20ME706PE
PROCESS PLANNING
AND COST
ESTIMATION
• UNIT I INTRODUCTION TO PROCESS PLANNING
• UNIT II PROCESS PLANNING ACTIVITIES
• UNIT III INTRODUCTION TO COST ESTIMATION
• UNIT IV PRODUCTION COST ESTIMATION
• UNIT V MACHINING TIME CALCULATION
Design the
product
Manufacturing
Process
planning
Stages
PROCESS PLANNING ACTIVITIES:
1. Drawing interpretation:
• Analyse finished part in engineering design.component
drawings(features,dimensions,geometric tolerances,surface
finish,material specification,part required).
2. Material evaluation and process selection:
• (Function,appearance,reliability,life,environment,compatibility,produc
tivity,cost).Evaluate the materials, (features,dimensions,geometric
tolerances transform rough state to finished state).Process
evolution(rough to finished).Part evolution(final state to initial state).
3. Selection of m/c,tooling,workholding devices:
• Economic considerations,production rate per unit cost,durability and
dependability,lower process rejection,minimum setup times,long life
of m/c,functional versatility.best m/c,make or buy,BEA .
4. Selecting process parameters:
• Machines selected,calculating operation setup time and cycle
time,tooling sequence,equipment capability,shop practice.
• Calculation of part processing time requires determination of
sequence of processing steps on each m/c as outplanning.
• Part loading,unloading,m/c indexing for 1 cycle.
• M/c cycle time allowances added to standard cycle time.Calculate
cycle time & m/c rates to find out cost.
5. Selecting quality assurance methods:
• Inspection criterias(dimensional,geometric,surface finish),tools and
techniques,increases costs&time.
6. Cost estimating:
• Process of determining the probable cost of product before
manufacture.
• Material,labour,overhead costs-profit.
• Material,mfg processes,batch size,make or buy.
7. Process planning documentation:
• Document clearly all the detail information.
• Documented as job routing or operating sheet.
• Production operations&associated m/c tools for component and
subassembly.
• Route sheet information as
part identification,processing,operation of m/c,std times,setup cycle
times,tooling requirements,production control information shows
planning lead time operation.
• Reasons: part process-design,job quote,cost estimate,std cost
systems,communication vehicle.
8. Communicate process knowledge:
• Mfg to shop floor,economy,consistent quality.
Computer Aided Process Planning
Retrieval (or variant) CAPP System
Selection of Process planning system
Major factors to be considered while selecting the
best process planning system are:
i. General Environment
ii. Organisational Structure
iii. Technical Expertise
iv. Needs and Objectives of the company
DRAWING INTERPRETATION
The following information can be obtained from the
interpretation of an engineering drawing:
i. Material of the product
ii. Number of parts to be produced
iii. Weight of the component
iv. Dimensions of the parts
v. Dimensional and geometric tolerances
vi. Size and Accuracy
TYPES OF DRAWINGS
1)DETAIL DRAWINGS
1.1) SINGLE –PART DRAWINGS
1.2) COLLECTIVE SINGLE –PART
DRAWINGS
2) ASSEMBLY DRAWINGS
2.1) SINGLE –PART ASSEMBLY
DRAWINGS
2.2) COLLECTIVE ASSEMBLY DRAWINGS
INFORMATION IN THE DRAWING SHEET
REQUIRED FOR PROCESS PLANNING
• DIMENSIONS
• MATERIAL SPECIFICATION
• SPECIAL MATERIAL TREATMENTS
• TOLERENCES, LIMITS AND FITS
• SURFACE FINISH
Material Selection Process
Material Evaluation Method
1. Shape or Geometry Consideration
2. Material Property Requirements
3. Manufacturing Considerations
Shape or Geometry Consideration
Some of the important shape or Geometry considerations are:
• Relative size
• Complexity
• Dimensional Tolerance
• Surface Finish
• Allowances
• Design for Assembly
• Design for Manufacturability
Some raw materials forms for common manufacturing processes
Material Property Requirements
i. Mechanical Properties
ii. Physical Properties
iii. Service Environment
Manufacturing Considerations
• Standard Components
• Ease of Manufacture
• Quantity and rate of components
• Minimum and Maximum
• Level of Quality
• QA and Inspection Requirements
• Ease of Assembly
Process Selection
Method
Factors considered for machine
selection
Steps in Machine Selection
Factors in tooling selection
• Manufacturing practice
• Manufacturing process
• Machine tool characteristics
• Capability
• Processing time
• Cutting tool availability
Operating requirements for tool
selection
• Workpiece material
• Operation
• Part geometry
• Tooling data
Factors affecting tooling performance
• Cutting tool materials
• Cutting tool geometry
• Cutting fluids
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING

More Related Content

Similar to INTRODUCTION TO PROCESS PLANNING

Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation Prabhu Bose
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)rajnitj19
 
Process planning and cost estimation
Process planning and cost estimationProcess planning and cost estimation
Process planning and cost estimationRaja P
 
PROCESS PLANNING AND COST ESTIMATION 5 UNITS PPT
PROCESS PLANNING AND COST ESTIMATION 5 UNITS PPTPROCESS PLANNING AND COST ESTIMATION 5 UNITS PPT
PROCESS PLANNING AND COST ESTIMATION 5 UNITS PPTFelix John
 
Bagian 5 PTI
Bagian 5 PTIBagian 5 PTI
Bagian 5 PTIHIMTI
 
Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...eSAT Journals
 
Lecture # 08 Reverse Engineering
Lecture # 08 Reverse EngineeringLecture # 08 Reverse Engineering
Lecture # 08 Reverse EngineeringSolomon Tekeste
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGSathishkumarM89
 
Computer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionComputer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionJayavendhanJ
 
CIM- 1-120000000-UNIT-1 INTRODUCTION.ppt
CIM- 1-120000000-UNIT-1 INTRODUCTION.pptCIM- 1-120000000-UNIT-1 INTRODUCTION.ppt
CIM- 1-120000000-UNIT-1 INTRODUCTION.pptdharma raja`
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGSathishkumarM89
 
TMA Module 2........................................................
TMA Module 2........................................................TMA Module 2........................................................
TMA Module 2........................................................4PS19AU411SyedaSoubi
 
Automotive presentation by Design Expert.
Automotive presentation by Design Expert. Automotive presentation by Design Expert.
Automotive presentation by Design Expert. ajay kumar suwalka
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )TAMILMECHKIT
 
Final project report
Final project reportFinal project report
Final project reportAnkit Sutaria
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process PlanningAsha A
 
Process planning and cost estimation unit i
Process planning and cost estimation  unit   iProcess planning and cost estimation  unit   i
Process planning and cost estimation unit is Kumaravel
 

Similar to INTRODUCTION TO PROCESS PLANNING (20)

Lecture 1 and 2
Lecture 1 and 2Lecture 1 and 2
Lecture 1 and 2
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)
 
Process planning and cost estimation
Process planning and cost estimationProcess planning and cost estimation
Process planning and cost estimation
 
PROCESS PLANNING AND COST ESTIMATION 5 UNITS PPT
PROCESS PLANNING AND COST ESTIMATION 5 UNITS PPTPROCESS PLANNING AND COST ESTIMATION 5 UNITS PPT
PROCESS PLANNING AND COST ESTIMATION 5 UNITS PPT
 
Bagian 5 PTI
Bagian 5 PTIBagian 5 PTI
Bagian 5 PTI
 
PROCESS PLANNING AND COST ESTIMATION
PROCESS PLANNING AND COST ESTIMATIONPROCESS PLANNING AND COST ESTIMATION
PROCESS PLANNING AND COST ESTIMATION
 
Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...
 
Lecture # 08 Reverse Engineering
Lecture # 08 Reverse EngineeringLecture # 08 Reverse Engineering
Lecture # 08 Reverse Engineering
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
Computer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionComputer Aided Design - Unit I Introduction
Computer Aided Design - Unit I Introduction
 
CIM- 1-120000000-UNIT-1 INTRODUCTION.ppt
CIM- 1-120000000-UNIT-1 INTRODUCTION.pptCIM- 1-120000000-UNIT-1 INTRODUCTION.ppt
CIM- 1-120000000-UNIT-1 INTRODUCTION.ppt
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
TMA Module 2........................................................
TMA Module 2........................................................TMA Module 2........................................................
TMA Module 2........................................................
 
Automotive presentation by Design Expert.
Automotive presentation by Design Expert. Automotive presentation by Design Expert.
Automotive presentation by Design Expert.
 
Process Planning and Cost Estimation
Process Planning and Cost EstimationProcess Planning and Cost Estimation
Process Planning and Cost Estimation
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
 
Final project report
Final project reportFinal project report
Final project report
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process Planning
 
Process planning and cost estimation unit i
Process planning and cost estimation  unit   iProcess planning and cost estimation  unit   i
Process planning and cost estimation unit i
 

More from DJAGADEESH1

More from DJAGADEESH1 (19)

PROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESPROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIES
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATION
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATION
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
POM UNIT-I.pdf
POM UNIT-I.pdfPOM UNIT-I.pdf
POM UNIT-I.pdf
 
POM UNIT-3.pdf
POM UNIT-3.pdfPOM UNIT-3.pdf
POM UNIT-3.pdf
 
POM UNIT-4.pdf
POM UNIT-4.pdfPOM UNIT-4.pdf
POM UNIT-4.pdf
 
Unit 5 Controlling.ppt
Unit 5 Controlling.pptUnit 5 Controlling.ppt
Unit 5 Controlling.ppt
 
POM UNIT-2.pdf
POM UNIT-2.pdfPOM UNIT-2.pdf
POM UNIT-2.pdf
 
PPCE Unit-5.pptx
PPCE Unit-5.pptxPPCE Unit-5.pptx
PPCE Unit-5.pptx
 
PPCE Unit-4.pptx
PPCE Unit-4.pptxPPCE Unit-4.pptx
PPCE Unit-4.pptx
 
PPCE Unit-2.pptx
PPCE Unit-2.pptxPPCE Unit-2.pptx
PPCE Unit-2.pptx
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
 
Unit V
Unit VUnit V
Unit V
 
Unit IV
Unit IVUnit IV
Unit IV
 
Unit III
Unit IIIUnit III
Unit III
 
Unit II
Unit IIUnit II
Unit II
 
Unit 1
Unit 1Unit 1
Unit 1
 
Heat treatment
Heat treatmentHeat treatment
Heat treatment
 

Recently uploaded

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Recently uploaded (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

INTRODUCTION TO PROCESS PLANNING

  • 2. • UNIT I INTRODUCTION TO PROCESS PLANNING • UNIT II PROCESS PLANNING ACTIVITIES • UNIT III INTRODUCTION TO COST ESTIMATION • UNIT IV PRODUCTION COST ESTIMATION • UNIT V MACHINING TIME CALCULATION
  • 3.
  • 5.
  • 6. PROCESS PLANNING ACTIVITIES: 1. Drawing interpretation: • Analyse finished part in engineering design.component drawings(features,dimensions,geometric tolerances,surface finish,material specification,part required). 2. Material evaluation and process selection: • (Function,appearance,reliability,life,environment,compatibility,produc tivity,cost).Evaluate the materials, (features,dimensions,geometric tolerances transform rough state to finished state).Process evolution(rough to finished).Part evolution(final state to initial state).
  • 7. 3. Selection of m/c,tooling,workholding devices: • Economic considerations,production rate per unit cost,durability and dependability,lower process rejection,minimum setup times,long life of m/c,functional versatility.best m/c,make or buy,BEA . 4. Selecting process parameters: • Machines selected,calculating operation setup time and cycle time,tooling sequence,equipment capability,shop practice. • Calculation of part processing time requires determination of sequence of processing steps on each m/c as outplanning. • Part loading,unloading,m/c indexing for 1 cycle. • M/c cycle time allowances added to standard cycle time.Calculate cycle time & m/c rates to find out cost.
  • 8. 5. Selecting quality assurance methods: • Inspection criterias(dimensional,geometric,surface finish),tools and techniques,increases costs&time. 6. Cost estimating: • Process of determining the probable cost of product before manufacture. • Material,labour,overhead costs-profit. • Material,mfg processes,batch size,make or buy.
  • 9. 7. Process planning documentation: • Document clearly all the detail information. • Documented as job routing or operating sheet. • Production operations&associated m/c tools for component and subassembly. • Route sheet information as part identification,processing,operation of m/c,std times,setup cycle times,tooling requirements,production control information shows planning lead time operation. • Reasons: part process-design,job quote,cost estimate,std cost systems,communication vehicle. 8. Communicate process knowledge: • Mfg to shop floor,economy,consistent quality.
  • 10.
  • 11.
  • 12.
  • 13.
  • 15. Retrieval (or variant) CAPP System
  • 16.
  • 17.
  • 18. Selection of Process planning system Major factors to be considered while selecting the best process planning system are: i. General Environment ii. Organisational Structure iii. Technical Expertise iv. Needs and Objectives of the company
  • 20. The following information can be obtained from the interpretation of an engineering drawing: i. Material of the product ii. Number of parts to be produced iii. Weight of the component iv. Dimensions of the parts v. Dimensional and geometric tolerances vi. Size and Accuracy
  • 24. 1.2) COLLECTIVE SINGLE –PART DRAWINGS
  • 26. 2.1) SINGLE –PART ASSEMBLY DRAWINGS
  • 28.
  • 29. INFORMATION IN THE DRAWING SHEET REQUIRED FOR PROCESS PLANNING • DIMENSIONS
  • 30. • MATERIAL SPECIFICATION • SPECIAL MATERIAL TREATMENTS
  • 33.
  • 35. Material Evaluation Method 1. Shape or Geometry Consideration 2. Material Property Requirements 3. Manufacturing Considerations
  • 36. Shape or Geometry Consideration Some of the important shape or Geometry considerations are: • Relative size • Complexity • Dimensional Tolerance • Surface Finish • Allowances • Design for Assembly • Design for Manufacturability
  • 37. Some raw materials forms for common manufacturing processes
  • 38. Material Property Requirements i. Mechanical Properties ii. Physical Properties iii. Service Environment Manufacturing Considerations • Standard Components • Ease of Manufacture • Quantity and rate of components • Minimum and Maximum • Level of Quality • QA and Inspection Requirements • Ease of Assembly
  • 39.
  • 41.
  • 42.
  • 43.
  • 44.
  • 45. Factors considered for machine selection
  • 46.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51.
  • 52. Steps in Machine Selection
  • 53. Factors in tooling selection • Manufacturing practice • Manufacturing process • Machine tool characteristics • Capability • Processing time • Cutting tool availability
  • 54.
  • 55.
  • 56.
  • 57. Operating requirements for tool selection • Workpiece material • Operation • Part geometry • Tooling data
  • 58.
  • 59.
  • 60. Factors affecting tooling performance • Cutting tool materials • Cutting tool geometry • Cutting fluids