CONTROL SYSTEMS
GOVERNOR CONTROL - WOODWARD ENGINE & TURBINE CONTROL SYSTEMS
JACK HECKMAN TUBE CO. - BOILER PRESSURE PARTS
KSB PUMPS - INDUSTRIAL PUMPS
RV INDUSTRIES - COMBUSTION EQUIPMENT & PRESSURE VESSELS
RW HOLLAND - HAIRPIN & SHELL & TUBE HEAT EXCHANGER
SSS CLUTCH - MECHANICAL AND HYDRAULIC CLUTCHES
TECHNOS - CONDENSER CLEANING SYSTEMS
SERGI - TRANSFORMER FIRE PREVENTION SYSTEMS
SIEMENS ENERGY - TURBINES, GENERATOR, SUBSTATIONS, ELECTRICAL EQUIPMENT
SOUTHERN CATHODIC - CATHODIC PROTECTION SYSTEMS
TRAYER - SUBMERSIBLE VACUUM SWITCHES UP TO 15KV
TURBINE SERVICES - TURBINE PARTS AND SERVICES
VOITH TURBO - FLUID COUPLINGS, VARIABLE SPEED DRIVES, TORQUE CONVERTER
WARREN ENVIRONMENTAL - HIGH BUILT, SPECIALIZED COATINGS
WEG MOTORS - ELECTRIC MOTORS AND TRANSFORMERS
COMPANIES & MAJOR PRODUCTS
5. RGE
4
PROJECT INTEGRATION BY RGE
concept &
design
procurement &
construction
installation operation &
maintenance+ + +
SINGLE SOURCE RESPONSIBILITY FOR ALL ASPECTS OF FUEL OIL OR GAS
TERMINAL IMPLEMENTATION
MEC ENGINEERING - PERFORMS STUDIES, DESIGN, DRAWINGS AND PERMITS IN ORDER TO EXECUTE PROJECT.
RG ENGINEERING - PERFORMS EQUIPMENT SUPPLY, CONSTRUCTION, INSTALLATION AND TESTING OF THE
PROJECT.
RGE-MEC - REPRESENT VARIOUS INTERNATIONAL ENGINEERING FIRMS WHO WE JOINT VENTURE FOR SPECIALTY
PROJECTS AND WHICH COMPLEMENT OUR DESIGN CAPABILITIES.
6. RGE
5
SERVICES OFFERED
• DESIGN, FABRICATION AND ERECTION OF STORAGE TANKS.
• DESIGN, FABRICATION AND INSTALLATION OF PIPING SYSTEMS.
• DESIGN, FABRICATION AND ERECTION OF STEEL STRUCTURES.
• ENGINEERING, PROCUREMENT AND ERECTION OF DESALINATION UNITS.
• ENGINEERING, PROCUREMENT AND INSTALLATION OF EXHAUST PLENUMS.
• DESIGN, FABRICATION AND ERECTION OF INLET FILTER HOUSES FOR STEAM GENERATORS.
• DESIGN, FABRICATION, INSTALLATION AND COMMISSIONING OF FIRE PROTECTION SYSTEM
FOR FUEL TANK FARM.
• ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING AND OPERATION OF DEMIN
WATER TREATMENT SYSTEM.
INDISPUTABLE THE LARGEST POWER AND INDUSTRIAL CONTRACTOR ISLAND WIDE
PROVIDING SERVICES PRIMARY TO THE PUERTO RICO ELECTRIC POWER AUTHORITY
INCLUDING BUT NOT LIMITED TO:
8. RGE
7
OIL & GAS PROJECTS OVER LAST 5 YEARS
Client Scope Date
VIWAPA Cleaning &Inspection FO Storage Tanks 10-14 St Thomas PP Ongoing
VIWAPA Design Build Fire Protection System LPG Facilities at St Thomas PP Ongoing
PUMA Repair Three Fuel Oil Storage Tanks at St Croix Airport Ongoing
VITOL
Electrical & Instrumentation Construction 2 LPG Terminals, St. Thomas & St.
Croix
Ongoing
VITOL Piping & Mechanical Construction 2 LPG Terminals, St. Thomas and St. Croix Ongoing
PREPA Repair One 70’ dia x 48’ HFO Storage Tank at South Coast SP Ongoing
PREPA Repair Two 220’ dia x 48’ high HFP Storage Tank at South Coast SP Ongoing
PREPA Replacement 20" HFO Piping between Palo Seco & San Juan PP Ongoing
WAPA Cleaning & inspection of HFO Storage Tank #7 at St Croix PP 2015
PUMA Design Build LPG Fire Protection, Grounding & Lighting Systems 2015
PUMA Rehabilitation of Tank 502 2015
LORD Design Build LPG Phase II Fire Protection at Bayamon Terminal 2015
PUMA Rehabilitation of North LPG Bullets 2015
PUMA Rehabilitation of South LPG Bullets 2015
PREPA Design-Build Foam Fire Protection HFO Storage Tanks, South Coast SP 2015
PUMA Rehabilitation of Tank 80 2015
PREPA Design-Build Foam Fire Protection HFO Storage Tanks, Palo Seco SP 2014
LAESA Design Build Two HFO storage tanks at the Pimentel power plant 2013
PREPA Installation Double Containment HFO line from SJ Docks - San Juan SP 2013
PREPA Refurbishing of Palo Seco SP Fuel Oil Tank Farms 2013
OIL & GAS PROJECTS
9. RGE
8
OIL & GAS PROJECTS
OIL & GAS PROJECTS OVER LAST 5 YEARS (CONT.)
PREPA
Installation Double Containment diesel line from ESSO terminal - San Juan
SP
2013
PREPA Design, fabrication and erection of 80’-0” x 48’-0” Raw Water Tank 2012
Positronic
Industries
Design, fabrication and erection of 150,000 gallons water tank 2012
PREPA Refurbishing of San Juan SP Fuel Oil Tank Farms 2012
CBI Design Build Fire Protection System for Diesel Storage Tanks San Juan SP 2012
PREPA Design Build Fire Protection System for HFO Storage Tanks San Juan SP 2011
TAMRIO Design, fabrication and erection of 100,000 gallons water tank 2011
LAESA Design Build LNG Gas Terminal at Pimentel Power Plant 2011
JM Caribbean Design, fabrication and erection of 100,000 gallons water tank 2010
Coopervision Design, fabrication and erection of 150,000 gallons water tank 2010
PREPA Refurbishing of Mayaguez PP Fuel Oil Tank Farms 2010
PREPA Refurbishing of Mayaguez PP 110' Dia. Diesel Storage Tank 2010
Fluor Corp. Design, fabrication and erection of 50’-0” x 80’-0” Ash recovery tank 2010
CORCO Major refurbishments of storage tanks in CORCO’s tank farm 2010 -2014
PREPA Design Build Fire Protection System for HFO Storage Tanks Aguirre SP 2010
PEERLESS Major refurbishment storage tanks in Peerless Oil Chemicals Tank Farm 2010-2013
PREPA Design Build Oil Water Separation System San Juan Steam Plant 2010
PREPA Design Build Oil Water Separation System South Coast Steam Plant 2010
PREPA Refurbish HFO 80' Dia. Day Storage Tank South Coast SP 2010
10. RGE
9
OIL & GAS PROJECTS
PROJECT DESCRIPTION:
DESIGN, SUPPLY, INSTALL, SUPERVISE AND SET IN SERVICE. THIS PROCECT CONSISTS OF
INSTALLING TANKS, PIPING, CONTROL SYSTEMS, FIRE PROTECTION, TO PROVIDE THE VIRGIN
ISLAND WATER AND POWER AUTHORITY (VIWAPA) EXISTING GAS TURBINES WITH PROPANE
FUEL. PROPANE SUPPLIER, VITOL ENERGY, CONTRACTED OUR SERVICES FOR THE DESIGN,
SUPPLY, SUPERVISION AND PLACING IN SERVICE THE MECHANICAL AND ELECTRICAL
SYSTEMS OF BOTH LPG TERMINALS AT THE SAINT THOMAS AND SAINT CROIX POWER
PLANTS.
LOCATION: ST THOMAS & ST CROIX
CLIENT: VITOL
FUEL: PROPANE
CONTACT: FERRAS ALBAGARIN
LPG GAS TERMINAL USVI
EPC 6,480,000 Gal. Propane Fuel Terminal
Project Value US$24,000,000.00
11. RGE
10
PROJECT DESCRIPTION:
RGE WAS RESPONSIBLE FOR THE REFURBISHMENT OF 22 PROPANE VESSELS, SCOPE OF
WORK INCLUDES SURFACE PREPARATION AND COATING APPLICATION, REPLACEMENT OF
VESSEL NOZZLES, NBIC MAJOR REPAIRS, FIRE PROTECTION DESING, CONSTRUCTION AND
COMISSIONING, ACCESS PLATFORMS REPLACEMENT AND INSTALLATION OF EXPLOSION
PROOF LIGHTING SYSTEMS
LOCATION: BAYAMON puerto rico
CLIENT: PUMA ENERGY CARIBE
FUEL: PROPANE
CONTACT: JEFFREY KANTOR
PUMA LPG STORAGE TERMINAL
OIL & GAS PROJECTS
12. RGE
PROJECT DESCRIPTION:
ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMISSIONING OF LNG TERMINAL FOR A
110MW POWER PLANT AT THE DOMINICAN REPUBLIC.
NATURAL GAS PIMENTEL DOMINICAN REPUBLIC
LOCATION: PIMENTEL DR
CLIENT: LAESA ltd
FUEL: PROPANE
CONTACT: VINICIO QUEVEDO
OIL & GAS PROJECTS
11
13. RGE
PROJECT DESCRIPTION:
RGE ACTING AS EPCC CONTRACTOR PERFORMED THE NECESSARY ENGINEERING, PROCURED
THE APPROPIATE FIRE PROTECTION EQUIMENT, PERFORMED THE NECESSARY CONSTRUCTION
DUTIES AND COMMISSIONED A UNIQUE IN ITS KIND FIRE PROTECTION SYSTEM FOR ONE OF
THE LARGEST FUEL TERMINAL IN THE CARIBBEAN.
COSTA SUR POWER PLANT
FIRE PROTECTION SYSTEM
LOCATION: PUERTO RICO
CLIENT: AEE
SYSTEM: FOAM
OIL & GAS PROJECTS
12
14. RGE
PROJECT DESCRIPTION:
RGE CONTINUED AN IMPECABLE TRAJECTORY OF GOALS AND WAS AWARED BY PREPA TO
PROVIDE THE EPCC OF THE FIRE PROTECTION SYSTEM OF 900MW POWER PLANT. RGEC WAS
THE CONTRACTOR TO TRANSFORM THIS POWER PLANT FROM A NON COMPLIANT NFPA
FACILITY TO A FULLY COMPLIANT POWER PLANT.
SCOPE OF WORK INCLUDED EPCC OF THE ENTIRE FACILITY INCLUDING TANK FARM,
OPERATING UNITS SUCH AS BOILERS AND TURBINES.
AGUIRRE POWER PLANT
FIRE PROTECTION SYSTEM
OIL & GAS PROJECTS
LOCATION: PUERTO RICO
CLIENT: AEE
SYSTEM: FOAM
13
15. RGE
PROJECT DESCRIPTION:
VALIDATING RGE’S POSITION AS LEADER IN FIRE PROTECTION SYSTEMS PREPA AWARDED THE
DESIGN AND CONSTRUCTION OF FIRE PROTECTION SYSTEMS FOR FUEL STORAGE TANKS IN
PALO SECO OF CENTRAL ELECTRIC POWER AUTHORITY . THE SYSTEM INCLUDES PUMPS,
CONTROL ROOM , LINES FOR EACH FUEL TANK, FOAM CHAMBERS AND CONTROL SYSTEM
WITH ALARMS AND DETECTORS
PALO SECO POWER PLANT
FIRE PROTECTION SYSTEM
OIL & GAS PROJECTS
LOCATION: PUERTO RICO
CLIENT: AEE
SYSTEM: FOAM
14
16. RGE
PROJECT DESCRIPTION:
RGE WAS AWARDED DESIGN/BUILD PROJECTS TO PROVIDE FIRE PROTECTION SYSTEMS FOR
LPG TANKS AT PUMA’S BAYAMON LPG TERMINAL. SCOPE OF WORK INCLUDED DISTRIBUTION
HEADER, LINES TO EACH LPG TANK AND CONTROL SYSTEM WITH ALARMS AND DETECTORS.
PUMA ENERGY LPG TERMINAL
MECHANICAL DESIGN FOR DELUGE FIRE SUPRESSION SYSTEM
OIL & GAS PROJECTS
LOCATION: BAYAMON, PR
CLIENT: PUMA ENERGY
COMPLETION: 2013
15
21. RGECOMMERCIAL REFERENCES
BANCO RESERVAS
NAIMILY FERNÁNDEZ B.
EJECUTIVA DE NEGOCIOS
NEGOCIOS CORPORATIVOS
(809) 960-4415
(809) 547-5553 (fax)
SIEMENS INC.
BARRIO PALMAS INDUSTRIAL ZONE
HWY 869 KM 1.2
CATAÑO PR 00962
MR. OMAR ORTIZ
(787) 622-9293
SSS CLUTCH COMPANY
610 WEST BASIN ROAD
NEW CASTLE, DE 19720
MR. MORGAN L. HENDRY
(302) 322-8080
DIAMOND POWER INTERNATIONAL, INC.
2600 EAST MAIN STREET
PO BOX 415
LANCASTER, OHIO 43130-0415
MR. MICHAEL P. MICHAEL
(740) 687-4088
FIRST BANK
PO BOX 9146
SAN JUAN, PR 00908-0146
MRS. ENID BURGOS
(787) 247-9349
BANCO POPULAR DE PR
268 AVE MUÑOZ RIVERA
WESTERN BANK WORLD PLAZA
4TH FLOOR, OFFICE 402
HATO REY , PR 00918
MR. ANGEL MATOS (787) 754-9205
20
22. RGE
CONTACT
ROBERTO CAMINO roberto.camino@rgepr.com
LUIS FABRE luis.fabre@rgepr.com
JOSE ROBLES jose.robles@rgepr.com
RG ENGINEERING, INC.
605 condado street, suite 322
san juan, pr 00907
tel. (787) 723-4623
fax. (787) 721-6678
21