0Copyright © LintonWharfe Limited 2009 and 2010
LintonWharfe
Source-Implement-Succeed
LintonWharfe
‘Nine-Box’ Project Management Framework
An holistic model for managing and
reporting on projects and programmes
Version 2.0 – August 2010
Colin Whalen
Tel: +44 7897 323 816
eMail: colin.whalen@lintonwharfe.com
Skype: colin.whalen
1Copyright © LintonWharfe Limited 2009 and 2010
LintonWharfe
Source-Implement-Succeed
LintonWharfe ‘Nine-Box’ Project Management Framework
Aims Benefits Stakeholders
• Overall business aims are clear.
• Line-of-sight to business
strategy or imperative for
change.
• Business benefits are
understood.
• Benefits can and will be
achieved.
• Key stakeholders are engaged
and committed.
• Those affected will be ready for
change.
Objectives and
Scope
Work Plans and
Deliverables
Risks, Issues and
Opportunities
The Project
• Objectives are clear and aligned
to aims.
• Scope is sensible, practical and
changes to scope are managed.
• Plans are robust and
milestones can and will be
achieved.
• Deliverables are aligned to
objectives.
• Relevant risks and issues are
understood, managed and
mitigated.
• Improvement opportunities are
identified and managed.
• The project is staffed with the
right skills.
• The team have the facilities,
tools, approach and motivation
to succeed.
• The objectives of suppliers are
known and supported by the
project.
• Relationships are positive and
sustainable.
• The budget is realistic and
understood; actual and forecast
expenditure is within budget.
• Opportunities to reduce costs
are managed.
The
Resources
Project Team
Suppliers and
Service Providers
Project
Financials
The Business
Copyright © LintonWharfe Limited 2009 and 2010
Complementary to standard Project Management tools and techniques, eg PRINCE2.
Basis for exception / RAG reporting of project status to Management, Project and Programme Boards.
2Copyright © LintonWharfe Limited 2009 and 2010
LintonWharfe
Source-Implement-Succeed
Project Scorecards – Example 1
The
Project
The Resources
The
Business
Aims
G
Benefits
A
StakeholdersStakeholdersStakeholders
A
Objectives and
Scope
G
Work Plans and
Deliverables
G
Risks and IssuesRisks and Issues
Risks, Issues and
Opportunities
A
Project TeamProject Team
R
Suppliers and
Service Providers
G
Project
Financials
G
3Copyright © LintonWharfe Limited 2009 and 2010
LintonWharfe
Source-Implement-Succeed
Project Scorecards – Example 2
Business
Alignment with
Business Aims G
Now:
• Approved business case aligned with
overall business aims and defined
strategies
Next:
• Monitor v. any changes in business
direction / aims.
Business Case
and Benefits G
Now:
• Business case and benefits approved by
Executive Committee Programme on 26-
Apr-09.
Next:
• Develop benefit measures and means of
tracking in parallel with e-HR design.
StakeholdersStakeholdersStakeholders
G
Now:
• Global webinars show-cased solution.
• Testing initial comms. to key stakeholders.
Next:
• Issue initial communications.
• Put plan/tracker in place.
Project Objectives and Scope
G
Now:
• As per business case.
Next:
• Survey HR Leaders on functional priorities.
• Establish scope/change and priority
management process (budget remains
fixed).
Work Plans
and Deliverables A
Now:
• Behind on contracting (see Suppliers).
• Implementation plans; high-level, by phase
/ release.
Next:
• Focus on contracting.
• Develop detailed plans.
StakeholdersStakeholders
Risks/Issues/Opportunities
(not shown elsewhere) A
Now:
• Market conditions may impact available
funding (ie reduce approved funding).
Next:
• Scenario planning for various funding
conditions.
Resources Project Team
G
Now:
• Core/UK team for Phase 1 identified.
• Testing role descriptions.
Next:
• Finalise role descriptions.
• Identify regional resources.
Suppliers
A
Now:
• Scope/pricing discussions now in diaries.
Next:
• Issue: need clarity / dates for lawyer-
T&C discussions.
• Issue: who signs contract? – Not yet
clear.
StakeholdersStakeholdersFinancials
A
Now:
• FY10/11-10/12 project funding approved.
Next:
• Ensure contract / pricing fits business case.
4Copyright © LintonWharfe Limited 2009 and 2010
LintonWharfe
Source-Implement-Succeed
Project Scorecards – Example 3 Business Dimension
Need overseas HR communications and also to plan next Project Board meeting
• Overall business aims for the project
are clear and aligned to the wider
Business Change Programme
imperatives for increased
organisational capability, agility and
efficiency.
• Broad business benefits were
identified during the previous
business case work and have now
been submitted in a form consistent
with the format required by the
Business Change Programme benefits
manager.
• As part of the recent updates to the
wider financial case, the project case
has been reviewed (and slightly
improved).
• Business representation on the
Project Board secured.
• Representative regional business
partners have input to the
requirements.
• Briefing meetings have been held
with each of the Strategic HR
Business Partners.
• Engaged with IS.
Current
Status
• Under ‘Stakeholders’, continue to
communicate the aims of the project
and demonstrate support for overall
business aims.
• In conjunction with the Business
Change Programme (Benefits
Manager):
- Develop measures for benefits.
- Develop actions plans for
realisation.
• Need to brief the oversees HR
network on the project (to ensure
awareness to inform any local HR
systems decisions).
• Last Project Board was 30th July;
need to plan next meeting.
• Follow-up with business contacts for
input into the final requirements.
To Do
• Overall business aims are clear.
• Line-of-sight to business strategy or
imperative for change.
• Business benefits are understood.
• Benefits can and will be achieved.
• Key stakeholders are engaged and
committed.
• Those affected will be ready for
change.
'Acid Test’ for
Green Rating
Aims Benefits Stakeholders
The
Business G A A
5Copyright © LintonWharfe Limited 2009 and 2010
LintonWharfe
Source-Implement-Succeed
Project Scorecards – Example 3 Project Dimension
On-track
• Objectives and scope are clearly
defined in the agreed Project Charter.
• Current focus is upon the completion
the software procurement /
evaluation process; this will inform
the final business case for the
project.
• Detailed work plan in place for
current stage of the project (through
to business case completion).
• Currently on-track.
• An initial work plan has been
developed for the implementation
(subject to change following the
current stage of the project).
• Project risks and issues have been
identified and are being managed
(and are managed as part of the
Change Programme governance
arrangements).
• No significant risks or issues at this
stage.
• Opportunity to exploit additional
software functionality being assessed.
Current
Status
• Nothing further at this stage.
• Further work will be required ahead
of the implementation stage of the
project to refine overall
implementation objectives and scope.
• Key work packages for the current
project stage are:
- Evaluate responses to short-list
potential suppliers (by end-
Oct).
- Finalise and issue Invitation to
Tender (by end-Oct).
• Continue to track risks and issues.
• Team workshop to identify
opportunities.
To Do
• Objectives are clear and aligned to
aims.
• Scope is sensible, practical and
changes to scope are managed.
• Plans are robust and milestones can
and will be achieved.
• Deliverables are aligned to
objectives.
• Relevant risks and issues are known
and, where possible, they are
managed and mitigated.
• Improvement opportunities are
identified and managed.
'Acid Test’ for
Green Rating
Objectives and
Scope
Work Plan and
Deliverables
Risks, Issues and
Opportunities
The
Project G G A
6Copyright © LintonWharfe Limited 2009 and 2010
LintonWharfe
Source-Implement-Succeed
Project Scorecards – Example 3 Resource Dimension
Need to consider internal HR resource involvement in the project
• Minimal resource commitment at this
stage with one full time interim
resource, supported on an ad hoc
basis by HR and IS resources as
required,
• The lack of a full time HR employee
engaged in the project is a risk in
terms of continuity, engagement and
solution ownership.
• A good range of potential providers
have expressed interest in the
procurement.
• Support to potential providers during
the market testing and short-listing
process has been more onerous than
planned / expected.
• Approved budget for sourcing and
business case has been established.
• Actual / forecast v. the budget is
tracked through the Change
Programme governance
arrangements.
• Currently expecting to under-spend
v. budget (avoiding use of some
planned consultancy spend and not
using contingency).
Current
Status
• Consider involving an existing
member of the HR Team on a more
substantial basis in the project.
• At this stage: ensure appropriate
suppliers are engaged in the
tendering process.
• Looking ahead: establish a Joint
Statement of Intent for the project
with the selected supplier(s).
• Continue to track out-turn against
budget through the Change
Programme governance
arrangements.
To Do
• The project is staffed with the right
skills.
• The team have the facilities, tools
and approach to succeed.
• The objectives of Suppliers are
known and supported by the project.
• Relationships are positive and
sustainable.
• The budget is realistic and
understood; actual and forecast
expenditure is within budget.
• Opportunities to reduce costs are
managed.
'Acid Test’ for
Green Rating’
Project
Team
Suppliers and
Service Providers
Project
Financials
The
Resource A G A

The LintonWharfe 'Nine Box Project Management Framework' (v.2)

  • 1.
    0Copyright © LintonWharfeLimited 2009 and 2010 LintonWharfe Source-Implement-Succeed LintonWharfe ‘Nine-Box’ Project Management Framework An holistic model for managing and reporting on projects and programmes Version 2.0 – August 2010 Colin Whalen Tel: +44 7897 323 816 eMail: colin.whalen@lintonwharfe.com Skype: colin.whalen
  • 2.
    1Copyright © LintonWharfeLimited 2009 and 2010 LintonWharfe Source-Implement-Succeed LintonWharfe ‘Nine-Box’ Project Management Framework Aims Benefits Stakeholders • Overall business aims are clear. • Line-of-sight to business strategy or imperative for change. • Business benefits are understood. • Benefits can and will be achieved. • Key stakeholders are engaged and committed. • Those affected will be ready for change. Objectives and Scope Work Plans and Deliverables Risks, Issues and Opportunities The Project • Objectives are clear and aligned to aims. • Scope is sensible, practical and changes to scope are managed. • Plans are robust and milestones can and will be achieved. • Deliverables are aligned to objectives. • Relevant risks and issues are understood, managed and mitigated. • Improvement opportunities are identified and managed. • The project is staffed with the right skills. • The team have the facilities, tools, approach and motivation to succeed. • The objectives of suppliers are known and supported by the project. • Relationships are positive and sustainable. • The budget is realistic and understood; actual and forecast expenditure is within budget. • Opportunities to reduce costs are managed. The Resources Project Team Suppliers and Service Providers Project Financials The Business Copyright © LintonWharfe Limited 2009 and 2010 Complementary to standard Project Management tools and techniques, eg PRINCE2. Basis for exception / RAG reporting of project status to Management, Project and Programme Boards.
  • 3.
    2Copyright © LintonWharfeLimited 2009 and 2010 LintonWharfe Source-Implement-Succeed Project Scorecards – Example 1 The Project The Resources The Business Aims G Benefits A StakeholdersStakeholdersStakeholders A Objectives and Scope G Work Plans and Deliverables G Risks and IssuesRisks and Issues Risks, Issues and Opportunities A Project TeamProject Team R Suppliers and Service Providers G Project Financials G
  • 4.
    3Copyright © LintonWharfeLimited 2009 and 2010 LintonWharfe Source-Implement-Succeed Project Scorecards – Example 2 Business Alignment with Business Aims G Now: • Approved business case aligned with overall business aims and defined strategies Next: • Monitor v. any changes in business direction / aims. Business Case and Benefits G Now: • Business case and benefits approved by Executive Committee Programme on 26- Apr-09. Next: • Develop benefit measures and means of tracking in parallel with e-HR design. StakeholdersStakeholdersStakeholders G Now: • Global webinars show-cased solution. • Testing initial comms. to key stakeholders. Next: • Issue initial communications. • Put plan/tracker in place. Project Objectives and Scope G Now: • As per business case. Next: • Survey HR Leaders on functional priorities. • Establish scope/change and priority management process (budget remains fixed). Work Plans and Deliverables A Now: • Behind on contracting (see Suppliers). • Implementation plans; high-level, by phase / release. Next: • Focus on contracting. • Develop detailed plans. StakeholdersStakeholders Risks/Issues/Opportunities (not shown elsewhere) A Now: • Market conditions may impact available funding (ie reduce approved funding). Next: • Scenario planning for various funding conditions. Resources Project Team G Now: • Core/UK team for Phase 1 identified. • Testing role descriptions. Next: • Finalise role descriptions. • Identify regional resources. Suppliers A Now: • Scope/pricing discussions now in diaries. Next: • Issue: need clarity / dates for lawyer- T&C discussions. • Issue: who signs contract? – Not yet clear. StakeholdersStakeholdersFinancials A Now: • FY10/11-10/12 project funding approved. Next: • Ensure contract / pricing fits business case.
  • 5.
    4Copyright © LintonWharfeLimited 2009 and 2010 LintonWharfe Source-Implement-Succeed Project Scorecards – Example 3 Business Dimension Need overseas HR communications and also to plan next Project Board meeting • Overall business aims for the project are clear and aligned to the wider Business Change Programme imperatives for increased organisational capability, agility and efficiency. • Broad business benefits were identified during the previous business case work and have now been submitted in a form consistent with the format required by the Business Change Programme benefits manager. • As part of the recent updates to the wider financial case, the project case has been reviewed (and slightly improved). • Business representation on the Project Board secured. • Representative regional business partners have input to the requirements. • Briefing meetings have been held with each of the Strategic HR Business Partners. • Engaged with IS. Current Status • Under ‘Stakeholders’, continue to communicate the aims of the project and demonstrate support for overall business aims. • In conjunction with the Business Change Programme (Benefits Manager): - Develop measures for benefits. - Develop actions plans for realisation. • Need to brief the oversees HR network on the project (to ensure awareness to inform any local HR systems decisions). • Last Project Board was 30th July; need to plan next meeting. • Follow-up with business contacts for input into the final requirements. To Do • Overall business aims are clear. • Line-of-sight to business strategy or imperative for change. • Business benefits are understood. • Benefits can and will be achieved. • Key stakeholders are engaged and committed. • Those affected will be ready for change. 'Acid Test’ for Green Rating Aims Benefits Stakeholders The Business G A A
  • 6.
    5Copyright © LintonWharfeLimited 2009 and 2010 LintonWharfe Source-Implement-Succeed Project Scorecards – Example 3 Project Dimension On-track • Objectives and scope are clearly defined in the agreed Project Charter. • Current focus is upon the completion the software procurement / evaluation process; this will inform the final business case for the project. • Detailed work plan in place for current stage of the project (through to business case completion). • Currently on-track. • An initial work plan has been developed for the implementation (subject to change following the current stage of the project). • Project risks and issues have been identified and are being managed (and are managed as part of the Change Programme governance arrangements). • No significant risks or issues at this stage. • Opportunity to exploit additional software functionality being assessed. Current Status • Nothing further at this stage. • Further work will be required ahead of the implementation stage of the project to refine overall implementation objectives and scope. • Key work packages for the current project stage are: - Evaluate responses to short-list potential suppliers (by end- Oct). - Finalise and issue Invitation to Tender (by end-Oct). • Continue to track risks and issues. • Team workshop to identify opportunities. To Do • Objectives are clear and aligned to aims. • Scope is sensible, practical and changes to scope are managed. • Plans are robust and milestones can and will be achieved. • Deliverables are aligned to objectives. • Relevant risks and issues are known and, where possible, they are managed and mitigated. • Improvement opportunities are identified and managed. 'Acid Test’ for Green Rating Objectives and Scope Work Plan and Deliverables Risks, Issues and Opportunities The Project G G A
  • 7.
    6Copyright © LintonWharfeLimited 2009 and 2010 LintonWharfe Source-Implement-Succeed Project Scorecards – Example 3 Resource Dimension Need to consider internal HR resource involvement in the project • Minimal resource commitment at this stage with one full time interim resource, supported on an ad hoc basis by HR and IS resources as required, • The lack of a full time HR employee engaged in the project is a risk in terms of continuity, engagement and solution ownership. • A good range of potential providers have expressed interest in the procurement. • Support to potential providers during the market testing and short-listing process has been more onerous than planned / expected. • Approved budget for sourcing and business case has been established. • Actual / forecast v. the budget is tracked through the Change Programme governance arrangements. • Currently expecting to under-spend v. budget (avoiding use of some planned consultancy spend and not using contingency). Current Status • Consider involving an existing member of the HR Team on a more substantial basis in the project. • At this stage: ensure appropriate suppliers are engaged in the tendering process. • Looking ahead: establish a Joint Statement of Intent for the project with the selected supplier(s). • Continue to track out-turn against budget through the Change Programme governance arrangements. To Do • The project is staffed with the right skills. • The team have the facilities, tools and approach to succeed. • The objectives of Suppliers are known and supported by the project. • Relationships are positive and sustainable. • The budget is realistic and understood; actual and forecast expenditure is within budget. • Opportunities to reduce costs are managed. 'Acid Test’ for Green Rating’ Project Team Suppliers and Service Providers Project Financials The Resource A G A