3. 3
Cedarvale Station Updates – January 2018
Complete
• Crossover section construction
Ongoing
• Noise and vibration monitoring
• Traffic deck installation on the south side of Eglinton
Upcoming
• Backfill of crossover section
• Completion of shoring on the south side of Eglinton Ave
• Allen Road South realignment
• Shoring on the north side of Eglinton Ave
6. Forest Hill Station Update
ACTIVITY LOCATION APPROXIMATE DURATION
WINTER 2018
Support of Excavation – Station Box South side of Eglinton Ave W Three (3) months remaining
Overnight Bell Utilities Relocation NE corner of Bathurst St and Eglinton Ave W Complete
Wet Utilities Relocation Bathurst St and Eglinton Ave W Ongoing through 2018
Hydro Utilities Relocation
NE work zone Bathurst St and Eglinton Ave
W
February 2018
Support of Excavation – Station Box North side of Eglinton Ave W June 2018