SlideShare a Scribd company logo
1 of 27
1
ACKNOWLEDGEMENT
We hereby take this opportunity to thanks NTPC Tanda for giving us this
opportunity to conduct our training in NTPC Tanda. We are grateful to
Shri S N Shukla (Supdt. TMD), for allowing us to conduct our training in
the Control and Instrumentation department. We are heartily indebted to
our project guide P S Rawat ( Engr. TMD) for providing us with detailed
in depth knowledge and very useful information about the process and
system used in the plant. His support was instrumental in our training
being fruitful. We are also thankful to the entire officer and staff of NTPC
Tanda for extending a helping hand whenever we need it.
DEEPAK VERMA
2
CONTENT
S.No. Description Page No.
1 Brief description of Tanda thermal project 3
2 Production of electricity 5
3 Description of thermal plant 9
4 Basic cycle of a power plant 10
5 Control and instrumentation unit 11
6 Important equipment of plant 14
7 Future prospects of NTPC Tanda 31
3
BRIEF DESCRIPTION OF TANDA THERMAL
PROJECT
Geographical location:-
The Tanda Thermal Power Project is located about 185kms from Lucknow.
It is nearly 55kms from Faizabad. The nearest rail ahead is Akhbarpur (now
called as Ambedkarnagar). The project lies in the Ambedkarnagar district
and is about 22kms from the nearest railway station.
The complete project is situated on the bank of Saryu River. The climate
conditions are quite favourable with greenery all around.
Features:-
● The plant has been designed by M/s. Desein
● The installed capacity is 4 X 110 MW
The water requirement of the station is met from the Saryu River through
Mehripur pumping Station constructed for feeding Mehripur Pump Canal.
The coal linkages for the station have been provided from North Karnpura &
BCCL. The power generation is evacuated through 220kV feeders connected
to Sultanpur (2 feeders), Basti & Gorakhpur (1 each) 220kV substations.
The total area of the power house including colony is 235 hectares and the
land for ash disposal is 170 hectares.
✓ The main plant equipments like boiler, turbine and generator have been
supplied by M/s BHEL
✓ Generator-transformer has been supplied M/s NGEF
✓ CHP(Coal Handling Plant) has been supplied by M/s TRF
✓ Cooling Towers by Paharapur Cooling Towers
4
✓ C&I(Control & Instrumentation sets) have been supplied by M/s ILK
✓ DM(De-mineralized) plant has been set up by M/s. WATCO,
Hyderabad
The designed boiler efficiency, turbine heat rate and unit heat rate are 84.7%
and 2172.8kcal/kWh & 2565.3kcal/kWh respectively.
The designed HHV of coal is 3850kcal/kg and the boiler is designed to work
at worst quality of coal having HHV of 3400kcal/kg.
Tanda plant PLF:-
5
2000 2006 2008
PRODUCTION OF ELECTRICITY
The means and steps involved in the production of electricity in a coal-fired
power station are described below.
6
Coal handling plant:
The coal, brought to the station by train or other means, we use wagon tripler
for putting the coal on the conveying belt which consists of mechanical
equipment and motor to drive it. Coal travels from the coal handling plant by
conveyer belt to the coal bunkers. There are magnetic separator and magnet
detecting device placed at conveyer to remove the magnetic element coming
with coal and to indicate magnetic element by the two devices respectively.
Now the coal is collected at certain place which is called stacking, from
where it is fed to the pulverizing mills which grinds it as fine as face powder.
The finely powdered coal mixed with pre-heated air is then blown into the
boiler by fan called Primary Air Fan where it burns, more like a gas than as a
solid in convectional domestic or industrial grate, with additional amount of
air called secondary air supplied by Forced Draft Fan. As the coal has been
grounded so finely the resultant ash is also a fine powder. Some of this ash
binds together to form lumps which fall into the ash pits at the bottom of the
furnace. The water quenched ash from the bottom of the furnace is conveyed
to pits for subsequent disposal or sale. Most of ash, still in fine particles form
is carried out of the boiler to the precipitators as dust, where it is trapped by
electrodes charged with high voltage electricity. The dust is then conveyed
by water to disposal areas or to bunkers for sale while the cleaned flue gases
pass on through ID Fan to be discharged up the chimney.
Way of producing steam by the boiler:
Coal
Handling
Plant,
CHP
Switch
Gear &
Switch
Yard
Turbines &
Generators
Boil
ers
Electrostatic
Precipitator,
ESP
7
Initially we maintain a certain temperature inside the boiler. We pass mixture
of oil and air which is ignited by igniter placed at the corner of the boiler. Oil
used in this purpose may be HSD, HFO and LSHS. After reaching a certain
temperature we pass powdered coal inside the boiler. This produces lots of
heat which helps in producing steam. The steam super-heated in further
tubes (Super Heater) and reaches a temperature about 540 degree centigrade
and about 135 kg per square centimetre pressure and then it passes to the
turbine where it is discharged through the nozzles on the turbine blades.
As the steam strikes on the turbine blades, shaft of the turbine gets
movement due to so it starts rotation and reaches a speed about 3000 rpm.
Then we control the speed of shaft by controlling the passes of powdered
coal to the boiler. The shaft of turbine is mechanically coupled with the shaft
of the generator due to so generator’ s shaft also rotates with a speed about
3000 rpm. The rotor is housed inside the stator having heavy coils of copper
bars in which electricity is produced through the movement of the magnetic
field created by movement of shaft i.e. rotor. The electricity passes from the
stator winding to the step-up transformer which increases its voltage so that
it can be transmitted efficiently over the power lines of the grid.
The steam which has given up its heat energy is changed back into water in
the condenser so that it is ready for re-use. The condenser contains many
kilometres of tubing through which the colder is constantly pumped. The
steam passing around the tubes looses the heat and is rapidly changed back
to water. But the two lots of water (i.e. boiler feed water & cooling water)
must NEVER MIX. The cooling water is drawn from the river, but the boiler
feed water must be absolutely pure, far purer than the water we drink, if it is
not to damage the boiler tubes.
To condense the large quantities of steam, huge and continuous volume of
cooling water is essential. In most of the power stations the same water is to
be used over and over again. So the heat which the water extracts from the
steam in the condenser is removed by pumping the water out to the cooling
towers. The cooling towers are simply concrete shells acting as huge
8
chimneys creating a draught (natural/mechanically assisted by fans) of air.
The water is sprayed out at the top of towers and as it falls into the pond
beneath it is cooled by the upward draught of air. The cold water in the pond
is then circulated by pumps to the condensers. Inevitably, however, some of
the water is drawn upwards as vapours by the draught and it is this which
forms the familiar white clouds which emerge from the towers seen
sometimes.
Why bother to change steam from the turbine back into water if it has to be
heated up again immediately? The answer lies in heat law of physics which
states that the boiling point of water is related to pressure. The lower the
pressure, the lower the temperature at which water boils. The turbine
designer want as low boiling point of water as possible because he can only
utilize the energy of the steam – when the steam changes back into water he
can get NO more work out of it. So a condenser is built, which by rapidly
changing the steam back into water creates a vacuum. This vacuum results in
a much lower boiling point which, in turns, means he can continue getting
work out of the stem well below 100 degree Celsius at which it would
normally change into water.
DESCRIPTION OF THERMAL PLANT
The plant is in fact designed on the modern concept of unit system. Each of
the turbo-generator is connected to its individual steam generating plant. The
steam turbine has inlet steam pressure of about 130kg/cm2 and super heat
type with a reheat temperature of 540 0C. Regenerative feed heating with 8
stages heaters have been adopted. There are two high pressure feed water
heaters connected with the exhaust of the H.P. turbine and the second one
from an extraction of M.P. turbine.
9
Constant pressure de-aeration is adopted for de-aeration and is fed from
auxiliary system header of the plant which maintains the de-aeration pressure
of 6kg/cm2 under all load conditions.
There are five low pressure heaters – two connected to the LP (Low
Pressure) turbine. The heat input from the grand steam condenser and the
ejector condenser is also recovered to improve the cycle efficiency. Drip
pump is also used to pump the drain from the 3rd LP (Low Pressure) heater
back to the condensate system. This also adds to the efficiency of the system.
Drains from various stages of steam turbine are treated so that the maximum
thermodynamics benefit is derived.
The plant is also provided with automatic control features. The operation of
the Coal Handling, Ash Handling, Water treatment Plant, River water Intake
pump is provided with remote as well as local manual control features to
cope with the requirements of such large units.
BASIC CYCLE OF A POWER PLANT
For proper functioning of a power plant, its working operation has been
divided into following main operation cycles.
✓ Steam cycle
✓ Feed water cycle
✓ Condensate water cycle
✓ Primary air cycle
✓ Flue gas cycle
✓ Secondary air cycle
10
Steam cycle: - This cycle basically deals with the flow of steam at
different pressure and temperature to different turbines namely HP, MP and
LP turbines which are connected to the generator. It can be explained from
the figure shown below
Steam coming out from super heater at 540degree C and 139kg per square
cm. Three cylinders of 2 set of main stop and governing valve arrangement
on either side of HP casing and each set consist of one stop valve and 2
governing valve assembling series. The steam from the boiler is admitted the
reheater where it heated at original temp. The reheated steam is taken to IP
casing through combined stop and interceptor valve arrangement at either of
IP casing. The exhaust from the IP casing has taken directly the LP casing.
The steam expanded in the LP turbine to a very low blade pressure which is
maintained by the condenser below atmospheric pressure about 3% of
makeup water is required to condensate the losses of cooling water due to
evaporation in cooling tower. Finally steam exhausted by LP turbine is
condensed in the surface type condenser type cooling water following
11
through a large no. of tubes. The HP, IP &LP turbine coupled in series and
mechanical power generated from steam transmitted to generator.
Feed water cycle:-
this cycle deals with the flow of water to boiler feed pump from feed storage
tank, which is later fed to the boiler drum passing through high pressure
heater and economizer
This system plays an important role in the supply of feed water to the boiler
at requisite pressure and steam/water ratio. This system starts from boiler
feed pump to feed regulating station via HP heaters
12
Boiler feed pump: this pump is horizontal and barrel design driven by an
electric motor through a hydraulic coupling. All the bearings of the pump
and motor are forced lubricated by oil lubricating system. The feed pump
consists of pump barrel into which is mounted the inside starter, together
with rotor. Water cooling and oil lubricating are provided with their
accessories. The brackets of the radial bearing of the suction side and the
radial and thrust bearing of the discharged side are fixed to low pressure.
High pressure heater: these are regenerative feed water heater operating at
high pressure and located by the side of turbine. It is connected in series on
feed water side and by such arrangement the feed water after feed pump
enters the hp heater. the steam supply to these heater from the bleed point of
the turbine through motor operated valves.
Condensate water cycle: - It deals with the water flowing through the
condenser which plays an important role in increasing the efficiency of the
plant. It consists of a feedback path from main ejector to hot well.
The steam after condensing in the condenser known as condensate, is
extracted out of the condenser hot well by condensate pump and taken to the
de-aerator through ejectors, gland steam cooler and series of LP heaters
13
Condensate pump: the function of these pumps is to pump out the
condensate to the deaerator taken to the de-aerator through ejectors, gland
steam cooler and series of LP heaters. This pump is rated generally for 160
cubic meter/hour at a pressure of 13.2 kg/cm square.
LP heater: - there are four LP heaters in which 4 extractions are used.
These heaters are equipped with necessary safety valves in the steam space
level indicator. The condensate flows in the u tube in 4 passes and extraction
steam washes the outside tubes.
Deaerator: - the inner corrosion can be prevented by removing dissolved
gases from the feed water. it can be achieved by embodying into the boiler
feed system a deaerating unit whose function is to remove the dissolved
gases. it works on two principles:: Henry law and solubility law.
Solubility law: solubility of gases decreases with increase in pressure and /or
decrease in pressure.
Henry law: the mass of gas with definite mass of liquid will dissolve at the
given temperature and is directly proportional to the partial pressure of the
gas in contact to liquid.
Primary air cycle: - In this cycle, air is used to carry pulverized coal
from mill to the burning zone of boiler.
Flue gas cycle: - In this cycle, gas containing waste materials are
removed from the system using various techniques like electrostatic
precipitator, ID fans etc. The flue gas, before being removed is used to heat
the primary and secondary air.
Secondary Air cycle: - In this cycle, fuel is mixed with air (known as
secondary air) for proper burning of coal.
14
IMPORTANT EQUIPMENTS OF PLANT
I. Mechanical Equipments:-
a.) Steam generating unit:-
Each steam is of semi outdoor, natural circulation, balanced draft type
designed to burn coal in pulverized form. It is direct fired type meeting the
requirements of latest Indian Boiler Regulation. It has a boiler rating of
375/380 tonnes per hour of steam at a super-heater outlet, at a steam
condition of 139kg/cm2 and a temperature of 5400C.
A re-heater is provided for reheating the exhaust steam from high pressure
system of the turbine to 5400C. The boiler furnace and the gas passages are
designed for low pressure in order to minimize the corrosion & slugging
effect. Closed pitched bore wall tubes with membrane/skin type construction
is adopted for the steam generator furnace walls to ensure maximum
availability and efficiency at MCR not less than 86%.
The unit is provided with two forced draft and two induced draft fans driven
by constant speed electric motors. Each fan is rated for 60% of MCR rating.
Regulation of draft system is by inlet vane control for Forced Draft fan. Shut
off dampers is equipped with pulverized coal firing air fans, coal air pipes,
burners, etc. Four – five pulverized mills are provided for each steam
generator out of which 3 – 4 are capable of meeting MCR with design coal.
Flame scanner is also provided. Furnace Surface Safeguard Supervisor
(FSSS) system is also provided to reduce the risk of explosions and back
fires in the steam generators.
For flame stabilization as well as operation at lower loads, oil burners are
provided. Light oil/gas pilot torch system is adopted for ignition of furnace
oil and pulverized coal.
15
b.) Mechanical Dust Collector & Electrostatic Precipitators:-
Combined – mechanical dust collector & electrostatic precipitator are
provided to arrange arresting of fly ash in order to reduce particle. Efficiency
of about 98% is achieved in this combined system.
c.) Turbine Generator Unit:-
A standard multi-stage, tandem compound extraction type, reheat type,
condensing turbine with seven uncontrolled extractions, operating at
3000rpm is designed to operate with steam condition of 130kg/cm2 at 5350C
at the throttle with reheating at an intermediate stage of 5350C and the
exhaust against a condenser pressure of 0.092kg/cm2 absolute is provided
and is directly coupled to a hydrogen cooled horizontal shaft, totally
enclosed rotating field type generator, designed to generate at 11,000kV,
50Hz, 3-phase with suitable high frequency excitation system. The turbine
and the generator have a nominal rating of 1, 10,000kW and 1, 25,000kVA
respectively at 2kg/cm2 H2 (gauge) pressure.
The turbine is provided with hydraulic (oil) governing system. The turbo-
generator is complete with all auxiliary systems and equipments, lubrication
systems, shaft, gland seal system, motor operated turning gear. All necessary
protective and supervisory instruments are provided to ensure trouble free,
safe and efficient operations of the units. The turbine – generator is
manufactured by M/s. BHEL.
d.) Condensing Equipments:-
Turn surface condenser of identical design, capable of maintaining a vacuum
of about 0.92kg/cm2 while condensing the steam at maximum rating of the
turbine is provided. These tubes are of aluminium–brass and tube sheet is of
16
aluminium-bronze. The condensers are spring mounted and directly
connected to the exhaust flange of the turbine with its axis to the right angles
to that of the turbine.
One starting ejector and two 100%
capacity running ejectors are provided to create and maintain the vacuum in
the condenser by taking out air and other non-condensable gases.
e.) De-aerating heater & Closed heaters:-
The unit is provided with a de-aerating heater and proper capacity of a feed
water tank of approximately 14min storage capacity when machine is
running at full load.
The tray type de-aerator is designed to keep
the oxygen content to 0.007ppm so that the oxygen content in the boiler feed
pump water is kept below any chemical detection.
Steam from extraction line and auxiliary heater
is supplied to the de-aerator which maintains a constant pressure of 6kg/cm2
abs. and the boiler feed pump at the constant pressure irrespective on the
load on the turbo-generator. The feed tank of de-aerator heater is placed on a
suitable elevation to provide sufficient NPSH for the boiler pumps. Level
controllers & communication through level switches is provided to keep the
level of the condensate in the storage tank at a preset value.
Regenerative in the storage on the
condensate is carried out in seven stages by steam of non-regulated
extraction from the turbine and tapping from cold reheat lines. The high
pressure cold heaters are both drain cooling and de-superheating zones in
addition to normal condensing zones. The low pressure feed water heaters
are equipped with only drain cooling and condensing zones.
f.) Boiler :-
● A steam generator is complex integration of following accessories:
1. Economiser 7. Div panels
17
2. Boiler drums 8. Platen SH
3. Down comers 9. Reheater
4. Burners
5. Bottom ring header 11. APHs
6. Water walls
Economiser:-
• Boiler Economiser is feed-water heaters in which the heat from waste
gases is recovered to raise the temperature of feed-water supplied to the
boiler.
• It preheats the feed water by utilizing the residual heat of the flue gas.
• It reduces the exhaust gas temperature and saves the fuel.
18
Boiler drum:-
• It is an enclosed Pressure Vessel
• Heat generated by Combustion of Fuel is transferred to water to
become steam
● Serves two main functions.
● Separating heat from the mixture of water and steam.
● It consists of all equipments used for purification of the steam after
being separated from water.
Boiler drum level control:-
● Important for both plant protection and equipment safety.
● Maintain drum up to level at boiler start-up and maintain the level at
constant steam load.
● Decrease in this level will uncover boiler tubes and get overheated and
damaged.
● Increase in this level will make separation between steam and
moisture difficult within drum.
● Controlled circulation is required to maintain the difference in the
density between water and steam with increase in pressure.
Down comers:-
● It carries water from boiler drum to the ring header.
● They are installed from outside the furnace to keep density difference
for natural circulation of water & steam.
● Heating and evaporating the feed water supplied to the boiler from the
economiser.
19
Water wall:-
• These are membrane walls, no. of tubes are joined.
• Vertical tubes connected at the top and bottom of the Headers.
• Receives water from the boiler drum by down – comers.
Advantage:-
• Increase in efficiency
• Better load response simpler combustion control.
• Quicker starting and stopping
• Increased availability of boiler.
• Heat transfer is better
• Weight is saved in refractory and structure
• Erection is made easy and quick
g.) HP & LP Bypass System:-
Provision of HP & LP bypass system is proposed having a capacity of 40%
steam bypass, making the unit suitable for quick restart as well as peaking
purposes. This has been necessary on account of grid conditions which
shows very acute storage of peaking.
II. Electrical Equipments:-
a.) Generator:-
20
The generator is directly coupled with its respective turbine normally rated
for 110 MW at 0.88 power factor (i.e. 125 MVA), 11kV, 3 phases, 50Hz.
The hydrogen cooling mechanism is used for the generator. The neutral point
of the generator is earthed through a single phase Distribution Transformer,
the secondary of which is shunted through a suitable resistance.
The excitation system consists of high frequency AC mains and pilot
exciters directly driven from the main shaft, silicon rectifying unit and
associated control gears.
b.) Generator Transformer:-
The generation voltage of 11kV is stepped up to 220kV by generator-
transformer (in short GT) whose low voltages side is directly connected with
the generator through an isolated phase bus duct. The rating of generator-
transformer is 125MVA, 11/220kV, 3 phase, 50 Hz having an ON/OFF
cooling. The high voltage side of the transformer is connected to the 220kV
system in 220kV switchyard.
c.) Unit Transformer:-
The bus-duct leading from the generator to the GT is tapped off conveniently
for connection to high voltage side of Unit Auxiliary Transformer used for
stepping down the voltage to 6.6kV for supplying power to the unit auxiliary
loads of the power station. The rating of the UAT is 15MVA, 11/6.6kV, 3-
phase, 50 Hz.
d.) Start-up cum Reserve Transformer:-
Each of the four units draw its start up power from the 220kV system
through two/three windings common start-up cum reserve transformer rated
21
for 30/10/20 MVA, 220/33/6.6 kV, 3 phase, 50Hz. The transformer supplies
the 33kV load requirements. This transformer also meets the requirement of
station loads like coal & ash handling, compressed air and water treatment
plant, station lightening and other common services as well as act as a
standby source of power to unit auxiliaries.
e.) L.T Auxiliary Transformer:-
For further step down of 6.6kV power from the reserve system for utilization
at medium voltage 16 nos. 1000kVA, 6.6kV/415V, 3-phase, 50Hz
transformers have been envisaged. The actual requirement is assessed after
detail design of the system.
Power for station illumination, unit wise is provided by five 300kVA,
6.6kV/415V, 3-phase, 4 wire transformers.
f.) DC Supply System:-
A station battery unit, complete with battery charger and control &
distribution system is installed as required for supply to all loads either for
normal operation or during any emergency conditions.
Exact rating is however determined after the detail study of all loads and
their durations.
g.) Switchgear:-
22
The drives for auxiliary equipment rated 150kW and above are operated at
6.6kV and drives having a rating below 150kW are operated at 415V, 3-
phase, and 4-wire system having a provision for single phase 230V. For
starting up of these motors suitable switchgears/starters are provided.
1. 6.6 kV Switchgears→ 6.6 kV power received from either Unit
Auxiliary Transformer or Reserve Transformer are connected to
respectively 6.6kV switchgear bank through suitable breakers for
further distribution to motors and to transformers for further step
down to 415V.
2. 415 V Switchgear→ The 415V supply from each 1000kVA
transformer are connected to a suitable 415V bus having its
distribution for different motors and starters. Motors capacity above
90kW are controlled by a 415V breaker from respective bus and that
of lower capacity by magnetic contractors grouped together in a sheet
metal cubicle for a number of motors, termed MCC. Protection and
control for individual motors is provided there.
h.) 220kV Switch Yard:
Generator Transformer step-up the 11 kV voltage generated by the Generator
to 220 kV. This voltage is used to charge the three buses in the Switch yard
which follows Double Bus Bar with Transfer Bus Scheme.
Switch yard provides protection between generator transformer and
transmission lines.
Major components of 220 kV Switch yard is:
● Buses (Bus #1, Bus #2 & Transfer Bus).
● Isolators.
● Circuit breaker.(Air Blast Circuit Breaker)
● Current Transformer (CT).
● Capacitor Voltage Transformer (CVT).
23
● Wave Tape.
● Potential Transformer (PT).
● Bays(4-Transmission line , 4-GT , 2-Station transformer , 1-Bus coupler ,
1- Transfer Bus)
The 4 Transmission lines are Basti Line, Gorakhpur Line, Sultanpur-I Line
and Sultanpur-II Line.
III. Auxiliary systems:
The following auxiliary systems for the 4X110 MW as envisaged is
described below:-
a.) Coal Handling System:-
Railway is only the means of transport of coal to this power station. Annual
coal requirement for 4X110 MW units is estimated to be approximately
13.70 lakhs mega tonnes. The coal yard in the layout is adequate for about
30 days storage with two coal stock piles and considering 3800 MT of coal
requirement daily.
Considering inadequate & irregular coal movement by railways it is
adequate to have a marshalling yard capable of handling two rakes a day
normally & three rakes occasionally. Railway siding and marshalling yard is
capable of meeting this requirement.
The coal handling system consists of two wagon tipplers with integral
weight bridge and marshalling equipment for unloading coal into hoppers.
Duplicate belt conveyor system each rated 600 tons/hr feeds coal from the
tippler hoppers to Crusher House. There are two crushers, each rated
600tons/hr. Crushed coal is either stacked in crusher coal yard or conveyed
straight to power house. Duplicate conveyor system carries coal to the top of
boiler bunkers. To stackers/re-claimers are there for stacking and re-claiming
of coal each rated 600 tons/hr.
24
In the power house, over the bunkers, duplicate belt conveyors run, each
provided with a travelling tippler. Suitable arrangements are made for
magnetic separation of iron particles from coal at the inlet to the crusher
house. An automatic belt weighing system is provided at the power house
entry point to register the amount of coal fed into the bunkers.
For emergency, manual arrangements are made for unloading the coal from
wagons and conveying the same to the crusher house.
Necessary dust suppressing equipment and ventilation equipment is provided
as a part of the coal conveying system. The operation of the entire system is
controlled and supervised from control room. The system also has necessary
interlock & safety features. For the purpose of shunting, it has three diesel
locomotives.
b.)Fuel Oil System:-
The fuel oil is made available to the power station in tank wagon. The lighter
grade oil such as light diesel oil is made available for starting of boiler from
cold condition & furnace oil is made available for flame stabilisation
purpose during low load operation and during any other period when flame
stability is not satisfactory. The oil received from the tank wagon is pumped
into the storage tank. The railway siding facilities provided is able to
accommodate on the rake of tank wagons. Two storage tanks for heavy oil
and one for light oil is provided. Provision is made for heating the tanks,
steam tracing the piping and supply of heating steam to tank wagons.
Oil from storage tank is pumped into day oil tanks. The day oil tank is
located near the boiler. Pumps and heaters sets of suitable design then pump
the oil from day storage to the burner. Return oil is fed back into the day
tank. Similar installation is provided for the light oil but the day tank is not
present.
25
b.) Ash Handling System:-
The ash disposal area is within the distance of 4~5kms from the power
station and this is a low lying area. The ash from the boiler hoppers is
conveyed to the ash disposal area either by direct sluicing or hydro-
pneumatic system. Boilers manufactured by M/s. BHEL or AVB are so
designed that it was possible to adopt either of the system for both fly as well
as bottom ash.
The ash disposal area has adequate
capacity for storage of ash for a 640 MW station for over 15 yrs without
reclamation. This area is now being used by Jaypee cement factory for
production of cement and ash bricks. However this area may also be used for
agriculture purposes by covering it with a layer of silt brought from the raw
water reservoir in future
c.) Cooling Water Management:-
The general arrangement & the system have been discussed earlier in the
report. Only the equipments involved in the mechanical system are described
below:-
Water from the raw water reservoir is pumped through clariflocculators. The
clarified water from these clarifloccolator flows to the cooling water basin
by gravity. A clarified pump is present which pumps the clarified water to
the DM plant. For this, three pumps are involved. The outlets from the
cooling water tower basins are connected to the common tunnel which takes
the water back to the power house. From this tunnel water is drawn through
the following pumps to the various equipments as follows:-
1. ) CW Pumps for circulating cooling water through turbine, condenser
and discharging the same to the op of the respective cooling towers. Two
CW Pumps each rated 50% capacity is installed.
2. ) Auxiliary Cooling Water Pumps for supplying cooling water to various
auxiliary equipment for their cooling. This water after circulation through
various bearings and heat exchangers leads to the CW discharge pipe
26
from the condenser for cooling through the cooling tower. The number of
pumps in this case is also two, each of 50% capacity.
3. ) Ash Water Pumps for supplying water for ash handling. There are two
pumps per unit. Ash water is discharged to the ash disposal area but this
continues the part of cooling water blow-down as well and therefore
forms the part of total make-up water of the cooling tower.
e.) Water Treatment Plant:-
A demineralising plant is provided for supplying make-up water for the heat
cycle. Clarified water is pumped from the clarified water storage pit which
passes through pressure filter, activated carbon filter, caution exchanger,
degassifier, anion exchanger and mixed bed exchanger. There are four
streams each rated 30m3/hr. Adequate facilities are provided for unloading,
handling and storage of chemicals. Waste effluent is neutralised before it is
discharged to outside drain.
FUTURE PROSPECTS OF NTPC TANDA
NTPC Tanda is providing electricity to 3 different cities (Gorakhpur, Basti &
Sultanpur).At present time, plant is delivering electricity up to PLF 102% i.e.
generating power more than specified. In near future, generating capacity of
plant is going to be increased by two units of 660MW each. So NTPC is
playing a major role in development of INDIA
REGARDS:-
For the humble guidance and cooperation, we are thankful to
● Mr.Sanjeev Gupta (DGM)
● Mr.A.K.Mishra (DGM)
● Mr.Lalit Kr. Singh (DY.SUPT)
27
● Mrs.Seema Deo (Sr.Engineer)
● Mr.Sudhir Basista (Engineer)
● Mr.Anand Choudhry (Engineer)
● Mr. A.H.Rizvi (Engineer)
● Mr.Rahul Kr.Jaiswal (E.T.)
● Miss.Poonam kumari (E.T)
● Miss.Saroj (E.T)

More Related Content

What's hot

thermal power plant
thermal power plant thermal power plant
thermal power plant GOD BRAIN
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurAbhishek Mathur
 
Talwandi sabo power plant (t
Talwandi sabo power plant (tTalwandi sabo power plant (t
Talwandi sabo power plant (t21403515
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)sometech
 
Sipat thermal power plant
Sipat thermal power plantSipat thermal power plant
Sipat thermal power plantJinendra Ninama
 
Panipat thermal power station training ppt
Panipat thermal power station training pptPanipat thermal power station training ppt
Panipat thermal power station training pptMohit Verma
 
PANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANTPANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANTSahil arora
 
Power plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikasPower plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikasVikas Gupta
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant pptPrakash Jarotia
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptEr. Aman Agrawal
 

What's hot (20)

thermal power plant
thermal power plant thermal power plant
thermal power plant
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathur
 
Talwandi sabo power plant (t
Talwandi sabo power plant (tTalwandi sabo power plant (t
Talwandi sabo power plant (t
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
 
Sipat thermal power plant
Sipat thermal power plantSipat thermal power plant
Sipat thermal power plant
 
Training Report, Thermal Power Plant Report, KSTPS Report
Training Report, Thermal Power Plant Report, KSTPS ReportTraining Report, Thermal Power Plant Report, KSTPS Report
Training Report, Thermal Power Plant Report, KSTPS Report
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant
 
Panipat thermal power station training ppt
Panipat thermal power station training pptPanipat thermal power station training ppt
Panipat thermal power station training ppt
 
ppt on kstps 2016
ppt on kstps 2016ppt on kstps 2016
ppt on kstps 2016
 
Richappt
RichapptRichappt
Richappt
 
Stps report
Stps reportStps report
Stps report
 
Power plant, Power Station and types of power plant
Power plant, Power Station and types of power plantPower plant, Power Station and types of power plant
Power plant, Power Station and types of power plant
 
PANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANTPANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANT
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal powerr plant
Thermal powerr plant  Thermal powerr plant
Thermal powerr plant
 
Power plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikasPower plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikas
 
Ntpc report harsh
Ntpc report  harshNtpc report  harsh
Ntpc report harsh
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 

Similar to NTPC Tanda Project Acknowledgement and Training Details

compalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docxcompalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docxVishalSen33
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02arvind singh rathore
 
Sandeep verma ppt on kstps
Sandeep verma ppt on kstps   Sandeep verma ppt on kstps
Sandeep verma ppt on kstps sandeep244266
 
Ntpc ppt complete
Ntpc ppt completeNtpc ppt complete
Ntpc ppt completeVikas Singh
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT Amit Gupta
 
Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardI.E.T. lucknow
 
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKKOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKRanjan Naik
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionSuvamSahu2
 
NTPC ,sipat voccational training
NTPC ,sipat voccational trainingNTPC ,sipat voccational training
NTPC ,sipat voccational trainingbhumit1
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORTUday Wankar
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantRabi Kumar
 
ntpc thermal power plant.ppt
ntpc thermal power plant.pptntpc thermal power plant.ppt
ntpc thermal power plant.pptKaushal Kumar
 
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingChandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingPragya wan
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Srikanta Sinha
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarRishikesh .
 

Similar to NTPC Tanda Project Acknowledgement and Training Details (20)

compalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docxcompalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docx
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
 
Sandeep verma ppt on kstps
Sandeep verma ppt on kstps   Sandeep verma ppt on kstps
Sandeep verma ppt on kstps
 
Ntpc2
Ntpc2Ntpc2
Ntpc2
 
Ntpc ppt complete
Ntpc ppt completeNtpc ppt complete
Ntpc ppt complete
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
 
Complete report
Complete reportComplete report
Complete report
 
Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyard
 
Harsh ntpc
Harsh ntpcHarsh ntpc
Harsh ntpc
 
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKKOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
 
Bandel training
Bandel trainingBandel training
Bandel training
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
 
NTPC ,sipat voccational training
NTPC ,sipat voccational trainingNTPC ,sipat voccational training
NTPC ,sipat voccational training
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
ntpc thermal power plant.ppt
ntpc thermal power plant.pptntpc thermal power plant.ppt
ntpc thermal power plant.ppt
 
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingChandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC Shaktinagar
 

Recently uploaded

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 

Recently uploaded (20)

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 

NTPC Tanda Project Acknowledgement and Training Details

  • 1. 1 ACKNOWLEDGEMENT We hereby take this opportunity to thanks NTPC Tanda for giving us this opportunity to conduct our training in NTPC Tanda. We are grateful to Shri S N Shukla (Supdt. TMD), for allowing us to conduct our training in the Control and Instrumentation department. We are heartily indebted to our project guide P S Rawat ( Engr. TMD) for providing us with detailed in depth knowledge and very useful information about the process and system used in the plant. His support was instrumental in our training being fruitful. We are also thankful to the entire officer and staff of NTPC Tanda for extending a helping hand whenever we need it. DEEPAK VERMA
  • 2. 2 CONTENT S.No. Description Page No. 1 Brief description of Tanda thermal project 3 2 Production of electricity 5 3 Description of thermal plant 9 4 Basic cycle of a power plant 10 5 Control and instrumentation unit 11 6 Important equipment of plant 14 7 Future prospects of NTPC Tanda 31
  • 3. 3 BRIEF DESCRIPTION OF TANDA THERMAL PROJECT Geographical location:- The Tanda Thermal Power Project is located about 185kms from Lucknow. It is nearly 55kms from Faizabad. The nearest rail ahead is Akhbarpur (now called as Ambedkarnagar). The project lies in the Ambedkarnagar district and is about 22kms from the nearest railway station. The complete project is situated on the bank of Saryu River. The climate conditions are quite favourable with greenery all around. Features:- ● The plant has been designed by M/s. Desein ● The installed capacity is 4 X 110 MW The water requirement of the station is met from the Saryu River through Mehripur pumping Station constructed for feeding Mehripur Pump Canal. The coal linkages for the station have been provided from North Karnpura & BCCL. The power generation is evacuated through 220kV feeders connected to Sultanpur (2 feeders), Basti & Gorakhpur (1 each) 220kV substations. The total area of the power house including colony is 235 hectares and the land for ash disposal is 170 hectares. ✓ The main plant equipments like boiler, turbine and generator have been supplied by M/s BHEL ✓ Generator-transformer has been supplied M/s NGEF ✓ CHP(Coal Handling Plant) has been supplied by M/s TRF ✓ Cooling Towers by Paharapur Cooling Towers
  • 4. 4 ✓ C&I(Control & Instrumentation sets) have been supplied by M/s ILK ✓ DM(De-mineralized) plant has been set up by M/s. WATCO, Hyderabad The designed boiler efficiency, turbine heat rate and unit heat rate are 84.7% and 2172.8kcal/kWh & 2565.3kcal/kWh respectively. The designed HHV of coal is 3850kcal/kg and the boiler is designed to work at worst quality of coal having HHV of 3400kcal/kg. Tanda plant PLF:-
  • 5. 5 2000 2006 2008 PRODUCTION OF ELECTRICITY The means and steps involved in the production of electricity in a coal-fired power station are described below.
  • 6. 6 Coal handling plant: The coal, brought to the station by train or other means, we use wagon tripler for putting the coal on the conveying belt which consists of mechanical equipment and motor to drive it. Coal travels from the coal handling plant by conveyer belt to the coal bunkers. There are magnetic separator and magnet detecting device placed at conveyer to remove the magnetic element coming with coal and to indicate magnetic element by the two devices respectively. Now the coal is collected at certain place which is called stacking, from where it is fed to the pulverizing mills which grinds it as fine as face powder. The finely powdered coal mixed with pre-heated air is then blown into the boiler by fan called Primary Air Fan where it burns, more like a gas than as a solid in convectional domestic or industrial grate, with additional amount of air called secondary air supplied by Forced Draft Fan. As the coal has been grounded so finely the resultant ash is also a fine powder. Some of this ash binds together to form lumps which fall into the ash pits at the bottom of the furnace. The water quenched ash from the bottom of the furnace is conveyed to pits for subsequent disposal or sale. Most of ash, still in fine particles form is carried out of the boiler to the precipitators as dust, where it is trapped by electrodes charged with high voltage electricity. The dust is then conveyed by water to disposal areas or to bunkers for sale while the cleaned flue gases pass on through ID Fan to be discharged up the chimney. Way of producing steam by the boiler: Coal Handling Plant, CHP Switch Gear & Switch Yard Turbines & Generators Boil ers Electrostatic Precipitator, ESP
  • 7. 7 Initially we maintain a certain temperature inside the boiler. We pass mixture of oil and air which is ignited by igniter placed at the corner of the boiler. Oil used in this purpose may be HSD, HFO and LSHS. After reaching a certain temperature we pass powdered coal inside the boiler. This produces lots of heat which helps in producing steam. The steam super-heated in further tubes (Super Heater) and reaches a temperature about 540 degree centigrade and about 135 kg per square centimetre pressure and then it passes to the turbine where it is discharged through the nozzles on the turbine blades. As the steam strikes on the turbine blades, shaft of the turbine gets movement due to so it starts rotation and reaches a speed about 3000 rpm. Then we control the speed of shaft by controlling the passes of powdered coal to the boiler. The shaft of turbine is mechanically coupled with the shaft of the generator due to so generator’ s shaft also rotates with a speed about 3000 rpm. The rotor is housed inside the stator having heavy coils of copper bars in which electricity is produced through the movement of the magnetic field created by movement of shaft i.e. rotor. The electricity passes from the stator winding to the step-up transformer which increases its voltage so that it can be transmitted efficiently over the power lines of the grid. The steam which has given up its heat energy is changed back into water in the condenser so that it is ready for re-use. The condenser contains many kilometres of tubing through which the colder is constantly pumped. The steam passing around the tubes looses the heat and is rapidly changed back to water. But the two lots of water (i.e. boiler feed water & cooling water) must NEVER MIX. The cooling water is drawn from the river, but the boiler feed water must be absolutely pure, far purer than the water we drink, if it is not to damage the boiler tubes. To condense the large quantities of steam, huge and continuous volume of cooling water is essential. In most of the power stations the same water is to be used over and over again. So the heat which the water extracts from the steam in the condenser is removed by pumping the water out to the cooling towers. The cooling towers are simply concrete shells acting as huge
  • 8. 8 chimneys creating a draught (natural/mechanically assisted by fans) of air. The water is sprayed out at the top of towers and as it falls into the pond beneath it is cooled by the upward draught of air. The cold water in the pond is then circulated by pumps to the condensers. Inevitably, however, some of the water is drawn upwards as vapours by the draught and it is this which forms the familiar white clouds which emerge from the towers seen sometimes. Why bother to change steam from the turbine back into water if it has to be heated up again immediately? The answer lies in heat law of physics which states that the boiling point of water is related to pressure. The lower the pressure, the lower the temperature at which water boils. The turbine designer want as low boiling point of water as possible because he can only utilize the energy of the steam – when the steam changes back into water he can get NO more work out of it. So a condenser is built, which by rapidly changing the steam back into water creates a vacuum. This vacuum results in a much lower boiling point which, in turns, means he can continue getting work out of the stem well below 100 degree Celsius at which it would normally change into water. DESCRIPTION OF THERMAL PLANT The plant is in fact designed on the modern concept of unit system. Each of the turbo-generator is connected to its individual steam generating plant. The steam turbine has inlet steam pressure of about 130kg/cm2 and super heat type with a reheat temperature of 540 0C. Regenerative feed heating with 8 stages heaters have been adopted. There are two high pressure feed water heaters connected with the exhaust of the H.P. turbine and the second one from an extraction of M.P. turbine.
  • 9. 9 Constant pressure de-aeration is adopted for de-aeration and is fed from auxiliary system header of the plant which maintains the de-aeration pressure of 6kg/cm2 under all load conditions. There are five low pressure heaters – two connected to the LP (Low Pressure) turbine. The heat input from the grand steam condenser and the ejector condenser is also recovered to improve the cycle efficiency. Drip pump is also used to pump the drain from the 3rd LP (Low Pressure) heater back to the condensate system. This also adds to the efficiency of the system. Drains from various stages of steam turbine are treated so that the maximum thermodynamics benefit is derived. The plant is also provided with automatic control features. The operation of the Coal Handling, Ash Handling, Water treatment Plant, River water Intake pump is provided with remote as well as local manual control features to cope with the requirements of such large units. BASIC CYCLE OF A POWER PLANT For proper functioning of a power plant, its working operation has been divided into following main operation cycles. ✓ Steam cycle ✓ Feed water cycle ✓ Condensate water cycle ✓ Primary air cycle ✓ Flue gas cycle ✓ Secondary air cycle
  • 10. 10 Steam cycle: - This cycle basically deals with the flow of steam at different pressure and temperature to different turbines namely HP, MP and LP turbines which are connected to the generator. It can be explained from the figure shown below Steam coming out from super heater at 540degree C and 139kg per square cm. Three cylinders of 2 set of main stop and governing valve arrangement on either side of HP casing and each set consist of one stop valve and 2 governing valve assembling series. The steam from the boiler is admitted the reheater where it heated at original temp. The reheated steam is taken to IP casing through combined stop and interceptor valve arrangement at either of IP casing. The exhaust from the IP casing has taken directly the LP casing. The steam expanded in the LP turbine to a very low blade pressure which is maintained by the condenser below atmospheric pressure about 3% of makeup water is required to condensate the losses of cooling water due to evaporation in cooling tower. Finally steam exhausted by LP turbine is condensed in the surface type condenser type cooling water following
  • 11. 11 through a large no. of tubes. The HP, IP &LP turbine coupled in series and mechanical power generated from steam transmitted to generator. Feed water cycle:- this cycle deals with the flow of water to boiler feed pump from feed storage tank, which is later fed to the boiler drum passing through high pressure heater and economizer This system plays an important role in the supply of feed water to the boiler at requisite pressure and steam/water ratio. This system starts from boiler feed pump to feed regulating station via HP heaters
  • 12. 12 Boiler feed pump: this pump is horizontal and barrel design driven by an electric motor through a hydraulic coupling. All the bearings of the pump and motor are forced lubricated by oil lubricating system. The feed pump consists of pump barrel into which is mounted the inside starter, together with rotor. Water cooling and oil lubricating are provided with their accessories. The brackets of the radial bearing of the suction side and the radial and thrust bearing of the discharged side are fixed to low pressure. High pressure heater: these are regenerative feed water heater operating at high pressure and located by the side of turbine. It is connected in series on feed water side and by such arrangement the feed water after feed pump enters the hp heater. the steam supply to these heater from the bleed point of the turbine through motor operated valves. Condensate water cycle: - It deals with the water flowing through the condenser which plays an important role in increasing the efficiency of the plant. It consists of a feedback path from main ejector to hot well. The steam after condensing in the condenser known as condensate, is extracted out of the condenser hot well by condensate pump and taken to the de-aerator through ejectors, gland steam cooler and series of LP heaters
  • 13. 13 Condensate pump: the function of these pumps is to pump out the condensate to the deaerator taken to the de-aerator through ejectors, gland steam cooler and series of LP heaters. This pump is rated generally for 160 cubic meter/hour at a pressure of 13.2 kg/cm square. LP heater: - there are four LP heaters in which 4 extractions are used. These heaters are equipped with necessary safety valves in the steam space level indicator. The condensate flows in the u tube in 4 passes and extraction steam washes the outside tubes. Deaerator: - the inner corrosion can be prevented by removing dissolved gases from the feed water. it can be achieved by embodying into the boiler feed system a deaerating unit whose function is to remove the dissolved gases. it works on two principles:: Henry law and solubility law. Solubility law: solubility of gases decreases with increase in pressure and /or decrease in pressure. Henry law: the mass of gas with definite mass of liquid will dissolve at the given temperature and is directly proportional to the partial pressure of the gas in contact to liquid. Primary air cycle: - In this cycle, air is used to carry pulverized coal from mill to the burning zone of boiler. Flue gas cycle: - In this cycle, gas containing waste materials are removed from the system using various techniques like electrostatic precipitator, ID fans etc. The flue gas, before being removed is used to heat the primary and secondary air. Secondary Air cycle: - In this cycle, fuel is mixed with air (known as secondary air) for proper burning of coal.
  • 14. 14 IMPORTANT EQUIPMENTS OF PLANT I. Mechanical Equipments:- a.) Steam generating unit:- Each steam is of semi outdoor, natural circulation, balanced draft type designed to burn coal in pulverized form. It is direct fired type meeting the requirements of latest Indian Boiler Regulation. It has a boiler rating of 375/380 tonnes per hour of steam at a super-heater outlet, at a steam condition of 139kg/cm2 and a temperature of 5400C. A re-heater is provided for reheating the exhaust steam from high pressure system of the turbine to 5400C. The boiler furnace and the gas passages are designed for low pressure in order to minimize the corrosion & slugging effect. Closed pitched bore wall tubes with membrane/skin type construction is adopted for the steam generator furnace walls to ensure maximum availability and efficiency at MCR not less than 86%. The unit is provided with two forced draft and two induced draft fans driven by constant speed electric motors. Each fan is rated for 60% of MCR rating. Regulation of draft system is by inlet vane control for Forced Draft fan. Shut off dampers is equipped with pulverized coal firing air fans, coal air pipes, burners, etc. Four – five pulverized mills are provided for each steam generator out of which 3 – 4 are capable of meeting MCR with design coal. Flame scanner is also provided. Furnace Surface Safeguard Supervisor (FSSS) system is also provided to reduce the risk of explosions and back fires in the steam generators. For flame stabilization as well as operation at lower loads, oil burners are provided. Light oil/gas pilot torch system is adopted for ignition of furnace oil and pulverized coal.
  • 15. 15 b.) Mechanical Dust Collector & Electrostatic Precipitators:- Combined – mechanical dust collector & electrostatic precipitator are provided to arrange arresting of fly ash in order to reduce particle. Efficiency of about 98% is achieved in this combined system. c.) Turbine Generator Unit:- A standard multi-stage, tandem compound extraction type, reheat type, condensing turbine with seven uncontrolled extractions, operating at 3000rpm is designed to operate with steam condition of 130kg/cm2 at 5350C at the throttle with reheating at an intermediate stage of 5350C and the exhaust against a condenser pressure of 0.092kg/cm2 absolute is provided and is directly coupled to a hydrogen cooled horizontal shaft, totally enclosed rotating field type generator, designed to generate at 11,000kV, 50Hz, 3-phase with suitable high frequency excitation system. The turbine and the generator have a nominal rating of 1, 10,000kW and 1, 25,000kVA respectively at 2kg/cm2 H2 (gauge) pressure. The turbine is provided with hydraulic (oil) governing system. The turbo- generator is complete with all auxiliary systems and equipments, lubrication systems, shaft, gland seal system, motor operated turning gear. All necessary protective and supervisory instruments are provided to ensure trouble free, safe and efficient operations of the units. The turbine – generator is manufactured by M/s. BHEL. d.) Condensing Equipments:- Turn surface condenser of identical design, capable of maintaining a vacuum of about 0.92kg/cm2 while condensing the steam at maximum rating of the turbine is provided. These tubes are of aluminium–brass and tube sheet is of
  • 16. 16 aluminium-bronze. The condensers are spring mounted and directly connected to the exhaust flange of the turbine with its axis to the right angles to that of the turbine. One starting ejector and two 100% capacity running ejectors are provided to create and maintain the vacuum in the condenser by taking out air and other non-condensable gases. e.) De-aerating heater & Closed heaters:- The unit is provided with a de-aerating heater and proper capacity of a feed water tank of approximately 14min storage capacity when machine is running at full load. The tray type de-aerator is designed to keep the oxygen content to 0.007ppm so that the oxygen content in the boiler feed pump water is kept below any chemical detection. Steam from extraction line and auxiliary heater is supplied to the de-aerator which maintains a constant pressure of 6kg/cm2 abs. and the boiler feed pump at the constant pressure irrespective on the load on the turbo-generator. The feed tank of de-aerator heater is placed on a suitable elevation to provide sufficient NPSH for the boiler pumps. Level controllers & communication through level switches is provided to keep the level of the condensate in the storage tank at a preset value. Regenerative in the storage on the condensate is carried out in seven stages by steam of non-regulated extraction from the turbine and tapping from cold reheat lines. The high pressure cold heaters are both drain cooling and de-superheating zones in addition to normal condensing zones. The low pressure feed water heaters are equipped with only drain cooling and condensing zones. f.) Boiler :- ● A steam generator is complex integration of following accessories: 1. Economiser 7. Div panels
  • 17. 17 2. Boiler drums 8. Platen SH 3. Down comers 9. Reheater 4. Burners 5. Bottom ring header 11. APHs 6. Water walls Economiser:- • Boiler Economiser is feed-water heaters in which the heat from waste gases is recovered to raise the temperature of feed-water supplied to the boiler. • It preheats the feed water by utilizing the residual heat of the flue gas. • It reduces the exhaust gas temperature and saves the fuel.
  • 18. 18 Boiler drum:- • It is an enclosed Pressure Vessel • Heat generated by Combustion of Fuel is transferred to water to become steam ● Serves two main functions. ● Separating heat from the mixture of water and steam. ● It consists of all equipments used for purification of the steam after being separated from water. Boiler drum level control:- ● Important for both plant protection and equipment safety. ● Maintain drum up to level at boiler start-up and maintain the level at constant steam load. ● Decrease in this level will uncover boiler tubes and get overheated and damaged. ● Increase in this level will make separation between steam and moisture difficult within drum. ● Controlled circulation is required to maintain the difference in the density between water and steam with increase in pressure. Down comers:- ● It carries water from boiler drum to the ring header. ● They are installed from outside the furnace to keep density difference for natural circulation of water & steam. ● Heating and evaporating the feed water supplied to the boiler from the economiser.
  • 19. 19 Water wall:- • These are membrane walls, no. of tubes are joined. • Vertical tubes connected at the top and bottom of the Headers. • Receives water from the boiler drum by down – comers. Advantage:- • Increase in efficiency • Better load response simpler combustion control. • Quicker starting and stopping • Increased availability of boiler. • Heat transfer is better • Weight is saved in refractory and structure • Erection is made easy and quick g.) HP & LP Bypass System:- Provision of HP & LP bypass system is proposed having a capacity of 40% steam bypass, making the unit suitable for quick restart as well as peaking purposes. This has been necessary on account of grid conditions which shows very acute storage of peaking. II. Electrical Equipments:- a.) Generator:-
  • 20. 20 The generator is directly coupled with its respective turbine normally rated for 110 MW at 0.88 power factor (i.e. 125 MVA), 11kV, 3 phases, 50Hz. The hydrogen cooling mechanism is used for the generator. The neutral point of the generator is earthed through a single phase Distribution Transformer, the secondary of which is shunted through a suitable resistance. The excitation system consists of high frequency AC mains and pilot exciters directly driven from the main shaft, silicon rectifying unit and associated control gears. b.) Generator Transformer:- The generation voltage of 11kV is stepped up to 220kV by generator- transformer (in short GT) whose low voltages side is directly connected with the generator through an isolated phase bus duct. The rating of generator- transformer is 125MVA, 11/220kV, 3 phase, 50 Hz having an ON/OFF cooling. The high voltage side of the transformer is connected to the 220kV system in 220kV switchyard. c.) Unit Transformer:- The bus-duct leading from the generator to the GT is tapped off conveniently for connection to high voltage side of Unit Auxiliary Transformer used for stepping down the voltage to 6.6kV for supplying power to the unit auxiliary loads of the power station. The rating of the UAT is 15MVA, 11/6.6kV, 3- phase, 50 Hz. d.) Start-up cum Reserve Transformer:- Each of the four units draw its start up power from the 220kV system through two/three windings common start-up cum reserve transformer rated
  • 21. 21 for 30/10/20 MVA, 220/33/6.6 kV, 3 phase, 50Hz. The transformer supplies the 33kV load requirements. This transformer also meets the requirement of station loads like coal & ash handling, compressed air and water treatment plant, station lightening and other common services as well as act as a standby source of power to unit auxiliaries. e.) L.T Auxiliary Transformer:- For further step down of 6.6kV power from the reserve system for utilization at medium voltage 16 nos. 1000kVA, 6.6kV/415V, 3-phase, 50Hz transformers have been envisaged. The actual requirement is assessed after detail design of the system. Power for station illumination, unit wise is provided by five 300kVA, 6.6kV/415V, 3-phase, 4 wire transformers. f.) DC Supply System:- A station battery unit, complete with battery charger and control & distribution system is installed as required for supply to all loads either for normal operation or during any emergency conditions. Exact rating is however determined after the detail study of all loads and their durations. g.) Switchgear:-
  • 22. 22 The drives for auxiliary equipment rated 150kW and above are operated at 6.6kV and drives having a rating below 150kW are operated at 415V, 3- phase, and 4-wire system having a provision for single phase 230V. For starting up of these motors suitable switchgears/starters are provided. 1. 6.6 kV Switchgears→ 6.6 kV power received from either Unit Auxiliary Transformer or Reserve Transformer are connected to respectively 6.6kV switchgear bank through suitable breakers for further distribution to motors and to transformers for further step down to 415V. 2. 415 V Switchgear→ The 415V supply from each 1000kVA transformer are connected to a suitable 415V bus having its distribution for different motors and starters. Motors capacity above 90kW are controlled by a 415V breaker from respective bus and that of lower capacity by magnetic contractors grouped together in a sheet metal cubicle for a number of motors, termed MCC. Protection and control for individual motors is provided there. h.) 220kV Switch Yard: Generator Transformer step-up the 11 kV voltage generated by the Generator to 220 kV. This voltage is used to charge the three buses in the Switch yard which follows Double Bus Bar with Transfer Bus Scheme. Switch yard provides protection between generator transformer and transmission lines. Major components of 220 kV Switch yard is: ● Buses (Bus #1, Bus #2 & Transfer Bus). ● Isolators. ● Circuit breaker.(Air Blast Circuit Breaker) ● Current Transformer (CT). ● Capacitor Voltage Transformer (CVT).
  • 23. 23 ● Wave Tape. ● Potential Transformer (PT). ● Bays(4-Transmission line , 4-GT , 2-Station transformer , 1-Bus coupler , 1- Transfer Bus) The 4 Transmission lines are Basti Line, Gorakhpur Line, Sultanpur-I Line and Sultanpur-II Line. III. Auxiliary systems: The following auxiliary systems for the 4X110 MW as envisaged is described below:- a.) Coal Handling System:- Railway is only the means of transport of coal to this power station. Annual coal requirement for 4X110 MW units is estimated to be approximately 13.70 lakhs mega tonnes. The coal yard in the layout is adequate for about 30 days storage with two coal stock piles and considering 3800 MT of coal requirement daily. Considering inadequate & irregular coal movement by railways it is adequate to have a marshalling yard capable of handling two rakes a day normally & three rakes occasionally. Railway siding and marshalling yard is capable of meeting this requirement. The coal handling system consists of two wagon tipplers with integral weight bridge and marshalling equipment for unloading coal into hoppers. Duplicate belt conveyor system each rated 600 tons/hr feeds coal from the tippler hoppers to Crusher House. There are two crushers, each rated 600tons/hr. Crushed coal is either stacked in crusher coal yard or conveyed straight to power house. Duplicate conveyor system carries coal to the top of boiler bunkers. To stackers/re-claimers are there for stacking and re-claiming of coal each rated 600 tons/hr.
  • 24. 24 In the power house, over the bunkers, duplicate belt conveyors run, each provided with a travelling tippler. Suitable arrangements are made for magnetic separation of iron particles from coal at the inlet to the crusher house. An automatic belt weighing system is provided at the power house entry point to register the amount of coal fed into the bunkers. For emergency, manual arrangements are made for unloading the coal from wagons and conveying the same to the crusher house. Necessary dust suppressing equipment and ventilation equipment is provided as a part of the coal conveying system. The operation of the entire system is controlled and supervised from control room. The system also has necessary interlock & safety features. For the purpose of shunting, it has three diesel locomotives. b.)Fuel Oil System:- The fuel oil is made available to the power station in tank wagon. The lighter grade oil such as light diesel oil is made available for starting of boiler from cold condition & furnace oil is made available for flame stabilisation purpose during low load operation and during any other period when flame stability is not satisfactory. The oil received from the tank wagon is pumped into the storage tank. The railway siding facilities provided is able to accommodate on the rake of tank wagons. Two storage tanks for heavy oil and one for light oil is provided. Provision is made for heating the tanks, steam tracing the piping and supply of heating steam to tank wagons. Oil from storage tank is pumped into day oil tanks. The day oil tank is located near the boiler. Pumps and heaters sets of suitable design then pump the oil from day storage to the burner. Return oil is fed back into the day tank. Similar installation is provided for the light oil but the day tank is not present.
  • 25. 25 b.) Ash Handling System:- The ash disposal area is within the distance of 4~5kms from the power station and this is a low lying area. The ash from the boiler hoppers is conveyed to the ash disposal area either by direct sluicing or hydro- pneumatic system. Boilers manufactured by M/s. BHEL or AVB are so designed that it was possible to adopt either of the system for both fly as well as bottom ash. The ash disposal area has adequate capacity for storage of ash for a 640 MW station for over 15 yrs without reclamation. This area is now being used by Jaypee cement factory for production of cement and ash bricks. However this area may also be used for agriculture purposes by covering it with a layer of silt brought from the raw water reservoir in future c.) Cooling Water Management:- The general arrangement & the system have been discussed earlier in the report. Only the equipments involved in the mechanical system are described below:- Water from the raw water reservoir is pumped through clariflocculators. The clarified water from these clarifloccolator flows to the cooling water basin by gravity. A clarified pump is present which pumps the clarified water to the DM plant. For this, three pumps are involved. The outlets from the cooling water tower basins are connected to the common tunnel which takes the water back to the power house. From this tunnel water is drawn through the following pumps to the various equipments as follows:- 1. ) CW Pumps for circulating cooling water through turbine, condenser and discharging the same to the op of the respective cooling towers. Two CW Pumps each rated 50% capacity is installed. 2. ) Auxiliary Cooling Water Pumps for supplying cooling water to various auxiliary equipment for their cooling. This water after circulation through various bearings and heat exchangers leads to the CW discharge pipe
  • 26. 26 from the condenser for cooling through the cooling tower. The number of pumps in this case is also two, each of 50% capacity. 3. ) Ash Water Pumps for supplying water for ash handling. There are two pumps per unit. Ash water is discharged to the ash disposal area but this continues the part of cooling water blow-down as well and therefore forms the part of total make-up water of the cooling tower. e.) Water Treatment Plant:- A demineralising plant is provided for supplying make-up water for the heat cycle. Clarified water is pumped from the clarified water storage pit which passes through pressure filter, activated carbon filter, caution exchanger, degassifier, anion exchanger and mixed bed exchanger. There are four streams each rated 30m3/hr. Adequate facilities are provided for unloading, handling and storage of chemicals. Waste effluent is neutralised before it is discharged to outside drain. FUTURE PROSPECTS OF NTPC TANDA NTPC Tanda is providing electricity to 3 different cities (Gorakhpur, Basti & Sultanpur).At present time, plant is delivering electricity up to PLF 102% i.e. generating power more than specified. In near future, generating capacity of plant is going to be increased by two units of 660MW each. So NTPC is playing a major role in development of INDIA REGARDS:- For the humble guidance and cooperation, we are thankful to ● Mr.Sanjeev Gupta (DGM) ● Mr.A.K.Mishra (DGM) ● Mr.Lalit Kr. Singh (DY.SUPT)
  • 27. 27 ● Mrs.Seema Deo (Sr.Engineer) ● Mr.Sudhir Basista (Engineer) ● Mr.Anand Choudhry (Engineer) ● Mr. A.H.Rizvi (Engineer) ● Mr.Rahul Kr.Jaiswal (E.T.) ● Miss.Poonam kumari (E.T) ● Miss.Saroj (E.T)