SlideShare a Scribd company logo
1 of 30
Download to read offline
Producing Tomorrow’s Energy
Hellisheidi Power Plant - is there an optimal design?
Professor Páll Valdimarsson, Atlas Copco Geothermal Competence Center
and Reykjavik University
Hellisheidi Power Plant
- is there an optimal design?
 The question of an optimal design in the sense of power production is
discussed
 The use of temperature versus heat duty and Carnot efficiency versus heat
duty diagrams for the analysis is presented
 The problem of defining design conditions for the plant is discussed
 The present well production is discussed from that point of view
 An attempt is made define an "optimal" plant for the present well
production, and the power production is estimated for a few configurations.
Real life power plant design
 The process has to be designed before any real production experience is
available from the wells
 The only available data is from exploratory wells and geophysical models
 The good earth scientist makes a safe and conservative estimate of the
expected well enthalpy
 The good and experience engineer makes a safe and conservative design
based on these estimates
 There is no other way to do the design!!!
 If everybody is roughly right, then the plant will be conservative, and could
produce more power if the design was aggressive.
Optimal design for power
 The power output is the score function
 The thermodynamic process parameters are optimized
 Investment cost is not minimized here
– but a “state of the art” technical level is assumed
 The well enthalpy is assumed constant
 The well flow is dependent on the wellhead pressure
– but within boundaries given by operational experience.
Simplified steam system
 The well production is determined by the wellhead pressure
 The collection system unifies flow from different wells and conveys it to the separator
 The separator pressure is a main design parameter for a steam plant
 The turbine design is based on the separator pressure
 Off-design separator pressure will influence turbine efficiency
 Pressure reduction will cause increased steam fraction and exergy losses.
P
P
Wellhead pressure
Collection system
Separator pressure
Steam for turbine
Mineralized brine
Well
Wellhead valve
Orifice or valve
Separator
cPbPam wellwellwell  2

1 km
Ring Road #1
Power Station
Wellpad
Wellpad
Wellpad
Wellpad
Ring Road #1
Wellpad
Main Power Station
Wellpad
Wellpad
Wellpad
Collector line 8
Collector line 26
Power Station for Units V and VI
Separator station 1
Separator station 2
Separator station 3
Supply line
Supply line
HE-05 HE-29 HE-43
HE-06 HE-11 HE-17
HE-31 HE-44 HE-48
HE-24 HE-27 HE-38
HE-03 HE-32 HE-51
HE-09 HE-14 HE-18 HE-50 HE-56
HE-15 HE-30
HE-47
Supply line 7
Supply line 6
Supply line 5
Supply line 1
HE-07 HE-12 HE-16
HE-41 HE-42
Supply line 4
HE-19HE-45
Supply line 2
Supply line 3
V
VI
I
II
III
IV
XI
Main Power Station
Power Station for Units V and VI
Separator station 1
Separator station 2
Separator station 3
Scenario from 2012 12 07
 Total flow from wells 1080 kg/s
 Average enthalpy 1737 kJ/kg
 HP gross power 268,5 MW
 LP gross power 23 MW
 Plant net power 276 MW
 This corresponds to 19,5 bar
gage unified wellhead
pressure
Well
Maximum
wellhead
pressure
Minimum
wellhead
pressure
Operating
wellhead
pressure
[bar g] [bar g] [bar g] a b c
HE-3 22 14 14 -0,1787 3,2647 15,27
HE-5 22 14 14 -0,3479 5,3899 50,35
HE-6 30 14 17 -0,0187 0,5304 25,77
HE-7 30 20 22 -0,0249 0,251 80,23
HE-9 30 14 22 -0,0033 0,0322 10,03
HE-11 30 16 16 -0,0042 -1,0015 67,39
HE-12 30 18 21 -0,0363 0,6606 66,87
HE-14 30 14 12 -0,0103 -0,138 34,81
HE-15 30 14 25 -0,0221 0,3316 38,81
HE-16 30 14 57 -0,009 0 29,2
HE-17 30 22 17 -0,029 0,7146 61,22
HE-18 27 14 13 -0,1453 2,8174 30,11
HE-19 30 22 22 -0,0458 0,6245 104,09
HE-24 30 14 17 -0,029 0,7146 61,22
HE-27 30 14 24 -0,0472 1,1312 19,35
HE-29 30 14 16 -0,0041 -0,0948 20,37
HE-30 30 18 16 -0,016 0,2279 42,47
HE-31 18 14 16 -0,1652 4,3899 56,42
HE-32 30 14 15 -0,0308 0,3701 49,38
HE-38 18 14 36 -0,0376 0,5779 22,78
HE-41 30 14 27 -0,0052 0,0507 25,69
HE-42 30 14 26 -0,0052 0,05 21,96
HE-43 30 14 15 -0,0148 0,5125 7,7
HE-44 30 14 18 -0,0472 1,0853 63,66
HE-45 30 20 25 -0,0085 0,2332 35,91
HE-46 18 14 30 -0,1183 2,9048 19,3
HE-47 30 22 18 -0,0073 -0,0686 58,38
HE-48 18 14 16 -0,0378 0,7752 55,78
HE-50 30 14 16 -0,0063 0,1487 16,14
HE-51 32 14 20 -0,0145 0,2191 7,793
HE-56 30 14 16 -0,0086 -1,5603 82,95
Production curve parameters
Flow from individual wells
10 14 18 22 26 30
0
20
40
60
80
100
Pwell
mdot;well
High pressure wells
A single well accounts for 10% of the plant flow!
Medium pressure wells
Low pressure wells
Flow from all wells, common wellhead pressure
10 14 18 22 26 30
700
800
900
1000
1100
1200
Pwell
m
Average enthalpy, common wellhead pressure
10 14 18 22 26 30
1675
1710
1745
1780
1815
1850
Pwell
haverage
Temperature as a function of removed heat
 The ideal case is if we could utilize the full flow without any boiling
 Pressure loss in the formation and in the transport up the well will cause
boiling and exergy loss
 Four curves are presented:
 Temperature assuming that the wellhead pressure is so high that no boiling
occurs, with the same flow and enthalpy as in the real operating scenario
 Temperature if the wellhead pressure is 10 bar g for all wells
 Temperature if the wellhead pressure is 19,5 bar g for all wells
 Temperature if the wellhead pressure is 30 bar g for all wells.
Temperature – heat duty diagram
-1400 -1200 -1000 -800 -600 -400 -200 0
100
150
200
250
300
350
400
Q [MW]
Temperature[°C]
Carnot efficiency as a function of removed heat
 The unit of area is MW of exergy (power producing potential)
 The ideal case is if we could utilize the full flow without any boiling
 Pressure loss in the formation and in the transport up the well will cause
boiling and exergy loss
 Four curves are presented:
 Carnot efficiency assuming that the wellhead pressure is so high that no
boiling occurs, with the same flow and enthalpy as in the real operating
scenario
 Carnot efficiency if the wellhead pressure is 10 bar g for all wells
 Carnot efficiency if the wellhead pressure is 19,5 bar g for all wells
 Carnot efficiency if the wellhead pressure is 30 bar g for all wells.
-1400 -1200 -1000 -800 -600 -400 -200 0
0,25
0,3
0,35
0,4
0,45
0,5
0,55
0,6
Q [MW]
hc
-1400 -1200 -1000 -800 -600 -400 -200 0
0,25
0,3
0,35
0,4
0,45
0,5
0,55
0,6
Q [MW]
hc
-1400 -1200 -1000 -800 -600 -400 -200 0
0,25
0,3
0,35
0,4
0,45
0,5
0,55
0,6
Q [MW]
hc
-1400 -1200 -1000 -800 -600 -400 -200 0
0,25
0,3
0,35
0,4
0,45
0,5
0,55
0,6
Q [MW]
hc
Carnot efficiency – Heat duty diagram
Wellhead pressure 19,5 bar g
No pressure loss and same flow
and enthalpy as if wellhead
pressure was19,5 bar g
Lost power potential because
of well pressure loss
Wellhead pressure 30 bar g
Wellhead pressure 10 bar g
Optimization
 Three alternatives:
 Modification of HP separator pressure, double flash plant
 Individual HP wellhead turbines and common MP plant
 HP steam turbines and ORC bottoming plant.
Double flash simplified
HP turbines
Wells
LP turbine
HP separator
LP separator
Double flash and wellhead pressure
 The reference scenario has 11,5 bar difference between the common
wellhead pressure and the HP separator pressure
 There is considerable gain in reducing this pressure difference
 The calculation assumes unchanged LP system
Double flash gross power
0 5 10 15 20 25 30
240000
260000
280000
300000
320000
340000
PHP;separator [bar absolute]
Wgross[kW]
Pressure difference 11,5 bar
Pressure difference 5 bar
Pressure difference 3 bar
Pressure difference 1 bar
Individual HP letdown turbines for HP wells
 The wells with high flow and pressure are connected to HP backpressure
units
 The HP backpressure is higher than the main plant HP separator pressure,
so the exhaust stem is inlet steam for the main plant
 The main plant is can then be designed for moderate separator pressure
 The concept is flexible and allows more wells to operate at individual
optimum wellhead pressure
 Previous studies indicate that gross power increase in the region of
10 – 15% can be obtained
 Same studies indicate that the economy of such modification is marginal.
Individual HP letdown turbines for HP wells
HP letdown separator
HP letdown turbine
Main plant HP separator
Main plant LP separator
Main plant HP turbine
Main plant LP turbine
Hybrid power plant
 The hybrid plant consists of HP steam back pressure turbines and a bottoming
ORC cycle with separate vaporizers for steam and brine
 The condensate from the steam heated vaporizer is mixed with the brine before
the ORC preheater to reduce risk of scaling
 The produced power is similar as the best performance of a dual flash plant
 Gas removal is easy from a knockout pot after the steam heated vaporizer at
the same pressure as the turbine backpressure
 The ORC radial turbines employed are with very high efficiency (85-87%) and
have a flat efficiency curve due to variable geometry nozzle guide vanes
 An air cooled cooling tower can be used, avoiding visual effects of steam
plume as well as avoiding need for makeup water
 The ORC plant is a scaled up copy of the Atlas Copco delivered ORC plant in
Pamukören, Turkey.
Gas removal knockout pot
Hybrid plant PFD
Steam backpressure turbine
Steam heated vaporizer
ORC turbine
Preheater
Brine heated vaporizer
Recuperator
Air cooled condenser
ORC circulation pump
Steam separator
1
3 2
4
5
6
e2
e1
7
e4
s1
s2
s3
s4
s5 s6
a1
a2
mwf = 3137 [kg/s]
To,1 = 25 [°C]
To,4 = 124,6 [°C]
Ts,1 = 191,6 [°C]
Po,1 = 2,437 [bar abs]
To,3 = 38,79 [°C]
Wpump,wf = 15753 [kW]
Wfan = 10380 [kW]
To,6 = 31,53 [°C]
me,1 = 1193 [kg/s]
xe,2 = 0,4475
Te,4 = 191,6 [°C]
he,1 = 1697 [kJ/kg]
Ts,3 = 127,6 [°C]
mwf,brine,vaporizer = 465,7 [kg/s]
mwf,steam,vaporizer = 2672 [kg/s]
To,7 = 57,11 [°C]
Ts,4 = 100 [°C]
Wpump,condensate = 796,4 [kW]
me,4 = 533,9 [kg/s]
Wsteam = 124999 [kW]
Wbinary = 257280 [kW]
Pe,4 = 13 [bar abs]
Po,4 = 24 [bar abs]
To,5 = 47,84 [°C]
Ts,5 = 127,6 [°C]
Ta1 = 5 [°C]
Ta2 = 20 [°C]
Wbinary,net = 218283 [kW]
Wnet = 336236 [kW]
Fluid$ = n-butane
Psteam,in = 13 [bar abs]
Psteam,out = 2,518 [bar abs]
0 50000 100000 150000 200000 250000 300000 350000
0
0,05
0,1
0,15
0,2
0,25
0,3
0,35
Q[i]
etaCarnot;c[i],etaCarnot;h[i]
Condenser Recuperator Preheater Brine vaporizer Steam vaporizer Superheater
Carnot efficiency diagram for the Pamukören plant
Conclusion
 The field in Hellisheiði has proven to be better than the original estimate
 The presented analysis is based on a single snapshot of the wells (from 2012
12 07), and well are likely to decline with time, moving the field closer to the
original estimate
 A double flash design optimized for the snapshot production seems to produce
close to 15% more power
 At least the same increase should be possible with individual HP letdown
turbines
 Similar power increase seems to be possible with the more expensive ORC
cycle
– offering easier gas removal
– does not have cooling tower steam plum
– does not need condensate for makeup
– but is more expensive for each kW produced.
Committed to
sustainable productivity.
Hellisheidi Power Plant - is there an optimal design?

More Related Content

What's hot

Hrsg & turbine as run energy efficiency assessment
Hrsg  & turbine as run energy efficiency assessmentHrsg  & turbine as run energy efficiency assessment
Hrsg & turbine as run energy efficiency assessment
D.Pawan Kumar
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
Kongkiert Tankayura
 
Turbofan Engine Design Report
Turbofan Engine Design ReportTurbofan Engine Design Report
Turbofan Engine Design Report
Nicholas Cordero
 
NTPC _Traning report_dhiraj
NTPC _Traning report_dhirajNTPC _Traning report_dhiraj
NTPC _Traning report_dhiraj
Dhiraj Kumar
 
287649737 90325-presentation-hrsg
287649737 90325-presentation-hrsg287649737 90325-presentation-hrsg
287649737 90325-presentation-hrsg
Srikanth321
 

What's hot (20)

Study and performance analysis of combustion chamber using ANSYS
Study and performance analysis of combustion chamber using ANSYSStudy and performance analysis of combustion chamber using ANSYS
Study and performance analysis of combustion chamber using ANSYS
 
30120140504017
3012014050401730120140504017
30120140504017
 
Hrsg & turbine as run energy efficiency assessment
Hrsg  & turbine as run energy efficiency assessmentHrsg  & turbine as run energy efficiency assessment
Hrsg & turbine as run energy efficiency assessment
 
Feedwater heaters by Himanshu Vaid
Feedwater heaters by Himanshu VaidFeedwater heaters by Himanshu Vaid
Feedwater heaters by Himanshu Vaid
 
Chapter 4 Gas Turbine
Chapter 4 Gas TurbineChapter 4 Gas Turbine
Chapter 4 Gas Turbine
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
 
Gas turbines working ppt
Gas turbines working pptGas turbines working ppt
Gas turbines working ppt
 
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCEMETHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
 
Gas turbine power plant
Gas turbine power plantGas turbine power plant
Gas turbine power plant
 
Steam turbine losses
Steam turbine  lossesSteam turbine  losses
Steam turbine losses
 
Condensate system
Condensate systemCondensate system
Condensate system
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines
 
Turbofan Engine Design Report
Turbofan Engine Design ReportTurbofan Engine Design Report
Turbofan Engine Design Report
 
STEAM NOZZLES
STEAM NOZZLESSTEAM NOZZLES
STEAM NOZZLES
 
NTPC _Traning report_dhiraj
NTPC _Traning report_dhirajNTPC _Traning report_dhiraj
NTPC _Traning report_dhiraj
 
Advancement in Turbine Technology
Advancement in Turbine TechnologyAdvancement in Turbine Technology
Advancement in Turbine Technology
 
Wheel space description
Wheel space descriptionWheel space description
Wheel space description
 
Air driven piezoelectric car
Air driven piezoelectric carAir driven piezoelectric car
Air driven piezoelectric car
 
Ic mid exam n solutn
Ic mid exam n solutnIc mid exam n solutn
Ic mid exam n solutn
 
287649737 90325-presentation-hrsg
287649737 90325-presentation-hrsg287649737 90325-presentation-hrsg
287649737 90325-presentation-hrsg
 

Similar to Hellisheidi Power Plant - is there an optimal design?

Bhushan powers and steels thalkuli,regali
Bhushan powers and steels thalkuli,regaliBhushan powers and steels thalkuli,regali
Bhushan powers and steels thalkuli,regali
Baroda
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
SHIVAJI CHOUDHURY
 
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu Chen
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]
Amardeep Jadeja
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans ppt
D.Pawan Kumar
 
Inplant training report
Inplant training reportInplant training report
Inplant training report
applesam8
 

Similar to Hellisheidi Power Plant - is there an optimal design? (20)

Bhushan powers and steels thalkuli,regali
Bhushan powers and steels thalkuli,regaliBhushan powers and steels thalkuli,regali
Bhushan powers and steels thalkuli,regali
 
POWER PLANT.pdf
POWER PLANT.pdfPOWER PLANT.pdf
POWER PLANT.pdf
 
DB VRF CATALOG LATEST VERSION (1).pdf
DB VRF CATALOG LATEST VERSION (1).pdfDB VRF CATALOG LATEST VERSION (1).pdf
DB VRF CATALOG LATEST VERSION (1).pdf
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )
 
P044058595
P044058595P044058595
P044058595
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
 
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applications
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
 
Schneider process automation power industry solutions
Schneider process automation power industry solutionsSchneider process automation power industry solutions
Schneider process automation power industry solutions
 
Paras ppt
Paras pptParas ppt
Paras ppt
 
Development of vapour absorption refrigeration system in vehicles
Development of vapour absorption refrigeration system in vehiclesDevelopment of vapour absorption refrigeration system in vehicles
Development of vapour absorption refrigeration system in vehicles
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans ppt
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
Inplant training report
Inplant training reportInplant training report
Inplant training report
 

More from Iceland Geothermal

More from Iceland Geothermal (20)

Geothermal Landscape study final
Geothermal Landscape study finalGeothermal Landscape study final
Geothermal Landscape study final
 
A1 Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
A1  Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...A1  Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
A1 Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
 
C4 - Geothermal Fuels Prosperity: How Geothermal Direct Use Projects Enable ...
C4 - Geothermal Fuels Prosperity:  How Geothermal Direct Use Projects Enable ...C4 - Geothermal Fuels Prosperity:  How Geothermal Direct Use Projects Enable ...
C4 - Geothermal Fuels Prosperity: How Geothermal Direct Use Projects Enable ...
 
C4 - Climeworks: Capturing CO2 from air
C4 - Climeworks: Capturing CO2 from airC4 - Climeworks: Capturing CO2 from air
C4 - Climeworks: Capturing CO2 from air
 
C4 - Opportunities to develop low-enthalpy geothermal project in Mexico
C4 - Opportunities to develop low-enthalpy geothermal project in MexicoC4 - Opportunities to develop low-enthalpy geothermal project in Mexico
C4 - Opportunities to develop low-enthalpy geothermal project in Mexico
 
C4 - Lithium recovery from high temperature geothermal brines.
C4 - Lithium recovery from high temperature geothermal brines.C4 - Lithium recovery from high temperature geothermal brines.
C4 - Lithium recovery from high temperature geothermal brines.
 
C4 - Transforming CO2 into a commercial product
C4 - Transforming CO2 into a commercial productC4 - Transforming CO2 into a commercial product
C4 - Transforming CO2 into a commercial product
 
C3 - Production Modelling for Sustainability
C3 - Production Modelling for SustainabilityC3 - Production Modelling for Sustainability
C3 - Production Modelling for Sustainability
 
C3 - IDDP2 A better tomorrow
C3 - IDDP2 A better tomorrowC3 - IDDP2 A better tomorrow
C3 - IDDP2 A better tomorrow
 
C3 - Production and reinjection at Hellisheiði: Holistic approach
C3 - Production and reinjection at Hellisheiði: Holistic approachC3 - Production and reinjection at Hellisheiði: Holistic approach
C3 - Production and reinjection at Hellisheiði: Holistic approach
 
C3 - Geothermal reservoir management and sustainable use
C3 - Geothermal reservoir management and sustainable useC3 - Geothermal reservoir management and sustainable use
C3 - Geothermal reservoir management and sustainable use
 
C2 - Optimization of existing systems: Improvement of plants in operation and...
C2 - Optimization of existing systems: Improvement of plants in operation and...C2 - Optimization of existing systems: Improvement of plants in operation and...
C2 - Optimization of existing systems: Improvement of plants in operation and...
 
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
 
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATIONC2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
 
C2 - ENGINEERING THE ENERGY TRANSITION
C2 - ENGINEERING THE  ENERGY TRANSITIONC2 - ENGINEERING THE  ENERGY TRANSITION
C2 - ENGINEERING THE ENERGY TRANSITION
 
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
 
C1 - Operation: Ownership Structure and its Effects
C1 - Operation: Ownership Structure and its EffectsC1 - Operation: Ownership Structure and its Effects
C1 - Operation: Ownership Structure and its Effects
 
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTSC1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
 
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
 
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyB4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
 

Recently uploaded

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 

Recently uploaded (20)

Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 

Hellisheidi Power Plant - is there an optimal design?

  • 1. Producing Tomorrow’s Energy Hellisheidi Power Plant - is there an optimal design? Professor Páll Valdimarsson, Atlas Copco Geothermal Competence Center and Reykjavik University
  • 2. Hellisheidi Power Plant - is there an optimal design?  The question of an optimal design in the sense of power production is discussed  The use of temperature versus heat duty and Carnot efficiency versus heat duty diagrams for the analysis is presented  The problem of defining design conditions for the plant is discussed  The present well production is discussed from that point of view  An attempt is made define an "optimal" plant for the present well production, and the power production is estimated for a few configurations.
  • 3. Real life power plant design  The process has to be designed before any real production experience is available from the wells  The only available data is from exploratory wells and geophysical models  The good earth scientist makes a safe and conservative estimate of the expected well enthalpy  The good and experience engineer makes a safe and conservative design based on these estimates  There is no other way to do the design!!!  If everybody is roughly right, then the plant will be conservative, and could produce more power if the design was aggressive.
  • 4. Optimal design for power  The power output is the score function  The thermodynamic process parameters are optimized  Investment cost is not minimized here – but a “state of the art” technical level is assumed  The well enthalpy is assumed constant  The well flow is dependent on the wellhead pressure – but within boundaries given by operational experience.
  • 5. Simplified steam system  The well production is determined by the wellhead pressure  The collection system unifies flow from different wells and conveys it to the separator  The separator pressure is a main design parameter for a steam plant  The turbine design is based on the separator pressure  Off-design separator pressure will influence turbine efficiency  Pressure reduction will cause increased steam fraction and exergy losses. P P Wellhead pressure Collection system Separator pressure Steam for turbine Mineralized brine Well Wellhead valve Orifice or valve Separator cPbPam wellwellwell  2 
  • 6.
  • 7.
  • 8. 1 km Ring Road #1 Power Station Wellpad Wellpad Wellpad Wellpad Ring Road #1 Wellpad
  • 9. Main Power Station Wellpad Wellpad Wellpad Collector line 8 Collector line 26 Power Station for Units V and VI Separator station 1 Separator station 2 Separator station 3 Supply line Supply line
  • 10. HE-05 HE-29 HE-43 HE-06 HE-11 HE-17 HE-31 HE-44 HE-48 HE-24 HE-27 HE-38 HE-03 HE-32 HE-51 HE-09 HE-14 HE-18 HE-50 HE-56 HE-15 HE-30 HE-47 Supply line 7 Supply line 6 Supply line 5 Supply line 1 HE-07 HE-12 HE-16 HE-41 HE-42 Supply line 4 HE-19HE-45 Supply line 2 Supply line 3 V VI I II III IV XI Main Power Station Power Station for Units V and VI Separator station 1 Separator station 2 Separator station 3
  • 11. Scenario from 2012 12 07  Total flow from wells 1080 kg/s  Average enthalpy 1737 kJ/kg  HP gross power 268,5 MW  LP gross power 23 MW  Plant net power 276 MW  This corresponds to 19,5 bar gage unified wellhead pressure Well Maximum wellhead pressure Minimum wellhead pressure Operating wellhead pressure [bar g] [bar g] [bar g] a b c HE-3 22 14 14 -0,1787 3,2647 15,27 HE-5 22 14 14 -0,3479 5,3899 50,35 HE-6 30 14 17 -0,0187 0,5304 25,77 HE-7 30 20 22 -0,0249 0,251 80,23 HE-9 30 14 22 -0,0033 0,0322 10,03 HE-11 30 16 16 -0,0042 -1,0015 67,39 HE-12 30 18 21 -0,0363 0,6606 66,87 HE-14 30 14 12 -0,0103 -0,138 34,81 HE-15 30 14 25 -0,0221 0,3316 38,81 HE-16 30 14 57 -0,009 0 29,2 HE-17 30 22 17 -0,029 0,7146 61,22 HE-18 27 14 13 -0,1453 2,8174 30,11 HE-19 30 22 22 -0,0458 0,6245 104,09 HE-24 30 14 17 -0,029 0,7146 61,22 HE-27 30 14 24 -0,0472 1,1312 19,35 HE-29 30 14 16 -0,0041 -0,0948 20,37 HE-30 30 18 16 -0,016 0,2279 42,47 HE-31 18 14 16 -0,1652 4,3899 56,42 HE-32 30 14 15 -0,0308 0,3701 49,38 HE-38 18 14 36 -0,0376 0,5779 22,78 HE-41 30 14 27 -0,0052 0,0507 25,69 HE-42 30 14 26 -0,0052 0,05 21,96 HE-43 30 14 15 -0,0148 0,5125 7,7 HE-44 30 14 18 -0,0472 1,0853 63,66 HE-45 30 20 25 -0,0085 0,2332 35,91 HE-46 18 14 30 -0,1183 2,9048 19,3 HE-47 30 22 18 -0,0073 -0,0686 58,38 HE-48 18 14 16 -0,0378 0,7752 55,78 HE-50 30 14 16 -0,0063 0,1487 16,14 HE-51 32 14 20 -0,0145 0,2191 7,793 HE-56 30 14 16 -0,0086 -1,5603 82,95 Production curve parameters
  • 12. Flow from individual wells 10 14 18 22 26 30 0 20 40 60 80 100 Pwell mdot;well High pressure wells A single well accounts for 10% of the plant flow! Medium pressure wells Low pressure wells
  • 13. Flow from all wells, common wellhead pressure 10 14 18 22 26 30 700 800 900 1000 1100 1200 Pwell m
  • 14. Average enthalpy, common wellhead pressure 10 14 18 22 26 30 1675 1710 1745 1780 1815 1850 Pwell haverage
  • 15. Temperature as a function of removed heat  The ideal case is if we could utilize the full flow without any boiling  Pressure loss in the formation and in the transport up the well will cause boiling and exergy loss  Four curves are presented:  Temperature assuming that the wellhead pressure is so high that no boiling occurs, with the same flow and enthalpy as in the real operating scenario  Temperature if the wellhead pressure is 10 bar g for all wells  Temperature if the wellhead pressure is 19,5 bar g for all wells  Temperature if the wellhead pressure is 30 bar g for all wells.
  • 16. Temperature – heat duty diagram -1400 -1200 -1000 -800 -600 -400 -200 0 100 150 200 250 300 350 400 Q [MW] Temperature[°C]
  • 17. Carnot efficiency as a function of removed heat  The unit of area is MW of exergy (power producing potential)  The ideal case is if we could utilize the full flow without any boiling  Pressure loss in the formation and in the transport up the well will cause boiling and exergy loss  Four curves are presented:  Carnot efficiency assuming that the wellhead pressure is so high that no boiling occurs, with the same flow and enthalpy as in the real operating scenario  Carnot efficiency if the wellhead pressure is 10 bar g for all wells  Carnot efficiency if the wellhead pressure is 19,5 bar g for all wells  Carnot efficiency if the wellhead pressure is 30 bar g for all wells.
  • 18. -1400 -1200 -1000 -800 -600 -400 -200 0 0,25 0,3 0,35 0,4 0,45 0,5 0,55 0,6 Q [MW] hc -1400 -1200 -1000 -800 -600 -400 -200 0 0,25 0,3 0,35 0,4 0,45 0,5 0,55 0,6 Q [MW] hc -1400 -1200 -1000 -800 -600 -400 -200 0 0,25 0,3 0,35 0,4 0,45 0,5 0,55 0,6 Q [MW] hc -1400 -1200 -1000 -800 -600 -400 -200 0 0,25 0,3 0,35 0,4 0,45 0,5 0,55 0,6 Q [MW] hc Carnot efficiency – Heat duty diagram Wellhead pressure 19,5 bar g No pressure loss and same flow and enthalpy as if wellhead pressure was19,5 bar g Lost power potential because of well pressure loss Wellhead pressure 30 bar g Wellhead pressure 10 bar g
  • 19. Optimization  Three alternatives:  Modification of HP separator pressure, double flash plant  Individual HP wellhead turbines and common MP plant  HP steam turbines and ORC bottoming plant.
  • 20. Double flash simplified HP turbines Wells LP turbine HP separator LP separator
  • 21. Double flash and wellhead pressure  The reference scenario has 11,5 bar difference between the common wellhead pressure and the HP separator pressure  There is considerable gain in reducing this pressure difference  The calculation assumes unchanged LP system
  • 22. Double flash gross power 0 5 10 15 20 25 30 240000 260000 280000 300000 320000 340000 PHP;separator [bar absolute] Wgross[kW] Pressure difference 11,5 bar Pressure difference 5 bar Pressure difference 3 bar Pressure difference 1 bar
  • 23. Individual HP letdown turbines for HP wells  The wells with high flow and pressure are connected to HP backpressure units  The HP backpressure is higher than the main plant HP separator pressure, so the exhaust stem is inlet steam for the main plant  The main plant is can then be designed for moderate separator pressure  The concept is flexible and allows more wells to operate at individual optimum wellhead pressure  Previous studies indicate that gross power increase in the region of 10 – 15% can be obtained  Same studies indicate that the economy of such modification is marginal.
  • 24. Individual HP letdown turbines for HP wells HP letdown separator HP letdown turbine Main plant HP separator Main plant LP separator Main plant HP turbine Main plant LP turbine
  • 25. Hybrid power plant  The hybrid plant consists of HP steam back pressure turbines and a bottoming ORC cycle with separate vaporizers for steam and brine  The condensate from the steam heated vaporizer is mixed with the brine before the ORC preheater to reduce risk of scaling  The produced power is similar as the best performance of a dual flash plant  Gas removal is easy from a knockout pot after the steam heated vaporizer at the same pressure as the turbine backpressure  The ORC radial turbines employed are with very high efficiency (85-87%) and have a flat efficiency curve due to variable geometry nozzle guide vanes  An air cooled cooling tower can be used, avoiding visual effects of steam plume as well as avoiding need for makeup water  The ORC plant is a scaled up copy of the Atlas Copco delivered ORC plant in Pamukören, Turkey.
  • 26. Gas removal knockout pot Hybrid plant PFD Steam backpressure turbine Steam heated vaporizer ORC turbine Preheater Brine heated vaporizer Recuperator Air cooled condenser ORC circulation pump Steam separator 1 3 2 4 5 6 e2 e1 7 e4 s1 s2 s3 s4 s5 s6 a1 a2 mwf = 3137 [kg/s] To,1 = 25 [°C] To,4 = 124,6 [°C] Ts,1 = 191,6 [°C] Po,1 = 2,437 [bar abs] To,3 = 38,79 [°C] Wpump,wf = 15753 [kW] Wfan = 10380 [kW] To,6 = 31,53 [°C] me,1 = 1193 [kg/s] xe,2 = 0,4475 Te,4 = 191,6 [°C] he,1 = 1697 [kJ/kg] Ts,3 = 127,6 [°C] mwf,brine,vaporizer = 465,7 [kg/s] mwf,steam,vaporizer = 2672 [kg/s] To,7 = 57,11 [°C] Ts,4 = 100 [°C] Wpump,condensate = 796,4 [kW] me,4 = 533,9 [kg/s] Wsteam = 124999 [kW] Wbinary = 257280 [kW] Pe,4 = 13 [bar abs] Po,4 = 24 [bar abs] To,5 = 47,84 [°C] Ts,5 = 127,6 [°C] Ta1 = 5 [°C] Ta2 = 20 [°C] Wbinary,net = 218283 [kW] Wnet = 336236 [kW] Fluid$ = n-butane Psteam,in = 13 [bar abs] Psteam,out = 2,518 [bar abs]
  • 27. 0 50000 100000 150000 200000 250000 300000 350000 0 0,05 0,1 0,15 0,2 0,25 0,3 0,35 Q[i] etaCarnot;c[i],etaCarnot;h[i] Condenser Recuperator Preheater Brine vaporizer Steam vaporizer Superheater Carnot efficiency diagram for the Pamukören plant
  • 28. Conclusion  The field in Hellisheiði has proven to be better than the original estimate  The presented analysis is based on a single snapshot of the wells (from 2012 12 07), and well are likely to decline with time, moving the field closer to the original estimate  A double flash design optimized for the snapshot production seems to produce close to 15% more power  At least the same increase should be possible with individual HP letdown turbines  Similar power increase seems to be possible with the more expensive ORC cycle – offering easier gas removal – does not have cooling tower steam plum – does not need condensate for makeup – but is more expensive for each kW produced.