SlideShare a Scribd company logo
1 of 14
Hello Class- This is a very rough draft of the assignment. I have
broken down each section and potential opportunities for you.
This is not all inclusive as you can be creative but you must
meet the deliverables of this assignment.
Scope and Schedule: At the end of week 4, you are to finalize
the initially approved scope from week two and start building
the project schedule. In this week, you are also to work on
building the project Work-Breakdown Structure (WBS). Project
scope and schedule will include the following components:
- Finalized project scope
- Project requirements – in more details
- WBS structure
- Developed project schedule
- Identify key milestones and deliverables
- Outline project resources and assign them to tasks
accordingly.
- Stakeholder engagement – communication plan
Make sure that there is a heading for each section.
Title Page – Name, date, etc
· Finalized Project Scope: Chapter 7 Scope Planning,
I just want a summary of what your final scope is.
· Project Requirements – Details
· WBS Structure- (Week 3) Chapter 7 Video, How to construct
a WBS?
·
· Developed Project Schedule – Chapter 8 Video – Develop
Project Schedule, Chapter 8 Reading Scheduling Projects – May
ways to show schedule just pick one.
Develop Project Schedule
Once you have an estimated duration for each activity in the
network must determine (based on durations and sequence)
whether the project can be realistically finished by the required
completion time.
· In order to do this, the contractor should estimate the duration
of each activity.
· He or she should establish an overall window of time for the
project.
Develop a project schedule that provides a timetable for each
activity and shows:
· The earliest times (or dates) at which each activity can start
and finish, based on the project estimated start time (or date)
· The latest times (or dates) by which each activity must start
and finish in order to complete the project by its required
completion time (or date)
· Incorporate Changes into Schedule
· Throughout a project, changes may occur that impact the
schedule.
· Changes might be initiated by the customer or the project
team, or they might be the result of an unanticipated
occurrence.
· Changes requested early in the project may have less of an
impact on schedule and budget than those requested later in the
project.
· When the customer requests a change, the contractor or project
team should estimate the impact on the project schedule and
budget and then obtain customer approval before proceeding.
· If the customer approves the proposed revisions to the project
schedule and budget, then any additional activities, revised
estimated durations, and revised estimated resources and
associated costs should be incorporated into the project
schedule and budget.
· With respect to the project schedule, changes can result in the
addition or deletion of activities, re-sequencing of activities,
changes to estimated durations for specific activities, or a new
required completion time for the project.
·
· Identify key milestones and deliverables – Write up your key
or show them on your graph and point them out. Discuss in a
summary what they are.
· Outline project resources and assign them to tasks accordingly
·
·
·
·
·
·
· Stakeholder engagement- communication plan
· 6-2aCreating a Stakeholder Engagement Assessment Matrix
· Project teams create a stakeholder engagement plan to define
how they will effectively engage stakeholders in planning and
performing the project based on the analysis of the
stakeholders’ needs, wants, and impacts. A primary tool used in
this plan is the stakeholder engagement assessment matrix. This
matrix typically includes a first column showing the
stakeholders. For each stakeholder, additional columns may
represent how much they are currently supporting or opposing
the project, where you would like them to be, barriers to their
changing, and strategies you may employ to move them.
Strategies for powerful and supporting stakeholders may include
accepting their ideas, compromising, or offering them trade-
offs, while strategies for opponents might entail doing the
minimum possible or fighting their demnds. It is not uncommon
to think that the best one can do with opposing stakeholders is
to help move them to a neutral position, while those who are
unaware of or neutral toward the project may be turned into
supporters.
· Exhibit 6.5 identifies both the current and target positions of
the stakeholder groups. The greater the change in position, the
greater the risk and the greater the engagement effort required.
Student Services had a relatively unimportant position in the old
system but would be critical to the new modularized operation.
Significant expenditure was anticipated in this area. It is of
interest to note that the initial analysis (see Exhibit 6.4) had
identified this group as “other stakeholder.” As the nature and
impact of changes become clearer, they can alter the relative
importance of different groups. Stakeholder positions and
stakeholder strategies must be reevaluated throughout the
project.
· Exhibit 6.5
· Modular Courses—Stakeholder Engagement Assessment
Matrix
STAKEHOLDER
CURRENT POSITION
TARGET POSITION
BARRIERS TO CHANGE
STRATEGY
Vice Chancellor
Leading
Leading
Competing day-to-day priorities
Ensure engagement is ‘efficient’ and effective. Consider
extending role of deputy Chancellor to cover for some day-to-
day activities.
Deans of Faculty
Resistant
Neutral, Supportive, or Leading
Some Deans more powerful than others (relates to student
numbers and academic ratings). ‘Power owners’ are very
influential.
Consider each Dean’s WIIFT individually. Consider strategies
for individuals as well as the group.
Academic Registrar (AR)
Supportive
Leading
Competing day-to-day priorities—lack of leadership skills.
Engage deputy, provide skills and mentorship.
Lecturers
Unaware to neutral
Neutral or supportive
Very large group with veto power through unionized actions.
Involve HR and legal department to evaluate
·
© 2018 Cengage®. May not be scanned, copied
or duplicated, or posted to a publicly accessible website, in
whole or in part, except for use as per mitted in a license
distributed with a certain product or service or otherwise on a
password -protected website or school -approved learning m
anagement system for classroom use. IS Example: Resource
Requirements
© 2018 Cengage®. May not be scanned, copied or
duplicated, or posted to a publicly accessible website, in whole
or in part, except for use as per mitted in a license distributed
with a certain product or service or otherwise on a password -
protected website or school -approved learning m anagement
system for classroom use. IS Example: Responsibility
Assignment Matrix
Project: scope of
project
Date: 09/19/2021
Project Management-GE 5103
Cloud Migration (Private cloud to AWS)
Week4_Scope and
Schedule
Finalized Scope:
The main purpose of this project is to transfer the data from one
cloud to another of high availability and performance of project,
so that we can secure the confidential files with access controls,
the data storage, servers, network infrastructure, and security
elements such as firewalls, setting up VPNs for project access
everything can be done with in a data center, so far we do have
3 data centers as 2 for production and one for disaster recovery ,
so if any disaster occurs then the data can be recovered from
disaster recovery center without any application delays.
Requirements:
Describe
Work Breakdown Structure:
You can use this for reference
Resource
Duration
Responsibility
Budget
Planned Start Date
Planned End Date
Project Manager
4mnths
Manage the project
$275
10/01/2021
01/31/2022
Software Engineer
4mnths
Develop the code and maintain
$250
10/01/2021
01/31/2022
Hardware Engineer
1mnth
Set up hardware
$125
01/01/2022
01/31/2022
Test Engineer
1mnth
1.Quality check of the product
2. Test if the product passes all safety and quality standard
$125
01/01/2022
01/31/2022
Logistic Manager
4mnths
Supply and maintain warehouse material during the project and
procurement shipping
$700k
10/01/2022
01/01/2022
Develop Project Schedule:
Resource
Month1
Month2
Month3
Month4
Project Manager
Assigning all the task to the team
And kick off the project
Checking every 15days for progress
Review the progress made till date and add new features if
required
Go through the project and identify if any missing features and
deliver the product to clients.
Software Engineer
Develop the working simulation.
Run, test and complete the simulation HW and SW team to
collaborate
Enhancements based on the hardware design; complete working
s/w based on the working h/w
Fix the bugs identified by the QA and retest in lower
environments and deliver error free software
Hardware Engineer
Develop the working simulation and decide on Hardware paths
needed for the device
Runs, test and complete the simulation
Check for any updates required for the hardware and add
additional capacity if required
Set up required hardware for final product and maintain.
Test Engineer
NA
Collects the list of supplies for procuring the hardware parts
Order and purchase the parts
Complete Regression, sandbox testing and write unit cases at
each stage
Logistic Manager
NA
NA
Review the work made till date and give a sample demo to stake
holders
Demo the final output and deliver to clients.
Key Milestones and Deliverables:
Identify key milestones in the project and explain why?
Course : :Project Management
Course Project
Overview:
This course project introduces an opportunity to explore all the
project stages (from inception to closing) facilitated
by the well-known Project Management Group Processes
(initiation, planning, execution, monitoring and control, an
d closure) as outlined in the PMBOK® Guide.
Two Project Options:
Data Center Transformation – to complete a migration
strategy/plan to complete the following two tasks:
On-Premise Transformation
Infrastructure And Application Migration to The Cloud
Pick your own project:
Students will have the option to also choose their own proj ect –
project scope will need to be approved by the course
instructor
As you progress through the weekly materials in the course, you
will apply the key principles and knowledge areas (
Scope, cost, schedule, quality, resources, risk management,
procurement, communication, and stakeholder managem
ent) to your project. You will use Microsoft Project software to
track the entire project management plan (PMP), dev
elop the schedule, and track the overall progress of the project.
As the project manager (PM) for a medium-scale pro
ject, you will apply fundamental principles and best practices to
conduct your project from inception to closing. Eac
h assignment provides further detail.
Known Scope:
The project will address client’s needs to upgrade their 3
existing legacy data centers and migrate eligible applicatio
ns to the Cloud:
Total of 3 primary data centers (2 for Production and 1 for
Disaster Recovery)
All 3 data centers share redundant WAN circuits (2 MPLS and 1
Point-2Point) for users and data traffic
Client has a total of 145 enterprise applications and 1350
servers:
450 Windows Servers
550 Unix Servers
350 ESX, VMWare, and legacy AIX servers
Allowed project budget is $1.5 Million with a $150K for
contengecies
The client is open to the top 3 Cloud providers (AWS, Azure,
and Google Cloud)
You have the ability to assemble your team
Stakeholders are also open to your specific and project needs
(define their roles and responsibilities as you see them
fit)
All 3 Data centers are in the United States – the DR DC must be
on a different State for recovery purposes
Requirements:
Meet the weekly assignments’ requirements (total of 4
assignments to complete the entire project) within the 8 week
s duration of the course.
You will be assigned as the main PM for the project, where you
will own the entire project
Your course instructor will act at the project sponsor – can
address all your questions and concerns and will provide
you feedback during the weekly assignments submissions.
The project will include internal and external stakeholders,
vendors, team members, and contractors.
A well-defined project charter must be approved by course
instructor by end of week one.
Your final project management plan as well as the weekly
submissions must adhere to the following formatting requ
irements:
APA version 7 is the required format for the entire paper.
Turnitin tool
Weekly Assignment - Structure:
Week 2 - Project Charter: At the end of week 2, you are to
create and submit the project charter. This is the first offi
cial document to be reviewed and approved by the project
sponsor. Project charter will include the following compo
nents:
High-level project scope
High-level project requirements
Business needs
Early estimation and forecasted cost
Stakeholder analysis (roles and responsibilities)
High-level Communication plan
High-Level Resource plan
Early risk indications
Week 4 – Scope and Schedule: At the end of week 4, you are to
finalize the initial approved scope from week one an
d start building the project schedule. In this week, you are also
to work on building the project Work-Breakdown Str
ucture (WBS). Project scope and schedule will include the
following components:
Finalized project scope
Project requirements – in more details
WBS structure
Developed project schedule
Identify key milestones and deliverables
Outline project resources and assign them to tasks accordingly.
Stakeholder engagement – communication plan
Week 6 – Budget and Risk Management: At the end of week 6,
you are to finalize the overall project cost and clearl
y document project risks gathered throughout the project. As
part of risk management plan, you are expected to shar
e a risk response plan. Project cost and risk management plans
will include the following components:
Overall project budget (utilizing EVM – share current and
forecasted project status)
Project requirements – updated
Cost management plan – outlining contingency plan for project
changes
Detailed risk management plan
Risk response plan
Risk mitigation plan
Change management process
How project RAID (Risk, Assumption, Issues, and
Dependencies) will be managed
Stakeholder engagement – communication plan
Week 8 – Quality and Project Closure: At the end of week 8,
you are to finalize the overall project management plan
(PMP). In this week, you are to integrate all previously
submitted components incorporated with instructor (project
sponsor) feedback into a single project management plan.
Project management plan will include the following comp
onents:
Project quality management plan to include an updated scope,
cost, schedule, communication, risk, resources, procur
ement, and quality)
Updated changes – Change Request (if any)
Project requirements – updated
Stakeholder register – updated
How project RAID (Risk, Assumption, Issues, and
Dependencies)
Document project lessons-learned
Project sponsor approval of the key project deliverables
For the project submission:
Students can use MS project (if they have access to it) or MS
Excel, Word documents, and any other free related soft
ware they are able to access as long as they meet the
assignment’s scoring rubrics/guidelines.

More Related Content

Similar to Hello Class- This is a very rough draft of the assignment. I have

My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailBarbara Franks
 
Chapter 4Defining the Project© McGraw-Hill Education. All ri.docx
Chapter 4Defining the Project© McGraw-Hill Education. All ri.docxChapter 4Defining the Project© McGraw-Hill Education. All ri.docx
Chapter 4Defining the Project© McGraw-Hill Education. All ri.docxketurahhazelhurst
 
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02Durga Prasad Mishra
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptxFawadAfridi6
 
Definition of requirements for each project phases.pdf
Definition of requirements for each project phases.pdfDefinition of requirements for each project phases.pdf
Definition of requirements for each project phases.pdfcalf_ville86
 
Project Management Starters.pptx
Project Management Starters.pptxProject Management Starters.pptx
Project Management Starters.pptxAnkitaNayak83
 
MDP2206-2217-Lec2.pdf
MDP2206-2217-Lec2.pdfMDP2206-2217-Lec2.pdf
MDP2206-2217-Lec2.pdfamirashraf61
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkitsIT-Toolkits.org
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_managementSociety of Women Engineers
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMdAliMujawar1
 
Presentation4 5.1.pptx
Presentation4 5.1.pptxPresentation4 5.1.pptx
Presentation4 5.1.pptxDrRRajalakshmi
 
Business scorecard multiple workstreams - Travis Barker, MPA GCPM (2018)
Business scorecard   multiple workstreams - Travis Barker, MPA GCPM (2018)Business scorecard   multiple workstreams - Travis Barker, MPA GCPM (2018)
Business scorecard multiple workstreams - Travis Barker, MPA GCPM (2018)Innovate Vancouver
 
Project Management How To
Project Management How ToProject Management How To
Project Management How Tokellyfrey
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfsaikumarmba2023
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 

Similar to Hello Class- This is a very rough draft of the assignment. I have (20)

My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFail
 
Chapter 4Defining the Project© McGraw-Hill Education. All ri.docx
Chapter 4Defining the Project© McGraw-Hill Education. All ri.docxChapter 4Defining the Project© McGraw-Hill Education. All ri.docx
Chapter 4Defining the Project© McGraw-Hill Education. All ri.docx
 
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
Definition of requirements for each project phases.pdf
Definition of requirements for each project phases.pdfDefinition of requirements for each project phases.pdf
Definition of requirements for each project phases.pdf
 
Project Management Starters.pptx
Project Management Starters.pptxProject Management Starters.pptx
Project Management Starters.pptx
 
MDP2206-2217-Lec2.pdf
MDP2206-2217-Lec2.pdfMDP2206-2217-Lec2.pdf
MDP2206-2217-Lec2.pdf
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkits
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_management
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptx
 
Presentation4 5.1.pptx
Presentation4 5.1.pptxPresentation4 5.1.pptx
Presentation4 5.1.pptx
 
Business scorecard multiple workstreams - Travis Barker, MPA GCPM (2018)
Business scorecard   multiple workstreams - Travis Barker, MPA GCPM (2018)Business scorecard   multiple workstreams - Travis Barker, MPA GCPM (2018)
Business scorecard multiple workstreams - Travis Barker, MPA GCPM (2018)
 
Project management
Project managementProject management
Project management
 
Project Management How To
Project Management How ToProject Management How To
Project Management How To
 
Project Management
Project ManagementProject Management
Project Management
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 

More from SusanaFurman449

Please read the description of the Religion ethnography carefully an.docx
Please read the description of the Religion ethnography carefully an.docxPlease read the description of the Religion ethnography carefully an.docx
Please read the description of the Religion ethnography carefully an.docxSusanaFurman449
 
PLEASE read the question carefully.  The creation of teen ido.docx
PLEASE read the question carefully.  The creation of teen ido.docxPLEASE read the question carefully.  The creation of teen ido.docx
PLEASE read the question carefully.  The creation of teen ido.docxSusanaFurman449
 
Please reflect on the relationship between faith, personal disciplin.docx
Please reflect on the relationship between faith, personal disciplin.docxPlease reflect on the relationship between faith, personal disciplin.docx
Please reflect on the relationship between faith, personal disciplin.docxSusanaFurman449
 
Please read the following questions and answer the questions.docx
Please read the following questions and answer the questions.docxPlease read the following questions and answer the questions.docx
Please read the following questions and answer the questions.docxSusanaFurman449
 
PRAISE FOR CRUCIAL CONVERSATIONS Relationships ar.docx
PRAISE FOR CRUCIAL CONVERSATIONS Relationships ar.docxPRAISE FOR CRUCIAL CONVERSATIONS Relationships ar.docx
PRAISE FOR CRUCIAL CONVERSATIONS Relationships ar.docxSusanaFurman449
 
Must Be a hip-hop concert!!!!attend a .docx
Must Be a             hip-hop concert!!!!attend a           .docxMust Be a             hip-hop concert!!!!attend a           .docx
Must Be a hip-hop concert!!!!attend a .docxSusanaFurman449
 
Mini-Paper #3 Johnson & Johnson and a Tale of Two Crises - An Eth.docx
Mini-Paper #3 Johnson & Johnson and a Tale of Two Crises - An Eth.docxMini-Paper #3 Johnson & Johnson and a Tale of Two Crises - An Eth.docx
Mini-Paper #3 Johnson & Johnson and a Tale of Two Crises - An Eth.docxSusanaFurman449
 
Please write these 2 assignments in first person.docx
Please write these 2 assignments in                 first person.docxPlease write these 2 assignments in                 first person.docx
Please write these 2 assignments in first person.docxSusanaFurman449
 
Personal Leadership Training plan AttributesColumbia South.docx
Personal Leadership Training plan  AttributesColumbia South.docxPersonal Leadership Training plan  AttributesColumbia South.docx
Personal Leadership Training plan AttributesColumbia South.docxSusanaFurman449
 
Need help on researching why women join gangs1.How does anxi.docx
Need help on researching why women join gangs1.How does anxi.docxNeed help on researching why women join gangs1.How does anxi.docx
Need help on researching why women join gangs1.How does anxi.docxSusanaFurman449
 
Jung Typology AssessmentThe purpose of this assignment is to ass.docx
Jung Typology AssessmentThe purpose of this assignment is to ass.docxJung Typology AssessmentThe purpose of this assignment is to ass.docx
Jung Typology AssessmentThe purpose of this assignment is to ass.docxSusanaFurman449
 
Journal of Organizational Behavior J. Organiz. Behav. 31, .docx
Journal of Organizational Behavior J. Organiz. Behav. 31, .docxJournal of Organizational Behavior J. Organiz. Behav. 31, .docx
Journal of Organizational Behavior J. Organiz. Behav. 31, .docxSusanaFurman449
 
LDR535 v4Organizational Change ChartLDR535 v4Page 2 of 2.docx
LDR535 v4Organizational Change ChartLDR535 v4Page 2 of 2.docxLDR535 v4Organizational Change ChartLDR535 v4Page 2 of 2.docx
LDR535 v4Organizational Change ChartLDR535 v4Page 2 of 2.docxSusanaFurman449
 
In this paper, you will select an ethics issue from among the topics.docx
In this paper, you will select an ethics issue from among the topics.docxIn this paper, you will select an ethics issue from among the topics.docx
In this paper, you will select an ethics issue from among the topics.docxSusanaFurman449
 
In the past few weeks, you practiced observation skills by watchin.docx
In the past few weeks, you practiced observation skills by watchin.docxIn the past few weeks, you practiced observation skills by watchin.docx
In the past few weeks, you practiced observation skills by watchin.docxSusanaFurman449
 
Overview After analyzing your public health issue in Milestone On.docx
Overview After analyzing your public health issue in Milestone On.docxOverview After analyzing your public health issue in Milestone On.docx
Overview After analyzing your public health issue in Milestone On.docxSusanaFurman449
 
Judicial OpinionsOverview After the simulation, justices writ.docx
Judicial OpinionsOverview After the simulation, justices writ.docxJudicial OpinionsOverview After the simulation, justices writ.docx
Judicial OpinionsOverview After the simulation, justices writ.docxSusanaFurman449
 
IntroductionReview the Vila Health scenario and complete the int.docx
IntroductionReview the Vila Health scenario and complete the int.docxIntroductionReview the Vila Health scenario and complete the int.docx
IntroductionReview the Vila Health scenario and complete the int.docxSusanaFurman449
 
In studying Social Problems, sociologists (and historians) identify .docx
In studying Social Problems, sociologists (and historians) identify .docxIn studying Social Problems, sociologists (and historians) identify .docx
In studying Social Problems, sociologists (and historians) identify .docxSusanaFurman449
 
I need help correcting an integrative review.This was the profes.docx
I need help correcting an integrative review.This was the profes.docxI need help correcting an integrative review.This was the profes.docx
I need help correcting an integrative review.This was the profes.docxSusanaFurman449
 

More from SusanaFurman449 (20)

Please read the description of the Religion ethnography carefully an.docx
Please read the description of the Religion ethnography carefully an.docxPlease read the description of the Religion ethnography carefully an.docx
Please read the description of the Religion ethnography carefully an.docx
 
PLEASE read the question carefully.  The creation of teen ido.docx
PLEASE read the question carefully.  The creation of teen ido.docxPLEASE read the question carefully.  The creation of teen ido.docx
PLEASE read the question carefully.  The creation of teen ido.docx
 
Please reflect on the relationship between faith, personal disciplin.docx
Please reflect on the relationship between faith, personal disciplin.docxPlease reflect on the relationship between faith, personal disciplin.docx
Please reflect on the relationship between faith, personal disciplin.docx
 
Please read the following questions and answer the questions.docx
Please read the following questions and answer the questions.docxPlease read the following questions and answer the questions.docx
Please read the following questions and answer the questions.docx
 
PRAISE FOR CRUCIAL CONVERSATIONS Relationships ar.docx
PRAISE FOR CRUCIAL CONVERSATIONS Relationships ar.docxPRAISE FOR CRUCIAL CONVERSATIONS Relationships ar.docx
PRAISE FOR CRUCIAL CONVERSATIONS Relationships ar.docx
 
Must Be a hip-hop concert!!!!attend a .docx
Must Be a             hip-hop concert!!!!attend a           .docxMust Be a             hip-hop concert!!!!attend a           .docx
Must Be a hip-hop concert!!!!attend a .docx
 
Mini-Paper #3 Johnson & Johnson and a Tale of Two Crises - An Eth.docx
Mini-Paper #3 Johnson & Johnson and a Tale of Two Crises - An Eth.docxMini-Paper #3 Johnson & Johnson and a Tale of Two Crises - An Eth.docx
Mini-Paper #3 Johnson & Johnson and a Tale of Two Crises - An Eth.docx
 
Please write these 2 assignments in first person.docx
Please write these 2 assignments in                 first person.docxPlease write these 2 assignments in                 first person.docx
Please write these 2 assignments in first person.docx
 
Personal Leadership Training plan AttributesColumbia South.docx
Personal Leadership Training plan  AttributesColumbia South.docxPersonal Leadership Training plan  AttributesColumbia South.docx
Personal Leadership Training plan AttributesColumbia South.docx
 
Need help on researching why women join gangs1.How does anxi.docx
Need help on researching why women join gangs1.How does anxi.docxNeed help on researching why women join gangs1.How does anxi.docx
Need help on researching why women join gangs1.How does anxi.docx
 
Jung Typology AssessmentThe purpose of this assignment is to ass.docx
Jung Typology AssessmentThe purpose of this assignment is to ass.docxJung Typology AssessmentThe purpose of this assignment is to ass.docx
Jung Typology AssessmentThe purpose of this assignment is to ass.docx
 
Journal of Organizational Behavior J. Organiz. Behav. 31, .docx
Journal of Organizational Behavior J. Organiz. Behav. 31, .docxJournal of Organizational Behavior J. Organiz. Behav. 31, .docx
Journal of Organizational Behavior J. Organiz. Behav. 31, .docx
 
LDR535 v4Organizational Change ChartLDR535 v4Page 2 of 2.docx
LDR535 v4Organizational Change ChartLDR535 v4Page 2 of 2.docxLDR535 v4Organizational Change ChartLDR535 v4Page 2 of 2.docx
LDR535 v4Organizational Change ChartLDR535 v4Page 2 of 2.docx
 
In this paper, you will select an ethics issue from among the topics.docx
In this paper, you will select an ethics issue from among the topics.docxIn this paper, you will select an ethics issue from among the topics.docx
In this paper, you will select an ethics issue from among the topics.docx
 
In the past few weeks, you practiced observation skills by watchin.docx
In the past few weeks, you practiced observation skills by watchin.docxIn the past few weeks, you practiced observation skills by watchin.docx
In the past few weeks, you practiced observation skills by watchin.docx
 
Overview After analyzing your public health issue in Milestone On.docx
Overview After analyzing your public health issue in Milestone On.docxOverview After analyzing your public health issue in Milestone On.docx
Overview After analyzing your public health issue in Milestone On.docx
 
Judicial OpinionsOverview After the simulation, justices writ.docx
Judicial OpinionsOverview After the simulation, justices writ.docxJudicial OpinionsOverview After the simulation, justices writ.docx
Judicial OpinionsOverview After the simulation, justices writ.docx
 
IntroductionReview the Vila Health scenario and complete the int.docx
IntroductionReview the Vila Health scenario and complete the int.docxIntroductionReview the Vila Health scenario and complete the int.docx
IntroductionReview the Vila Health scenario and complete the int.docx
 
In studying Social Problems, sociologists (and historians) identify .docx
In studying Social Problems, sociologists (and historians) identify .docxIn studying Social Problems, sociologists (and historians) identify .docx
In studying Social Problems, sociologists (and historians) identify .docx
 
I need help correcting an integrative review.This was the profes.docx
I need help correcting an integrative review.This was the profes.docxI need help correcting an integrative review.This was the profes.docx
I need help correcting an integrative review.This was the profes.docx
 

Recently uploaded

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 

Hello Class- This is a very rough draft of the assignment. I have

  • 1. Hello Class- This is a very rough draft of the assignment. I have broken down each section and potential opportunities for you. This is not all inclusive as you can be creative but you must meet the deliverables of this assignment. Scope and Schedule: At the end of week 4, you are to finalize the initially approved scope from week two and start building the project schedule. In this week, you are also to work on building the project Work-Breakdown Structure (WBS). Project scope and schedule will include the following components: - Finalized project scope - Project requirements – in more details - WBS structure - Developed project schedule - Identify key milestones and deliverables - Outline project resources and assign them to tasks accordingly. - Stakeholder engagement – communication plan Make sure that there is a heading for each section. Title Page – Name, date, etc · Finalized Project Scope: Chapter 7 Scope Planning, I just want a summary of what your final scope is. · Project Requirements – Details · WBS Structure- (Week 3) Chapter 7 Video, How to construct a WBS? · · Developed Project Schedule – Chapter 8 Video – Develop Project Schedule, Chapter 8 Reading Scheduling Projects – May ways to show schedule just pick one.
  • 2. Develop Project Schedule Once you have an estimated duration for each activity in the network must determine (based on durations and sequence) whether the project can be realistically finished by the required completion time. · In order to do this, the contractor should estimate the duration of each activity. · He or she should establish an overall window of time for the project. Develop a project schedule that provides a timetable for each activity and shows: · The earliest times (or dates) at which each activity can start and finish, based on the project estimated start time (or date) · The latest times (or dates) by which each activity must start and finish in order to complete the project by its required completion time (or date) · Incorporate Changes into Schedule · Throughout a project, changes may occur that impact the schedule. · Changes might be initiated by the customer or the project team, or they might be the result of an unanticipated occurrence. · Changes requested early in the project may have less of an impact on schedule and budget than those requested later in the project. · When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget and then obtain customer approval before proceeding. · If the customer approves the proposed revisions to the project schedule and budget, then any additional activities, revised estimated durations, and revised estimated resources and associated costs should be incorporated into the project schedule and budget. · With respect to the project schedule, changes can result in the addition or deletion of activities, re-sequencing of activities,
  • 3. changes to estimated durations for specific activities, or a new required completion time for the project. · · Identify key milestones and deliverables – Write up your key or show them on your graph and point them out. Discuss in a summary what they are. · Outline project resources and assign them to tasks accordingly · · · · · · · Stakeholder engagement- communication plan · 6-2aCreating a Stakeholder Engagement Assessment Matrix · Project teams create a stakeholder engagement plan to define how they will effectively engage stakeholders in planning and performing the project based on the analysis of the stakeholders’ needs, wants, and impacts. A primary tool used in this plan is the stakeholder engagement assessment matrix. This matrix typically includes a first column showing the stakeholders. For each stakeholder, additional columns may represent how much they are currently supporting or opposing the project, where you would like them to be, barriers to their changing, and strategies you may employ to move them. Strategies for powerful and supporting stakeholders may include accepting their ideas, compromising, or offering them trade- offs, while strategies for opponents might entail doing the minimum possible or fighting their demnds. It is not uncommon to think that the best one can do with opposing stakeholders is
  • 4. to help move them to a neutral position, while those who are unaware of or neutral toward the project may be turned into supporters. · Exhibit 6.5 identifies both the current and target positions of the stakeholder groups. The greater the change in position, the greater the risk and the greater the engagement effort required. Student Services had a relatively unimportant position in the old system but would be critical to the new modularized operation. Significant expenditure was anticipated in this area. It is of interest to note that the initial analysis (see Exhibit 6.4) had identified this group as “other stakeholder.” As the nature and impact of changes become clearer, they can alter the relative importance of different groups. Stakeholder positions and stakeholder strategies must be reevaluated throughout the project. · Exhibit 6.5 · Modular Courses—Stakeholder Engagement Assessment Matrix STAKEHOLDER CURRENT POSITION TARGET POSITION BARRIERS TO CHANGE STRATEGY Vice Chancellor Leading Leading Competing day-to-day priorities Ensure engagement is ‘efficient’ and effective. Consider extending role of deputy Chancellor to cover for some day-to- day activities. Deans of Faculty Resistant Neutral, Supportive, or Leading Some Deans more powerful than others (relates to student numbers and academic ratings). ‘Power owners’ are very influential.
  • 5. Consider each Dean’s WIIFT individually. Consider strategies for individuals as well as the group. Academic Registrar (AR) Supportive Leading Competing day-to-day priorities—lack of leadership skills. Engage deputy, provide skills and mentorship. Lecturers Unaware to neutral Neutral or supportive Very large group with veto power through unionized actions. Involve HR and legal department to evaluate · © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as per mitted in a license distributed with a certain product or service or otherwise on a password -protected website or school -approved learning m anagement system for classroom use. IS Example: Resource Requirements © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as per mitted in a license distributed with a certain product or service or otherwise on a password - protected website or school -approved learning m anagement system for classroom use. IS Example: Responsibility Assignment Matrix
  • 6. Project: scope of project Date: 09/19/2021 Project Management-GE 5103 Cloud Migration (Private cloud to AWS) Week4_Scope and Schedule Finalized Scope: The main purpose of this project is to transfer the data from one cloud to another of high availability and performance of project, so that we can secure the confidential files with access controls, the data storage, servers, network infrastructure, and security elements such as firewalls, setting up VPNs for project access everything can be done with in a data center, so far we do have 3 data centers as 2 for production and one for disaster recovery , so if any disaster occurs then the data can be recovered from disaster recovery center without any application delays. Requirements: Describe
  • 7. Work Breakdown Structure: You can use this for reference Resource Duration Responsibility Budget Planned Start Date Planned End Date Project Manager 4mnths Manage the project $275 10/01/2021 01/31/2022 Software Engineer 4mnths Develop the code and maintain $250 10/01/2021 01/31/2022 Hardware Engineer 1mnth Set up hardware $125 01/01/2022 01/31/2022 Test Engineer 1mnth 1.Quality check of the product 2. Test if the product passes all safety and quality standard $125 01/01/2022 01/31/2022 Logistic Manager
  • 8. 4mnths Supply and maintain warehouse material during the project and procurement shipping $700k 10/01/2022 01/01/2022 Develop Project Schedule: Resource Month1 Month2 Month3 Month4 Project Manager Assigning all the task to the team And kick off the project Checking every 15days for progress Review the progress made till date and add new features if required Go through the project and identify if any missing features and deliver the product to clients. Software Engineer Develop the working simulation. Run, test and complete the simulation HW and SW team to collaborate Enhancements based on the hardware design; complete working s/w based on the working h/w Fix the bugs identified by the QA and retest in lower environments and deliver error free software Hardware Engineer Develop the working simulation and decide on Hardware paths needed for the device Runs, test and complete the simulation Check for any updates required for the hardware and add
  • 9. additional capacity if required Set up required hardware for final product and maintain. Test Engineer NA Collects the list of supplies for procuring the hardware parts Order and purchase the parts Complete Regression, sandbox testing and write unit cases at each stage Logistic Manager NA NA Review the work made till date and give a sample demo to stake holders Demo the final output and deliver to clients. Key Milestones and Deliverables: Identify key milestones in the project and explain why? Course : :Project Management Course Project Overview: This course project introduces an opportunity to explore all the project stages (from inception to closing) facilitated by the well-known Project Management Group Processes (initiation, planning, execution, monitoring and control, an d closure) as outlined in the PMBOK® Guide. Two Project Options:
  • 10. Data Center Transformation – to complete a migration strategy/plan to complete the following two tasks: On-Premise Transformation Infrastructure And Application Migration to The Cloud Pick your own project: Students will have the option to also choose their own proj ect – project scope will need to be approved by the course instructor As you progress through the weekly materials in the course, you will apply the key principles and knowledge areas ( Scope, cost, schedule, quality, resources, risk management, procurement, communication, and stakeholder managem ent) to your project. You will use Microsoft Project software to track the entire project management plan (PMP), dev elop the schedule, and track the overall progress of the project. As the project manager (PM) for a medium-scale pro ject, you will apply fundamental principles and best practices to conduct your project from inception to closing. Eac h assignment provides further detail. Known Scope: The project will address client’s needs to upgrade their 3 existing legacy data centers and migrate eligible applicatio ns to the Cloud: Total of 3 primary data centers (2 for Production and 1 for Disaster Recovery) All 3 data centers share redundant WAN circuits (2 MPLS and 1 Point-2Point) for users and data traffic Client has a total of 145 enterprise applications and 1350 servers:
  • 11. 450 Windows Servers 550 Unix Servers 350 ESX, VMWare, and legacy AIX servers Allowed project budget is $1.5 Million with a $150K for contengecies The client is open to the top 3 Cloud providers (AWS, Azure, and Google Cloud) You have the ability to assemble your team Stakeholders are also open to your specific and project needs (define their roles and responsibilities as you see them fit) All 3 Data centers are in the United States – the DR DC must be on a different State for recovery purposes Requirements: Meet the weekly assignments’ requirements (total of 4 assignments to complete the entire project) within the 8 week s duration of the course. You will be assigned as the main PM for the project, where you will own the entire project Your course instructor will act at the project sponsor – can address all your questions and concerns and will provide you feedback during the weekly assignments submissions. The project will include internal and external stakeholders, vendors, team members, and contractors. A well-defined project charter must be approved by course instructor by end of week one. Your final project management plan as well as the weekly submissions must adhere to the following formatting requ irements: APA version 7 is the required format for the entire paper.
  • 12. Turnitin tool Weekly Assignment - Structure: Week 2 - Project Charter: At the end of week 2, you are to create and submit the project charter. This is the first offi cial document to be reviewed and approved by the project sponsor. Project charter will include the following compo nents: High-level project scope High-level project requirements Business needs Early estimation and forecasted cost Stakeholder analysis (roles and responsibilities) High-level Communication plan High-Level Resource plan Early risk indications Week 4 – Scope and Schedule: At the end of week 4, you are to finalize the initial approved scope from week one an d start building the project schedule. In this week, you are also to work on building the project Work-Breakdown Str ucture (WBS). Project scope and schedule will include the following components: Finalized project scope Project requirements – in more details WBS structure Developed project schedule Identify key milestones and deliverables Outline project resources and assign them to tasks accordingly.
  • 13. Stakeholder engagement – communication plan Week 6 – Budget and Risk Management: At the end of week 6, you are to finalize the overall project cost and clearl y document project risks gathered throughout the project. As part of risk management plan, you are expected to shar e a risk response plan. Project cost and risk management plans will include the following components: Overall project budget (utilizing EVM – share current and forecasted project status) Project requirements – updated Cost management plan – outlining contingency plan for project changes Detailed risk management plan Risk response plan Risk mitigation plan Change management process How project RAID (Risk, Assumption, Issues, and Dependencies) will be managed Stakeholder engagement – communication plan Week 8 – Quality and Project Closure: At the end of week 8, you are to finalize the overall project management plan (PMP). In this week, you are to integrate all previously submitted components incorporated with instructor (project sponsor) feedback into a single project management plan. Project management plan will include the following comp onents: Project quality management plan to include an updated scope,
  • 14. cost, schedule, communication, risk, resources, procur ement, and quality) Updated changes – Change Request (if any) Project requirements – updated Stakeholder register – updated How project RAID (Risk, Assumption, Issues, and Dependencies) Document project lessons-learned Project sponsor approval of the key project deliverables For the project submission: Students can use MS project (if they have access to it) or MS Excel, Word documents, and any other free related soft ware they are able to access as long as they meet the assignment’s scoring rubrics/guidelines.