SlideShare a Scribd company logo
1 of 10
Download to read offline
International Journal of Applied Power Engineering (IJAPE)
Vol. 1, No. 1, April 2012, pp. 37~46
ISSN: 2252-8792 37
Journal homepage: http://iaesjournal.com/online/index.php/IJAPE
Reduced Dielectric Losses for Underground Cable Distribution
Systems
HamzahEteruddin*, Abdullah Asuhaimi bin Mohd Zin**
*Departement of Electrical Engineering, Lancang Kuning University
**Departement of Electrical Power Engineering, UniversitiTeknologi Malaysia
Article Info ABSTRACT
Article history:
Received Jan 13, 2012
Revised Mar 14, 2012
Accepted Mar 26, 2012
This paper describes the process to reduce dielectric losses for underground
cable distribution system. As already known, that system is an alternative
solution to energy distribution systems in urban areas. Influence of large
capacitance is a separate issue that needs to be resolved. Large capacitance
effect on Express Feeder of 10 miles long has resulted in power losses more
than 100 MW per month. In the no-load condition, current dispatch has
recorded 10 Amperes, and has increased the voltage at receiving end by 200-
500 Volts, with leading power factors. Installation of the inductor to reduce
cable loss dielectrics is done by changing the power factor (pf) to 0.85
lagging. After installation of the inductor, which is 5 mH/700 kVAR,
dielectric losses is reduced to 3.57%, which is from105,983 kW to 102,195
kWh per month. The capacitive leakage current has also been reduced from
249.61 Ampere to 245.17 Ampere.
Keyword:
Dielectric Losses
Underground Cables
Distribution System
Capasitance
Copyright © 2012 Institute of Advanced Engineering and Science.
All rights reserved.
Corresponding Author:
Hamzah Eteruddin
Departement of Electrical Engineering,
LancangKuning University,
YosSudarsoRoad, km 8 – Rumbai, Pekanbaru28265, Indonesia.
Email: hamzah128@gmail.com
1. INTRODUCTION
The most important things required in the power system is a matter of quantity and quality of the
received energy on the consumer side. Delivery quantity is required to distribute electric power to all
consumers in a region or area served, so the benefits from the existence of electric energy can be felt by the
public. Increasing the quantity of electric power distribution will increase the electrification ratio in an area.
At the same time, the quality of distribution of electrical energy is required to maintain the availability of
electrical energy consumers in accordance with the standards used.
Quantity and quality of electric energy distribution in urban areas often face problems, such as
difficulty in getting right of way (ROW) for transmission and distribution networks. The land acquisition
process for this purpose is not an easy thing to do at this time. This is due to the limited land that can be used
for over head line.
Underground cable distribution system is an alternative solution to distribute electrical energy in
urban areas, so the city will be looked magnificent and clean. However, the construction cost of underground
cable per km was much higher than over head line [1]. Development of distribution network is relatively
tougher because the branching process (tapping) is much harder when compared to the airways. Anyhow
underground cable is more protected from wind, lightning strikes, and disturbances of animals (like
monkeys), which may cause short circuit.
Musabaqoh Tilawatil Qur'an (MTQ) national level event was held in the mid-1980s at Pekanbaru,
which is the capital of Riau province. In meeting the demand of electric power to serve all activities, the
ISSN: 2252-8792
IJAPE Vol. 1, No. 1, April 2012 : 37 – 46
38
feeder in the district of "Simpang Tiga" and surrounding areas can no longer serve it. Thus, it needs the
additional feeder in order to serve the requirements of specific loads around the location of the event.
At the same time, the problem of urban congestion and the limited land that can be used as well as
encouragement to pay attention to issues of beauty and scenery of Pekanbaru city should be tackled. This
consequence is not possible for the addition of new feeders by using a medium-voltage over head line (OHL).
Hence the utility (PLN Pekanbaru)has constructed Express Feeder using underground cable distribution
between substation (SS) TelukLembu (TLB) and substation MTQ, to continue to serve the power demand.
1.1. Literature Review
The difference of voltage level between the sending and the receiving end is due to the parameters
of the line system (R, L, C). If the voltage level at the receiving end is lower than on the sending end then it
is caused by the influence of R and L, so it is an inductive load. Meanwhile, if the voltage level at the
receiving end is larger than the sending end, this is caused by the influence of R and C, so it is a capacitive
load. Both cases can be described from the phasor diagram as shown in Figure 1, where VR= Voltage at
receiving end, VS=Voltage at sending end, R=Line Resistance, X=Line Reactance, Z=Line Impedance, I=
Line current, α= phase angle between voltage and currentat receiving end, δ= phase angle between VR and
VS.
Figure 1. Power system phasor diagrams
Rules or standards used by the PLN (Persero) for the received voltage tolerance on the customer
side is +5% and -10% of the working voltage (system) [2]. A large voltage drop will result in the loss of
electric service to consumers and producers. The potential differences between the sending and the receiving
end cannot be avoided. To keep the voltage difference is not too high on both sides, inductive reactive power
or capacitive reactive power compensation is commonly used.
A lot of research has been done in an attempt to improve the voltage level at transmission or
distribution line. When the voltage level at the receiving end is less than the sending end, a capacitive
reactive power compensation is to be performed. If the voltage at the receiving end is greater than the
sending end, then inductive reactive power compensation has to be performed. Improvement of the voltage
levels will reduce the power loss in the line. The level of improvement is determined by the value of reactive
power, which can be obtained by installing inductors or capacitors. Most research conducted is to increase
the voltage at the receiving end due to an inductive load. However, few researches has been undertaken to
reduce the voltage. Indrayanti (2011) installs an inductor at the sending end based on the load flow data
obtaindon average at 17.00. Then the results were used to calculate the magnitude of dielectric losses of
underground cables. [3].
On the other hand, there is also the voltage difference between the conductors and cable sheath. The
voltage difference will affect the capacitancevalue of the cable.The flux distribution in alternating current
(a.c) cable insulation is complex and shown in Figure 2. The stress is a maximum at the conductor surface
and varies throughout the insulation. It was decreasing with distance from the conductor surface, because of
the differing permittivities of the components and the distribution of the flux at various times. The screened
cable used for alternating voltages has a clearly defined stress pattern, while that of cables used on direct
current (d.c) transmission has a changing pattern depending on temperature due to cable loading [4].
1.2. Underground Cable Capacitance
A single core cable is infact an electrostatic capacitor because it has two electrodes, the core of the
cable and the sheath separated by dielectric material. Figure 3 shows, the capacitance of the underground
cable a single-core. By definition, capacitance is the ratio of the charge on one of electrodes to potential
difference between the electrodes [5, 6]. Capacitance of the single core underground cable can be calculated
using the equation (1) [6].
IJAPE ISSN: 2252-8792
Title of manuscript is short and clear, implies research results (First Author)
39
Figure 2. Flux distribution that occurs in a three-core
cable.
Figure 3. Capacitance of a single core cable.
[ ]
2
Farad
ln i
c
l
C
r
r
π ε⋅ ⋅ ⋅
=
 
 
 
(1)
Where; C = capacitance value for single core underground cable,ri= the inner radius of the sheath, rc= radius
of the conductor, l=cable lenght, ε=permittivity of the dielectric material.
While for the three-core cable, the capacitance value can be calculated, if the dielectric is assumed
uniform between the core and the sheath. However, normally it is not so and, therefore, it is desirable to find
the capacitance by measurements. In a three core cable, sheath is at earth potential and the three conductors
are at supply potentials. There are six capacitances form between these systems. Three capacitances are
between the sheath and the conductors and the other three capacitances are between the conductors. The
capacitance of three cores underground cable could be calculated using the equation (2) [6].
[ ]2
2
Farad
ln
c
l
C
D
r
π ε⋅ ⋅ ⋅
=
 
 
 
(2)
Where D = conductor spacing.
If the distance between the conductorsareassumed symmetrical, and voltage stressesare uniformly
distributed on the cable insulation. Then, as shown in Figure 4, the capacitance value can be calculated using
equation (3).
Figure 3. Capacitancesbetween cores and to sheath of a three core cable.
[ ]0 1 23 FaradC C C= + ⋅ (3)
Where C0 = capacitance value for three cores underground cable, C1 = the capacitance between conductor
and the sheath, and C2 = the capacitance between each conductor.
Table 1 shows the data from the electrical underground cable of XLPE insulation materials.
Compounds that have good electrical properties are required for distribution cables with operating voltages
above 3 kV. IEC502 standard requires that products must have a dielectric loss angle (DLA) and the
ISSN: 2252-8792
IJAPE Vol. 1, No. 1, April 2012 : 37 – 46
40
permittivity is not greater than 0.75 with a range of angles 85 °C ambient. Besides, DLA at 80 °C must not
exceed the value at 60 °C. This requires that when there is an open-circuit fault occur, while the cable is
being energized with a high voltage, the wires will be hot even though there is no current flowing inside it [6,
7]. Figure 5 shows the physical shape of the underground cable NA2XSEFGbY used in this analysis. The
technical data is as shown in Table 2 [8].
Figure 4. Equivalent capacitance of a three core cable.
Table 1. Electrical Data Crosslinked Polyethylene (XLPE) cable
Description Value
Type GP 8
Volume resistivity (min)
at 20°C (Ω m)
1 x 1014
Permittivity at 50 Hz 2.3-5.2
tan σ at 50 Hz 0.0004-0.005
Figure 5. Underground Cable NA2XSEFGbY (Courtesy of Kabel Metal Indonesia)
The value of Inductor needs to compensate the reactive power can be determined by knowing the
power factor at the sending and the receiving end. By using these two values, the addition value of inductive
reactive impedance that required can be obtained in Henry and VAr.
Table 2. Electrical and Mechanical Data of NA2XSEFGbY 240 mm2
.
Description Value Description Value
Cross Section of Conductor (mm2
) 240 DC Resistance at 20 o
C (Ω/km) 0.125
Conductor Diameter (mm) 18.7 AC Resistance at 90 o
C (Ω/km) 0.162
Insulation Thickness (mm) 55 DC Insulation Resistance at 20o
C (MΩ.km) 700
Insulation Diameter (mm) 31.3 Current Carrying Capacity in Air (A) 453
Armor Thickness (mm) 0.80 Current Carrying Capacity in ground (A) 385
Sheath Thickness (mm) 3.6 Capacitance per phase (µF/km) 0.307
Cable Weight (kg/km) 9.600 Inductance per phase (mH/km) 0.302
Min. Bending Radius (mm) 78.0 Max short circuit current of screen (kA/sec) 4.53
Overall Cable Diameter (mm) 85 Max short circuit current of conduct (kA/sec) 22.98
IJAPE ISSN: 2252-8792
Title of manuscript is short and clear, implies research results (First Author)
41
1.3. Underground cable Energy Losses
An underground cable consists of three main components, namely the conductor, dielectric
materials, and sheath. When the cable is energized by a voltage electric, current will flow, and will heat the
cable. The temperature rise of a cable body depends upon the rate of generation and dissipation of heat by the
body. Thermal effects that occurred will result in losses. The losses are; (1) conductor losses, (2) dielectric
losses, and (3) sheath losses [6].
This paper discusses the dielectric losses in underground cables, which is one of the three types of
electric losses associated with an underground cable. As already known, that if it is energized with alternating
current there will be a large capacitance effect, so it will involve the phase voltages and power factors. For
single core cables, the dielectric loss can be calculated using the equation (4) [4, 6].
[ ]1
2
2 tan WattDP f C Vπ σ= ⋅ ⋅ ⋅ ⋅ ⋅ (4)
where :
1DP = Dielectric Loss [Watt]
f = Frequency [Hz]
C = Capasitance [Farad/meter]
V = Line to netral Voltage [Volt]
tan σ = Dielectric Loss Angle (DLA)
While for a three-core cable, the dielectric losses can be calculated using the equation (5)
[ ]3 1
3 WattD DP P= ⋅ (5)
There are several models that can be used in analyzing the transmission and distribution lines.
Transmission or distribution lines can be modeled based on the value of its capacitive leakage current. This
value is influenced by several things, including the length of lines, the system voltage level, and the distance
conductor to ground (earth).
For a small capacitance value, it can be ignored. This usually occurs in over head lines that are less
than 80 km (short-line model). Meanwhile, if the capacitance values ismedium, it must be included in the
analysis. There are two models that could be done, first by assuming that the capacitance is distributed
equally on both ends of lines (model "phi" = Π). Alternatively, it assumed to be unity at the center of the
lines (Model "T"). It usually called the medium line model, which is the overhead distribution lines system
with length ≤ 240 km. Meanwhile, if capacitance value is large, the value of distributed capacitance should
be analyzed along the line. In the overhead lines, usually it is called a model of long line (> 240 km) [9, 10].
2. SYSTEM ANALYSIS
Distribution lines medium-voltage underground cables that join the TLB - MTQ, installed 80-100
cm under the surface of the road. Track is used is to trace the roadside of TanjungRhu, Dr. Sutomo, Hang
Tuah, Pattimura, and General Sudirman streets. The single-line diagram is as shown in Figure 6.
Figure 6. One line diagram Distribution Line TelukLembu Substation – MTQ Substation.
ISSN: 2252-8792
IJAPE Vol. 1, No. 1, April 2012 : 37 – 46
42
Express Feeder is 10 km in length using an aluminum conductor XLPE insulation right (Cross
Linked Poly Ethylene) of the type NA2XSEFGbY measuring 3 x 240 mm2
. Feeders finally managed by PT.
PLN (Persero) Region SimpangTiga, whichreceived supply from the TelukLembusubstation (SS), using
underground cable distribution line 20 kV [11]. XLPE insulated cable has the dielectric loss lower than on
other types of insulation such as PVC (Polyvinyl chloride) and EPR (Ethylene Propylene Rubber) [4, 12].
Furthermore the voltage and current profiles are obtained at TelukLembu SS, based on hours of
operation on December 6, 2010. The data is as shown in Table 3. From the table, it is shown that the peak
load begins at 18:00 hours until 21:00 pm. Where the maximum load occurs at phase 'T' at 19:00, with the
average peak load is equal to 237.66 Ampere. The additionalsubstantial load occurs during hours of 17:00 to
18:00 pm. The increase reached 17%, where at 17:00 the new average weight of 190.66 Ampere with a
voltage of 20.3 kV Amperes, while at 18.00 pm rose to 224.33 Ampere. The minimum peak load occurred at
06.00 am, with the largest decrease occurred in the period from 9:00 p.m. to 22:00 pm.
Table 3 also shows that, the maximum peak voltage occurs at 18.00 pm, which is 20,600 Volts. As
been seen, the peak voltage occurs when the load average is quite large (224.33 Ampere). The minimum peak
voltage of 19,200 Volt occurred at 1:00 pm. The other thing is at 1:00 to 2:00, system voltage is less the 20
kV. It could be a period before where interruption in these lines will take place.
Table 3. Express Feeder TLB – MTQ Profile
Time
MTQ Exp Feeder Current (A) Volt
(V)Phase R Phase S Phase T
01:00 167 167 178 19,200
02:00 165 165 175 19,900
03:00 160 160 172 20,100
04:00 157 157 168 20,200
05:00 155 155 165 20,200
06:00 150 150 160 20,300
07:00 154 153 163 20,500
08:00 170 176 174 20,000
09:00 170 177 173 20,000
10:00 176 179 178 20,200
11:00 182 187 185 20,200
12:00 180 179 181 20,300
13:00 178 186 183 20,500
14:00 187 195 191 20,200
15:00 190 197 196 20,300
16:00 185 186 194 20,300
17:00 187 187 198 20,300
18:00 220 219 234 20,600
19:00 233 233 247 20,100
20:00 231 231 245 20,200
21:00 220 220 235 20,200
22:00 195 196 196 20,100
23:00 199 182 187 20,100
24:00 193 192 190 20,200
Table 4. MTQ SS Load Data
Time
Outgoing Line
(Amp)
Incoming
Line
(Amp)
Volt
(kV)
17:00
L1 195 L1 192
20,500L2 201 L2 200
L3 200 L3 196
18:00
L1 211 L1 206
20,700L2 217 L2 213
L3 216 L3 212
19:00
L1 249 L1 245
20,100L2 252 L2 251
L3 255 L3 254
20:00
L1 240 L1 236
20,800L2 242 L2 239
L3 245 L3 242
21:00
L1 236 L1 233
20,400L2 240 L2 239
L3 242 L3 241
3. RESEARCH METHOD
The method used in analyzing underground cable distribution system which is 10 km long, uses two
circuit models: (1) nominal "pi" (π) circuit, and (2) nominal "T" circuit. At the nominal "pi" (π) circuit, it is
assumed that the capacitance is evenly distributed along the cable,the model is divided equally on both ends
of lines, while the inductive impedance is in the middle of lines. Figure 7.a. shows that the CS and CR are the
capacitance of the lines which is at the sending and the receiving end. For the nominal "T" circuit, it is
assumed that the capacitance is evenly distributed along the wire, modeled as a capacitance which is at the
center of the lines, while the inductive impedance is modeled equally divided on both ends of lines. Both
model of theses circuit are as shown in Figure 7.
The use of underground cables resulted in the existence of capacitance effects in the system. In this
system, the power factor is 0.9 leading. Therefore, it is necessary to have an inductive reactive power
compensation. Considering the system is a capacitive reactive power, it needs to be installed inductive
reactive power. So that's why, inductor as a supplier of inductive reactive power should be installed.
IJAPE ISSN: 2252-8792
Title of manuscript is short and clear, implies research results (First Author)
43
CSVS VR
IS IL
Load
SCI
1
1
2 LineZ 2
1
2 LineZ
CS CRVS VR
IL
SCI RCI
LineI
IS
Load
LineZ
1LineI 2LineI
(a). Nominal Phi “Π” (b). Nominal T
Figure 7. GI TelukLembu – GH MTQ Distribution Line model
SCI RCI SCI
1
1
2 LineZ 2
1
2 LineZ
LineI
LineZ
1LineI 2LineI
Figure 8. Inductor installed at the sending end or TelukLembu Substation
This analysis is conducted with the addition of the inductor with 2 (two) scenarios. First scenario is
to place or install the inductor at the sending or the TLB SubStation side. Then do the analysis of the system.
The circuit is as shown in Figure 8. The second scenario is to place or install the inductor on the receiving
end or MTQ substation side. The circuit is as shown in Figure 9. Afterwards an inductive reactive power
requirement of the system is calculated. Then using that data, the similar analysis using scenario 1 and
scenario 2 is conducted. The calculation is done with the help of Matrix Laboratory software (MatLab). The
calculation is performed at every hour, from 01:00 hours until 24.00 pm.
SCI RCI
SCI
1
1
2 LineZ 2
1
2 LineZ
LineI
LineZ
1LineI 2LineI
Figure 9. Inductor installed at the sending end or MTQ Substation
4. RESULTS AND ANALYSIS
The results of the analysis conducted on the third circuit of Figures 7, 8 and 9 are as shown in
Table 5.
4.1. Exsisting Condition
Under these conditions is seen that the average voltage on the GH MTQ 2.43% is larger than its
sending end (TLB SS). The total capacitive leakage current that occurs during the 24 hours is 249.61
Ampere. The dielectric loss that occurred in line is equal to 3.53 MW. Assuming a month is 30 days and the
profile of the system every day for a month is similar, then its losses amounted to 105.98 MW per month.
IJAPE Vol. 1, No. 1, April 2012
44
(a). Nominal “Phi” Π
Figure 10.
Table 5. Voltage and current profiles before and after the
Time
Existing Condition
Voltage
ArusBocor
TLB
[Volt]
MTQ
[Volt]
01:00 19200 19,625.27
02:00 19900 20,318.84
03:00 20100 20,507.61
04:00 20200 20,599.00
05:00 20200 20,593.02
06:00 20300 20,680.14
07:00 20500 20,888.56
08:00 20000 20,431.60
09:00 20000 20,431.60
10:00 20200 20,642.58
11:00 20300 20,760.46
12:00 20300 20,750.20
13:00 20500 20,954.35
14:00 20200 20,676.75
15:00 20300 20,785.23
16:00 20300 20,769.85
17:00 20300 20,775.83
18:00 20600 21,161.94
19:00 20100 20,696.43
20:00 20200 20,791.24
21:00 20200 20,743.39
22:00 20100 20,588.78
23:00 20100 20,572.54
24:00 20200 20,678.46
4.2. Scenario1
The inductor is placed at the sending
for the improvement of the system.
2.25% than before installing the induc
capacitive leakage current is also decreased by 1.06% to 248.55 Ampere, where previously 249.61 Ampere.
This also resulted in lower power losses
for a month, then the power loss
4.3. Scenario 2
Meanwhile, for the second scenario, the results obtained are better than the first scenario. The
average voltage at the receiving end is almost the same as the sending end, which is on average is lower by
0.01%. Capacitive leakage current decreased to 245.17 Ampere only. Thi
line dropped to 126.25 kW, compared with the existing conditions, of 3.41 MW. Furthermore, when
compared to scenario 1, the losseswas reduced to 87.69 kW. With the same assumptions (similar every day
for a month), then the losses per month could be save from 3.79 MW (3.57%) for model Phi and 3.65 MW
(3.45%) for model “T”.
2 : 37 – 46
(a). Nominal “Phi” Π (b). Nominal “T”
10. Voltage graph profiles that occur in three condition
5. Voltage and current profiles before and after the installation of Inductor
Existing Condition Inductor at TLB
ArusBocor
[A]
Dielec
Loss
[kWh]
Voltage
MTQ
[Volt]
ArusBocor
[A]
Rugi2
saluran
[kWh]
Voltage
MTQ
[Volt]
9.89 132.96 19,223.46 9.85 131.73 19,196.67
10.24 142.67 19,922.73 10.21 141.43 19,894.98
10.34 145.45 20,121.85 10.31 144.23 20,093.83
10.39 146.82 20,221.19 10.36 145.63 20,193.03
10.39 146.78 20,220.76 10.36 145.60 20,192.61
10.44 148.13 20,319.80 10.40 146.99 20,291.51
10.54 151.09 20,520.33 10.51 149.92 20,491.76
10.30 144.19 20,023.61 10.26 142.89 19,995.72
10.30 144.19 20,023.61 10.26 142.89 19,995.72
10.40 147.13 20,224.33 10.36 145.79 20,196.15
10.46 148.71 20,325.58 10.42 147.30 20,297.25
10.46 148.63 20,324.84 10.42 147.26 20,296.52
10.56 151.57 20,525.07 10.52 150.18 20,496.47
10.41 147.38 20,226.79 10.37 145.92 20,198.60
10.46 148.89 20,327.36 10.42 147.39 20,299.03
10.46 148.78 20,326.26 10.42 147.34 20,297.93
10.46 148.82 20,326.69 10.42 147.36 20,298.35
10.64 153.83 20,632.77 10.59 152.04 20,603.99
10.39 146.81 20,135.44 10.34 144.93 20,107.34
10.44 148.21 20,235.03 10.39 146.34 20,206.79
10.43 147.86 20,231.59 10.38 146.17 20,203.36
10.36 146.03 20,127.69 10.32 144.53 20,099.63
10.36 145.91 20,126.53 10.32 144.47 20,098.47
10.41 147.39 20,226.91 10.37 145.93 20,198.72
The inductor is placed at the sending end or TLB SS (see Figure 10). This configuration
the improvement of the system. The voltage at the receiving end (MTQ) decreased
2.25% than before installing the inductor, or only up to 0.13% from the sending end. While the total
capacitive leakage current is also decreased by 1.06% to 248.55 Ampere, where previously 249.61 Ampere.
This also resulted in lower power losses is reduced to 3.49 MW. With the same assumptions
he power loss will decrease 1.16 MW (model Phi) and 1.02 MW (model “T”)
second scenario, the results obtained are better than the first scenario. The
average voltage at the receiving end is almost the same as the sending end, which is on average is lower by
0.01%. Capacitive leakage current decreased to 245.17 Ampere only. This resulted in dielectric losses in the
line dropped to 126.25 kW, compared with the existing conditions, of 3.41 MW. Furthermore, when
compared to scenario 1, the losseswas reduced to 87.69 kW. With the same assumptions (similar every day
n the losses per month could be save from 3.79 MW (3.57%) for model Phi and 3.65 MW
ISSN: 2252-8792
(b). Nominal “T”
installation of Inductor
Inductor at MTQ
Voltage
MTQ
[Volt]
ArusBocor
[A]
Dielec
Loss
[kWh]
19,196.67 9.72 128.53
19,894.98 10.08 138.15
20,093.83 10.18 141.00
20,193.03 10.24 142.44
20,192.61 10.24 142.47
20,291.51 10.29 143.93
20,491.76 10.39 146.77
19,995.72 10.13 139.51
19,995.72 10.13 139.51
20,196.15 10.23 142.29
20,297.25 10.28 143.64
20,296.52 10.28 143.68
20,496.47 10.38 146.53
20,198.60 10.23 142.16
20,299.03 10.28 143.55
20,297.93 10.28 143.61
20,298.35 10.28 143.59
20,603.99 10.42 147.57
20,107.34 10.16 140.32
20,206.79 10.21 141.75
20,203.36 10.22 141.92
20,099.63 10.17 140.71
20,098.47 10.18 140.77
20,198.72 10.23 142.16
his configuration is created
he voltage at the receiving end (MTQ) decreased on the average of
tor, or only up to 0.13% from the sending end. While the total
capacitive leakage current is also decreased by 1.06% to 248.55 Ampere, where previously 249.61 Ampere.
to 3.49 MW. With the same assumptions of similar profile
(model “T”).
second scenario, the results obtained are better than the first scenario. The
average voltage at the receiving end is almost the same as the sending end, which is on average is lower by
s resulted in dielectric losses in the
line dropped to 126.25 kW, compared with the existing conditions, of 3.41 MW. Furthermore, when
compared to scenario 1, the losseswas reduced to 87.69 kW. With the same assumptions (similar every day
n the losses per month could be save from 3.79 MW (3.57%) for model Phi and 3.65 MW
IJAPE
(a). Nominal “Phi” Π
Figure 11. Graph of power loss that occurs during the 24 hours
Moreover, using both scenarios,it can be seen that the selection of the location of the installation or
placement of the inductor location also affec
scenarios are have shown improvement in the system. However, result obtained when using the second
scenario is much better. This can be seen from the voltage at the receiving end, leak current cap
line losses which are decreased.
Hence, by using the second scenario it will produce a technically better system. In addition, the PT.
PLN (Persero) will be able to save the technical losses occurs on their systems. By using almost the same
cost, certainly the second scenario is a better choice since the results are significantly better.
Table 6. Comparison of Losses Model "Phi" and the Model T before and after the installation of Inductor
Dielectric losses per day before installing inductor
Dielectric losses per dayafter installing inductor at sending end
Saving losses
Saving for a month
Dielectric losses per dayafter installing
Saving losses
Saving for a month
5. CONCLUSION
Based on the description above it
scenario, where the position of the inductor is placed at the receiving or the MTQ SS. It can save losses of
PT. PLN (Persero) per month of 3.788 MW (3.57%) for model Phi and 3.65 MW (3.45%) for model “T”.
When compared with the first scenario just save of 1.16 MW (1.09%) only per mon
MW (0.9 %) for model “T”.
ACKNOWLEDGEMENTS
The authors would like to thank Universiti Teknologi Malaysia and Lancang Kuning University
providing the financial and technical support for the research. The authors also would like to thanks
(Persero), for providing data and permission to
REFERENCES
[1] B. L. Theraja, A Textbook of Electrical Technology: Electronic devices &
& Company Ltd., 2005.
[2] PT. PLN (Persero), "Tegangan-
[3] V. N. Indrayanti, "Studi Pemasangan
di Express Feeder 20 kV GI. TelukLembu
Universitas Lancang Kuning, Pekanbaru, 2011.
[4] G. F. Moore and B. C. Ltd, Electric Cables Handbook: Blackwell Science, 1997.
[5] P. A. Laplante, Comprehensive Dictionary of Electrical Engineering, Second ed. Malvern: CRC Press, 2005.
[6] C. L. Wadhwa, Electrical Power Systems: New Age International, 2006.
ISSN: 2252-8792
Title of manuscript is short and clear, implies research results (First Author)
(a). Nominal “Phi” Π (b). Nominal “T”
11. Graph of power loss that occurs during the 24 hours
Moreover, using both scenarios,it can be seen that the selection of the location of the installation or
placement of the inductor location also affects the performance of the system. Both the first and second
scenarios are have shown improvement in the system. However, result obtained when using the second
scenario is much better. This can be seen from the voltage at the receiving end, leak current cap
Hence, by using the second scenario it will produce a technically better system. In addition, the PT.
PLN (Persero) will be able to save the technical losses occurs on their systems. By using almost the same
t, certainly the second scenario is a better choice since the results are significantly better.
Table 6. Comparison of Losses Model "Phi" and the Model T before and after the installation of Inductor
Description
Model Phi
[kW]
losses per day before installing inductor 3,532.78
Dielectric losses per dayafter installing inductor at sending end 3,494.23
1,156.57
Dielectric losses per dayafter installing inductor at receiving end 3,406.51
126.27
3,788.24
Based on the description above it can be seen that the second scenario is much better than the first
of the inductor is placed at the receiving or the MTQ SS. It can save losses of
PT. PLN (Persero) per month of 3.788 MW (3.57%) for model Phi and 3.65 MW (3.45%) for model “T”.
When compared with the first scenario just save of 1.16 MW (1.09%) only per month for model Phi and 1.02
would like to thank Universiti Teknologi Malaysia and Lancang Kuning University
financial and technical support for the research. The authors also would like to thanks
data and permission to present this paper.
B. L. Theraja, A Textbook of Electrical Technology: Electronic devices & circuits in S.I. system of units: S. Chand
-Tegangan Standar," ed. Jakarta: PT. PLN (Persero), 1995, p. 5.
Pemasangan Induktor pada Jaringan Kabel Bawah-Tanah untuk Kompensa
di Express Feeder 20 kV GI. TelukLembu - GH. MTQ PT. PLN (Persero) Cab.Pekanbaru," TeknikElektro,
Kuning, Pekanbaru, 2011.
G. F. Moore and B. C. Ltd, Electric Cables Handbook: Blackwell Science, 1997.
lante, Comprehensive Dictionary of Electrical Engineering, Second ed. Malvern: CRC Press, 2005.
C. L. Wadhwa, Electrical Power Systems: New Age International, 2006.
Title of manuscript is short and clear, implies research results (First Author)
45
(b). Nominal “T”
11. Graph of power loss that occurs during the 24 hours
Moreover, using both scenarios,it can be seen that the selection of the location of the installation or
ts the performance of the system. Both the first and second
scenarios are have shown improvement in the system. However, result obtained when using the second
scenario is much better. This can be seen from the voltage at the receiving end, leak current capacitive and
Hence, by using the second scenario it will produce a technically better system. In addition, the PT.
PLN (Persero) will be able to save the technical losses occurs on their systems. By using almost the same
t, certainly the second scenario is a better choice since the results are significantly better.
Table 6. Comparison of Losses Model "Phi" and the Model T before and after the installation of Inductor
Model Phi
[kW]
Model T
[kW]
3,532.78 3,528.23
3,494.23 3,494.27
38.55 33.96
1,156.57 1,018.91
3,406.51 3,406.54
126.27 121.69
3,788.24 3,650.60
seen that the second scenario is much better than the first
of the inductor is placed at the receiving or the MTQ SS. It can save losses of
PT. PLN (Persero) per month of 3.788 MW (3.57%) for model Phi and 3.65 MW (3.45%) for model “T”.
th for model Phi and 1.02
would like to thank Universiti Teknologi Malaysia and Lancang Kuning University for
financial and technical support for the research. The authors also would like to thanks PT. PLN
circuits in S.I. system of units: S. Chand
Standar," ed. Jakarta: PT. PLN (Persero), 1995, p. 5.
Kompensasi Arus Kapasitif
GH. MTQ PT. PLN (Persero) Cab.Pekanbaru," TeknikElektro,
lante, Comprehensive Dictionary of Electrical Engineering, Second ed. Malvern: CRC Press, 2005.
ISSN: 2252-8792
IJAPE Vol. 1, No. 1, April 2012 : 37 – 46
46
[7] I. E. Commission, "Extruded Solid Dielectric Insulated Power Cables For Rated Voltages from 1 kV Up To 30 kV,"
ed. Geneva: IEC Press, 1983.
[8] S. N. Indonesia, "Persyaratan Umum Instalasi Listrik 2000," vol. SNI 04-0225-2000, ed. Jakarta: Badan
Standardisasi Nasional, 2000.
[9] T. Gönen, Electric power transmission system engineering: analysis and design, 2nd ed.: CRC Press, 2009.
[10] J. J. Grainger and W. D. Stevenson, Power System Analysis: McGraw-Hill, 1994.
[11] PT. PLN (Persero), "Generating and Transmission Data of Central Sumatra," P3BS, Ed., ed. Padang, 2010.
[12] B. Richardson and R. Ramachandran, "Enhanced energy efficiency of underground cables," in Transmission and
Distribution Conference and Exposition, 2010 IEEE PES, 2010, pp. 1-5.
BIOGRAPHIES OF AUTHORS
Hamzah Eteruddin received the Electrical Engineering degree from LancangKuning University,
Indonesia, in 1994, and the M.Eng. degree from GadjahMada University, Indonesia, in 2003.
Currently, he ispursuing his Ph.D at UniversitiTeknologi Malaysia (UTM), Johor Bahru. His
research interests include power system protection, power system analysis, fault in underground
cables and over head lines, Power Transmission Lines, Energy. Hamzah is a corporate member
of Association of Indonesia Mechanical Electrical Professionalis (APEI) and Chairman of APEI
at Riau Province.
Abdullah Asuhaimi Mohd Zin received the B.Sc. degree from Gadjah Mada University,
Indonesia, in 1976, the M.Sc. degree from University of Strathclyde, Strathclyde, U.K. in 1981,
and the Ph.D. degree from the University of Manchester Institute of Science and Technology,
Manchester, U.K., in 1988.
Currently, he is a Professor and Head of Power Engineering Research Group (PERG), Faculty of
Electrical Engineering, UniversitiTeknologi Malaysia, Johor Bahru. His research interests
include power system protection, application of neural network in power system, arcing fault in
underground cables, power quality and dynamic equivalent of power systems. Dr. Mohd Zin is a
corporate member of The Institution of Engineers, Malaysia (IEM) and a member of the Institute
of Electrical Engineers (U.K.). He is a registered Professional Engineer (P. Eng.) in Malaysia
and Chartered Engineer (C.Eng.) in the United Kingdom.)

More Related Content

What's hot

Effect of Passive Damping on the Performance of Buck Converter for Magnet Load
Effect of Passive Damping on the Performance of Buck Converter for Magnet LoadEffect of Passive Damping on the Performance of Buck Converter for Magnet Load
Effect of Passive Damping on the Performance of Buck Converter for Magnet Loadpaperpublications3
 
Full IEDM paper version - as last submitted
Full IEDM paper version - as last submittedFull IEDM paper version - as last submitted
Full IEDM paper version - as last submittedDavid Goren
 
Lecture 09 transmission lines
Lecture 09   transmission linesLecture 09   transmission lines
Lecture 09 transmission linesbhaavan22
 
Darkawi_et_al_CEIDP_2012_VF_IEEE
Darkawi_et_al_CEIDP_2012_VF_IEEEDarkawi_et_al_CEIDP_2012_VF_IEEE
Darkawi_et_al_CEIDP_2012_VF_IEEEAbdallah Darkawi
 
DC bus stabilization using passive damping network in distributed power syste...
DC bus stabilization using passive damping network in distributed power syste...DC bus stabilization using passive damping network in distributed power syste...
DC bus stabilization using passive damping network in distributed power syste...TELKOMNIKA JOURNAL
 
An Electrolytic-Free Offline LED Driver with a Ceramic-Capacitor-Based Compac...
An Electrolytic-Free Offline LED Driver with a Ceramic-Capacitor-Based Compac...An Electrolytic-Free Offline LED Driver with a Ceramic-Capacitor-Based Compac...
An Electrolytic-Free Offline LED Driver with a Ceramic-Capacitor-Based Compac...Projectsatbangalore
 
Copper Design BEUKES
Copper Design BEUKESCopper Design BEUKES
Copper Design BEUKESNick Beukes
 
A Family of Neutral Point Clamped Full-Bridge Topologies for Transformerless ...
A Family of Neutral Point Clamped Full-Bridge Topologies for Transformerless ...A Family of Neutral Point Clamped Full-Bridge Topologies for Transformerless ...
A Family of Neutral Point Clamped Full-Bridge Topologies for Transformerless ...Projectsatbangalore
 
Types of transmission lines
Types of transmission linesTypes of transmission lines
Types of transmission linesSelf-employed
 
Voltage Clamped Dc-Dc Convertor with Reduced Reverse Recovery Current And Sta...
Voltage Clamped Dc-Dc Convertor with Reduced Reverse Recovery Current And Sta...Voltage Clamped Dc-Dc Convertor with Reduced Reverse Recovery Current And Sta...
Voltage Clamped Dc-Dc Convertor with Reduced Reverse Recovery Current And Sta...IJMER
 
Inductance of transmission line
Inductance of transmission lineInductance of transmission line
Inductance of transmission linevishalgohel12195
 
Analysis of Electric Circuit Model on Atmospheric Pressure Dielectric Barrier...
Analysis of Electric Circuit Model on Atmospheric Pressure Dielectric Barrier...Analysis of Electric Circuit Model on Atmospheric Pressure Dielectric Barrier...
Analysis of Electric Circuit Model on Atmospheric Pressure Dielectric Barrier...AM Publications
 
Architecture of an efficient dual band 1.8/2.5 GHz rectenna for RF energy har...
Architecture of an efficient dual band 1.8/2.5 GHz rectenna for RF energy har...Architecture of an efficient dual band 1.8/2.5 GHz rectenna for RF energy har...
Architecture of an efficient dual band 1.8/2.5 GHz rectenna for RF energy har...TELKOMNIKA JOURNAL
 
Effect of HVTL Phase Transposition on Pipelines Induced Voltage
Effect of HVTL Phase Transposition on Pipelines Induced VoltageEffect of HVTL Phase Transposition on Pipelines Induced Voltage
Effect of HVTL Phase Transposition on Pipelines Induced Voltageijeei-iaes
 
An algorithm for selection and design of hybrid power supplies for MEMS with ...
An algorithm for selection and design of hybrid power supplies for MEMS with ...An algorithm for selection and design of hybrid power supplies for MEMS with ...
An algorithm for selection and design of hybrid power supplies for MEMS with ...Kimberly Cook-Chennault
 

What's hot (20)

Effect of Passive Damping on the Performance of Buck Converter for Magnet Load
Effect of Passive Damping on the Performance of Buck Converter for Magnet LoadEffect of Passive Damping on the Performance of Buck Converter for Magnet Load
Effect of Passive Damping on the Performance of Buck Converter for Magnet Load
 
Full IEDM paper version - as last submitted
Full IEDM paper version - as last submittedFull IEDM paper version - as last submitted
Full IEDM paper version - as last submitted
 
Lecture 09 transmission lines
Lecture 09   transmission linesLecture 09   transmission lines
Lecture 09 transmission lines
 
Darkawi_et_al_CEIDP_2012_VF_IEEE
Darkawi_et_al_CEIDP_2012_VF_IEEEDarkawi_et_al_CEIDP_2012_VF_IEEE
Darkawi_et_al_CEIDP_2012_VF_IEEE
 
Il2616361640
Il2616361640Il2616361640
Il2616361640
 
DC bus stabilization using passive damping network in distributed power syste...
DC bus stabilization using passive damping network in distributed power syste...DC bus stabilization using passive damping network in distributed power syste...
DC bus stabilization using passive damping network in distributed power syste...
 
An Electrolytic-Free Offline LED Driver with a Ceramic-Capacitor-Based Compac...
An Electrolytic-Free Offline LED Driver with a Ceramic-Capacitor-Based Compac...An Electrolytic-Free Offline LED Driver with a Ceramic-Capacitor-Based Compac...
An Electrolytic-Free Offline LED Driver with a Ceramic-Capacitor-Based Compac...
 
Copper Design BEUKES
Copper Design BEUKESCopper Design BEUKES
Copper Design BEUKES
 
A Family of Neutral Point Clamped Full-Bridge Topologies for Transformerless ...
A Family of Neutral Point Clamped Full-Bridge Topologies for Transformerless ...A Family of Neutral Point Clamped Full-Bridge Topologies for Transformerless ...
A Family of Neutral Point Clamped Full-Bridge Topologies for Transformerless ...
 
Types of transmission lines
Types of transmission linesTypes of transmission lines
Types of transmission lines
 
Voltage Clamped Dc-Dc Convertor with Reduced Reverse Recovery Current And Sta...
Voltage Clamped Dc-Dc Convertor with Reduced Reverse Recovery Current And Sta...Voltage Clamped Dc-Dc Convertor with Reduced Reverse Recovery Current And Sta...
Voltage Clamped Dc-Dc Convertor with Reduced Reverse Recovery Current And Sta...
 
AC TRANSMISSION by Dr. Kundur
AC TRANSMISSION by Dr. Kundur AC TRANSMISSION by Dr. Kundur
AC TRANSMISSION by Dr. Kundur
 
Inductance of transmission line
Inductance of transmission lineInductance of transmission line
Inductance of transmission line
 
Analysis of Electric Circuit Model on Atmospheric Pressure Dielectric Barrier...
Analysis of Electric Circuit Model on Atmospheric Pressure Dielectric Barrier...Analysis of Electric Circuit Model on Atmospheric Pressure Dielectric Barrier...
Analysis of Electric Circuit Model on Atmospheric Pressure Dielectric Barrier...
 
Gm3511451152
Gm3511451152Gm3511451152
Gm3511451152
 
Architecture of an efficient dual band 1.8/2.5 GHz rectenna for RF energy har...
Architecture of an efficient dual band 1.8/2.5 GHz rectenna for RF energy har...Architecture of an efficient dual band 1.8/2.5 GHz rectenna for RF energy har...
Architecture of an efficient dual band 1.8/2.5 GHz rectenna for RF energy har...
 
Effect of HVTL Phase Transposition on Pipelines Induced Voltage
Effect of HVTL Phase Transposition on Pipelines Induced VoltageEffect of HVTL Phase Transposition on Pipelines Induced Voltage
Effect of HVTL Phase Transposition on Pipelines Induced Voltage
 
wireless power transfer
wireless power transferwireless power transfer
wireless power transfer
 
An algorithm for selection and design of hybrid power supplies for MEMS with ...
An algorithm for selection and design of hybrid power supplies for MEMS with ...An algorithm for selection and design of hybrid power supplies for MEMS with ...
An algorithm for selection and design of hybrid power supplies for MEMS with ...
 
Bilal Muhthassim_3
Bilal Muhthassim_3Bilal Muhthassim_3
Bilal Muhthassim_3
 

Similar to Reduced Dielectric Losses for Underground Cable Distribution Systems

Analysis and optimization of wireless power transfer link
Analysis and optimization of wireless power transfer linkAnalysis and optimization of wireless power transfer link
Analysis and optimization of wireless power transfer linkAjay Kumar Sah
 
Application of LFAC { Hz} for electrical power transmission system: a compara...
Application of LFAC { Hz} for electrical power transmission system: a compara...Application of LFAC { Hz} for electrical power transmission system: a compara...
Application of LFAC { Hz} for electrical power transmission system: a compara...TELKOMNIKA JOURNAL
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Lineijtsrd
 
Effect of Dew and Raindrops on Electric Field around EHV Transmission Lines
Effect of Dew and Raindrops on Electric Field around EHV Transmission LinesEffect of Dew and Raindrops on Electric Field around EHV Transmission Lines
Effect of Dew and Raindrops on Electric Field around EHV Transmission LinesTELKOMNIKA JOURNAL
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parametersfiraoltemesgen1
 
Quantitative Modeling and Simulation of Single-Electron Transistor
Quantitative Modeling and Simulation of Single-Electron TransistorQuantitative Modeling and Simulation of Single-Electron Transistor
Quantitative Modeling and Simulation of Single-Electron TransistorIRJET Journal
 
Introduction gadgets have gained a lot of attention.pdf
Introduction gadgets have gained a lot of attention.pdfIntroduction gadgets have gained a lot of attention.pdf
Introduction gadgets have gained a lot of attention.pdfbkbk37
 
Modeling of solar array and analyze the current transient response of shunt s...
Modeling of solar array and analyze the current transient response of shunt s...Modeling of solar array and analyze the current transient response of shunt s...
Modeling of solar array and analyze the current transient response of shunt s...Editor Jacotech
 
Modeling of solar array and analyze the current transient
Modeling of solar array and analyze the current transientModeling of solar array and analyze the current transient
Modeling of solar array and analyze the current transientEditor Jacotech
 
Capacitance and Cable Testing
Capacitance and Cable TestingCapacitance and Cable Testing
Capacitance and Cable TestingHussein Kassem
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...IJMERJOURNAL
 
Design aspects of high voltage transmission line
Design aspects of high voltage transmission lineDesign aspects of high voltage transmission line
Design aspects of high voltage transmission linejournalBEEI
 

Similar to Reduced Dielectric Losses for Underground Cable Distribution Systems (20)

Design and implementation of an efficient WPT system
Design and implementation of an efficient WPT systemDesign and implementation of an efficient WPT system
Design and implementation of an efficient WPT system
 
Analysis and optimization of wireless power transfer link
Analysis and optimization of wireless power transfer linkAnalysis and optimization of wireless power transfer link
Analysis and optimization of wireless power transfer link
 
Transfer function and Impulse Response Simulation of Power Line Channel
Transfer function and Impulse Response Simulation of Power Line ChannelTransfer function and Impulse Response Simulation of Power Line Channel
Transfer function and Impulse Response Simulation of Power Line Channel
 
Application of LFAC { Hz} for electrical power transmission system: a compara...
Application of LFAC { Hz} for electrical power transmission system: a compara...Application of LFAC { Hz} for electrical power transmission system: a compara...
Application of LFAC { Hz} for electrical power transmission system: a compara...
 
wireless power transfer
wireless power transferwireless power transfer
wireless power transfer
 
CLL/S Detuned compensation network for electric vehicles wireless charging ap...
CLL/S Detuned compensation network for electric vehicles wireless charging ap...CLL/S Detuned compensation network for electric vehicles wireless charging ap...
CLL/S Detuned compensation network for electric vehicles wireless charging ap...
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
 
Effect of Dew and Raindrops on Electric Field around EHV Transmission Lines
Effect of Dew and Raindrops on Electric Field around EHV Transmission LinesEffect of Dew and Raindrops on Electric Field around EHV Transmission Lines
Effect of Dew and Raindrops on Electric Field around EHV Transmission Lines
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
 
Quantitative Modeling and Simulation of Single-Electron Transistor
Quantitative Modeling and Simulation of Single-Electron TransistorQuantitative Modeling and Simulation of Single-Electron Transistor
Quantitative Modeling and Simulation of Single-Electron Transistor
 
B011120723
B011120723B011120723
B011120723
 
Introduction gadgets have gained a lot of attention.pdf
Introduction gadgets have gained a lot of attention.pdfIntroduction gadgets have gained a lot of attention.pdf
Introduction gadgets have gained a lot of attention.pdf
 
Modeling of solar array and analyze the current transient response of shunt s...
Modeling of solar array and analyze the current transient response of shunt s...Modeling of solar array and analyze the current transient response of shunt s...
Modeling of solar array and analyze the current transient response of shunt s...
 
Modeling of solar array and analyze the current transient
Modeling of solar array and analyze the current transientModeling of solar array and analyze the current transient
Modeling of solar array and analyze the current transient
 
1743 1748
1743 17481743 1748
1743 1748
 
1743 1748
1743 17481743 1748
1743 1748
 
R01043105113
R01043105113R01043105113
R01043105113
 
Capacitance and Cable Testing
Capacitance and Cable TestingCapacitance and Cable Testing
Capacitance and Cable Testing
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
 
Design aspects of high voltage transmission line
Design aspects of high voltage transmission lineDesign aspects of high voltage transmission line
Design aspects of high voltage transmission line
 

More from IJAPEJOURNAL

Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...IJAPEJOURNAL
 
Underwater Target Tracking Using Unscented Kalman Filter
Underwater Target Tracking Using Unscented Kalman FilterUnderwater Target Tracking Using Unscented Kalman Filter
Underwater Target Tracking Using Unscented Kalman FilterIJAPEJOURNAL
 
Investigation of Dependent Rikitake System to Initiation Point
Investigation of Dependent Rikitake System to Initiation PointInvestigation of Dependent Rikitake System to Initiation Point
Investigation of Dependent Rikitake System to Initiation PointIJAPEJOURNAL
 
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineOptimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineIJAPEJOURNAL
 
Impact of Buried Conductor Length on Computation of Earth Grid Resistance
Impact of Buried Conductor Length on Computation of Earth Grid ResistanceImpact of Buried Conductor Length on Computation of Earth Grid Resistance
Impact of Buried Conductor Length on Computation of Earth Grid ResistanceIJAPEJOURNAL
 
Enhancing Photoelectric Conversion Efficiency of Solar Panel by Water Cooling
Enhancing Photoelectric Conversion Efficiency of Solar Panel by Water CoolingEnhancing Photoelectric Conversion Efficiency of Solar Panel by Water Cooling
Enhancing Photoelectric Conversion Efficiency of Solar Panel by Water CoolingIJAPEJOURNAL
 
PMU-Based Transmission Line Parameter Identification at China Southern Power ...
PMU-Based Transmission Line Parameter Identification at China Southern Power ...PMU-Based Transmission Line Parameter Identification at China Southern Power ...
PMU-Based Transmission Line Parameter Identification at China Southern Power ...IJAPEJOURNAL
 
Investigation of Electric Field Distribution Inside 500/220 kV Transformation...
Investigation of Electric Field Distribution Inside 500/220 kV Transformation...Investigation of Electric Field Distribution Inside 500/220 kV Transformation...
Investigation of Electric Field Distribution Inside 500/220 kV Transformation...IJAPEJOURNAL
 
Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...
Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...
Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...IJAPEJOURNAL
 
Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...
Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...
Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...IJAPEJOURNAL
 
An Application of Ulam-Hyers Stability in DC Motors
An Application of Ulam-Hyers Stability in DC MotorsAn Application of Ulam-Hyers Stability in DC Motors
An Application of Ulam-Hyers Stability in DC MotorsIJAPEJOURNAL
 
Implementation of Hybrid Generation Power System in Pakistan
Implementation of Hybrid Generation Power System in PakistanImplementation of Hybrid Generation Power System in Pakistan
Implementation of Hybrid Generation Power System in PakistanIJAPEJOURNAL
 
Modeling and Simulation of SVPWM Based Application
Modeling and Simulation of SVPWM Based ApplicationModeling and Simulation of SVPWM Based Application
Modeling and Simulation of SVPWM Based ApplicationIJAPEJOURNAL
 
Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...
Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...
Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...IJAPEJOURNAL
 
Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...
Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...
Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...IJAPEJOURNAL
 
Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...
Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...
Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...IJAPEJOURNAL
 
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...IJAPEJOURNAL
 
Hybrid Generation Power System for Domestic Applications
Hybrid Generation Power System for Domestic ApplicationsHybrid Generation Power System for Domestic Applications
Hybrid Generation Power System for Domestic ApplicationsIJAPEJOURNAL
 
Ash Cooler Heat Recovery Under Energy Conservation Scheme
Ash Cooler Heat Recovery Under Energy Conservation SchemeAsh Cooler Heat Recovery Under Energy Conservation Scheme
Ash Cooler Heat Recovery Under Energy Conservation SchemeIJAPEJOURNAL
 
Harmonic Voltage Distortions in Power Systems Due to Non Linear Loads
Harmonic Voltage Distortions in Power Systems Due to Non Linear LoadsHarmonic Voltage Distortions in Power Systems Due to Non Linear Loads
Harmonic Voltage Distortions in Power Systems Due to Non Linear LoadsIJAPEJOURNAL
 

More from IJAPEJOURNAL (20)

Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
 
Underwater Target Tracking Using Unscented Kalman Filter
Underwater Target Tracking Using Unscented Kalman FilterUnderwater Target Tracking Using Unscented Kalman Filter
Underwater Target Tracking Using Unscented Kalman Filter
 
Investigation of Dependent Rikitake System to Initiation Point
Investigation of Dependent Rikitake System to Initiation PointInvestigation of Dependent Rikitake System to Initiation Point
Investigation of Dependent Rikitake System to Initiation Point
 
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineOptimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
 
Impact of Buried Conductor Length on Computation of Earth Grid Resistance
Impact of Buried Conductor Length on Computation of Earth Grid ResistanceImpact of Buried Conductor Length on Computation of Earth Grid Resistance
Impact of Buried Conductor Length on Computation of Earth Grid Resistance
 
Enhancing Photoelectric Conversion Efficiency of Solar Panel by Water Cooling
Enhancing Photoelectric Conversion Efficiency of Solar Panel by Water CoolingEnhancing Photoelectric Conversion Efficiency of Solar Panel by Water Cooling
Enhancing Photoelectric Conversion Efficiency of Solar Panel by Water Cooling
 
PMU-Based Transmission Line Parameter Identification at China Southern Power ...
PMU-Based Transmission Line Parameter Identification at China Southern Power ...PMU-Based Transmission Line Parameter Identification at China Southern Power ...
PMU-Based Transmission Line Parameter Identification at China Southern Power ...
 
Investigation of Electric Field Distribution Inside 500/220 kV Transformation...
Investigation of Electric Field Distribution Inside 500/220 kV Transformation...Investigation of Electric Field Distribution Inside 500/220 kV Transformation...
Investigation of Electric Field Distribution Inside 500/220 kV Transformation...
 
Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...
Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...
Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...
 
Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...
Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...
Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...
 
An Application of Ulam-Hyers Stability in DC Motors
An Application of Ulam-Hyers Stability in DC MotorsAn Application of Ulam-Hyers Stability in DC Motors
An Application of Ulam-Hyers Stability in DC Motors
 
Implementation of Hybrid Generation Power System in Pakistan
Implementation of Hybrid Generation Power System in PakistanImplementation of Hybrid Generation Power System in Pakistan
Implementation of Hybrid Generation Power System in Pakistan
 
Modeling and Simulation of SVPWM Based Application
Modeling and Simulation of SVPWM Based ApplicationModeling and Simulation of SVPWM Based Application
Modeling and Simulation of SVPWM Based Application
 
Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...
Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...
Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...
 
Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...
Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...
Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...
 
Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...
Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...
Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...
 
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
 
Hybrid Generation Power System for Domestic Applications
Hybrid Generation Power System for Domestic ApplicationsHybrid Generation Power System for Domestic Applications
Hybrid Generation Power System for Domestic Applications
 
Ash Cooler Heat Recovery Under Energy Conservation Scheme
Ash Cooler Heat Recovery Under Energy Conservation SchemeAsh Cooler Heat Recovery Under Energy Conservation Scheme
Ash Cooler Heat Recovery Under Energy Conservation Scheme
 
Harmonic Voltage Distortions in Power Systems Due to Non Linear Loads
Harmonic Voltage Distortions in Power Systems Due to Non Linear LoadsHarmonic Voltage Distortions in Power Systems Due to Non Linear Loads
Harmonic Voltage Distortions in Power Systems Due to Non Linear Loads
 

Recently uploaded

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Reduced Dielectric Losses for Underground Cable Distribution Systems

  • 1. International Journal of Applied Power Engineering (IJAPE) Vol. 1, No. 1, April 2012, pp. 37~46 ISSN: 2252-8792 37 Journal homepage: http://iaesjournal.com/online/index.php/IJAPE Reduced Dielectric Losses for Underground Cable Distribution Systems HamzahEteruddin*, Abdullah Asuhaimi bin Mohd Zin** *Departement of Electrical Engineering, Lancang Kuning University **Departement of Electrical Power Engineering, UniversitiTeknologi Malaysia Article Info ABSTRACT Article history: Received Jan 13, 2012 Revised Mar 14, 2012 Accepted Mar 26, 2012 This paper describes the process to reduce dielectric losses for underground cable distribution system. As already known, that system is an alternative solution to energy distribution systems in urban areas. Influence of large capacitance is a separate issue that needs to be resolved. Large capacitance effect on Express Feeder of 10 miles long has resulted in power losses more than 100 MW per month. In the no-load condition, current dispatch has recorded 10 Amperes, and has increased the voltage at receiving end by 200- 500 Volts, with leading power factors. Installation of the inductor to reduce cable loss dielectrics is done by changing the power factor (pf) to 0.85 lagging. After installation of the inductor, which is 5 mH/700 kVAR, dielectric losses is reduced to 3.57%, which is from105,983 kW to 102,195 kWh per month. The capacitive leakage current has also been reduced from 249.61 Ampere to 245.17 Ampere. Keyword: Dielectric Losses Underground Cables Distribution System Capasitance Copyright © 2012 Institute of Advanced Engineering and Science. All rights reserved. Corresponding Author: Hamzah Eteruddin Departement of Electrical Engineering, LancangKuning University, YosSudarsoRoad, km 8 – Rumbai, Pekanbaru28265, Indonesia. Email: hamzah128@gmail.com 1. INTRODUCTION The most important things required in the power system is a matter of quantity and quality of the received energy on the consumer side. Delivery quantity is required to distribute electric power to all consumers in a region or area served, so the benefits from the existence of electric energy can be felt by the public. Increasing the quantity of electric power distribution will increase the electrification ratio in an area. At the same time, the quality of distribution of electrical energy is required to maintain the availability of electrical energy consumers in accordance with the standards used. Quantity and quality of electric energy distribution in urban areas often face problems, such as difficulty in getting right of way (ROW) for transmission and distribution networks. The land acquisition process for this purpose is not an easy thing to do at this time. This is due to the limited land that can be used for over head line. Underground cable distribution system is an alternative solution to distribute electrical energy in urban areas, so the city will be looked magnificent and clean. However, the construction cost of underground cable per km was much higher than over head line [1]. Development of distribution network is relatively tougher because the branching process (tapping) is much harder when compared to the airways. Anyhow underground cable is more protected from wind, lightning strikes, and disturbances of animals (like monkeys), which may cause short circuit. Musabaqoh Tilawatil Qur'an (MTQ) national level event was held in the mid-1980s at Pekanbaru, which is the capital of Riau province. In meeting the demand of electric power to serve all activities, the
  • 2. ISSN: 2252-8792 IJAPE Vol. 1, No. 1, April 2012 : 37 – 46 38 feeder in the district of "Simpang Tiga" and surrounding areas can no longer serve it. Thus, it needs the additional feeder in order to serve the requirements of specific loads around the location of the event. At the same time, the problem of urban congestion and the limited land that can be used as well as encouragement to pay attention to issues of beauty and scenery of Pekanbaru city should be tackled. This consequence is not possible for the addition of new feeders by using a medium-voltage over head line (OHL). Hence the utility (PLN Pekanbaru)has constructed Express Feeder using underground cable distribution between substation (SS) TelukLembu (TLB) and substation MTQ, to continue to serve the power demand. 1.1. Literature Review The difference of voltage level between the sending and the receiving end is due to the parameters of the line system (R, L, C). If the voltage level at the receiving end is lower than on the sending end then it is caused by the influence of R and L, so it is an inductive load. Meanwhile, if the voltage level at the receiving end is larger than the sending end, this is caused by the influence of R and C, so it is a capacitive load. Both cases can be described from the phasor diagram as shown in Figure 1, where VR= Voltage at receiving end, VS=Voltage at sending end, R=Line Resistance, X=Line Reactance, Z=Line Impedance, I= Line current, α= phase angle between voltage and currentat receiving end, δ= phase angle between VR and VS. Figure 1. Power system phasor diagrams Rules or standards used by the PLN (Persero) for the received voltage tolerance on the customer side is +5% and -10% of the working voltage (system) [2]. A large voltage drop will result in the loss of electric service to consumers and producers. The potential differences between the sending and the receiving end cannot be avoided. To keep the voltage difference is not too high on both sides, inductive reactive power or capacitive reactive power compensation is commonly used. A lot of research has been done in an attempt to improve the voltage level at transmission or distribution line. When the voltage level at the receiving end is less than the sending end, a capacitive reactive power compensation is to be performed. If the voltage at the receiving end is greater than the sending end, then inductive reactive power compensation has to be performed. Improvement of the voltage levels will reduce the power loss in the line. The level of improvement is determined by the value of reactive power, which can be obtained by installing inductors or capacitors. Most research conducted is to increase the voltage at the receiving end due to an inductive load. However, few researches has been undertaken to reduce the voltage. Indrayanti (2011) installs an inductor at the sending end based on the load flow data obtaindon average at 17.00. Then the results were used to calculate the magnitude of dielectric losses of underground cables. [3]. On the other hand, there is also the voltage difference between the conductors and cable sheath. The voltage difference will affect the capacitancevalue of the cable.The flux distribution in alternating current (a.c) cable insulation is complex and shown in Figure 2. The stress is a maximum at the conductor surface and varies throughout the insulation. It was decreasing with distance from the conductor surface, because of the differing permittivities of the components and the distribution of the flux at various times. The screened cable used for alternating voltages has a clearly defined stress pattern, while that of cables used on direct current (d.c) transmission has a changing pattern depending on temperature due to cable loading [4]. 1.2. Underground Cable Capacitance A single core cable is infact an electrostatic capacitor because it has two electrodes, the core of the cable and the sheath separated by dielectric material. Figure 3 shows, the capacitance of the underground cable a single-core. By definition, capacitance is the ratio of the charge on one of electrodes to potential difference between the electrodes [5, 6]. Capacitance of the single core underground cable can be calculated using the equation (1) [6].
  • 3. IJAPE ISSN: 2252-8792 Title of manuscript is short and clear, implies research results (First Author) 39 Figure 2. Flux distribution that occurs in a three-core cable. Figure 3. Capacitance of a single core cable. [ ] 2 Farad ln i c l C r r π ε⋅ ⋅ ⋅ =       (1) Where; C = capacitance value for single core underground cable,ri= the inner radius of the sheath, rc= radius of the conductor, l=cable lenght, ε=permittivity of the dielectric material. While for the three-core cable, the capacitance value can be calculated, if the dielectric is assumed uniform between the core and the sheath. However, normally it is not so and, therefore, it is desirable to find the capacitance by measurements. In a three core cable, sheath is at earth potential and the three conductors are at supply potentials. There are six capacitances form between these systems. Three capacitances are between the sheath and the conductors and the other three capacitances are between the conductors. The capacitance of three cores underground cable could be calculated using the equation (2) [6]. [ ]2 2 Farad ln c l C D r π ε⋅ ⋅ ⋅ =       (2) Where D = conductor spacing. If the distance between the conductorsareassumed symmetrical, and voltage stressesare uniformly distributed on the cable insulation. Then, as shown in Figure 4, the capacitance value can be calculated using equation (3). Figure 3. Capacitancesbetween cores and to sheath of a three core cable. [ ]0 1 23 FaradC C C= + ⋅ (3) Where C0 = capacitance value for three cores underground cable, C1 = the capacitance between conductor and the sheath, and C2 = the capacitance between each conductor. Table 1 shows the data from the electrical underground cable of XLPE insulation materials. Compounds that have good electrical properties are required for distribution cables with operating voltages above 3 kV. IEC502 standard requires that products must have a dielectric loss angle (DLA) and the
  • 4. ISSN: 2252-8792 IJAPE Vol. 1, No. 1, April 2012 : 37 – 46 40 permittivity is not greater than 0.75 with a range of angles 85 °C ambient. Besides, DLA at 80 °C must not exceed the value at 60 °C. This requires that when there is an open-circuit fault occur, while the cable is being energized with a high voltage, the wires will be hot even though there is no current flowing inside it [6, 7]. Figure 5 shows the physical shape of the underground cable NA2XSEFGbY used in this analysis. The technical data is as shown in Table 2 [8]. Figure 4. Equivalent capacitance of a three core cable. Table 1. Electrical Data Crosslinked Polyethylene (XLPE) cable Description Value Type GP 8 Volume resistivity (min) at 20°C (Ω m) 1 x 1014 Permittivity at 50 Hz 2.3-5.2 tan σ at 50 Hz 0.0004-0.005 Figure 5. Underground Cable NA2XSEFGbY (Courtesy of Kabel Metal Indonesia) The value of Inductor needs to compensate the reactive power can be determined by knowing the power factor at the sending and the receiving end. By using these two values, the addition value of inductive reactive impedance that required can be obtained in Henry and VAr. Table 2. Electrical and Mechanical Data of NA2XSEFGbY 240 mm2 . Description Value Description Value Cross Section of Conductor (mm2 ) 240 DC Resistance at 20 o C (Ω/km) 0.125 Conductor Diameter (mm) 18.7 AC Resistance at 90 o C (Ω/km) 0.162 Insulation Thickness (mm) 55 DC Insulation Resistance at 20o C (MΩ.km) 700 Insulation Diameter (mm) 31.3 Current Carrying Capacity in Air (A) 453 Armor Thickness (mm) 0.80 Current Carrying Capacity in ground (A) 385 Sheath Thickness (mm) 3.6 Capacitance per phase (µF/km) 0.307 Cable Weight (kg/km) 9.600 Inductance per phase (mH/km) 0.302 Min. Bending Radius (mm) 78.0 Max short circuit current of screen (kA/sec) 4.53 Overall Cable Diameter (mm) 85 Max short circuit current of conduct (kA/sec) 22.98
  • 5. IJAPE ISSN: 2252-8792 Title of manuscript is short and clear, implies research results (First Author) 41 1.3. Underground cable Energy Losses An underground cable consists of three main components, namely the conductor, dielectric materials, and sheath. When the cable is energized by a voltage electric, current will flow, and will heat the cable. The temperature rise of a cable body depends upon the rate of generation and dissipation of heat by the body. Thermal effects that occurred will result in losses. The losses are; (1) conductor losses, (2) dielectric losses, and (3) sheath losses [6]. This paper discusses the dielectric losses in underground cables, which is one of the three types of electric losses associated with an underground cable. As already known, that if it is energized with alternating current there will be a large capacitance effect, so it will involve the phase voltages and power factors. For single core cables, the dielectric loss can be calculated using the equation (4) [4, 6]. [ ]1 2 2 tan WattDP f C Vπ σ= ⋅ ⋅ ⋅ ⋅ ⋅ (4) where : 1DP = Dielectric Loss [Watt] f = Frequency [Hz] C = Capasitance [Farad/meter] V = Line to netral Voltage [Volt] tan σ = Dielectric Loss Angle (DLA) While for a three-core cable, the dielectric losses can be calculated using the equation (5) [ ]3 1 3 WattD DP P= ⋅ (5) There are several models that can be used in analyzing the transmission and distribution lines. Transmission or distribution lines can be modeled based on the value of its capacitive leakage current. This value is influenced by several things, including the length of lines, the system voltage level, and the distance conductor to ground (earth). For a small capacitance value, it can be ignored. This usually occurs in over head lines that are less than 80 km (short-line model). Meanwhile, if the capacitance values ismedium, it must be included in the analysis. There are two models that could be done, first by assuming that the capacitance is distributed equally on both ends of lines (model "phi" = Π). Alternatively, it assumed to be unity at the center of the lines (Model "T"). It usually called the medium line model, which is the overhead distribution lines system with length ≤ 240 km. Meanwhile, if capacitance value is large, the value of distributed capacitance should be analyzed along the line. In the overhead lines, usually it is called a model of long line (> 240 km) [9, 10]. 2. SYSTEM ANALYSIS Distribution lines medium-voltage underground cables that join the TLB - MTQ, installed 80-100 cm under the surface of the road. Track is used is to trace the roadside of TanjungRhu, Dr. Sutomo, Hang Tuah, Pattimura, and General Sudirman streets. The single-line diagram is as shown in Figure 6. Figure 6. One line diagram Distribution Line TelukLembu Substation – MTQ Substation.
  • 6. ISSN: 2252-8792 IJAPE Vol. 1, No. 1, April 2012 : 37 – 46 42 Express Feeder is 10 km in length using an aluminum conductor XLPE insulation right (Cross Linked Poly Ethylene) of the type NA2XSEFGbY measuring 3 x 240 mm2 . Feeders finally managed by PT. PLN (Persero) Region SimpangTiga, whichreceived supply from the TelukLembusubstation (SS), using underground cable distribution line 20 kV [11]. XLPE insulated cable has the dielectric loss lower than on other types of insulation such as PVC (Polyvinyl chloride) and EPR (Ethylene Propylene Rubber) [4, 12]. Furthermore the voltage and current profiles are obtained at TelukLembu SS, based on hours of operation on December 6, 2010. The data is as shown in Table 3. From the table, it is shown that the peak load begins at 18:00 hours until 21:00 pm. Where the maximum load occurs at phase 'T' at 19:00, with the average peak load is equal to 237.66 Ampere. The additionalsubstantial load occurs during hours of 17:00 to 18:00 pm. The increase reached 17%, where at 17:00 the new average weight of 190.66 Ampere with a voltage of 20.3 kV Amperes, while at 18.00 pm rose to 224.33 Ampere. The minimum peak load occurred at 06.00 am, with the largest decrease occurred in the period from 9:00 p.m. to 22:00 pm. Table 3 also shows that, the maximum peak voltage occurs at 18.00 pm, which is 20,600 Volts. As been seen, the peak voltage occurs when the load average is quite large (224.33 Ampere). The minimum peak voltage of 19,200 Volt occurred at 1:00 pm. The other thing is at 1:00 to 2:00, system voltage is less the 20 kV. It could be a period before where interruption in these lines will take place. Table 3. Express Feeder TLB – MTQ Profile Time MTQ Exp Feeder Current (A) Volt (V)Phase R Phase S Phase T 01:00 167 167 178 19,200 02:00 165 165 175 19,900 03:00 160 160 172 20,100 04:00 157 157 168 20,200 05:00 155 155 165 20,200 06:00 150 150 160 20,300 07:00 154 153 163 20,500 08:00 170 176 174 20,000 09:00 170 177 173 20,000 10:00 176 179 178 20,200 11:00 182 187 185 20,200 12:00 180 179 181 20,300 13:00 178 186 183 20,500 14:00 187 195 191 20,200 15:00 190 197 196 20,300 16:00 185 186 194 20,300 17:00 187 187 198 20,300 18:00 220 219 234 20,600 19:00 233 233 247 20,100 20:00 231 231 245 20,200 21:00 220 220 235 20,200 22:00 195 196 196 20,100 23:00 199 182 187 20,100 24:00 193 192 190 20,200 Table 4. MTQ SS Load Data Time Outgoing Line (Amp) Incoming Line (Amp) Volt (kV) 17:00 L1 195 L1 192 20,500L2 201 L2 200 L3 200 L3 196 18:00 L1 211 L1 206 20,700L2 217 L2 213 L3 216 L3 212 19:00 L1 249 L1 245 20,100L2 252 L2 251 L3 255 L3 254 20:00 L1 240 L1 236 20,800L2 242 L2 239 L3 245 L3 242 21:00 L1 236 L1 233 20,400L2 240 L2 239 L3 242 L3 241 3. RESEARCH METHOD The method used in analyzing underground cable distribution system which is 10 km long, uses two circuit models: (1) nominal "pi" (π) circuit, and (2) nominal "T" circuit. At the nominal "pi" (π) circuit, it is assumed that the capacitance is evenly distributed along the cable,the model is divided equally on both ends of lines, while the inductive impedance is in the middle of lines. Figure 7.a. shows that the CS and CR are the capacitance of the lines which is at the sending and the receiving end. For the nominal "T" circuit, it is assumed that the capacitance is evenly distributed along the wire, modeled as a capacitance which is at the center of the lines, while the inductive impedance is modeled equally divided on both ends of lines. Both model of theses circuit are as shown in Figure 7. The use of underground cables resulted in the existence of capacitance effects in the system. In this system, the power factor is 0.9 leading. Therefore, it is necessary to have an inductive reactive power compensation. Considering the system is a capacitive reactive power, it needs to be installed inductive reactive power. So that's why, inductor as a supplier of inductive reactive power should be installed.
  • 7. IJAPE ISSN: 2252-8792 Title of manuscript is short and clear, implies research results (First Author) 43 CSVS VR IS IL Load SCI 1 1 2 LineZ 2 1 2 LineZ CS CRVS VR IL SCI RCI LineI IS Load LineZ 1LineI 2LineI (a). Nominal Phi “Π” (b). Nominal T Figure 7. GI TelukLembu – GH MTQ Distribution Line model SCI RCI SCI 1 1 2 LineZ 2 1 2 LineZ LineI LineZ 1LineI 2LineI Figure 8. Inductor installed at the sending end or TelukLembu Substation This analysis is conducted with the addition of the inductor with 2 (two) scenarios. First scenario is to place or install the inductor at the sending or the TLB SubStation side. Then do the analysis of the system. The circuit is as shown in Figure 8. The second scenario is to place or install the inductor on the receiving end or MTQ substation side. The circuit is as shown in Figure 9. Afterwards an inductive reactive power requirement of the system is calculated. Then using that data, the similar analysis using scenario 1 and scenario 2 is conducted. The calculation is done with the help of Matrix Laboratory software (MatLab). The calculation is performed at every hour, from 01:00 hours until 24.00 pm. SCI RCI SCI 1 1 2 LineZ 2 1 2 LineZ LineI LineZ 1LineI 2LineI Figure 9. Inductor installed at the sending end or MTQ Substation 4. RESULTS AND ANALYSIS The results of the analysis conducted on the third circuit of Figures 7, 8 and 9 are as shown in Table 5. 4.1. Exsisting Condition Under these conditions is seen that the average voltage on the GH MTQ 2.43% is larger than its sending end (TLB SS). The total capacitive leakage current that occurs during the 24 hours is 249.61 Ampere. The dielectric loss that occurred in line is equal to 3.53 MW. Assuming a month is 30 days and the profile of the system every day for a month is similar, then its losses amounted to 105.98 MW per month.
  • 8. IJAPE Vol. 1, No. 1, April 2012 44 (a). Nominal “Phi” Π Figure 10. Table 5. Voltage and current profiles before and after the Time Existing Condition Voltage ArusBocor TLB [Volt] MTQ [Volt] 01:00 19200 19,625.27 02:00 19900 20,318.84 03:00 20100 20,507.61 04:00 20200 20,599.00 05:00 20200 20,593.02 06:00 20300 20,680.14 07:00 20500 20,888.56 08:00 20000 20,431.60 09:00 20000 20,431.60 10:00 20200 20,642.58 11:00 20300 20,760.46 12:00 20300 20,750.20 13:00 20500 20,954.35 14:00 20200 20,676.75 15:00 20300 20,785.23 16:00 20300 20,769.85 17:00 20300 20,775.83 18:00 20600 21,161.94 19:00 20100 20,696.43 20:00 20200 20,791.24 21:00 20200 20,743.39 22:00 20100 20,588.78 23:00 20100 20,572.54 24:00 20200 20,678.46 4.2. Scenario1 The inductor is placed at the sending for the improvement of the system. 2.25% than before installing the induc capacitive leakage current is also decreased by 1.06% to 248.55 Ampere, where previously 249.61 Ampere. This also resulted in lower power losses for a month, then the power loss 4.3. Scenario 2 Meanwhile, for the second scenario, the results obtained are better than the first scenario. The average voltage at the receiving end is almost the same as the sending end, which is on average is lower by 0.01%. Capacitive leakage current decreased to 245.17 Ampere only. Thi line dropped to 126.25 kW, compared with the existing conditions, of 3.41 MW. Furthermore, when compared to scenario 1, the losseswas reduced to 87.69 kW. With the same assumptions (similar every day for a month), then the losses per month could be save from 3.79 MW (3.57%) for model Phi and 3.65 MW (3.45%) for model “T”. 2 : 37 – 46 (a). Nominal “Phi” Π (b). Nominal “T” 10. Voltage graph profiles that occur in three condition 5. Voltage and current profiles before and after the installation of Inductor Existing Condition Inductor at TLB ArusBocor [A] Dielec Loss [kWh] Voltage MTQ [Volt] ArusBocor [A] Rugi2 saluran [kWh] Voltage MTQ [Volt] 9.89 132.96 19,223.46 9.85 131.73 19,196.67 10.24 142.67 19,922.73 10.21 141.43 19,894.98 10.34 145.45 20,121.85 10.31 144.23 20,093.83 10.39 146.82 20,221.19 10.36 145.63 20,193.03 10.39 146.78 20,220.76 10.36 145.60 20,192.61 10.44 148.13 20,319.80 10.40 146.99 20,291.51 10.54 151.09 20,520.33 10.51 149.92 20,491.76 10.30 144.19 20,023.61 10.26 142.89 19,995.72 10.30 144.19 20,023.61 10.26 142.89 19,995.72 10.40 147.13 20,224.33 10.36 145.79 20,196.15 10.46 148.71 20,325.58 10.42 147.30 20,297.25 10.46 148.63 20,324.84 10.42 147.26 20,296.52 10.56 151.57 20,525.07 10.52 150.18 20,496.47 10.41 147.38 20,226.79 10.37 145.92 20,198.60 10.46 148.89 20,327.36 10.42 147.39 20,299.03 10.46 148.78 20,326.26 10.42 147.34 20,297.93 10.46 148.82 20,326.69 10.42 147.36 20,298.35 10.64 153.83 20,632.77 10.59 152.04 20,603.99 10.39 146.81 20,135.44 10.34 144.93 20,107.34 10.44 148.21 20,235.03 10.39 146.34 20,206.79 10.43 147.86 20,231.59 10.38 146.17 20,203.36 10.36 146.03 20,127.69 10.32 144.53 20,099.63 10.36 145.91 20,126.53 10.32 144.47 20,098.47 10.41 147.39 20,226.91 10.37 145.93 20,198.72 The inductor is placed at the sending end or TLB SS (see Figure 10). This configuration the improvement of the system. The voltage at the receiving end (MTQ) decreased 2.25% than before installing the inductor, or only up to 0.13% from the sending end. While the total capacitive leakage current is also decreased by 1.06% to 248.55 Ampere, where previously 249.61 Ampere. This also resulted in lower power losses is reduced to 3.49 MW. With the same assumptions he power loss will decrease 1.16 MW (model Phi) and 1.02 MW (model “T”) second scenario, the results obtained are better than the first scenario. The average voltage at the receiving end is almost the same as the sending end, which is on average is lower by 0.01%. Capacitive leakage current decreased to 245.17 Ampere only. This resulted in dielectric losses in the line dropped to 126.25 kW, compared with the existing conditions, of 3.41 MW. Furthermore, when compared to scenario 1, the losseswas reduced to 87.69 kW. With the same assumptions (similar every day n the losses per month could be save from 3.79 MW (3.57%) for model Phi and 3.65 MW ISSN: 2252-8792 (b). Nominal “T” installation of Inductor Inductor at MTQ Voltage MTQ [Volt] ArusBocor [A] Dielec Loss [kWh] 19,196.67 9.72 128.53 19,894.98 10.08 138.15 20,093.83 10.18 141.00 20,193.03 10.24 142.44 20,192.61 10.24 142.47 20,291.51 10.29 143.93 20,491.76 10.39 146.77 19,995.72 10.13 139.51 19,995.72 10.13 139.51 20,196.15 10.23 142.29 20,297.25 10.28 143.64 20,296.52 10.28 143.68 20,496.47 10.38 146.53 20,198.60 10.23 142.16 20,299.03 10.28 143.55 20,297.93 10.28 143.61 20,298.35 10.28 143.59 20,603.99 10.42 147.57 20,107.34 10.16 140.32 20,206.79 10.21 141.75 20,203.36 10.22 141.92 20,099.63 10.17 140.71 20,098.47 10.18 140.77 20,198.72 10.23 142.16 his configuration is created he voltage at the receiving end (MTQ) decreased on the average of tor, or only up to 0.13% from the sending end. While the total capacitive leakage current is also decreased by 1.06% to 248.55 Ampere, where previously 249.61 Ampere. to 3.49 MW. With the same assumptions of similar profile (model “T”). second scenario, the results obtained are better than the first scenario. The average voltage at the receiving end is almost the same as the sending end, which is on average is lower by s resulted in dielectric losses in the line dropped to 126.25 kW, compared with the existing conditions, of 3.41 MW. Furthermore, when compared to scenario 1, the losseswas reduced to 87.69 kW. With the same assumptions (similar every day n the losses per month could be save from 3.79 MW (3.57%) for model Phi and 3.65 MW
  • 9. IJAPE (a). Nominal “Phi” Π Figure 11. Graph of power loss that occurs during the 24 hours Moreover, using both scenarios,it can be seen that the selection of the location of the installation or placement of the inductor location also affec scenarios are have shown improvement in the system. However, result obtained when using the second scenario is much better. This can be seen from the voltage at the receiving end, leak current cap line losses which are decreased. Hence, by using the second scenario it will produce a technically better system. In addition, the PT. PLN (Persero) will be able to save the technical losses occurs on their systems. By using almost the same cost, certainly the second scenario is a better choice since the results are significantly better. Table 6. Comparison of Losses Model "Phi" and the Model T before and after the installation of Inductor Dielectric losses per day before installing inductor Dielectric losses per dayafter installing inductor at sending end Saving losses Saving for a month Dielectric losses per dayafter installing Saving losses Saving for a month 5. CONCLUSION Based on the description above it scenario, where the position of the inductor is placed at the receiving or the MTQ SS. It can save losses of PT. PLN (Persero) per month of 3.788 MW (3.57%) for model Phi and 3.65 MW (3.45%) for model “T”. When compared with the first scenario just save of 1.16 MW (1.09%) only per mon MW (0.9 %) for model “T”. ACKNOWLEDGEMENTS The authors would like to thank Universiti Teknologi Malaysia and Lancang Kuning University providing the financial and technical support for the research. The authors also would like to thanks (Persero), for providing data and permission to REFERENCES [1] B. L. Theraja, A Textbook of Electrical Technology: Electronic devices & & Company Ltd., 2005. [2] PT. PLN (Persero), "Tegangan- [3] V. N. Indrayanti, "Studi Pemasangan di Express Feeder 20 kV GI. TelukLembu Universitas Lancang Kuning, Pekanbaru, 2011. [4] G. F. Moore and B. C. Ltd, Electric Cables Handbook: Blackwell Science, 1997. [5] P. A. Laplante, Comprehensive Dictionary of Electrical Engineering, Second ed. Malvern: CRC Press, 2005. [6] C. L. Wadhwa, Electrical Power Systems: New Age International, 2006. ISSN: 2252-8792 Title of manuscript is short and clear, implies research results (First Author) (a). Nominal “Phi” Π (b). Nominal “T” 11. Graph of power loss that occurs during the 24 hours Moreover, using both scenarios,it can be seen that the selection of the location of the installation or placement of the inductor location also affects the performance of the system. Both the first and second scenarios are have shown improvement in the system. However, result obtained when using the second scenario is much better. This can be seen from the voltage at the receiving end, leak current cap Hence, by using the second scenario it will produce a technically better system. In addition, the PT. PLN (Persero) will be able to save the technical losses occurs on their systems. By using almost the same t, certainly the second scenario is a better choice since the results are significantly better. Table 6. Comparison of Losses Model "Phi" and the Model T before and after the installation of Inductor Description Model Phi [kW] losses per day before installing inductor 3,532.78 Dielectric losses per dayafter installing inductor at sending end 3,494.23 1,156.57 Dielectric losses per dayafter installing inductor at receiving end 3,406.51 126.27 3,788.24 Based on the description above it can be seen that the second scenario is much better than the first of the inductor is placed at the receiving or the MTQ SS. It can save losses of PT. PLN (Persero) per month of 3.788 MW (3.57%) for model Phi and 3.65 MW (3.45%) for model “T”. When compared with the first scenario just save of 1.16 MW (1.09%) only per month for model Phi and 1.02 would like to thank Universiti Teknologi Malaysia and Lancang Kuning University financial and technical support for the research. The authors also would like to thanks data and permission to present this paper. B. L. Theraja, A Textbook of Electrical Technology: Electronic devices & circuits in S.I. system of units: S. Chand -Tegangan Standar," ed. Jakarta: PT. PLN (Persero), 1995, p. 5. Pemasangan Induktor pada Jaringan Kabel Bawah-Tanah untuk Kompensa di Express Feeder 20 kV GI. TelukLembu - GH. MTQ PT. PLN (Persero) Cab.Pekanbaru," TeknikElektro, Kuning, Pekanbaru, 2011. G. F. Moore and B. C. Ltd, Electric Cables Handbook: Blackwell Science, 1997. lante, Comprehensive Dictionary of Electrical Engineering, Second ed. Malvern: CRC Press, 2005. C. L. Wadhwa, Electrical Power Systems: New Age International, 2006. Title of manuscript is short and clear, implies research results (First Author) 45 (b). Nominal “T” 11. Graph of power loss that occurs during the 24 hours Moreover, using both scenarios,it can be seen that the selection of the location of the installation or ts the performance of the system. Both the first and second scenarios are have shown improvement in the system. However, result obtained when using the second scenario is much better. This can be seen from the voltage at the receiving end, leak current capacitive and Hence, by using the second scenario it will produce a technically better system. In addition, the PT. PLN (Persero) will be able to save the technical losses occurs on their systems. By using almost the same t, certainly the second scenario is a better choice since the results are significantly better. Table 6. Comparison of Losses Model "Phi" and the Model T before and after the installation of Inductor Model Phi [kW] Model T [kW] 3,532.78 3,528.23 3,494.23 3,494.27 38.55 33.96 1,156.57 1,018.91 3,406.51 3,406.54 126.27 121.69 3,788.24 3,650.60 seen that the second scenario is much better than the first of the inductor is placed at the receiving or the MTQ SS. It can save losses of PT. PLN (Persero) per month of 3.788 MW (3.57%) for model Phi and 3.65 MW (3.45%) for model “T”. th for model Phi and 1.02 would like to thank Universiti Teknologi Malaysia and Lancang Kuning University for financial and technical support for the research. The authors also would like to thanks PT. PLN circuits in S.I. system of units: S. Chand Standar," ed. Jakarta: PT. PLN (Persero), 1995, p. 5. Kompensasi Arus Kapasitif GH. MTQ PT. PLN (Persero) Cab.Pekanbaru," TeknikElektro, lante, Comprehensive Dictionary of Electrical Engineering, Second ed. Malvern: CRC Press, 2005.
  • 10. ISSN: 2252-8792 IJAPE Vol. 1, No. 1, April 2012 : 37 – 46 46 [7] I. E. Commission, "Extruded Solid Dielectric Insulated Power Cables For Rated Voltages from 1 kV Up To 30 kV," ed. Geneva: IEC Press, 1983. [8] S. N. Indonesia, "Persyaratan Umum Instalasi Listrik 2000," vol. SNI 04-0225-2000, ed. Jakarta: Badan Standardisasi Nasional, 2000. [9] T. Gönen, Electric power transmission system engineering: analysis and design, 2nd ed.: CRC Press, 2009. [10] J. J. Grainger and W. D. Stevenson, Power System Analysis: McGraw-Hill, 1994. [11] PT. PLN (Persero), "Generating and Transmission Data of Central Sumatra," P3BS, Ed., ed. Padang, 2010. [12] B. Richardson and R. Ramachandran, "Enhanced energy efficiency of underground cables," in Transmission and Distribution Conference and Exposition, 2010 IEEE PES, 2010, pp. 1-5. BIOGRAPHIES OF AUTHORS Hamzah Eteruddin received the Electrical Engineering degree from LancangKuning University, Indonesia, in 1994, and the M.Eng. degree from GadjahMada University, Indonesia, in 2003. Currently, he ispursuing his Ph.D at UniversitiTeknologi Malaysia (UTM), Johor Bahru. His research interests include power system protection, power system analysis, fault in underground cables and over head lines, Power Transmission Lines, Energy. Hamzah is a corporate member of Association of Indonesia Mechanical Electrical Professionalis (APEI) and Chairman of APEI at Riau Province. Abdullah Asuhaimi Mohd Zin received the B.Sc. degree from Gadjah Mada University, Indonesia, in 1976, the M.Sc. degree from University of Strathclyde, Strathclyde, U.K. in 1981, and the Ph.D. degree from the University of Manchester Institute of Science and Technology, Manchester, U.K., in 1988. Currently, he is a Professor and Head of Power Engineering Research Group (PERG), Faculty of Electrical Engineering, UniversitiTeknologi Malaysia, Johor Bahru. His research interests include power system protection, application of neural network in power system, arcing fault in underground cables, power quality and dynamic equivalent of power systems. Dr. Mohd Zin is a corporate member of The Institution of Engineers, Malaysia (IEM) and a member of the Institute of Electrical Engineers (U.K.). He is a registered Professional Engineer (P. Eng.) in Malaysia and Chartered Engineer (C.Eng.) in the United Kingdom.)