SlideShare a Scribd company logo
1 of 53
20ME706PE
PROCESS PLANNING
AND COST
ESTIMATION
•UNIT I INTRODUCTION TO PROCESS PLANNING
•UNIT II PROCESS PLANNING ACTIVITIES
•UNIT III INTRODUCTION TO COST ESTIMATION
•UNIT IV PRODUCTION COST ESTIMATION
•UNIT V MACHINING TIME CALCULATION
UNIT V
MACHINING TIME CALCULATION
• Estimation of machining time
• Importance of machine time calculation
• Calculation of machining time for different lathe operations,
Drilling and Boring
• Machining time calculation for Milling, Shaping and Planning
• Machining time calculation for grinding
Introduction
• To estimate the total cost of any product involving machining
operations, the machining cost is to be estimated primarily.
• In order to estimate the machining cost, one has to calculate
the machining time required for these machining operations.
• After knowing the machining time and rate of machining, the
total machining cost can be calculated.
• Therefore the estimation of machining time for various
operations such as lathe, drilling. boring, shaping, planning,
milling and grinding operations are very essential in the cost
estimation activity.
What is meant by Machining Time?
• It is time for which the machine works on the component
• From the time when the tool touches the work to when the
tool leaves the component after completion of operation
• The machining time depends on die type and extent of
machining required, material being machined, speed, feed,
depth of cut and number of cuts required
• In addition to the actual machining time, an estimator has to
consider other time elements such as set-up time, handling
time, tear down time, down time and allowances to the
workers.
FACTORS TO BE CONSIDERED FOR
MACHINE TIME CALCULATION
•Set up time
•Operation time
•Tear down time
•Personal allowance
•Fatigue allowance
•Checking allowance
•Miscellaneous allowance
SETUPTIME
• This takes into account the time required to prepare the
machine for doing the job with the time taken to study the
blue print.
• The time to prepare the machine, in turn
• The time to install and adjust the tools in the machine, as well
as to make the machine ready to start the work.
OPERATION TIME
• The sum of handling time and machining time for a job is
called operation time.
• It is the duration of time that elapses between output of two
consecutive units of production.
TEAR DOWN TIME
• Tear down time takes into account the time necessary to
remove from the machine all tools and accessories, such as
jigs and fixtures, gauges and instruments etc.
• The time required for clearing operational chips from the
machine table and clearing of the machine itself are included
on this.
• Tear down time is generally 10 minute per shift of 8 hrs.
PERSONALALLOWANCE
• The time allowed for workers to meet their personal needs,
such as going to the urinal, drinking water, smoking, washing
their hands, etc is known as personal allowance.
• It is generally 5 to 10 minutes
FATIGUE ALLOWANCE
• The long working hours and poor working conditions such as
poor lighting, poor ventilation etc., cause fatigue
• Fatigue effect the efficiency of worker
• Fatigue decreases the worker capacity to work.
• The allowance for fatigue is taken depending upon the type
of work.
IMPORTANCE OF MACHINING TIME
CALCULATION
•To find the manufacturing cost of a particular job the
calculation of machining time is important, this
requires one or more machining operations.
•After determining the total time for machining, and
knowing the machining cost per unit time, the total
cost of machining can be worked out.
•Machining time is calculated by applying certain
basic formulae, tables of variables and constants.
• The basic formula used is
TRAVEL OF THE TOOL
• This is determined from the dimensions in the actual drawing of the part to be
manufactured.
• The necessary allowances for the tool approach and over-run for clearing the
tool off the job are taken into account with the actual length of the work, to
find the travel of the tool.
FEED
• Feed is the distance, through which the tool advances into the job in
one revolution
• If the work or the distance that the table holding the work travels is
one stroke of the tool. In metric units, feed is usually expressed in
mm/revolution or mm/stroke.
• Feed depends on the depth of cut, fitness of the work desired, rpm of
the job, etc.
DEPTH OF CUT
• It is the penetration of the cutting tool into the job in a single cut.
• In metric units, the depth of cut is expressed in mm.
• The depth of cut depends upon the fitness of the job required, such as
higher depth of cut for rough cut and smaller depth of cut for finish
cut.
RPM
• It represents the number of revolutions of the m/c spindle in one
minute.
• Thus it is the number of revolutions per minute of the job or of tool.
CUTTING SPEED
• The cutting speed can be defined as the relative surface speed
between the tool and the job.
• It is expressed in meters per minute (mpm)
• For example if a job of diameter D mm is revolving at a speed of N
rpm
CALCULATION OF MACHINING TIME FOR
DIFFERENT LATHE
OPERATIONS
Where D = Diameter of given blank,
d = diameter of blank after turning.
• In turning operation, the depth of cut should not exceed 3 mm for
rough cuts and 0.7 5 mm for finishing cuts.
FACING OPERATION
KNURLING
Continued…
REAMING
EXTERNAL RELIEF TURNING
TAPPING
THREADING
DRILLING
BORING
CHAMFERING
MACHINING TIME FOR SHAPING AND PLANING
• Shaping, planning and slotting operations are carried out on
reciprocating machines with a single point cutting tool.
Formula used
Estimation of time for milling operation
The approach is the distance the cutter must be engaged
before the full depth of cut is reached.
When cutter diameter is less than the width of the work.
(b) When cutter diameter is greater than the width of the
work.
Slab milling operation:
Estimation of time for Grinding operation
Formula used
MACHINING TIME CALCULATION
MACHINING TIME CALCULATION
MACHINING TIME CALCULATION
MACHINING TIME CALCULATION

More Related Content

Similar to MACHINING TIME CALCULATION

Process planning with an example
Process planning with an exampleProcess planning with an example
Process planning with an exampleHiran Gabriel
 
Introduction to Manufacturing Systemsshaping machine.pdf
Introduction to Manufacturing Systemsshaping machine.pdfIntroduction to Manufacturing Systemsshaping machine.pdf
Introduction to Manufacturing Systemsshaping machine.pdfPrabathDissanayake8
 
PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)Asim Aslam
 
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUSTInternship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUSTHamza Nasir
 
internship presentation.pptx
internship presentation.pptxinternship presentation.pptx
internship presentation.pptxChinmaiKumar
 
2. LATHE OPERATIONS.ppt
2. LATHE OPERATIONS.ppt2. LATHE OPERATIONS.ppt
2. LATHE OPERATIONS.pptMPIndhu
 
lathe operations
lathe operationslathe operations
lathe operationsRaja P
 
Chapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersChapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersRAHUL THAKER
 
Machining time and costs
Machining time and costsMachining time and costs
Machining time and costsendika55
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.pptSandipanMaji3
 
Economics of metal cutting operations
Economics of metal cutting operationsEconomics of metal cutting operations
Economics of metal cutting operationsDarshan Panchal
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation Prabhu Bose
 

Similar to MACHINING TIME CALCULATION (20)

unit 03 ppt MT- 2.pptx
unit 03 ppt MT- 2.pptxunit 03 ppt MT- 2.pptx
unit 03 ppt MT- 2.pptx
 
Process planning with an example
Process planning with an exampleProcess planning with an example
Process planning with an example
 
Introduction to Manufacturing Systemsshaping machine.pdf
Introduction to Manufacturing Systemsshaping machine.pdfIntroduction to Manufacturing Systemsshaping machine.pdf
Introduction to Manufacturing Systemsshaping machine.pdf
 
PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)
 
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUSTInternship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
 
SNSCT
SNSCTSNSCT
SNSCT
 
internship presentation.pptx
internship presentation.pptxinternship presentation.pptx
internship presentation.pptx
 
2. LATHE OPERATIONS.ppt
2. LATHE OPERATIONS.ppt2. LATHE OPERATIONS.ppt
2. LATHE OPERATIONS.ppt
 
lathe operations
lathe operationslathe operations
lathe operations
 
All in 1 IE
All in 1 IEAll in 1 IE
All in 1 IE
 
Drilling operation
Drilling operationDrilling operation
Drilling operation
 
Milling Machine
Milling MachineMilling Machine
Milling Machine
 
Chapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersChapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centers
 
Machining time and costs
Machining time and costsMachining time and costs
Machining time and costs
 
Drilling
DrillingDrilling
Drilling
 
Drilling (1)
Drilling (1)Drilling (1)
Drilling (1)
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
Economics of metal cutting operations
Economics of metal cutting operationsEconomics of metal cutting operations
Economics of metal cutting operations
 
Machine tools
Machine toolsMachine tools
Machine tools
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 

More from DJAGADEESH1

INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGDJAGADEESH1
 
PROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESPROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESDJAGADEESH1
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONDJAGADEESH1
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONDJAGADEESH1
 
Unit 5 Controlling.ppt
Unit 5 Controlling.pptUnit 5 Controlling.ppt
Unit 5 Controlling.pptDJAGADEESH1
 
PPCE Unit -1.pptx
PPCE Unit -1.pptxPPCE Unit -1.pptx
PPCE Unit -1.pptxDJAGADEESH1
 
PPCE Unit-4.pptx
PPCE Unit-4.pptxPPCE Unit-4.pptx
PPCE Unit-4.pptxDJAGADEESH1
 
PPCE Unit-2.pptx
PPCE Unit-2.pptxPPCE Unit-2.pptx
PPCE Unit-2.pptxDJAGADEESH1
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptxDJAGADEESH1
 

More from DJAGADEESH1 (19)

INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
PROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESPROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIES
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATION
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
POM UNIT-I.pdf
POM UNIT-I.pdfPOM UNIT-I.pdf
POM UNIT-I.pdf
 
POM UNIT-3.pdf
POM UNIT-3.pdfPOM UNIT-3.pdf
POM UNIT-3.pdf
 
POM UNIT-4.pdf
POM UNIT-4.pdfPOM UNIT-4.pdf
POM UNIT-4.pdf
 
Unit 5 Controlling.ppt
Unit 5 Controlling.pptUnit 5 Controlling.ppt
Unit 5 Controlling.ppt
 
POM UNIT-2.pdf
POM UNIT-2.pdfPOM UNIT-2.pdf
POM UNIT-2.pdf
 
PPCE Unit -1.pptx
PPCE Unit -1.pptxPPCE Unit -1.pptx
PPCE Unit -1.pptx
 
PPCE Unit-4.pptx
PPCE Unit-4.pptxPPCE Unit-4.pptx
PPCE Unit-4.pptx
 
PPCE Unit-2.pptx
PPCE Unit-2.pptxPPCE Unit-2.pptx
PPCE Unit-2.pptx
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
 
Unit V
Unit VUnit V
Unit V
 
Unit IV
Unit IVUnit IV
Unit IV
 
Unit III
Unit IIIUnit III
Unit III
 
Unit II
Unit IIUnit II
Unit II
 
Unit 1
Unit 1Unit 1
Unit 1
 
Heat treatment
Heat treatmentHeat treatment
Heat treatment
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 

MACHINING TIME CALCULATION

  • 2. •UNIT I INTRODUCTION TO PROCESS PLANNING •UNIT II PROCESS PLANNING ACTIVITIES •UNIT III INTRODUCTION TO COST ESTIMATION •UNIT IV PRODUCTION COST ESTIMATION •UNIT V MACHINING TIME CALCULATION
  • 3. UNIT V MACHINING TIME CALCULATION • Estimation of machining time • Importance of machine time calculation • Calculation of machining time for different lathe operations, Drilling and Boring • Machining time calculation for Milling, Shaping and Planning • Machining time calculation for grinding
  • 4. Introduction • To estimate the total cost of any product involving machining operations, the machining cost is to be estimated primarily. • In order to estimate the machining cost, one has to calculate the machining time required for these machining operations. • After knowing the machining time and rate of machining, the total machining cost can be calculated. • Therefore the estimation of machining time for various operations such as lathe, drilling. boring, shaping, planning, milling and grinding operations are very essential in the cost estimation activity.
  • 5. What is meant by Machining Time? • It is time for which the machine works on the component • From the time when the tool touches the work to when the tool leaves the component after completion of operation • The machining time depends on die type and extent of machining required, material being machined, speed, feed, depth of cut and number of cuts required • In addition to the actual machining time, an estimator has to consider other time elements such as set-up time, handling time, tear down time, down time and allowances to the workers.
  • 6. FACTORS TO BE CONSIDERED FOR MACHINE TIME CALCULATION •Set up time •Operation time •Tear down time •Personal allowance •Fatigue allowance •Checking allowance •Miscellaneous allowance
  • 7. SETUPTIME • This takes into account the time required to prepare the machine for doing the job with the time taken to study the blue print. • The time to prepare the machine, in turn • The time to install and adjust the tools in the machine, as well as to make the machine ready to start the work.
  • 8. OPERATION TIME • The sum of handling time and machining time for a job is called operation time. • It is the duration of time that elapses between output of two consecutive units of production. TEAR DOWN TIME • Tear down time takes into account the time necessary to remove from the machine all tools and accessories, such as jigs and fixtures, gauges and instruments etc. • The time required for clearing operational chips from the machine table and clearing of the machine itself are included on this. • Tear down time is generally 10 minute per shift of 8 hrs.
  • 9. PERSONALALLOWANCE • The time allowed for workers to meet their personal needs, such as going to the urinal, drinking water, smoking, washing their hands, etc is known as personal allowance. • It is generally 5 to 10 minutes FATIGUE ALLOWANCE • The long working hours and poor working conditions such as poor lighting, poor ventilation etc., cause fatigue • Fatigue effect the efficiency of worker • Fatigue decreases the worker capacity to work. • The allowance for fatigue is taken depending upon the type of work.
  • 10. IMPORTANCE OF MACHINING TIME CALCULATION •To find the manufacturing cost of a particular job the calculation of machining time is important, this requires one or more machining operations. •After determining the total time for machining, and knowing the machining cost per unit time, the total cost of machining can be worked out. •Machining time is calculated by applying certain basic formulae, tables of variables and constants.
  • 11. • The basic formula used is TRAVEL OF THE TOOL • This is determined from the dimensions in the actual drawing of the part to be manufactured. • The necessary allowances for the tool approach and over-run for clearing the tool off the job are taken into account with the actual length of the work, to find the travel of the tool.
  • 12. FEED • Feed is the distance, through which the tool advances into the job in one revolution • If the work or the distance that the table holding the work travels is one stroke of the tool. In metric units, feed is usually expressed in mm/revolution or mm/stroke. • Feed depends on the depth of cut, fitness of the work desired, rpm of the job, etc. DEPTH OF CUT • It is the penetration of the cutting tool into the job in a single cut. • In metric units, the depth of cut is expressed in mm. • The depth of cut depends upon the fitness of the job required, such as higher depth of cut for rough cut and smaller depth of cut for finish cut.
  • 13. RPM • It represents the number of revolutions of the m/c spindle in one minute. • Thus it is the number of revolutions per minute of the job or of tool. CUTTING SPEED • The cutting speed can be defined as the relative surface speed between the tool and the job. • It is expressed in meters per minute (mpm) • For example if a job of diameter D mm is revolving at a speed of N rpm
  • 14. CALCULATION OF MACHINING TIME FOR DIFFERENT LATHE OPERATIONS
  • 15. Where D = Diameter of given blank, d = diameter of blank after turning. • In turning operation, the depth of cut should not exceed 3 mm for rough cuts and 0.7 5 mm for finishing cuts.
  • 16.
  • 17.
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35. MACHINING TIME FOR SHAPING AND PLANING • Shaping, planning and slotting operations are carried out on reciprocating machines with a single point cutting tool.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41. Estimation of time for milling operation
  • 42. The approach is the distance the cutter must be engaged before the full depth of cut is reached. When cutter diameter is less than the width of the work.
  • 43. (b) When cutter diameter is greater than the width of the work.
  • 45.
  • 46. Estimation of time for Grinding operation
  • 47.
  • 48.