Warehouse Management Overview
WM interfaces with the following areas:
1. Inventory Management
2. Quality Management
3. Production Planning – This is the focus area for the following slides.
4. Shipping
2
WM-PP Interface
There are two scenario in for WM-PP Interface :
• WM-PP Scenario not active
• WM-PP Scenario active
3
WM-PP Interface not active
4
What is Control Cycle ?
For each material and PSA in the plant , one needs to define the following :
1. Storage bin to which the materials will be supplied to
2. Type of material staging.
Transaction Code:
LPK1/LPK2/LPK3-Create/Change/Display
LS41 – List of Control Cycles
LPK4-Automatic creation of control cycles for release order parts
Pre-requisite :
Number range defined for Control Cycle.
5
Different types of Staging
Sr.No PICK PARTS
Indicator=1
CRATE PARTS
Indicator =2
RELEASE PARTS
Indicator =3
MANUAL STAGING
Indicator =4
1 Staging is process order
dependent
Staging is process order
independent. This is used
for materials stored in
crates or standard
containers
Staging process is
independent of the
order. The dept.
determines the quantity
required
Staging is process order dependent.
2 Material staging can be
created manually – LP10
OR automatically
Material staging is always
done manually –
LP11(Standard)
Material Staging is done
manually via- LP12
(Standard)
Here staging is done manually, and
used in areas where business needs to
stage material incase of damage and
excess consumption.
3 Requirement number here
is the production order
number .If the order is >
10, then it truncated from
right to left
Requirement number is the
production supply area ,
dynamic bin is not
supported. The quantity to
be staged is defined in the
control cycle.
Requirement number is
the production supply
area
Dynamic bin coordinate not supported
in manual staging
4 Can have one control cycle
for all materials
One control cycle per
material per PSA.Here , one
control cycle for multiple
materials per PSA does not
work.
Need to have control
cycle for each material
.Due to system
performance you can
create one control cycle
for multiple materials
Can have one control cycle for
multiple materials per PSA.
6
Production Supply Area
• PSA lies in the production area. It is in the PSA that the material staging is done
• PSA groups together the work centers near to production storage bins, taking the material staging
type into consideration.
• A PSA area is defined per plant and storage location under for a warehouse number under WM-
PP Interface.
Transaction for Creation :PK05
Standard Production Supply Area:
100-Production Supply Area
7
Production Supply Area Determination
Work Centre Master Data
• If no information is maintained in the work center the
system checks in BOM
Bill of Material (BOM)
• If no information is found in the BOM , then the system
check for source supply area in the material master data
Material Master Data
8
Movement Type Determination
• The system will first which Storage type
is assigned in the control cycle. For
eg.100
Control Cycle
• To the storage type a replenishment
movement type is assigned ,and hence the
system determines the movement type. For
e.g.-319 –Replenish for Production
Storage Type
9
Production Storage Bin
• A production storage bin is a storage bin in the PSA.
• A production storage bin , is used in the control cycle for each material and PSA. This helps the
system to understand the bin where the material will be staged.
• It is created as a normal bin.
• You can have dynamic bins for Pick Parts, and the staging will be done for particular orders.
10
Process Flow
Process
Order
Release
Order
Material Staging
manually/Automa
tic
A Transfer
requirement is
created with
requirement type
“p”
With reference to
the TR a TO is
created via
LB13.TO Creation
can be
manual/automatic
GI for the material
consumption
The following depend on the settings in the production schedule profile:
1. Automatic/Manual Staging
2. Transfer requirement/delivery creation upon release
• WM is responsible to provide materials for production.
• It does so by supplying the needed materials to storage bins to production area.
• This is done so through creation of transfer orders for every transfer requirements.
• The subsequent goods issues posting reduces the stocks that have been removed from “production”
storage bins ,and no additional activities are required in WM
Material will be staged in
100 –Production Supply
Area
11
Interface Active V/s Interface In-Active
12
Sr.No WM-PP Active WM-PP Inactive
1 Once order released , staging
needs to be carried out
No Staging required.
2 Control cycles required Control Cycle not required
3 PSA area and production
storage bins required
PSA and bins not required
4 319/320 movement type used
for staging
These movement types are not used
5 Upon goods issue , material
gets consumed and no
additional activity required in
WM
Upon goods issue, materials gets
consumed in IM, in WM TR and TO needs
to be processed and confirmed to clear
the negative quants.
6 PSA -100 used here 914- Goods in Production Area is used

More Related Content

What's hot

Automatic batch determination based on shelf life
Automatic batch determination based on shelf lifeAutomatic batch determination based on shelf life
Automatic batch determination based on shelf life
Mauricio Beltran
 
STO process with config 5th method
STO  process with config 5th methodSTO  process with config 5th method
STO process with config 5th method
Mohammed Azhad
 

What's hot (20)

SAP EWM Pick Cancellation Process
SAP EWM Pick Cancellation ProcessSAP EWM Pick Cancellation Process
SAP EWM Pick Cancellation Process
 
Availability Check in SAP SD
Availability Check in SAP SDAvailability Check in SAP SD
Availability Check in SAP SD
 
Automatic picking configuration in delivery in sap sd
Automatic picking configuration in delivery in sap sdAutomatic picking configuration in delivery in sap sd
Automatic picking configuration in delivery in sap sd
 
EWM POSC AND WOCR
EWM POSC AND WOCREWM POSC AND WOCR
EWM POSC AND WOCR
 
Automatic batch determination based on shelf life
Automatic batch determination based on shelf lifeAutomatic batch determination based on shelf life
Automatic batch determination based on shelf life
 
SAP EWM Cross Docking
SAP EWM Cross DockingSAP EWM Cross Docking
SAP EWM Cross Docking
 
Availability Check in SAP SD
Availability Check in SAP SDAvailability Check in SAP SD
Availability Check in SAP SD
 
Route determination
Route determinationRoute determination
Route determination
 
SAP EWM Kitting
SAP EWM KittingSAP EWM Kitting
SAP EWM Kitting
 
Intercompany config
Intercompany configIntercompany config
Intercompany config
 
Free goods determination
Free goods determinationFree goods determination
Free goods determination
 
Pipeline process in SAP MM
Pipeline process in SAP MMPipeline process in SAP MM
Pipeline process in SAP MM
 
SAP ATP check for Sales Order
SAP ATP check for Sales OrderSAP ATP check for Sales Order
SAP ATP check for Sales Order
 
SAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna NookellaSAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna Nookella
 
Kitting with SAP EWM
Kitting with SAP EWMKitting with SAP EWM
Kitting with SAP EWM
 
SAP STO config
SAP STO configSAP STO config
SAP STO config
 
STO process with config 5th method
STO  process with config 5th methodSTO  process with config 5th method
STO process with config 5th method
 
Serial number profile configuration for material
Serial number profile configuration for materialSerial number profile configuration for material
Serial number profile configuration for material
 
Stock transfer using stock transport order
Stock transfer using stock transport orderStock transfer using stock transport order
Stock transfer using stock transport order
 
SAP EWM BATCH MANAGEMENT
SAP EWM BATCH MANAGEMENTSAP EWM BATCH MANAGEMENT
SAP EWM BATCH MANAGEMENT
 

Viewers also liked

Configuration documentation wm
Configuration documentation wmConfiguration documentation wm
Configuration documentation wm
Joseph JO
 
Mm warehouse management-configuration
Mm warehouse management-configurationMm warehouse management-configuration
Mm warehouse management-configuration
nitinbjambagi
 
Warehouse Management System
Warehouse Management SystemWarehouse Management System
Warehouse Management System
RRChandran
 
Batch search strategy
Batch search strategyBatch search strategy
Batch search strategy
Jaya Kapoor
 
SAP Automatic batch determination
SAP Automatic batch determinationSAP Automatic batch determination
SAP Automatic batch determination
Amit Pandey
 
Batch Expiration Date Management in SAP MRP/MPS
Batch Expiration Date Management in SAP MRP/MPS Batch Expiration Date Management in SAP MRP/MPS
Batch Expiration Date Management in SAP MRP/MPS
Vijay Pisipaty
 

Viewers also liked (20)

Sap wm pdf
Sap wm pdfSap wm pdf
Sap wm pdf
 
Configuration documentation wm
Configuration documentation wmConfiguration documentation wm
Configuration documentation wm
 
Mm warehouse management-configuration
Mm warehouse management-configurationMm warehouse management-configuration
Mm warehouse management-configuration
 
Warehouse Management System
Warehouse Management SystemWarehouse Management System
Warehouse Management System
 
LO530 Warehouse Management
LO530 Warehouse ManagementLO530 Warehouse Management
LO530 Warehouse Management
 
Sap mm full
Sap mm fullSap mm full
Sap mm full
 
Warehousing
WarehousingWarehousing
Warehousing
 
Batch Verification in RF
Batch Verification in RFBatch Verification in RF
Batch Verification in RF
 
Batch Verification in SAP RF
Batch Verification in SAP RFBatch Verification in SAP RF
Batch Verification in SAP RF
 
Batch search strategy
Batch search strategyBatch search strategy
Batch search strategy
 
SAP Automatic batch determination
SAP Automatic batch determinationSAP Automatic batch determination
SAP Automatic batch determination
 
Batch Expiration Date Management in SAP MRP/MPS
Batch Expiration Date Management in SAP MRP/MPS Batch Expiration Date Management in SAP MRP/MPS
Batch Expiration Date Management in SAP MRP/MPS
 
Pp batch management-presentation
Pp batch management-presentationPp batch management-presentation
Pp batch management-presentation
 
Warehouse
WarehouseWarehouse
Warehouse
 
SAP MM Standard Business Processes
SAP MM Standard Business ProcessesSAP MM Standard Business Processes
SAP MM Standard Business Processes
 
Presentazione PP WM
Presentazione PP WMPresentazione PP WM
Presentazione PP WM
 
Ctac S/4HANA - Simplify Your Future - SAP: Nic vervoort
Ctac S/4HANA - Simplify Your Future - SAP: Nic vervoortCtac S/4HANA - Simplify Your Future - SAP: Nic vervoort
Ctac S/4HANA - Simplify Your Future - SAP: Nic vervoort
 
Qm overview
Qm overview Qm overview
Qm overview
 
Introduction to sap r3 (mm)
Introduction to sap r3 (mm)Introduction to sap r3 (mm)
Introduction to sap r3 (mm)
 
SAP Material Batch Master Change Control Solution
SAP Material Batch Master Change Control SolutionSAP Material Batch Master Change Control Solution
SAP Material Batch Master Change Control Solution
 

Similar to WM - PP Interface

Anwar bayali report
Anwar bayali   reportAnwar bayali   report
Anwar bayali report
Adeel Farooq
 
Sap mrp materials requirements planning
Sap mrp   materials requirements planningSap mrp   materials requirements planning
Sap mrp materials requirements planning
madhu jetty
 
Just In Time and Lean Management
Just In Time and Lean ManagementJust In Time and Lean Management
Just In Time and Lean Management
Ruhi Beri
 
Mrp 1 deepak 12mt07ind009
Mrp 1 deepak 12mt07ind009Mrp 1 deepak 12mt07ind009
Mrp 1 deepak 12mt07ind009
Akash Maurya
 

Similar to WM - PP Interface (20)

PPC Chapter 8.pdf
PPC Chapter 8.pdfPPC Chapter 8.pdf
PPC Chapter 8.pdf
 
Internship Report - Tactical Supply Chain Improvements.pptx
Internship Report - Tactical Supply Chain Improvements.pptxInternship Report - Tactical Supply Chain Improvements.pptx
Internship Report - Tactical Supply Chain Improvements.pptx
 
INTRODUCTION TO RCM.ppt
INTRODUCTION TO RCM.pptINTRODUCTION TO RCM.ppt
INTRODUCTION TO RCM.ppt
 
MA1.ppt
MA1.pptMA1.ppt
MA1.ppt
 
Preguntas y respuestas examen de SAP PP
Preguntas y respuestas examen de SAP PPPreguntas y respuestas examen de SAP PP
Preguntas y respuestas examen de SAP PP
 
5 MRP.ppt
5 MRP.ppt5 MRP.ppt
5 MRP.ppt
 
5 MRP.ppt
5 MRP.ppt5 MRP.ppt
5 MRP.ppt
 
14 synchronous manufacturing
14 synchronous manufacturing14 synchronous manufacturing
14 synchronous manufacturing
 
World class factory equipment spare parts program
World class factory equipment spare parts programWorld class factory equipment spare parts program
World class factory equipment spare parts program
 
Planning Process and CBP V1.1.ppt
Planning Process and CBP V1.1.pptPlanning Process and CBP V1.1.ppt
Planning Process and CBP V1.1.ppt
 
Terry towel oracle ebs scoping
Terry towel oracle ebs scopingTerry towel oracle ebs scoping
Terry towel oracle ebs scoping
 
Pull Vs. Push Production
Pull Vs. Push ProductionPull Vs. Push Production
Pull Vs. Push Production
 
Anwar bayali report
Anwar bayali   reportAnwar bayali   report
Anwar bayali report
 
SCM EWM Solution
SCM EWM SolutionSCM EWM Solution
SCM EWM Solution
 
Sap mrp materials requirements planning
Sap mrp   materials requirements planningSap mrp   materials requirements planning
Sap mrp materials requirements planning
 
Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-pp
 
Just In Time and Lean Management
Just In Time and Lean ManagementJust In Time and Lean Management
Just In Time and Lean Management
 
Mrp 1 deepak 12mt07ind009
Mrp 1 deepak 12mt07ind009Mrp 1 deepak 12mt07ind009
Mrp 1 deepak 12mt07ind009
 
Instrumentation & control of typical material handling of FGD Plant
Instrumentation & control of typical material handling of FGD PlantInstrumentation & control of typical material handling of FGD Plant
Instrumentation & control of typical material handling of FGD Plant
 
flexible manufacturing system
flexible manufacturing systemflexible manufacturing system
flexible manufacturing system
 

Recently uploaded

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 

Recently uploaded (20)

Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 

WM - PP Interface

  • 1. 1
  • 2. Warehouse Management Overview WM interfaces with the following areas: 1. Inventory Management 2. Quality Management 3. Production Planning – This is the focus area for the following slides. 4. Shipping 2
  • 3. WM-PP Interface There are two scenario in for WM-PP Interface : • WM-PP Scenario not active • WM-PP Scenario active 3
  • 5. What is Control Cycle ? For each material and PSA in the plant , one needs to define the following : 1. Storage bin to which the materials will be supplied to 2. Type of material staging. Transaction Code: LPK1/LPK2/LPK3-Create/Change/Display LS41 – List of Control Cycles LPK4-Automatic creation of control cycles for release order parts Pre-requisite : Number range defined for Control Cycle. 5
  • 6. Different types of Staging Sr.No PICK PARTS Indicator=1 CRATE PARTS Indicator =2 RELEASE PARTS Indicator =3 MANUAL STAGING Indicator =4 1 Staging is process order dependent Staging is process order independent. This is used for materials stored in crates or standard containers Staging process is independent of the order. The dept. determines the quantity required Staging is process order dependent. 2 Material staging can be created manually – LP10 OR automatically Material staging is always done manually – LP11(Standard) Material Staging is done manually via- LP12 (Standard) Here staging is done manually, and used in areas where business needs to stage material incase of damage and excess consumption. 3 Requirement number here is the production order number .If the order is > 10, then it truncated from right to left Requirement number is the production supply area , dynamic bin is not supported. The quantity to be staged is defined in the control cycle. Requirement number is the production supply area Dynamic bin coordinate not supported in manual staging 4 Can have one control cycle for all materials One control cycle per material per PSA.Here , one control cycle for multiple materials per PSA does not work. Need to have control cycle for each material .Due to system performance you can create one control cycle for multiple materials Can have one control cycle for multiple materials per PSA. 6
  • 7. Production Supply Area • PSA lies in the production area. It is in the PSA that the material staging is done • PSA groups together the work centers near to production storage bins, taking the material staging type into consideration. • A PSA area is defined per plant and storage location under for a warehouse number under WM- PP Interface. Transaction for Creation :PK05 Standard Production Supply Area: 100-Production Supply Area 7
  • 8. Production Supply Area Determination Work Centre Master Data • If no information is maintained in the work center the system checks in BOM Bill of Material (BOM) • If no information is found in the BOM , then the system check for source supply area in the material master data Material Master Data 8
  • 9. Movement Type Determination • The system will first which Storage type is assigned in the control cycle. For eg.100 Control Cycle • To the storage type a replenishment movement type is assigned ,and hence the system determines the movement type. For e.g.-319 –Replenish for Production Storage Type 9
  • 10. Production Storage Bin • A production storage bin is a storage bin in the PSA. • A production storage bin , is used in the control cycle for each material and PSA. This helps the system to understand the bin where the material will be staged. • It is created as a normal bin. • You can have dynamic bins for Pick Parts, and the staging will be done for particular orders. 10
  • 11. Process Flow Process Order Release Order Material Staging manually/Automa tic A Transfer requirement is created with requirement type “p” With reference to the TR a TO is created via LB13.TO Creation can be manual/automatic GI for the material consumption The following depend on the settings in the production schedule profile: 1. Automatic/Manual Staging 2. Transfer requirement/delivery creation upon release • WM is responsible to provide materials for production. • It does so by supplying the needed materials to storage bins to production area. • This is done so through creation of transfer orders for every transfer requirements. • The subsequent goods issues posting reduces the stocks that have been removed from “production” storage bins ,and no additional activities are required in WM Material will be staged in 100 –Production Supply Area 11
  • 12. Interface Active V/s Interface In-Active 12 Sr.No WM-PP Active WM-PP Inactive 1 Once order released , staging needs to be carried out No Staging required. 2 Control cycles required Control Cycle not required 3 PSA area and production storage bins required PSA and bins not required 4 319/320 movement type used for staging These movement types are not used 5 Upon goods issue , material gets consumed and no additional activity required in WM Upon goods issue, materials gets consumed in IM, in WM TR and TO needs to be processed and confirmed to clear the negative quants. 6 PSA -100 used here 914- Goods in Production Area is used

Editor's Notes

  1. In case of WM-PP interface not active , the following is the process flow: 1.Creation of Production/Process Order 2.A goods issue is created with reference to a Process Order. This is a material document with Movement Type:961 3.The material document generates a TR which causes the stock to move to interim storage type 914- Goods Issue to Production Area. This causes a negative quant to be created in the interim storage type 4.With reference to a TR a TO is created. 5. On confirmation of the TO the negative quant is cleared ,and this ends the process.