Extended metro in stockholm, stockholm county council
1. Extended Metro in Stockholm
Helsinki 2015-11-04
Extended Metro AdministrationStockholm County Council
2. Stockholm – one of the fastest
growing regions in Europe
Two buses
per day
In 2030
approx
2,4 million
35-40 000
per year
Extended Metro AdministrationStockholm County Council
3. The 2013 Stockholm negotiation
The negotiation was led by
government negotiatiators
Assignment:
An expansion of the
Stockholm Metro system
Increasing housing
construction in the Stockholm
region.
An agreement was signed after
10 month.
Mr
HG Wessberg
Ms Catharina
Håkansson
Boman
Extended Metro AdministrationStockholm County Council
4. 14 000
appartments
5 400
appartments
13 500
appartments
40 000
appartments
2 100
appartments
3 000
appartments
Extended Metro Administration
Sidan 5
Stockholm Metro system, year 2025
78 000
New homes
6. Total investment SEK 25,7 billion
RAIL INFRASTRUCTURE
SEK 19,5 billion
Finance
Government 13 650 million
City of Stockholm 2 950 million
Municipality of Nacka 850 million
City of Solna 600 million
Municipality of Järfälla 800 million
Stockholm County Council
650 million
DEPOT OCH TRAINS
SEK 6,2 billion
Finance
Stockholm County Council
SEK 6,2 billion
Extended Metro AdministrationStockholm County Council
7. A new adminstration
Stockholm County Council is responsible for
the metro expansion
March 2014: The extended metro
administration was formed
Task: Planning, Design and Construction
of the new Metro
Extended Metro AdministrationStockholm County Council
8. Extended Metro Administration
County Council
Nacka, Gullmarsplan/
Söderort
Advisory board
Project boardProject board
Project board
Head of Extended Metro Administration
Board
Depot, Signal,
Rolling stock
Odenplan-
Arenastaden
Järfälla-Barkarby
Engineering and Environment
Permission and Land acquisition
Procurement
Communication
Economy and Administration
Extended Metro AdministrationStockholm County Council
9. Main Schedule 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Barkarby
Planning
Legal permits
Design
Procurement & construction
Arenastaden
Planning
Legal permits
Design
Procurement & construction
Nacka/söderort
Planning
Legal permits
Design
Procurement & construction
Depot & trains
Planning
Legal permits
Design
Procurement & construction
Extended Metro AdministrationStockholm County Council
10. Akalla - Barkarby
Facts
Track length 3,3 km
2 new stations
Rock excavation
500.000m3
Construction period
2016 -2021
SEK 3 billion
Extended Metro AdministrationStockholm County Council
11. Odenplan - Arenastaden
Facts
Track length 4,6 km
2 new stations
Rock excavation
580.000m3
Construction period
2016 -2022
SEK 4 billion
Extended Metro AdministrationStockholm County Council
12. Facts
Track length 11 km
5 new stations
Rock excavation
1.500.000m3
Construction period
2018 -2025
SEK 12.5 billion
Extended Metro AdministrationStockholm County Council
Kungsträdgården- Nacka/Söderort
13. Depot, Rolling Stock &
Signalling system
Extended Metro Administration
Sidan 14
Facts
• 1 depot Stabling & maintenance
• Tunnel and tracks
• Construction 2018-22
• SEK 3,4 billion
14. Where are we now?
Extended Metro Administration
Sidan 15
15. Extended Metro Administration
Sidan 16
Legal documents/processes
Planning process
Railway plan
Detailed development plans
Decisions on Environmental impact
Application to the Land and
Environmental Court
17. Förvaltning för utbyggd tunnelbana
Sidan 18
Information
Open house with
information for the public
Pressreleases
Newsletters
Advertising in papers
And more…
19. Tunneling
All tunnels and stations will be done in hard
crystalline rock (+250 MPa).
Traditional methods with drill and blast will be
used instead of TBM (Tunneling Boring Machine).
Extended Metro Administration
Page 20
20. Cut and cower, Odenplan
Extended Metro Administration
Sidan 21
The green line
was constructed in
the 1940’s
The new platform
will be in the
same level
28. Profile – Extension to Nacka
Extended Metro Administration
Page 30
Sofia
approx.
100 m
29. Deep stations
Extended Metro Administration
Page 31
The new stations will be situated deep or very deep,
30 to 90 meters under ground level.
The deepest station, Sofia, will only be served by
elevators.
Deep station in Barcelona. Pia Lindberg Nedby
36. Procurement
Extended Metro Administration
Page 38
The Extended Metro Administration have to follow
the Act on Procurement in the Water, Energy, Transport
and Postal Services Sectors ( in Swedish “LUF”).
37. Buisness form
The contracts will have different buisness forms
consisting of:
Extended Metro Administration
Sidan 39
Contract form
• Design and build
• Traditional contract
• Combinations
Form of payment
• Fixed price
• Unit price
• Other and/or combinations
Level of cooperation
• Cooperation (behavior)
• Cooperation/Partnering
Procurement procedure
• Open procedure
• Negotiated procedure
38. Contract division, example
Extended Metro Administration
Sidan 40
Civil works (including tunneling) 1-3 contracts
Construction work (stations) 1-3 contracts
BEST works (Rail, Electric, Signal and Telecommunication) 1 contract
39. Announcement and invitation
Extended Metro Administration
Page 41
Qualification will mostly be done by TransQ (Achilles)
The suppliers that are qualified, according to
relevant requirements for a contract,
will get an invitation to tender.
To be able to get an invitation
the suppliers must be registered in TransQ.
Announcements can/will be done to inform the
market about procurements.
In general we will not start a procurement before we
have the necessary decisions for the current project.
40. Ongoing procurement- Art in the
new Metro
The Stockholm Metro is famous for its extensive
focus on art and has an international reputation
as "The world's longest art gallery". More than
150 artists have so far helped to give the
Stockholm Metro its own unique look.
Each new station will have
a unique look which also
contributes to increasing
safety and navigability for
travellers.
Extended Metro Administration
Page 42
41. Extended Metro Administration
Sidan 43
Preliminary design
- procurement in December 2015/January 2016
Upcoming procurement
Procurement will be performed trough ZeroChaos.com
ZeroChaos is a global, vendor-neutral provider of integrated
workforce management solutions.
42. Procurements 2016
Preparatory works, Barkarby
- temporary roads
Access tunnels, Barkarby.
Preparatory works, Arenastaden
Civil works (tunneling) Barkarby
Förvaltning för utbyggd tunnelbana
Sidan 44
43. Procurementplan
A plan where all upcoming procurements are
specified for the extension.
The plan will be updated as often as necessary.
The information will be shown at:
www.sll.se/nyatunnelbanan
Extended Metro Administration
Sidan 45