B E C K I N S O N ’ S
Creating predictable outcomes
for complex shutdowns,
critical projects
and revamps
Ken Beckemeyer, Consultant/President—47 years managing
major FCCU, delayed coker revamps and turnarounds with exten-
sive experience in project management, constructability studies,
planning/scheduling, heavy lifting and rigging.
James Robinson, Consultant/Vice President—provides develop-
ment and coordination of estimating, planning and cost controls for
critical path projects. His experience lies in the three major sectors of
the petroleum industry including upstream, midstream and down-
stream.
Whitney Strickland, Consultant/Partner—began as a field crafts-
man in a refinery 32 years ago and has since managed/consulted or
invested in a number of successful petrochemical service compa-
nies including those specializing in safety, turnaround execution,
welding, tower and refractory services as well as planning, schedul-
ing and cost estimating.
Russell Hillenburg, Consultant/Partner—a third-generation
shop-fabrication business owner specializing in reactor and tower
internals. He is not only fabrication-savvy but also possesses good
project/personnel management and problem-solving skills.
Chad Beckemeyer, Consultant/Vice President—over 16 years of
experience in project management, project controls, scheduling,
estimating and field supervision of craftsman on major projects
such as FCCU and delayed coker revamps as well as major expan-
sions in other industries.
Beckinson Team Leaders
Phases
of Project
Constructability
12320 Barker Cypress Road, Suite 600 #328
Cypress, TX 77429
Phone: 281-414-1994
Email: beckinson@brccp.com
www.beckinson.com
Ask yourself these questions:
Do your turnarounds meet their planned goals?
Are they taking too long and costing too much?
Are you getting less than optimal results?
Are your projects safe and event-free?
Are they competitive and predictable?
Is financial legerdemain masking the true cost?
Are lessons-learned helping make
future projects more predictable or
is knowledge being lost over time?
10
Increase your project
success rate by creating
a predictable project.
Our in-the-field and
on-the-ground experience
is an invaluable asset.
The old proverb “The early bird
catches the worm” is also true for
projects such as turnarounds, shut-
downs and revamps. The earlier
you begin, the better you prepare
and the more effort you apply—the
better the results. Realistic per-proj-
ect and overall cost estimates are
viable only when such key elements
as deliverables and constructabili-
ty issues are addressed as early as
possible. This helps to significantly
reduce the amount of rework later
in the project. Rework can be a ma-
jor source of time/cost overruns. We
help you come to the project better
prepared for better results.
Beckinson’s experience provides
an invaluable interface between
the owner and the engineering
construction firm during all phases
of your project. We help define and
prioritize the scope and review
high-level estimates. We assist in
contractor and fabricator selection
based on their history, quality and
safety records. We aid in detailed
estimate oversight and review,
planning, scheduling, logistics,
low-level cost estimating, project
scope and more. We consult during
project execution on such strategic
tasks as lifts, repairs and work-
arounds. We also assist during post
turnaround, start-up and project
closeout and we help you take les-
sons learned forward.
◆ We provide independent resources
for your core team
◆ We interface between owners and
their engineering/construction
firms
◆ FCCU, coker units and general
turnarounds, shutdowns and
revamps are our specialty
◆ Our on-the-ground experience
provides unprecedented expertise
to help prevent cost/time overruns,
resolve constructability/fit-up
mishaps in advance and keep
re-work at a minimum
◆ We help make your project more
predictable through industry best
practices in safety, quality and
efficiency
Despite over a century of know-how,
increased efficiencies and decades
of technical advances, the overall
performance for today’s complex
turnarounds is unnecessarily incon-
sistent. By making optimum use of
Beckinson’s construction knowledge
and experience throughout your
project’s planning, design, procure-
ment and field operations phases,
you can achieve more predictable
results. We assist your key people
with the following:
n FCCU Projects
n Coker Projects
n Maintenance Projects
n General Turnarounds
We offer a selection of quality
services individualized throughout
several or all of our many services:
n Consulting
n Constructability Studies
n Crane Selection
n Rigging Plans
n Budgeting
n Schedules
n Risk Assessment
n Procurement
n Coordinating
n Logistics/Plot Plans
n Cold Eye Reviews
Budgeting
associated costs
We consult with and
assist each project
team in creating
the initial budget
estimate per project.
P H A S E
1 Consulting and
reviewing
We help define and
prioritize the scope
and review high-level
project estimates
and create a
high-level schedule
for the project.
2
P H A S E
Establish
cost priorities
Help make sure
the scope and
budget are in
alignment
and back up
engineering on
the overall cost
estimate.
4
P H A S E
Constructability/
deliverables
reviews
Provide
constructability
reviews and
complete
deliverables.
5
P H A S E
Assist with
contractor
selection
Consult with owner
and/or engineering
company on vendor
and contractor
selection with
experience, safety
and quality records
as key qualifiers.
6
P H A S E
Assist in
presenting
findings/plans
to corporate
Assist in
presenting
budget and
schedule to
owner/operator.
7
P H A S E
Coordinate
pre-turnaround
activities
Track costs, ensure
schedule is properly
updated and on
track, provide
construction insight,
help optimize
schedule/budget and
assist with logistics.
8
P H A S E
Mitigate
critical schedule
impact during
turnaround
Schedule/budget
oversight to ensure
proper updating,
help develop quick
plans when an
unknown activity
develops so as to
mitigate critical
schedule impact.
9
P H A S E
Closing out
Close out schedule/
budget and provide
“lessons learned”
in easily accessible
package for future
projects.
10
P H A S E
Help engineering
define
deliverables
Assist engineering
with deliverables
for the initial
project phases.
3
P H A S E
Event-free, predictable
and economic turnaround
outcomes are within reach.
Our Mission
With BECKINSON’s proven success, experience and
the right people, we will create predictable projects to
enhance Safety, Quality and Performance for our clients.

More Related Content

What's hot

Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
T. Luoma_project_engineer_Instrumentation_Automation_controls
T. Luoma_project_engineer_Instrumentation_Automation_controlsT. Luoma_project_engineer_Instrumentation_Automation_controls
T. Luoma_project_engineer_Instrumentation_Automation_controlsTero Luoma
 
DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17 DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17 Deborah Hines
 
Goodwin, John MULTIPURPOSE RESUME
Goodwin, John MULTIPURPOSE RESUMEGoodwin, John MULTIPURPOSE RESUME
Goodwin, John MULTIPURPOSE RESUMEJohn Goodwin
 
Construction phases
Construction phasesConstruction phases
Construction phasesMeesum Zaidi
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
Mechanical Engineer History
Mechanical Engineer HistoryMechanical Engineer History
Mechanical Engineer HistoryMohamed Talkhan
 
Construction Management Services
Construction Management ServicesConstruction Management Services
Construction Management ServicesDavid Rosacker
 
Project Management Control
Project Management ControlProject Management Control
Project Management ControlVinay Mangrulkar
 
Mohammed_Attique - CV.pdf
Mohammed_Attique - CV.pdfMohammed_Attique - CV.pdf
Mohammed_Attique - CV.pdfmohammedattique
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
CV ISMAIL SHAIKH-31.10.2015
CV ISMAIL SHAIKH-31.10.2015CV ISMAIL SHAIKH-31.10.2015
CV ISMAIL SHAIKH-31.10.2015Ismail Shaikh
 

What's hot (19)

Mahesh - Resume (3)
Mahesh -   Resume (3)Mahesh -   Resume (3)
Mahesh - Resume (3)
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
T. Luoma_project_engineer_Instrumentation_Automation_controls
T. Luoma_project_engineer_Instrumentation_Automation_controlsT. Luoma_project_engineer_Instrumentation_Automation_controls
T. Luoma_project_engineer_Instrumentation_Automation_controls
 
DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17 DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17
 
Sachin parab
Sachin parabSachin parab
Sachin parab
 
Goodwin, John MULTIPURPOSE RESUME
Goodwin, John MULTIPURPOSE RESUMEGoodwin, John MULTIPURPOSE RESUME
Goodwin, John MULTIPURPOSE RESUME
 
David Fitzsimmons Resume
David Fitzsimmons ResumeDavid Fitzsimmons Resume
David Fitzsimmons Resume
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
DESIGN & BUILD
DESIGN & BUILDDESIGN & BUILD
DESIGN & BUILD
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
Resume - Kamarudheen Parayirikkal
Resume - Kamarudheen ParayirikkalResume - Kamarudheen Parayirikkal
Resume - Kamarudheen Parayirikkal
 
Mechanical Engineer History
Mechanical Engineer HistoryMechanical Engineer History
Mechanical Engineer History
 
PRANAB _Resume
PRANAB _ResumePRANAB _Resume
PRANAB _Resume
 
Construction Management Services
Construction Management ServicesConstruction Management Services
Construction Management Services
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
updated cv as of july 2015
updated cv as  of july 2015updated cv as  of july 2015
updated cv as of july 2015
 
Mohammed_Attique - CV.pdf
Mohammed_Attique - CV.pdfMohammed_Attique - CV.pdf
Mohammed_Attique - CV.pdf
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
CV ISMAIL SHAIKH-31.10.2015
CV ISMAIL SHAIKH-31.10.2015CV ISMAIL SHAIKH-31.10.2015
CV ISMAIL SHAIKH-31.10.2015
 

Similar to Beckinson Ebrochure

Clear Construction QLD - Capability Statement3
Clear Construction QLD - Capability Statement3Clear Construction QLD - Capability Statement3
Clear Construction QLD - Capability Statement3Benjamin Leavy
 
pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016Chris Nash
 
R&M Property Group Ltd brochure - 2018
R&M Property Group Ltd  brochure - 2018R&M Property Group Ltd  brochure - 2018
R&M Property Group Ltd brochure - 2018Thomas McKenna
 
1-Wind Energy RHDHV_Brochure
1-Wind Energy RHDHV_Brochure1-Wind Energy RHDHV_Brochure
1-Wind Energy RHDHV_BrochureHieu Phan Trung
 
Five Key Considerations for Design Build Projects
Five Key Considerations for Design Build ProjectsFive Key Considerations for Design Build Projects
Five Key Considerations for Design Build ProjectsSuzanne Cody
 
Sterling Project Management profile for project management, contruction manag...
Sterling Project Management profile for project management, contruction manag...Sterling Project Management profile for project management, contruction manag...
Sterling Project Management profile for project management, contruction manag...thomassterling
 
Resume-1- Ashraf Khan (1)
Resume-1- Ashraf Khan (1)Resume-1- Ashraf Khan (1)
Resume-1- Ashraf Khan (1)Ashraf Khan
 
092811 Updated Contech Brochure
092811 Updated Contech Brochure092811 Updated Contech Brochure
092811 Updated Contech BrochurePaul Smith
 
CHIP WEDEKINDFINALRESUME
CHIP WEDEKINDFINALRESUMECHIP WEDEKINDFINALRESUME
CHIP WEDEKINDFINALRESUMEChip Wedekind
 
Construction estimator
Construction estimatorConstruction estimator
Construction estimatorRana Alyas
 
Construction Estimator
Construction EstimatorConstruction Estimator
Construction EstimatorRana Alyas
 
Tarek Gamil El Fergani_CV
Tarek Gamil El Fergani_CVTarek Gamil El Fergani_CV
Tarek Gamil El Fergani_CVTarek Fergani
 

Similar to Beckinson Ebrochure (20)

towerst-resume-2a
towerst-resume-2atowerst-resume-2a
towerst-resume-2a
 
Lukas CV
Lukas CVLukas CV
Lukas CV
 
New Updated 7.62 Resume8
New Updated 7.62 Resume8New Updated 7.62 Resume8
New Updated 7.62 Resume8
 
New Updated 7.62 Resume8
New Updated 7.62 Resume8New Updated 7.62 Resume8
New Updated 7.62 Resume8
 
Clear Construction QLD - Capability Statement3
Clear Construction QLD - Capability Statement3Clear Construction QLD - Capability Statement3
Clear Construction QLD - Capability Statement3
 
pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016
 
cv_rajesh_kachhawah
cv_rajesh_kachhawahcv_rajesh_kachhawah
cv_rajesh_kachhawah
 
R&M Property Group Ltd brochure - 2018
R&M Property Group Ltd  brochure - 2018R&M Property Group Ltd  brochure - 2018
R&M Property Group Ltd brochure - 2018
 
Sohaib_CV-
Sohaib_CV-Sohaib_CV-
Sohaib_CV-
 
Assarpour_Amir
Assarpour_AmirAssarpour_Amir
Assarpour_Amir
 
1-Wind Energy RHDHV_Brochure
1-Wind Energy RHDHV_Brochure1-Wind Energy RHDHV_Brochure
1-Wind Energy RHDHV_Brochure
 
Five Key Considerations for Design Build Projects
Five Key Considerations for Design Build ProjectsFive Key Considerations for Design Build Projects
Five Key Considerations for Design Build Projects
 
Sterling Project Management profile for project management, contruction manag...
Sterling Project Management profile for project management, contruction manag...Sterling Project Management profile for project management, contruction manag...
Sterling Project Management profile for project management, contruction manag...
 
Donald Buchanan CV
Donald Buchanan CVDonald Buchanan CV
Donald Buchanan CV
 
Resume-1- Ashraf Khan (1)
Resume-1- Ashraf Khan (1)Resume-1- Ashraf Khan (1)
Resume-1- Ashraf Khan (1)
 
092811 Updated Contech Brochure
092811 Updated Contech Brochure092811 Updated Contech Brochure
092811 Updated Contech Brochure
 
CHIP WEDEKINDFINALRESUME
CHIP WEDEKINDFINALRESUMECHIP WEDEKINDFINALRESUME
CHIP WEDEKINDFINALRESUME
 
Construction estimator
Construction estimatorConstruction estimator
Construction estimator
 
Construction Estimator
Construction EstimatorConstruction Estimator
Construction Estimator
 
Tarek Gamil El Fergani_CV
Tarek Gamil El Fergani_CVTarek Gamil El Fergani_CV
Tarek Gamil El Fergani_CV
 

Beckinson Ebrochure

  • 1. B E C K I N S O N ’ S Creating predictable outcomes for complex shutdowns, critical projects and revamps Ken Beckemeyer, Consultant/President—47 years managing major FCCU, delayed coker revamps and turnarounds with exten- sive experience in project management, constructability studies, planning/scheduling, heavy lifting and rigging. James Robinson, Consultant/Vice President—provides develop- ment and coordination of estimating, planning and cost controls for critical path projects. His experience lies in the three major sectors of the petroleum industry including upstream, midstream and down- stream. Whitney Strickland, Consultant/Partner—began as a field crafts- man in a refinery 32 years ago and has since managed/consulted or invested in a number of successful petrochemical service compa- nies including those specializing in safety, turnaround execution, welding, tower and refractory services as well as planning, schedul- ing and cost estimating. Russell Hillenburg, Consultant/Partner—a third-generation shop-fabrication business owner specializing in reactor and tower internals. He is not only fabrication-savvy but also possesses good project/personnel management and problem-solving skills. Chad Beckemeyer, Consultant/Vice President—over 16 years of experience in project management, project controls, scheduling, estimating and field supervision of craftsman on major projects such as FCCU and delayed coker revamps as well as major expan- sions in other industries. Beckinson Team Leaders Phases of Project Constructability 12320 Barker Cypress Road, Suite 600 #328 Cypress, TX 77429 Phone: 281-414-1994 Email: beckinson@brccp.com www.beckinson.com Ask yourself these questions: Do your turnarounds meet their planned goals? Are they taking too long and costing too much? Are you getting less than optimal results? Are your projects safe and event-free? Are they competitive and predictable? Is financial legerdemain masking the true cost? Are lessons-learned helping make future projects more predictable or is knowledge being lost over time? 10
  • 2. Increase your project success rate by creating a predictable project. Our in-the-field and on-the-ground experience is an invaluable asset. The old proverb “The early bird catches the worm” is also true for projects such as turnarounds, shut- downs and revamps. The earlier you begin, the better you prepare and the more effort you apply—the better the results. Realistic per-proj- ect and overall cost estimates are viable only when such key elements as deliverables and constructabili- ty issues are addressed as early as possible. This helps to significantly reduce the amount of rework later in the project. Rework can be a ma- jor source of time/cost overruns. We help you come to the project better prepared for better results. Beckinson’s experience provides an invaluable interface between the owner and the engineering construction firm during all phases of your project. We help define and prioritize the scope and review high-level estimates. We assist in contractor and fabricator selection based on their history, quality and safety records. We aid in detailed estimate oversight and review, planning, scheduling, logistics, low-level cost estimating, project scope and more. We consult during project execution on such strategic tasks as lifts, repairs and work- arounds. We also assist during post turnaround, start-up and project closeout and we help you take les- sons learned forward. ◆ We provide independent resources for your core team ◆ We interface between owners and their engineering/construction firms ◆ FCCU, coker units and general turnarounds, shutdowns and revamps are our specialty ◆ Our on-the-ground experience provides unprecedented expertise to help prevent cost/time overruns, resolve constructability/fit-up mishaps in advance and keep re-work at a minimum ◆ We help make your project more predictable through industry best practices in safety, quality and efficiency Despite over a century of know-how, increased efficiencies and decades of technical advances, the overall performance for today’s complex turnarounds is unnecessarily incon- sistent. By making optimum use of Beckinson’s construction knowledge and experience throughout your project’s planning, design, procure- ment and field operations phases, you can achieve more predictable results. We assist your key people with the following: n FCCU Projects n Coker Projects n Maintenance Projects n General Turnarounds We offer a selection of quality services individualized throughout several or all of our many services: n Consulting n Constructability Studies n Crane Selection n Rigging Plans n Budgeting n Schedules n Risk Assessment n Procurement n Coordinating n Logistics/Plot Plans n Cold Eye Reviews Budgeting associated costs We consult with and assist each project team in creating the initial budget estimate per project. P H A S E 1 Consulting and reviewing We help define and prioritize the scope and review high-level project estimates and create a high-level schedule for the project. 2 P H A S E Establish cost priorities Help make sure the scope and budget are in alignment and back up engineering on the overall cost estimate. 4 P H A S E Constructability/ deliverables reviews Provide constructability reviews and complete deliverables. 5 P H A S E Assist with contractor selection Consult with owner and/or engineering company on vendor and contractor selection with experience, safety and quality records as key qualifiers. 6 P H A S E Assist in presenting findings/plans to corporate Assist in presenting budget and schedule to owner/operator. 7 P H A S E Coordinate pre-turnaround activities Track costs, ensure schedule is properly updated and on track, provide construction insight, help optimize schedule/budget and assist with logistics. 8 P H A S E Mitigate critical schedule impact during turnaround Schedule/budget oversight to ensure proper updating, help develop quick plans when an unknown activity develops so as to mitigate critical schedule impact. 9 P H A S E Closing out Close out schedule/ budget and provide “lessons learned” in easily accessible package for future projects. 10 P H A S E Help engineering define deliverables Assist engineering with deliverables for the initial project phases. 3 P H A S E Event-free, predictable and economic turnaround outcomes are within reach. Our Mission With BECKINSON’s proven success, experience and the right people, we will create predictable projects to enhance Safety, Quality and Performance for our clients.