SlideShare a Scribd company logo
1 of 3
Download to read offline
ROCKY PROSPER, PMP
SR. PROJECT MANAGER
612 Holm Oak Lane, Mandeville, LA 70471
985-237-5393  rockyprosper@gmail.com
SUMMARY OF QUALIFICATION
Certified PMP with thirty-five years of project management, engineering / design, and construction experience on oil & gas,
petro-chemical and pipeline industry projects, with an emphasis on shut-in / turnaround planning / execution and the design,
construction and installation of offshore processing / treating facilities, compressor stations, subsea tie-backs and retro-fits.
Experienced in project and team development, capital cost estimates, planning, evaluations, contracts, turnkey execution
including detail design, construction, procurement, regulatory compliance, quality assurance, fabrication, and installations.
Developing and managing project scope, budget and schedule for teams of multi-discipline engineers and designers.
PROFESSIONAL EXPERIENCE
Audubon Engineering Company, Covington, LA, 2004 – 2015
Project Manager - Chevron (Relief / Vent System Gap Assessments)
 Responsible for project deliverables and client interface for approximately 20 offshore facilities with an average of
3,500 man / hours per facility.
 Responsibilities included the coordination of multiple project teams consisting of mechanical & process engineers
and designers, along with planning, scheduling, cost control and coordination of offshore field work.
 Project scope consisted of data acquisition, identifying data gaps, overpressure scenario analysis, field
verification, process modeling, relief calculations using iPRSM and HYSYS, flare / vent system evaluations and
generating gap mitigation reports.
Project Manager - Apache (Phase 2 SEMS Mitigation)
 Responsible for project deliverables and client interface for approximately 23 offshore facilities with an average of
1,500 man / hours per facility.
 Responsibilities included coordination of multiple project teams consisting of mechanical and process engineers
and detailed design of modifications. Also responsible for planning, scheduling, cost control and coordination of
offshore field work.
 Project scope consisted of field verification of SFDs and identification of relief system deficiencies, relief
calculations, developing instrument data sheets, flare / vent system analysis using Visual Flow, close out of
SEMS action items and developing construction work packages.
Project Manager - Chevron (ST151 Facility Upgrade)
 Responsible for project deliverables and client / construction interface.
 Responsibilities included the coordination of detailed process, mechanical, structural & electrical, instrumentation,
control systems engineering / design and field wide shut-in planning. Also managed planning, scheduling,
procurement support, cost control, construction management and coordination of sub-contractors.
 The $50M project scope included the multi-platform demolition / removal of a 45’ x 48’ x 20’ (110,000 ton) tank
and new design, construction & installation of a 45’ x 48’ structural pancake deck and skid packages (Electrostatic
Heater Treater, Water Skimmer, Good/Bad Oil Tank, Free Water Knock Out Drum, LACT Unit, Pumps),
Equipment RFQ packages, procurement & support and construction planning & support.
Project Manager - ERT (EC346 Facility Upgrade)
 Responsible for project deliverables and client / construction interface.
 Responsibilities included the coordination of mechanical, structural, electrical, instrumentation engineering,
detailed design and shut-in planning. Also managed planning, scheduling, procurement support, cost control,
construction management and coordination of sub-contractors.
 The project scope included new pipeline installation, modifying the existing topsides facility and installing two new
100 ton equipment modules to increase the oil production capacity by 25% to accommodate sub-sea production.
ROCKY PROSPER, PMP
Page 2
985-237-5393  rockyprosper@gmail.com
Project Manager - ERT (EC381 Subsea Tie-Back)
 Responsible for project deliverables and client / construction interface for the topsides facility subsea production
expansion.
 Responsibilities included the coordination of mechanical, structural, electrical, instrumentation engineering,
detailed design and shut-in planning. Also managed planning, scheduling, procurement support, cost control,
construction management and coordination of sub-contractors.
 The project scope included modifying the existing topsides facility and installing new subsea pipeline and topsides
equipment to increase the production capacity by 20% to accommodate production from the new sub-sea wells.
Project Manager - Rhodia (Boiler Re-tube)
 Responsible for planning, scheduling, procurement support, cost control, construction management and
coordination of sub-contractors for the boiler tubes replacement during the plant turnaround.
 The re-tube consisted of replacing 120 burnt out tubes in the sludge boiler where extensive confined space entry
and hot work was required to successfully complete the project. The boiler tubes were then hydro tested and
chemically cleaned prior to returning the unit into service.
 Project completed on schedule with no incidents.
Project Manager - Swift Energy (Field Acquisition Due Diligence)
 Responsible for field surveys and assessment reporting.
 The project consisted of assessing the equipment and condition of inland production barges and land locations for
12 production fields across south Louisiana.
 Scope included developing reports on equipment data, production capacities, regulatory deficiencies,
replacement cost and recommended upgrades.
Project Manager - Taylor Energy (Mississippi Canyon 21)
 Responsible for the shut-in planning, scheduling, procurement support, cost control, construction management
and coordination of the multi-phased facility conversion.
 The project scope included converting the existing MC-21B drilling platform into a production facility and flowing
all production through 8” & 10” pipelines to TEC SP-60F platform for final processing and metering. Upgrades
included the addition of HP & LP separators, surge vessel and booster & pipeline pumps to handle 22,000 BPD;
two 7 MMSCFD 1750HP 3 stage reciprocating gas compressors; two 125 kW generators & MCC building;
relocation of the existing test separator, pipelines and launchers, office/storage building & fuel gas skids and the
installation of new deck extensions.
 Construction, installation, relocation and demolition phases were organized to minimize SIMOPS impact to
operations and production down time.
Project Manager - Siemens US Filter (Moho Bilondo FPSO)
 Responsible for project deliverables and client / construction interface.
 Responsibilities included the coordination of mechanical, structural, electrical, instrumentation engineering and
detailed design for 10 sea water injection skid packages. Deliverables included package fabrication drawings,
pipe stress and structural analysis.
Construction Manager - Siemens US Filter (Bohai Bay - Conoco Phillips China)
 Responsible for construction deliverables and client interface.
 Responsibilities included planning, scheduling, material tracking and shipping of foreign & domestic equipment,
change order negotiations and overseeing the fabrication, assembly, factory acceptance testing and load out of 5
sea water injection skid packages; including a 106 ton 14’ OD x 90’ Vacuum Deaerator Tower, two 110 ton Fine
Filter skid packages with two 16’ OD filters on each, Coarse Filter skid, Air Scour Blower skid and Vacuum Pump
skid. The vessels and skid packages were fabricated and assembled at two locations in the Houston area.
Project Manager - Premier Industries (Morsa West – Angola Drilling)
 Responsible for project deliverables and client / construction interface.
 Responsibilities included the coordination of pressure vessel design, mechanical, structural, electrical,
instrumentation engineering, detailed design, planning, scheduling, change orders and cost control for 7 topsides
production skid packages.
 The packages consisted of a 10,000 BPD Production Separator, Test Separator and Export Pumps main process
module, Flare Knockout package, Hot Oil skid, De-gasser skid, Inlet Heater skid and 2 Chemical Injection skids.
ROCKY PROSPER, PMP
Page 3
985-237-5393  rockyprosper@gmail.com
Project Manager - Taylor Energy (South Pass 60F)
 Responsible for project deliverables and client / construction interface for complete production facility retrofit.
 Responsibilities included the coordination of mechanical, structural, electrical, instrumentation engineering,
detailed design and shut-in planning.
 The project scope included disassembly and salvage of the MC20 platform module, modification of the salvaged
production module, construction of a new office / lab building, slug catcher and pipeline manifold, installation of
the FC-150 temporary crane for the disassembly and heavy lift removal of 2 abandoned compressors from the
platform and modifications and tie-in’s to SPN Resources’ SP60 “C&B” facilities to receive production from 60F.
Project Manager - Helis Oil & Gas (Willow Cove)
 Responsible for turnkey design, construction and installation of the 2,000 BOPD / 5 MMSCFD / 3,000 BWPD
production facility barge, 15,000 barrel oil storage barge and pipelines located in the Atchafalaya basin in St.
Martin parish.
 Project scope included a 150’ x 240’ production barge complete with Line Heater, HP, LP & Test Separators, Oil
Heater Treaters, Gas Dehydration, Fuel Gas conditioning, Water Treating, VRU & Flash Gas Compressors,
Metering, control systems, Oil Storage barge, 4” Gas Sales Pipeline and 3” Produced Water Pipeline.
Project Manager - Shell SIEP-EPP (Deepwater Services) 1999 - 2003
 Shut-In planning coordinator for the Ursa, Mars, Ram Powell & Brutus TLP expansion projects.
 Responsible for coordinating the development of construction planning & scheduling for the overall shut-in execution .
 Responsibilities included interfacing with the expansion, field improvement, operations / surveillance and drilling
project teams, dealing with SIMOPS issues, temporary deck space planning, POB planning, transportation (marine &
air), contingency planning, and development of the shut-in execution manual.
 Helped develop and implement the “Construct the Limit” and detailed shut-in planning “Workshops” and after action
reviews. Developed many of the planning, tracking & status tools and systems now being used.
 Other assignments included: coordinator for the Brutus HSE audit team, management of the HSE audit punch list
database and coordinator for the “Topsides Work Process” development teams.
Design Project Manager - Texaco / Marathon (“Petronius” Deep Water Platform) 1996 - 1998
 Responsible for interfacing with engineering and coordinating / directing the 50 person design team through
preliminary layout and detailed design phases of the 60,000 BOPD / 100 MMSCFD topsides production facility
simultaneous design / build project.
 Responsibilities included setup of initial design criteria, monitoring, scheduling & reporting of budget man-hours,
finalizing designs through client reviews and construction deliverables.
 Construction interface between engineering / design and fabrication teams assisting in the resolution of conflicts and
design / fabrication interface issues.
Project Manager / Coordinator - Mobil Exploration & Producing, U.S. 1994 - 1995
 Responsible for turnkey engineering, detail design, construction and installation interface on numerous offshore
production facility upgrades, equipment retrofit projects and pipelines.
Construction Manager - Seawolf Services 1992 - 1993
 Responsible for the design and construction of numerous offshore production equipment skid packages and platform
retrofit projects.
President/General Manager - Advanced Design Technologies 1989 - 1991
 Responsible for all business operations, project management, engineering, design, construction, installation and client
interface of offshore production facility upgrades and equipment retrofit projects.
Project Manager - Continental Engineering 1985 - 1988
 Responsible for engineering, design, construction and installation interface on all offshore production facility
upgrades, equipment retrofits and pipeline projects.
EDUCATION & CERTIFICATIONS
Project Management Professional (PMP), Certified through Project Management Institute (PMI), 2015
University of Southwestern Louisiana - Studies in Industrial Technology
SW La Vocational Technical School – Drafting Design

More Related Content

What's hot

Resume Thad Gilbert
Resume Thad GilbertResume Thad Gilbert
Resume Thad GilbertThad Gilbert
 
Philip Karow_FinalResumeJL
Philip Karow_FinalResumeJLPhilip Karow_FinalResumeJL
Philip Karow_FinalResumeJLPhil Karow
 
Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)kevin breiter
 
Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)Ken Peartree
 
Projects CV January 2016
Projects CV January 2016Projects CV January 2016
Projects CV January 2016Bryan Johnson
 
Current Fluor Resume
Current Fluor ResumeCurrent Fluor Resume
Current Fluor ResumeRoy Firtha
 
PERSONAL EXPERIENCE RECORD-2015
PERSONAL EXPERIENCE RECORD-2015PERSONAL EXPERIENCE RECORD-2015
PERSONAL EXPERIENCE RECORD-2015gufron gufron
 
Bert Savoie Resume
Bert Savoie ResumeBert Savoie Resume
Bert Savoie ResumeBert Savoie
 
Andrew Duff 2016r24_NR
Andrew Duff 2016r24_NRAndrew Duff 2016r24_NR
Andrew Duff 2016r24_NRAndrew Duff
 
Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton
 
Tarek Ewiss Resume- to date 2016 1
Tarek Ewiss Resume- to date 2016 1Tarek Ewiss Resume- to date 2016 1
Tarek Ewiss Resume- to date 2016 1Tarek Ewiss
 
SVResume -Lead Mch Enginer June16
SVResume -Lead Mch Enginer June16SVResume -Lead Mch Enginer June16
SVResume -Lead Mch Enginer June16Sudhakar Vallala
 
abhinav rawat resume
abhinav rawat resumeabhinav rawat resume
abhinav rawat resumeAbhinav Rawat
 

What's hot (20)

Resume Thad Gilbert
Resume Thad GilbertResume Thad Gilbert
Resume Thad Gilbert
 
Philip Karow_FinalResumeJL
Philip Karow_FinalResumeJLPhilip Karow_FinalResumeJL
Philip Karow_FinalResumeJL
 
Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)
 
Darrell Resume2014
Darrell Resume2014Darrell Resume2014
Darrell Resume2014
 
Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)
 
Topside
TopsideTopside
Topside
 
Projects CV January 2016
Projects CV January 2016Projects CV January 2016
Projects CV January 2016
 
Current Fluor Resume
Current Fluor ResumeCurrent Fluor Resume
Current Fluor Resume
 
PERSONAL EXPERIENCE RECORD-2015
PERSONAL EXPERIENCE RECORD-2015PERSONAL EXPERIENCE RECORD-2015
PERSONAL EXPERIENCE RECORD-2015
 
CV-2015 Rev 0
CV-2015 Rev 0CV-2015 Rev 0
CV-2015 Rev 0
 
Bert Savoie Resume
Bert Savoie ResumeBert Savoie Resume
Bert Savoie Resume
 
Andrew Duff 2016r24_NR
Andrew Duff 2016r24_NRAndrew Duff 2016r24_NR
Andrew Duff 2016r24_NR
 
Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton - CV December 2016
Cameron Punton - CV December 2016
 
Tarek Ewiss Resume- to date 2016 1
Tarek Ewiss Resume- to date 2016 1Tarek Ewiss Resume- to date 2016 1
Tarek Ewiss Resume- to date 2016 1
 
CV.
CV.CV.
CV.
 
Ronald-Smith
Ronald-SmithRonald-Smith
Ronald-Smith
 
Prudhivi__Rushi_CV
Prudhivi__Rushi_CVPrudhivi__Rushi_CV
Prudhivi__Rushi_CV
 
SVResume -Lead Mch Enginer June16
SVResume -Lead Mch Enginer June16SVResume -Lead Mch Enginer June16
SVResume -Lead Mch Enginer June16
 
CV of KP Tomy
CV of KP TomyCV of KP Tomy
CV of KP Tomy
 
abhinav rawat resume
abhinav rawat resumeabhinav rawat resume
abhinav rawat resume
 

Similar to Rocky Prosper PMP - Project Manager - June 2015

1. Melissa Fagan 2017 - Geosyntec
1. Melissa Fagan 2017 - Geosyntec1. Melissa Fagan 2017 - Geosyntec
1. Melissa Fagan 2017 - GeosyntecMelissa Fagan, P.E.
 
James Council Resume
James Council ResumeJames Council Resume
James Council ResumeJamescc
 
Roger Berryment Resume 2
Roger Berryment Resume 2Roger Berryment Resume 2
Roger Berryment Resume 2Roger Berryment
 
LOU NICKSIC - Industrial - Oil and Gas Resume 041116
LOU NICKSIC - Industrial - Oil and Gas Resume  041116LOU NICKSIC - Industrial - Oil and Gas Resume  041116
LOU NICKSIC - Industrial - Oil and Gas Resume 041116Lou Nicksic
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATRommel Siasat
 
SKHOWARD Resume 9-17-16
SKHOWARD Resume 9-17-16SKHOWARD Resume 9-17-16
SKHOWARD Resume 9-17-16Kevin Howard
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302Rhod Mayers
 
B Levitt Resume 03_16_2
B Levitt Resume 03_16_2B Levitt Resume 03_16_2
B Levitt Resume 03_16_2Brian Levitt
 
Dale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli
 
Venkat updated resume Latest 11-01-16
Venkat updated resume Latest 11-01-16Venkat updated resume Latest 11-01-16
Venkat updated resume Latest 11-01-16Venkatesh Rajendran
 
Sam's current resume-2
Sam's current resume-2Sam's current resume-2
Sam's current resume-2Sam Marino
 
Sam's current resume-2
Sam's current resume-2Sam's current resume-2
Sam's current resume-2Sam Marino
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins ResumeRusty Adkins
 

Similar to Rocky Prosper PMP - Project Manager - June 2015 (20)

1. Melissa Fagan 2017 - Geosyntec
1. Melissa Fagan 2017 - Geosyntec1. Melissa Fagan 2017 - Geosyntec
1. Melissa Fagan 2017 - Geosyntec
 
James Council Resume
James Council ResumeJames Council Resume
James Council Resume
 
Roger Berryment Resume
Roger Berryment ResumeRoger Berryment Resume
Roger Berryment Resume
 
Roger Berryment Resume 2
Roger Berryment Resume 2Roger Berryment Resume 2
Roger Berryment Resume 2
 
LOU NICKSIC - Industrial - Oil and Gas Resume 041116
LOU NICKSIC - Industrial - Oil and Gas Resume  041116LOU NICKSIC - Industrial - Oil and Gas Resume  041116
LOU NICKSIC - Industrial - Oil and Gas Resume 041116
 
CV of broosto -7-2016
CV of broosto -7-2016CV of broosto -7-2016
CV of broosto -7-2016
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
 
SKHOWARD Resume 9-17-16
SKHOWARD Resume 9-17-16SKHOWARD Resume 9-17-16
SKHOWARD Resume 9-17-16
 
Trdrag 04 13 16
Trdrag 04 13 16Trdrag 04 13 16
Trdrag 04 13 16
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302
 
KANNAN RESUME
KANNAN RESUMEKANNAN RESUME
KANNAN RESUME
 
B Levitt Resume 03_16_2
B Levitt Resume 03_16_2B Levitt Resume 03_16_2
B Levitt Resume 03_16_2
 
Salman Resume 2016
Salman Resume  2016Salman Resume  2016
Salman Resume 2016
 
yousef_cv_mk
yousef_cv_mk yousef_cv_mk
yousef_cv_mk
 
Dale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli Resume
Dale Buzzelli Resume
 
Venkat updated resume Latest 11-01-16
Venkat updated resume Latest 11-01-16Venkat updated resume Latest 11-01-16
Venkat updated resume Latest 11-01-16
 
Sam's current resume-2
Sam's current resume-2Sam's current resume-2
Sam's current resume-2
 
Sam's current resume-2
Sam's current resume-2Sam's current resume-2
Sam's current resume-2
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins Resume
 
Ahmed Elsonbaty Resume Oct_2016
Ahmed Elsonbaty Resume Oct_2016Ahmed Elsonbaty Resume Oct_2016
Ahmed Elsonbaty Resume Oct_2016
 

Rocky Prosper PMP - Project Manager - June 2015

  • 1. ROCKY PROSPER, PMP SR. PROJECT MANAGER 612 Holm Oak Lane, Mandeville, LA 70471 985-237-5393  rockyprosper@gmail.com SUMMARY OF QUALIFICATION Certified PMP with thirty-five years of project management, engineering / design, and construction experience on oil & gas, petro-chemical and pipeline industry projects, with an emphasis on shut-in / turnaround planning / execution and the design, construction and installation of offshore processing / treating facilities, compressor stations, subsea tie-backs and retro-fits. Experienced in project and team development, capital cost estimates, planning, evaluations, contracts, turnkey execution including detail design, construction, procurement, regulatory compliance, quality assurance, fabrication, and installations. Developing and managing project scope, budget and schedule for teams of multi-discipline engineers and designers. PROFESSIONAL EXPERIENCE Audubon Engineering Company, Covington, LA, 2004 – 2015 Project Manager - Chevron (Relief / Vent System Gap Assessments)  Responsible for project deliverables and client interface for approximately 20 offshore facilities with an average of 3,500 man / hours per facility.  Responsibilities included the coordination of multiple project teams consisting of mechanical & process engineers and designers, along with planning, scheduling, cost control and coordination of offshore field work.  Project scope consisted of data acquisition, identifying data gaps, overpressure scenario analysis, field verification, process modeling, relief calculations using iPRSM and HYSYS, flare / vent system evaluations and generating gap mitigation reports. Project Manager - Apache (Phase 2 SEMS Mitigation)  Responsible for project deliverables and client interface for approximately 23 offshore facilities with an average of 1,500 man / hours per facility.  Responsibilities included coordination of multiple project teams consisting of mechanical and process engineers and detailed design of modifications. Also responsible for planning, scheduling, cost control and coordination of offshore field work.  Project scope consisted of field verification of SFDs and identification of relief system deficiencies, relief calculations, developing instrument data sheets, flare / vent system analysis using Visual Flow, close out of SEMS action items and developing construction work packages. Project Manager - Chevron (ST151 Facility Upgrade)  Responsible for project deliverables and client / construction interface.  Responsibilities included the coordination of detailed process, mechanical, structural & electrical, instrumentation, control systems engineering / design and field wide shut-in planning. Also managed planning, scheduling, procurement support, cost control, construction management and coordination of sub-contractors.  The $50M project scope included the multi-platform demolition / removal of a 45’ x 48’ x 20’ (110,000 ton) tank and new design, construction & installation of a 45’ x 48’ structural pancake deck and skid packages (Electrostatic Heater Treater, Water Skimmer, Good/Bad Oil Tank, Free Water Knock Out Drum, LACT Unit, Pumps), Equipment RFQ packages, procurement & support and construction planning & support. Project Manager - ERT (EC346 Facility Upgrade)  Responsible for project deliverables and client / construction interface.  Responsibilities included the coordination of mechanical, structural, electrical, instrumentation engineering, detailed design and shut-in planning. Also managed planning, scheduling, procurement support, cost control, construction management and coordination of sub-contractors.  The project scope included new pipeline installation, modifying the existing topsides facility and installing two new 100 ton equipment modules to increase the oil production capacity by 25% to accommodate sub-sea production.
  • 2. ROCKY PROSPER, PMP Page 2 985-237-5393  rockyprosper@gmail.com Project Manager - ERT (EC381 Subsea Tie-Back)  Responsible for project deliverables and client / construction interface for the topsides facility subsea production expansion.  Responsibilities included the coordination of mechanical, structural, electrical, instrumentation engineering, detailed design and shut-in planning. Also managed planning, scheduling, procurement support, cost control, construction management and coordination of sub-contractors.  The project scope included modifying the existing topsides facility and installing new subsea pipeline and topsides equipment to increase the production capacity by 20% to accommodate production from the new sub-sea wells. Project Manager - Rhodia (Boiler Re-tube)  Responsible for planning, scheduling, procurement support, cost control, construction management and coordination of sub-contractors for the boiler tubes replacement during the plant turnaround.  The re-tube consisted of replacing 120 burnt out tubes in the sludge boiler where extensive confined space entry and hot work was required to successfully complete the project. The boiler tubes were then hydro tested and chemically cleaned prior to returning the unit into service.  Project completed on schedule with no incidents. Project Manager - Swift Energy (Field Acquisition Due Diligence)  Responsible for field surveys and assessment reporting.  The project consisted of assessing the equipment and condition of inland production barges and land locations for 12 production fields across south Louisiana.  Scope included developing reports on equipment data, production capacities, regulatory deficiencies, replacement cost and recommended upgrades. Project Manager - Taylor Energy (Mississippi Canyon 21)  Responsible for the shut-in planning, scheduling, procurement support, cost control, construction management and coordination of the multi-phased facility conversion.  The project scope included converting the existing MC-21B drilling platform into a production facility and flowing all production through 8” & 10” pipelines to TEC SP-60F platform for final processing and metering. Upgrades included the addition of HP & LP separators, surge vessel and booster & pipeline pumps to handle 22,000 BPD; two 7 MMSCFD 1750HP 3 stage reciprocating gas compressors; two 125 kW generators & MCC building; relocation of the existing test separator, pipelines and launchers, office/storage building & fuel gas skids and the installation of new deck extensions.  Construction, installation, relocation and demolition phases were organized to minimize SIMOPS impact to operations and production down time. Project Manager - Siemens US Filter (Moho Bilondo FPSO)  Responsible for project deliverables and client / construction interface.  Responsibilities included the coordination of mechanical, structural, electrical, instrumentation engineering and detailed design for 10 sea water injection skid packages. Deliverables included package fabrication drawings, pipe stress and structural analysis. Construction Manager - Siemens US Filter (Bohai Bay - Conoco Phillips China)  Responsible for construction deliverables and client interface.  Responsibilities included planning, scheduling, material tracking and shipping of foreign & domestic equipment, change order negotiations and overseeing the fabrication, assembly, factory acceptance testing and load out of 5 sea water injection skid packages; including a 106 ton 14’ OD x 90’ Vacuum Deaerator Tower, two 110 ton Fine Filter skid packages with two 16’ OD filters on each, Coarse Filter skid, Air Scour Blower skid and Vacuum Pump skid. The vessels and skid packages were fabricated and assembled at two locations in the Houston area. Project Manager - Premier Industries (Morsa West – Angola Drilling)  Responsible for project deliverables and client / construction interface.  Responsibilities included the coordination of pressure vessel design, mechanical, structural, electrical, instrumentation engineering, detailed design, planning, scheduling, change orders and cost control for 7 topsides production skid packages.  The packages consisted of a 10,000 BPD Production Separator, Test Separator and Export Pumps main process module, Flare Knockout package, Hot Oil skid, De-gasser skid, Inlet Heater skid and 2 Chemical Injection skids.
  • 3. ROCKY PROSPER, PMP Page 3 985-237-5393  rockyprosper@gmail.com Project Manager - Taylor Energy (South Pass 60F)  Responsible for project deliverables and client / construction interface for complete production facility retrofit.  Responsibilities included the coordination of mechanical, structural, electrical, instrumentation engineering, detailed design and shut-in planning.  The project scope included disassembly and salvage of the MC20 platform module, modification of the salvaged production module, construction of a new office / lab building, slug catcher and pipeline manifold, installation of the FC-150 temporary crane for the disassembly and heavy lift removal of 2 abandoned compressors from the platform and modifications and tie-in’s to SPN Resources’ SP60 “C&B” facilities to receive production from 60F. Project Manager - Helis Oil & Gas (Willow Cove)  Responsible for turnkey design, construction and installation of the 2,000 BOPD / 5 MMSCFD / 3,000 BWPD production facility barge, 15,000 barrel oil storage barge and pipelines located in the Atchafalaya basin in St. Martin parish.  Project scope included a 150’ x 240’ production barge complete with Line Heater, HP, LP & Test Separators, Oil Heater Treaters, Gas Dehydration, Fuel Gas conditioning, Water Treating, VRU & Flash Gas Compressors, Metering, control systems, Oil Storage barge, 4” Gas Sales Pipeline and 3” Produced Water Pipeline. Project Manager - Shell SIEP-EPP (Deepwater Services) 1999 - 2003  Shut-In planning coordinator for the Ursa, Mars, Ram Powell & Brutus TLP expansion projects.  Responsible for coordinating the development of construction planning & scheduling for the overall shut-in execution .  Responsibilities included interfacing with the expansion, field improvement, operations / surveillance and drilling project teams, dealing with SIMOPS issues, temporary deck space planning, POB planning, transportation (marine & air), contingency planning, and development of the shut-in execution manual.  Helped develop and implement the “Construct the Limit” and detailed shut-in planning “Workshops” and after action reviews. Developed many of the planning, tracking & status tools and systems now being used.  Other assignments included: coordinator for the Brutus HSE audit team, management of the HSE audit punch list database and coordinator for the “Topsides Work Process” development teams. Design Project Manager - Texaco / Marathon (“Petronius” Deep Water Platform) 1996 - 1998  Responsible for interfacing with engineering and coordinating / directing the 50 person design team through preliminary layout and detailed design phases of the 60,000 BOPD / 100 MMSCFD topsides production facility simultaneous design / build project.  Responsibilities included setup of initial design criteria, monitoring, scheduling & reporting of budget man-hours, finalizing designs through client reviews and construction deliverables.  Construction interface between engineering / design and fabrication teams assisting in the resolution of conflicts and design / fabrication interface issues. Project Manager / Coordinator - Mobil Exploration & Producing, U.S. 1994 - 1995  Responsible for turnkey engineering, detail design, construction and installation interface on numerous offshore production facility upgrades, equipment retrofit projects and pipelines. Construction Manager - Seawolf Services 1992 - 1993  Responsible for the design and construction of numerous offshore production equipment skid packages and platform retrofit projects. President/General Manager - Advanced Design Technologies 1989 - 1991  Responsible for all business operations, project management, engineering, design, construction, installation and client interface of offshore production facility upgrades and equipment retrofit projects. Project Manager - Continental Engineering 1985 - 1988  Responsible for engineering, design, construction and installation interface on all offshore production facility upgrades, equipment retrofits and pipeline projects. EDUCATION & CERTIFICATIONS Project Management Professional (PMP), Certified through Project Management Institute (PMI), 2015 University of Southwestern Louisiana - Studies in Industrial Technology SW La Vocational Technical School – Drafting Design